Question Bank
Question Bank
Question Bank
Contract administration is the management of the contract between the employer, or client, and
the building contractor.
Contract administration formally starts when the building contractor is hired to deliver the building
project and associated works
What is Contract?
A contract is a legally binding or valid agreement between two parties.
Elements of contract:
1. Offer and acceptance.
2. An intention between the parties to create binding relations
3. Consideration to be paid for the promise made
4. Legal capacity of the parties to act
5. Genuine consent of the parties
6. Legality of the agreement
An agreement that lacks one or more of the elements listed above is not a valid contract
CONTROLLING PROJECTS:
A contract administrator’s role only starts when a building contract is in place between the em-
ployers and the contractor. The contract administrator is responsible for a variety of services from
the time the contract starts to the time it ends.
3)Penalty:
It is a fine imposed on the contractor for non- fulfillment of his contractual obligations such as
failure to maintain required progress of work, delay in completion, poor quality or work, bad work-
manship etc.
Compensation for The contractor is liable to pay compensation to the delay in completion
owner for delay attributed to him in completion of work. The amount of compensation may be
stated as a percentage of the estimated cost of work for each unit of time delay. The maximum
of work: limit of compensation may be 10% of the contract price.
4)Liquidated Damages:
It is a fixed stipulated sum payable by the contractor on account of penalty for delays and does
not bear any relationship to the real damage to the owner. It is generally high and fixed per day
for excess period over the specified in the contract for completing the work.
5)Valuation of Variations:
The valuation of variations is based on change orders issued in writing by the owner. Generally,
the variation in individual items of work should not be more than 25% and variation in total cost
should not exceed 10%.
6)Settlement of Disputes:
Efforts should be made to resolve disputes amicably between the owner and the contractor
through mutual discussions and negotiations. Arbitration clause may be incorporated in the con-
tract to settle disputes not resolved through mutual discussions and negotiations.
9) Price Escalation:
During execution of the work, labor wages and material prices may increase as a result of in-
flation. The contract conditions should therefore, include on appropriate clause for payment of
escalation to the contractor. The compensation for escalation is normally worked out at quarterly
intervals with respect to the cost of work executed during that period.
The prime purpose of the Bill of Quantities (BOQ) is to enable all contractors tendering for a con-
tract to price on exactly the same information. So, billing shall be based on Bill of Quantities
(BOQ) to enable all contractors to follow a contract to price to get paid for the work done
Role of billing engineer in construction is about preparing bills for payments and performing the
estimation of quantities along with order of materials.
The payment to the contractors for works are made on the basis of measurements recorded in
the measurement books. When the work or supply is completed or sufficiently progressed, the de-
tailed measurements are taken usually by the supervisor and recorded in the measurement book
and an abstract of quantities are prepared and the cost is calculated at the rate of the contract
agreement. From the abstract of quantity and the rate, a bill is prepared for payment.
Billing must be done in skillful way with the planning, monitoring, analysis of all the work related to
payments based on BOQ. For Non-BOQ items, analysis of rates to be done before raising bills
2. Types of Bills
The various standard forms of bills and vouchers are used for payment, according to the nature
of works. White forms are used for running bills and Yellow forms are used for final bills. Companies
have their own system of coding the bills.
2. Types of Bills
• First and Final bill
• Running account Bill
• Lump sum contract Bil
• Hand receipt
a) First and Final Bill: This form is used for making payment to the contractor both for
works and suppliers, when a single payment is to be made on the completion of the
whole work or supply as final payment. This type of bill is generally adopted for petty works
or split up works in projects.
b) Running Account Bill: Used for advance payment without any measurement. It may
be used for running bill payment for advance for unmeasured work only or combination
of unmeasured work and measured work or if ‘on account’ payment is to be made but
an advance payment already made for the same work is outstanding.
c) Lump Sum Contract Bill: In the L.S. contract methods, a number ofintermediate pay-
ments are made in L.S. contract running account bill form before final payment is made.
Intermediate payment is made for
(i) value of measure up items of work executed forming part of the contract.
(ii) value of authorized extra work done on account of additions or modifications in the
work executed supported by details in either case. In the final L.S. bill, the full amount as
entered in the contract is paid adding the amount of authorized extras and deducting
authorized omission and the intermediate payments already made.
d) Hand Receipt: Hand receipt is a simple form of voucher intended to be used for small
miscellaneous payments and advances for which none of the above forms is suitable.
The purpose of payment and the designation of the officer making payment duly sup-
ported by measurement book entry should be furnished on the hand receipt No agree-
ment is necessary for payments made through Hand receipt form.
3. Types of Payments
a) First and Final Payment
b) Running on Interim or ‘on account’ payment.
c) Final payment
d) Advance payment
e) Secured Advance payment
a) First and Final Payment: The term indicates a single payment made for a job or con-
tract on its completion. In this case the payment finished by one payment after the com-
pletion of the work. This is usually applicable for small work.
b) Running or interim ‘on account’ payment: This means payment made on a running
account to a contractor for works done or supplies made by him, duly measured and
entered in measurement book. This is effected when only a part of the whole work or sup-
ply has been done and the work or supply is in progress. During the progress of the work,
the contractor is paid from time to time.
c) Final Payment: This is the last payment made to a contractor on a running account,
on completion of this contract and the full settlement of the account.
d) Advance Payment: This means the payment made on a running account to a con-
tractor for work done by him but not measured. Advance payment is not generally made
to the contractor, but may be made under special circumstances when the work is suf-
ficiently progressed, but measurement cannot be taken for certain valid reasons. The
value of work done shall not be less than the advance proposed. Detailed measurements
shall be taken as soon as possible and advance payment adjusted in the final bill.
e) Secured Advance Payment: This payment is made on the security of materials brought
4. Preparation, Examination and Payment of Bills
The bills for payment shall be prepared with respect to the measurements recorded in the
measurement book. All entries in the measurement book with regard to the description and
quantities of work or supplies made are checked. Arithmetical calculations of the contents or
area are verified. When, the bill is on running account then it is compared with the quantities
etc. with the previous bill.
It is checked whether deduction in respect of the following have been properly made.
a) Recovery for advance payment
b) Recovery in respect of departmental materials issued to the contractors.
c) Hire charges for departmental materials issued to the contractors.
d) Amount to be withheld towards security deposit.
e) Recovery towards penalty for slow progress, non-return of temporary issue of materials etc.
In case of final bills, the field officers should certify about the due fulfillment of contract and
satisfactory completion of work. The memorandum of payment is then made. The compe-
tent officer records a formal pay order specifying both in words and figures the net amount
payable. However, the contractor is required to acknowledge the gross amount payable
inclusive of recoveries proposes in the bill. The number and date of the voucher for payment
will be entered in the measurement book.
Building Commissioning:
Building Commissioning is the professional practice that ensures buildings are delivered
according to the Owner's Project Requirements (OPR). Buildings that are properly commis-
sioned typically have fewer change orders, tend to be more energy efficient, and have
lower operation and maintenance cost.
Ensuring the building systems are operating as intended and Owner/Operators have the
information and training they need. It is the Owner/Operator’s way of making sure that the
project’s energy related systems are installed, calibrated and performing according to
the project requirements.
A commissioned building provides optimized energy efficiency, indoor air quality, occu-
pant comfort and sets the stage for reduced operation and maintenance costs
The level and depth of commissioning required is determined by the size of the project
and by the needs defined in the owner’s project requirements.
Pre-Handover Meeting
Areas of Concern:
The General Contractor and the Owner/Operator must coordinate on critical tasks prior to
project completion
An early, focused review of the status of all critical activities and project requirements
leading to completion and occupancy will help ensure a successful handover. At 60 days
from the expected substantial completion date, a building pre-handover meeting should
occur. Both the Development
Team (Prime Consultant, General Contractor, Development Consultant / Project Manager
and the operations team (Owner/Operator of the project) should attend and review the
status of the following:
The handover of the site to the client takes place once the contract administrator has
confirmed that the works defined in the contract are complete. However, it should be
planned well in advance, and any special requirements included in appointment docu-
ments and contracts.
Confirming the works as complete and fit for occupation should involve all key stakehold-
ers. In this regard, confirming that sustainability requirements have been met, e.g. features
included and commissioned, and construction measures evidenced, will be part of the
wider review of completed quality against the scope of works
1. Consultant/Project Manager:
Plan and coordinate the activities of the General Contractor, Prime
Consultant and Owner/Operator so complete O&M manuals are available at handover.
2. Consultants:
❑ Review the General Contractor’s draft table of contents and submit comments to the
General Contractor within 15 calendar days
❑ Review the complete O&M manuals to ensure completeness and accuracy, and pro-
vide written comments to the General Contractor within 30 calendar days
❑ Ensure that an appropriate deficiency holdback is applied to the
General Contractor’s payment until approved O&M manuals have been submitted to the
Owner/Operator
3. General Contractor:
❑ Engage experienced and qualified staff or consultants to prepare the
O&M manuals
❑ Submit a draft table of contents at the pre-handover meeting (60 calendar days prior
to expected substantial completion) for approval by the design consultants, Owner/Oper-
ator and commissioning authority
❑ Prepare the O&M manuals in accordance with the approved table of contents and
submit the complete O&M manuals to the Prime
Consultant and Owner / Operator with the application for substantial completion
4. Owner/Operator
❑ Review the O&M manuals submitted by the General Contractor and inform the consul-
tant if any information is missing, or clarification required, within 15 business days
Without as-built drawings at the time of handover, the Owner/Operator will not have the
reference drawings they need to troubleshoot or resolve building issues.
The General Contractor must submit to the Owner/Operator two copies of white prints and
electronic PDF and CAD drawing files
Without as-built drawings at the time of handover, the Owner/Operator will not have the
reference drawings they need to troubleshoot or resolve building issues. The General
Contractor must submit to the Owner/Operator two copies of white prints and electronic
PDF and CAD drawing files
1. Prime Consultant:
❑ Review the accuracy and completeness of the as-built drawings prepared by the Gen-
eral Contractor and ensure these comply with the requirements of the contract
❑ Finalize the as-built drawings promptly to meet the General Contractor’s obligation to
the Owner/Operator
2. General Contractor:
❑ At 75% completion, coordinate with the Prime Consultant to initiate the preparation of
the as-built drawings
❑ Submit complete as-built drawings to the Prime Consultant and BC Housing with the
application for substantial completion
❑ Submit complete and approved as-built drawings to the Owner / Operator no later than
30 calendar days after substantial completion
❑ Ensure that an appropriate amount is held back from the progress billings until com-
plete and approved as-built drawings have been received.
Training and Orientation
The Development Team and Commissioning Agent (if applicable) are responsible for training and
providing an orientation to the Owner / Operator’s maintenance staff. The training session should
incorporate all building systems and should match the staff’s level of expertise.
The Development Team and Commissioning Agent (if applicable) should begin the building
commissioning process prior to occupancy, at or before substantial completion.
Substantial Completion
The construction contract is
SUBSTANTIALLY COMPLETE when the Prime Consultant issues a certificate of completion for the
work as a whole, and the building is ready to use for the purpose intended.
Responsible Parties:
1. Prime Consultant:
❑ Conduct deficiency inspections to determine if the General Contractor’s application is valid
and to assess the value of the deficiencies
❑ Prepare a deficiency list that incorporates all deficiencies noted by the project sub-consultants,
Owner/Operator and BC Housing
❑ Carefully evaluate the cost of deficiencies to ensure the deficiency hold back is adequate to
complete the remaining and deficient work to the satisfaction of the Prime Consultant and the
Owner/Operator
❑ If the application is valid, issue the certificate of completion to the
General Contractor and Owner/Operator no later than 10 calendar days from the General Con-
tractor’s application for substantial performance
2. General Contractor:
❑ Upon substantial performance of the work, submit a list and estimate of deficiencies to the
Prime Consultant with the application for substantial performance
❑ Immediately following the issuance of the certificate of completion, establish a reasonable
date for correcting deficiencies and inform the
Owner/Operator in writing of the date
3. Owner / Operator:
❑ Upon the General Contractor’s request for certification of substantial performance, conduct
inspections with the Prime Consultant and General Contractor to identify deficiencies
Construction Deficiencies
After substantial completion, the General Contractor should correct all deficiencies identified by
the Prime Consultant, the Owner/Operator
1. Prime Consultant:
❑ Review and provide written sign-off on correction of deficiencies to confirm compliance with the
contract documents
❑ Establish a deficiency hold back in the amount of twice the value of the deficiencies when certi-
fying progress payment at substantial completion
❑ Avoid certifying partial release of the deficiency hold back, unless for seasonal deficiencies
3. General Contractor:
Correct the deficiencies to the satisfaction of the Prime Consultant and Owner/Operator, accord-
ing to the agreed-upon schedule.
4. Owner / Operator:
❑ To differentiate General Contractor deficiencies from tenant or Owner/Operator damage,
agree with the General Contractor on a process for addressing damage to the premises during
Owner/Operator or tenant move-in
❑ Discuss the General Contractor’s performance issues and appropriate action with Project Man-
ager
❑ At the completion of the project, inform the bonding company of major issues regarding the
General Contractor’s performance
Occupancy Permit
The occupancy permit is issued when the municipality has deemed the building to be complete
and ready to use for its intended purpose. Obtaining the occupancy permit involves the work
of numerous parties, including all the consultants, the General Contractor, subcontractors and
authorities having jurisdiction over the project. This requires careful planning and coordination by
the Development Team to enable the
Owner/Operator to meet their target occupancy date.
1. Prime Consultant:
❑ Review the key activities and timelines leading to building occupancy and timelines in the over-
all development schedule so that these can be managed to meet the target occupancy date
❑ Consider a pre-occupancy inspection (or dry run) with the Prime Consultant and the city/munici-
pal staff to identify issues that might affect final occupancy approval
❑ Communicate promptly on issues that could delay occupancy and recommend remedial ac-
tion to bring the project back on track
Building Handover Meeting
A building handover meeting should take place to formalize the handover of the project from
the General Contractor to the
Owner/Operator and to address specific issues that the Owner/Operator may face as they begin
operating and maintaining their building.
All stakeholders attend the building handover meeting. The Development Consultant / Project
Manager, General Contractor, Prime Consultant, Owner/Operator representatives including those
responsible for building operations should all be present at the meeting
At the end of the defects liability period contractor must submit a notice to the owner / operator
who is obliged to inspect the works within the period specified in order to determine whether any
defects are present. If any defects are identified, the owner / operator is obliged to provide the
contractor with a defects list, which have arisen during the defects liability period and which the
contractor must rectify in order to achieve final completion of the works.
With these, the contractor’s liabilities and obligations in relation to a subcontractor’s defects
comes to an end and ………..any remaining portion of the subcontractor’s defects period is
agreed and assumed by the employer
Certificate of final completion constitutes conclusive evidence as to the sufficiency of the works
and that the contractors obligations have been fulfilled other than latent defects.
Conflicts
Conflicts on the construction site are a common occurrence. Disputes and disagreements are
going to arise when you have multiple parties such as general contractors, owners, architects,
subcontractors working together to complete a project. These stakeholders have different opin-
ions and interpretations on how things are supposed to be done. Those differing opinions often
lead to conflicts.
-Poor contract administration:, meaning the employer, contractor or subcontractor fails to un-
derstand and/or comply with contractual obligations
-Errors and omission in design: which means projects are out of compliance, fail to meet speci-
fications or just don’t match stakeholder expectations
-Double meaning in specifications:, meaning specs were not clear in the first place
-Sloppy quality standards: that fail to catch and correct mistakes on a reasonable timeline
-Lack of communication: between owners, investors, contractors, subcontractors and laborers
2. Act fast
When problems arise, it’s important to start the resolution process sooner rather than later. The
longer you wait, the more expensive and time consuming conflicts become.
Plus, each day that passes is more time for each party to cement their point of view and be-
come more intractable. As soon as you recognize a problem, you should call a meeting, talk to
the parties involved, review contracts for details, just do something.
Resolving conflicts doesn’t always result in a win-win situation for all involved. It’s important that
once a resolution has been decided upon, everyone involved gets an explanation and is clear
on what is expected moving forward. They might not always agree with the decision, but provid-
ing a reasonable explanation following up will go a long way in accepting the decision.
Institutionalized Conflict Avoidance
1. Build Teamwork
Teamwork is not only essential for a successful project, but it’s also critical to avoid disputes in
construction.
Arbitration
Arbitration is a process in which a dispute is submitted to an impartial outsider who makes a de-
cision which is usually binding on both the parties
A procedure in which a dispute is submitted, by agreement of the parties, to one or more arbi-
trators who make a binding decision on the dispute. In choosing arbitration, the parties opt for a
private dispute resolution procedure instead of going to court.
The Basics:
❑ The arbitrator enforces his own point of view on the contending parties and the opinions of the
participants are not given any predominance.
❑ Arbitration is a judicial process
❑ The award of the arbitrator is binding and rests on equity and justice, i.e., there is no scope for
compromise
Duties of Arbitrator:
❑ To administer oath to the parties and witness appearing
❑ To act judicially and impartially
❑ To put necessary interrogatories to any party to the dispute
❑ To determine by and to whom the costs of reference and the award shall be paid
❑ To award interest
❑ To fix amount, mode and time of payment
Advantages of Arbitration:
1. Fairness
There is an element of fairness that prevails in the arbitration process from the very inception. The
parties have a say in the selection of arbitrators, the parties are heard individually in an arbitration
proceeding and even more importantly, the very establishment of the process of arbitration is on
the basis of the fact that the parties decide to settle their disputes amicably.
2. Preserves time
The process of arbitration preserves time loss of not only the parties but also saves the time of the
court. Most of the civil cases take a lot of time to be resolved by the courts. Often a generation
lapses before the completion of the arbitration process. The emergence of the processes of al-
ternative dispute resolution had been to reduce the time of the adjudication process. In addition
to it, there is a requirement to resolve commercial disputes in the fastest way possible.
3. Cost effective
The time saved In the process of arbitration also saves the money involved in the process. Com-
pared to adjudication the costs involved in the arbitration is minimal. The quality of it being cost
effective is one of the reasons that the parties prefer using arbitration as a means to resolve their
disputes
4. Confidentiality
Another factor leading to the popularity of the process is the importance given to the confiden-
tial information involved in the process. During the term of the process, it is kept in mind that the
confidentiality of the parties is not tampered with. The recent amendment to the Arbitration and
Conciliation Act in the year 2019 in India makes the parties in the arbitration duty-bound to keep
the utmost confidentiality of the process.
5. Binding
The decision made at the end of the arbitration process draws a sense of culmination because
of several factors such as the agreement between the parties, the inclusion of legality, the non-
appealable conditions of the arbitral award, etc.
Therefore arbitration is preferred over most of the other forms of ADR because it provides a sense
of surety. Furthermore, the arbitral awards are enforceable which makes arbitration a binding
process.
STATUTORY CONSIDERATIONS IN ARCHITECTURE
Building codes are a series of ordinances enacted by a state or local governmental entity, establishing min
mum requirements that must be met in the construction and maintenance of buildings.
This is an introduction to various building codes in professional practice emphasizing the importance of
codes and regulations to protect public health, safety and welfare and to ensure compliance with the local
authority.
PURPOSE OF CODES
The government establishes requirements and standards to protect people from unsafe living and working
conditions which resulted in a recommendation that a NATIONAL BUILDING CODE be prepared to unify
the building regulations throughout the country.
The codes includes various aspect for regulation on design & construction:
The National Building Code of India (NBC), (a comprehensive building Code), is a national instrument pro-
viding guidelines for regulating the building construction activities across the
country.
It serves as a Model Code for adoption by all agencies involved in building construction works be they Public
Works Departments, other government construction departments, local bodies or private construction agen-
cies.
The Code mainly contains administrative regulations, development control rules and general building re-
quirements; fire safety requirements; stipulations regarding materials, structural design and construction
(including safety); and building and plumbing services.
The National Building Code was first published in 1970 at the instance of Planning Commission and then
revised in 1983. Thereafter three major amendments were issued, two in 1987 and the third in 1997.
The Bureau of Indian Standards was established with the objective of harmonious development of standard-
ization activity in India.
This Bureau, Under the Bureau of Indian Standards Act, 1986, established Indian Standards, by a process of
consultation involving consumers, manufacturers, Government and regulatory bodies, technologists, scien-
tists and testing laboratories through duly constituted committees.
The first version of the NATIONAL BUILDING CODE was published in 1970. Since the publication in 1970
version of the NATIONAL BUILDING CODE a large number of comments and useful suggestions for modi-
fications and additions to different parts and sections of the code were received.
Schedule (referred to under Article 243W) added by the Constitution (74th Amendment) Act, 1992 w.e.f
01.06.1993),
1. Urban planning including town planning.
2. Regulation of land use and construction of buildings
3. Planning for economic and social development
4. Roads and bridges
5. Water supply for domestic, industrial and commercial purposes.
6. Public health , sanitation conservancy and solid waste
7. Fire services
8. Urban forestry, protection of the environment and promotion of ecological aspects.
9. Safeguarding the interests of weaker sections of society, including the handicapped and mentally retarded.
10. Slum improvement and upgradation
11. Urban poverty alleviation.
12. Provision of urban amenities and facilities such as parks, gardens, playgrounds.
13. Promotion of cultural, educational and aesthetic aspects.
14. Burials and burial grounds; cremations, cremation grounds; and electric crematoriums.
15. Cattle ponds; prevention of cruelty to animals.
16. Vital statistics including registration of births and deaths.
17. Public amenities including street lighting, parking lots, bus stops and public conveniences.
18. Regulation of slaughter houses and tanneries.
AUTHORITIES HAVING JURISDICTION
1) Municipal Corporation
2) Municipality
3) Notified Area Committee
4) Town Area Committee
5) Cantonment Board
6) Township
7) Port Trust
8) Special Purpose Agency like:
▪ Town improvement trusts.
▪ Urban development authorities.
▪ Water supply and sewerage boards.
▪ Housing boards.
▪ Pollution control boards.
▪ Electricity supply boards.
▪ City transport boards.
PROFESSIONAL PRACTICE II: NATIONAL BUILDING CODE Salient Features of NBC 2016
PROFESSIONAL PRACTICE II: NATIONAL BUILDING CODE Salient Features of NBC 2016
PART 1 : DEFINITIONS
It lists the terms appearing in all the parts/sections of the National Building Code of India. However, some
common definitions are reproduced in this part also.
PART 2: ADMINISTRATION
It covers :
The development control rules and general building requirements for proper planning and design at the
layout and building level to
ensure health safety, public safety and desired quality of life.
Provides provisions for covered area, plinth area, FAR, amenities, land use classification, height/ size of
rooms, kitchens etc.
It covers the requirements of building materials and components, and criteria for accepting new or alterna-
tive building materials and components.
Each team to be multi disciplinary team of need based professionals, depending upon type, size, magnitude,
complexity in the project; such as:
STRUCTURED APPROACH
Stages in Building Permit Process
1. Submission of application by owner along with
-Building plan
-Service plan
-Specifications
-Structural design sufficiency certificate by engineer/
structural engineer and owner
-Certificate of engagement of builder/constructor (
-Certificate of supervision by architect/engineer
It covers the administrative aspects of the Code, such as applicability of the Code, organization of building
department for enforcement of the Code, procedure for obtaining development and building permits, and
responsibility of the owner and all professionals involved in the planning, design and construction of the
building.
Ease of doing business through detailed and updated provision for streamlining
the approval process in respect of different agencies in the form of an
integrated approval process through single window approach , thereby
avoiding separate clearances from various authorities.
Updated provision on computerization of approval process
Reinforcement of the provisions on the mechanism of ensuring certification of
structural safety of buildings by the competent professional and peer review of
design of buildings.
Fixation of responsibility for geotechnical engineer and contractor , where
involved in a building construction project.
This Part deals with the development control rules and general building requirements to ensure health and
safety of the public.
FIRE PREVENTION
LIFE SAFETY
FIRE PROTECTION
LIFE SAFETY
Exit requirements
Occupant load
Egress components
Exit capacities and
arrangement
No. of exits
Max. travel distance
Doorways, corridors &
passageways
Staircases pressurization
Ramps
Compartmentation
Smoke control
Illumination/escape lighting
Fire detection & alarm
system
Fire fighting shaft
FIRE PROTECTION
FIRE PREVENTION
◆ Table 1 on fire resistance ratings of structural and non-structural elements has been updated.
◆ Detailed provisions on fire separating walls, fire separating floors and fire partitions
◆ Separate comprehensive clause on electrical power supply distribution for fire and life safety
systems
◆ Detailed provisions on air conditioning systems towards safety and smoke control integration
◆ Glass façade requirements have been detailed towards fire protection and
smoke exhaust aspects
◆ Comprehensive clause on Fire Command Centre (FCC)
Erstwhile Table 23 on minimum requirements for fire fighting installations
(now Table 7 ) comprehensively
Detailed provisions have been included on fire water storage , fire pump
room , sprinkler system and various alternative fire suppression systems .
Detailed provisions on the concept of progressive evacuation in case of
hospital buildings.
Provisions on refuge area have been updated including for D 6 occupancy
and introduced for apartment buildings of height 60 m and above
Provisions specific to atrium , commercial kitchen and car parking
facilities
Provisions specific to Metro Stations and Metro Railways
LIFE SAFETY
◆ Components of means of egress - exit access, exit and exit discharge
◆ Table on capacity factors - modified based on the aspect of width per person approach used
globally
◆ Requirement for displaying the occupancy load for assembly buildings and call centres.
◆ Well integrated provisions on firefighting shaft to access the floor on fire and also allows
egress/evacuation of the occupants with simultaneous use of refuge area.
◆ Updated provisions on compartmentation with fire barrier and its passive fire safety
requirements for respective occupancies.
CATEGORIES OF MATERIALS
2016 Seismic
Zoning Map
Part 6/Sec 3B Bamboo
Updated design provisions for
• bamboo trusses, and
• bamboo foundations.
Inclusion of provisions relating to use of
• bamboo as reinforcement in concrete,
• bamboo based materials/panel products as walling/roofing material, and
Inclusion of requirements for high speed lifts and lifts for tall
buildings including elaboration of lifts for fire fighting and
emergency evacuation and inclusion of considerations for machine
room less (MRL)
Updation of preliminary design provisions for lifts to cover the
requirements for various building functions.
Inclusion of provisions for seismic resistance aspects in lifts.
This new chapter on escalators and moving walks covers all aspects
relating to their
•Planning;
•Installation;
•Operation, maintenance; and
•Inspection for ensuring safe movement of people with satisfactory performance.
Updation of the new Part 11 ‘Approach to Sustainability’ which was added to NBC 2005 through its Amend-
ment No. 1 for covering guidelines for making buildings and built environment energy
efficient and environmentally compatible.
Covers all aspects of energy conservation such as electrical energy conservation, water conservation, use of
low embodied energy materials, renewable energy utilization, etc.
The chapter is intended to help in meeting relevant sustainable development goals (SDG) laid down by the
United Nations .
CONCLUSION
What it means?
An easement is a part of your land that can be used without your consent, such as by utility companies.
An easement is an interest in a real estate property or parcel of land. If you grant someone an easement, you
are giving them the right to use your property in some way, without giving them actual ownership over it.
Right of easement is basically a form of PRIVILEGE the integral part of which is to do an act or prevent cer-
tain acts on some other land for enjoyment of one’s own land.
The concept of easement has been defined under SECTION 4 of The Indian Easements Act, 1882.
What it means?
Various easement rights
Disturbance of easement
Any type of interference for peaceful enjoyment of easement rights acquired by the dominant
owner is called disturbance
Building Byelaws
It is the strict rules which must be obeyed by everyone. If everyone makes buildings without obeying any
rules then there will be problems of:
Zones
Details to be included:
Basement
Building Structure
Ramps under roof
Covered services area
Covered swimming pool
Carpet Area
V
Net usable area within building
To calculate carpet area deduct following areas from plinth area:
❖ Lift well
❖ Thickness of wall
❖ Vertical shafts for services
❖ Any cut-out in floor plate
Floor Space Index (FSI) or Floor Area Ratio (FAR)
It is a Centralized Regulatory Body which will have powers equal to Quasi Courts “ and will regulated all
matters related to real estate development & growth in India.
Each & Every real estate project, developers & real Estate agents in India has been “ Compulsorily “ have to
be registered as per well drafted procedures with RERA.
Developers or Agents will not able to offer any real estate project or products to customers & investors with-
out registering themselves & the said project or product
Real Estate Developers, projects & Agents will be charged Penalty in tune of amount equal to 10% of project
cost or imprisonment of 3 years or Both depending upon case to case basis.
7. Informal process
In the process of arbitration, the selection of the arbitrator is based on the choice of the parties.
The setting during the time of the procedure is informal and is suitable for discussion. Unlike, the
courtroom where a level of formality has to be maintained arbitration allows the friendly ex-
change of words without much mannerisms to be followed.
8. Prevention of hostility
Since the process of arbitration includes within its scope discussion and solving the issue at hand
amicably, therefore hostility is prevented. Unlike, the process of the court, where there are open
argumentation and hurling of accusations, arbitration incites amicable discussion.
10. Control
The parties in a dispute have greater control over the process of arbitration than that of any other
dispute resolution process this is because of the fact that the from the starting the parties are in a
position of control. The parties are directly involved in the decision- making process through their
consent to the agreement.
Disadvantages of Arbitration:
1) There is a small scope of appeal in the arbitration award. The very fact that there is less scope
of appeal in awards is one of the most glaring disadvantages of arbitration. whenever there is a
problem with the award, there would be no scope of appealor correction.
2) There are varied guidelines of arbitration and it is very difficult to choose among those guide-
lines. Similarly, there are a number of institutions providing the facility of arbitration, it becomes
very difficult to choose among the organizations.
3) In some countries, there are different statutes for domestic and international arbitration. This
makes it difficult to ascertain the applicability of the laws relating to international arbitration.
4) If arbitration is binding, both sides give up their right to an appeal that means there is no real
opportunity to correct what one party may feel is an erroneous arbitration decision
5) If the matter is complicated but the amount of money involved is modest, then the arbitrator’s
fee may make arbitration uneconomical, that means there is no real opportunity to correct what
one party may feel is an erroneous arbitration decision
1. Arbitration is consensual
Arbitration can only take place if both parties have agreed to it. In the case of future disputes aris-
ing under a contract, the parties insert an arbitration clause in the relevant contract. An existing
dispute can be referred to arbitration by means of a submission agreement between the parties.
In contrast to mediation, a party cannot unilaterally withdraw from arbitration.
2. Arbitration Agreement
Arbitration agreement means an agreement by the parties to submit to arbitration all or certain
disputes which have arisen or which may arise between them in respect of a defined legal rela-
tionship, whether contractual or not.
It may be in the form of an arbitration clause in a contract or in the form of a separate agree-
ment
PROPERTY VALUE
What it means?
2. Its scrap or salvage value of the asset (the price you think you can sell it
for at the end of its useful life)
3. The useful life of the asset (how many years you think it will last)
To calculate the straight-line depreciation rate for your asset, simply subtract
the salvage value from the asset cost to get total depreciation, then divide
that by useful life to get annual depreciation:
annual depreciation = (purchase price - salvage value) / useful life
2. Sinking fund method
Sinking fund method is a method of calculating depreciation for an asset in
which apart from calculating depreciation, it also keeps aside a fund for
replacing the asset at the end of its useful life.
This method is used when the assets that need to be replaced are of high cost.
To avoid paying for the replacement of assets at a time, companies maintain a
sinking fund that will help them recover the cost of the asset while also
accounting for its depreciation.
How Sinking Fund functions:
Sinking fund functions as an account where the company stores funds in
anticipation that it will become dysfunctional after a certain point of time.
Instead of expenditure that will arise at a time which can cause a significant
impact on company’s profit, it is better that such an expense can be anticipated
and the funds for replacement of such an asset can be made wisely.
3. Reducing Balance method
The reducing balance method is an accelerated depreciation system of
recording larger depreciation expenses during the earlier years of an asset's
useful life and recording smaller depreciation expenses during the asset's later
years.
The reducing balance method of depreciation is most useful when an asset has
higher utility or productivity at the start of its useful life, as it results in
depreciation expenses that reflect the assets' productivity, functionality, and
capacity to generate revenue.
The reducing-balance method, also known as the declining- balance method, in
the initial years of an asset’s “service.” As with the straight-line method, you
apply the same depreciation rate each year to what’s called the “adjusted
basis” of your property. But unlike straight-line, with the reducing-balance
method, you’ll be depreciating a different amount each year as the balance
diminishes.
Computing Valuation:
Methods Valuation:
1. Land & building method
2. Composite rate method
3. Development potential method 4. Rent capitalization method
5. Profit capitalization method
6. Market-Rent-Profit method
2. The Building and Other Construction Workers’ Welfare Cess Act (Cess
Act).
All such statutes stand for the good running of a business organization as well
as for building up healthy relation among the employer and employee as well.
Hence, both of them must be aware of their rights and responsibilities and not to
violate the said statutes for their personal gains.
Registration of establishments
The employer of an establishment to which this Act applies and to which this Act
may be applicable at any time is required to make an application in the
prescribed form with prescribed fee for the registration of his establishment
within a period of sixty days of the commencement of the Act or within sixty
days from the date on which this Act becomes applicable to the establishment.
In case, any change occurs in the ownership or management or other
prescribed particulars in respect of such establishment, the particulars
regarding such change shall be intimated by the employer to the registering
officer within thirty days of such change in such form as may be prescribed.
Revocation of registration
The registration of any establishment has been obtained by misrepresentation
or suppression of any material fact or that the provisions of this Act are not
being complied with in relation to any work carried on by such establishment, or
that for any other reason the registration has become useless or ineffective and,
therefore, requires to be revoked, he may, after giving an opportunity to the
employer of the establishment to be heard, revoke the registration.
Wages of construction laborers in India:
There are two methods of making wage payments to labourers:
• Time rate system
• Piece rate system
Not only does construction site safety decrease the risk of injuries to the public,
but it also reduces the risk of work-related injuries and accidents.
Nearly a quarter of all work-related fatalities occur in the construction industry,
and many more injuries that do not lead to death occur as well.
The Building and other Construction workers (Regulation of Employment
and conditions of Service) Act, 1996
The Building and other Construction workers (Regulation of Employment
and conditions of Service) Central Rules, 1998
Salient features of the Safety & Health Provisions
Objectives
❖To regulate the employment & conditions of Service
❖To provide for Safety, Health & Welfare measures
❖To give the Building & Construction workers Social Security
Applicability
Every establishment which employs or had employed ten or more workers
directly or through a Contractor / Subcontractor (undertaking to produce a given
result or supplying building workers for any work of the establishment, excluding
supply of goods or articles of manufacture)
Responsibilities of Employer
❖It shall be the duty of every employer to comply with requirements of rules
❖Employer shall not permit an employee to do anything not in accordance with
the generally accepted principles of standard safe operating practices
connected with building and other construction work
❖Employer will not allow lifting appliances, lifting gear, lifting device, transport
equipment, vehicles or any other device or equipment to be used by the building
workers which does not comply with provision of rules
❖Employer shall maintain the latrines, urinals, washing facilities and canteen in
a clean and hygienic condition
SAFETY AND HEALTH
GENERAL PROVISIONS
Fire protection
❖An employer shall ensure that site is provided with fire extinguishing
equipment sufficient to extinguish any probable fire
❖Number of trained persons required to operate the fire extinguishing
equipment
❖Fire extinguishers shall be properly maintained and inspected at regular
intervals of not more than one year
❖Every launch or boat or other craft used for transport of building workers and
the cabin of every lifting appliances including mobile crane, adequate number of
portable fire-extinguishing equipment of suitable type shall be provided
Emergency Action Plan
❖Where more than 500 building workers are employed emergency action plan
to handle the emergencies is prepared and submitted for the approval of the
Director General
Dust, gases, fumes etc.
❖An employer shall prevent concentration of dust, gases or fumes by providing
suitable means to control their concentration within the permissible limit so that
they may not cause injury or pose health hazard to building worker
Corrosive substances
❖Corrosive substances, including alkalis and acids, shall be stored in such a
manner that it does not endanger the building worker
❖Suitable protective equipment shall be provided during handling or use of
such substances
❖In the case of spillage of such substances on the building worker, immediate
remedial measures shall be taken by the employer
Eye protection
❖Suitable personal protective equipment for the protection of eyes shall be
provided
❖Building worker engaged in operations like welding, cutting, chipping, grinding
or similar operations which may cause hazard to his eyes shall use such eye
protection
SAFETY ORGANISATION
Safety committee
• Establishments, wherein 500 or more building workers are ordinarily
employed, safety committee shall be constituted by employer represented by
equal number of representative of employer and building worker
• Safety committee shall meet at regular intervals at least once in a month and
shall be chaired by person having overall control over affairs of site
Safety officer
❖Establishment wherein 500 or more building worker are employed, employer
shall appoint safety officer
❖Safety officer may be assisted by suitable and adequate staff
Reporting of accident
❖Notice of any accident on the construction site which either causes loss of life
or disables a building worker from working for a period of forty eight hours or
more immediately following the accident, shall forthwith be sent to
➢Regional Labour commissioner (Central) board with which the building worker
involved in accident was registered as a beneficiary
➢Director general and next in kin or other relative
❖Notice of accident at construction site which causes loss of life or disables
such building worker from work for more than ten days following the accident
shall also be sent to:
➢Office incharge of nearest police station ➢district magistrate
MEDICAL FACILITIES
Medical examination of building workers
• Building worker who is employed for a work involving risk or hazards as the
Director General considers appropriate shall be medically examined
• Every operator of a crane, winch or other lifting appliances, transport
equipment or vehicle shall be medically examined and again periodically
• No building worker shall be charged for medical examination Record of such
medical examination shall be maintained
Ambulance Van
An ambulance van shall be provided or an arrangement shall be made with a
nearby hospital for providing such ambulance van for transportation of serious
cases of accident or sickness of the building workers to the hospital promptly
and such van is maintained in good repair and is equipped with standard
facilities
First-aid
• Sufficient number of first-aid boxes or cupboards shall be provided and
maintained
• The box should be distinctly marked “First-aid” and shall be equipped with
specified articles
• Trained first-aider shall be engaged at site
WELFARE
Latrines and urinal accommodation
❖Adequate number of Latrines and urinals to be provided at construction site
❖Conveniently situated and accessible to building workers at all times
❖Adequately lighted and shall be maintained in clean and sanitary condition
❖Those connected with flush sewage system shall comply with requirement of
public health authorities
Canteens
❖In every place wherein not less than 250 workers are employed, the employer
shall provide adequate canteen in specified manner
❖Canteen shall consist of dining hall with sufficient furniture, kitchen, store-
room, pantry and washing places
❖Sufficiently lighted at all times when any person has access to it
❖Premises shall be maintained in clean and sanitary condition
Drinking Water
Employer shall ensure sufficient supply of wholesome drinking water
All such points shall be legibly marked “Drinking Water” in a language
understood by a majority of the persons
No such point shall be situated within six metres of any washing place, urinal or
latrine
PENLTIES
Penalty for contravention of provisions regarding safety measures
• Whoever contravenes the provisions of any rules shall be punishable with
imprisonment for a term which may extend to three months, or with fine which
may extend to two thousand rupees, or with both
• If any person who has been convicted of any offence punishable is again
guilty of an offence, he shall be punishable on a subsequent conviction with
imprisonment upto six months or with fine upto two thousand rupees or with
both