0% found this document useful (0 votes)
221 views8 pages

Block Masonry Rate Analysis

This document provides market rates for various types of hollow block masonry work in Khyber Pakhtunkhwa, Pakistan for 2020. It includes rates for hollow block masonry walls up to 20 feet height using different cement-sand mortar ratios (1:8, 1:2, 1:3, 1:4) and hollow blocks of varying sizes. The rates are given per 100 cubic feet and include costs for materials, labor, contractor profit, overhead costs and taxes. Material costs make up 57.14-60.06% of the composite rates while labor accounts for 20.44-23.36%. The composite and labor-only rates vary based on the cement-sand ratio and block

Uploaded by

Ali shahzad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
221 views8 pages

Block Masonry Rate Analysis

This document provides market rates for various types of hollow block masonry work in Khyber Pakhtunkhwa, Pakistan for 2020. It includes rates for hollow block masonry walls up to 20 feet height using different cement-sand mortar ratios (1:8, 1:2, 1:3, 1:4) and hollow blocks of varying sizes. The rates are given per 100 cubic feet and include costs for materials, labor, contractor profit, overhead costs and taxes. Material costs make up 57.14-60.06% of the composite rates while labor accounts for 20.44-23.36%. The composite and labor-only rates vary based on the cement-sand ratio and block

Uploaded by

Ali shahzad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

GOVERNMENT OF KHYBER PAKHTUNKHWA

MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-40-g Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:8 cement sand
mortar using Hollow Block 16"x8"x8" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 1.33000 Bag 550.00 1 Bag 731.50

Water Charges for 541.90802 Ltr 0.25 1 Ltr 135.48


Construction
Coarse Sand 13.30000 Cft 2,600.00 100 Cft 345.80

Hollow Block 16" x 8" x 170.00000 No 46.40 1 No 7,888.00


8"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 57.14 % 9,260.78

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.00000 Day 600.00 1 Day 1,200.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 99.00

TOTAL LABOUR 23.36 % 3,399.00

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 2,449.35


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 15,109.13 Per CUM : Rs 5,335.74

Labour Rates Per 100Cft Rs. 4,042.50 Per CUM : Rs 1,427.60

735
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-a Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:2 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 4.80000 Bag 550.00 1 Bag 2,640.00

Water Charges for 785.52002 Ltr 0.25 1 Ltr 196.38


Construction
Coarse Sand 12.00000 Cft 2,600.00 100 Cft 312.00

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 60.06 % 13,208.38

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 20.44 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,323.26


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 20,480.66 Per CUM : Rs 7,232.69

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

736
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-b Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:3 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 3.60000 Bag 550.00 1 Bag 1,980.00

Water Charges for 744.65997 Ltr 0.25 1 Ltr 186.16


Construction
Coarse Sand 13.50000 Cft 2,600.00 100 Cft 351.00

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 59.39 % 12,577.16

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 21.11 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,200.18


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 19,726.36 Per CUM : Rs 6,966.31

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

737
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-c Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:4 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 2.88000 Bag 550.00 1 Bag 1,584.00

Water Charges for 720.14398 Ltr 0.25 1 Ltr 180.04


Construction
Coarse Sand 14.40000 Cft 2,600.00 100 Cft 374.40

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 58.97 % 12,198.44

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 21.53 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,126.33


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 19,273.78 Per CUM : Rs 6,806.48

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

738
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-d Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:5 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5"
wall thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 2.40000 Bag 550.00 1 Bag 1,320.00

Water Charges for 703.79999 Ltr 0.25 1 Ltr 175.95


Construction
Coarse Sand 15.00000 Cft 2,600.00 100 Cft 390.00

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 58.67 % 11,945.95

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 21.83 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,077.09


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 18,972.06 Per CUM : Rs 6,699.93

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

739
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-e Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:6 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 2.06000 Bag 550.00 1 Bag 1,133.00

Water Charges for 692.18402 Ltr 0.25 1 Ltr 173.05


Construction
Coarse Sand 15.40000 Cft 2,600.00 100 Cft 400.40

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 58.45 % 11,766.45

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 22.05 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,042.09


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 18,757.55 Per CUM : Rs 6,624.17

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

740
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-f Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:7 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 1.80000 Bag 550.00 1 Bag 990.00

Water Charges for 683.60400 Ltr 0.25 1 Ltr 170.90


Construction
Coarse Sand 15.90000 Cft 2,600.00 100 Cft 413.40

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 58.29 % 11,634.30

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 22.21 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 3,016.32


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 18,599.64 Per CUM : Rs 6,568.41

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61

741
GOVERNMENT OF KHYBER PAKHTUNKHWA
MRS CELL COMMUNICATION & WORKS DEPARTMENT

MARKET RATE SYSTEM 2020 - KPK

CHAPTER NO. 07 , BRICK MASONRY

DESCRIPTION OF ITEM : Spec. No : 6.22

Item Code : 07-41-g Unit (British) : 100Cft

Item Name : Hollow Block Masonry in walls upto 20 feet height in 1:8 cement sand
mortar using Hollow Block 16"x8"x6" factory manufactured with 1.5" wall
thickness and strenght of 1200 psi.

Detail Qty Unit Rate (Rs) Amount

MATERIAL
Ordinary Portland Cement 1.60000 Bag 550.00 1 Bag 880.00

Water Charges for 676.56000 Ltr 0.25 1 Ltr 169.14


Construction
Coarse Sand 16.00000 Cft 2,600.00 100 Cft 416.00

Hollow Block 16" x 8" x 225.00000 No 44.00 1 No 9,900.00


6"
Scaffolding (for Brick) 20.00000 Sft 800.00 100 Sft 160.00

TOTAL MATERIAL 58.15 % 11,525.14

LABOUR
Mason 1.50000 Day 1,200.00 1 Day 1,800.00

Labourer 2.89000 Day 600.00 1 Day 1,734.00

Water Man 0.50000 Day 600.00 1 Day 300.00

Sundries (Labour Only): 3.00 % 115.02

TOTAL LABOUR 22.35 % 3,949.02

Contractor Profit 10% + Over Heads on(M+L+E) 2% + 19.50 % 2,995.03


Income Tax 7.5%

Composite Rates Per 100Cft Rs. 18,469.19 Per CUM : Rs 6,522.34

Labour Rates Per 100Cft Rs. 4,696.65 Per CUM : Rs 1,658.61