0% found this document useful (0 votes)
26 views12 pages

Assignment 4

The document discusses investment project evaluation for two projects, Project A and Project B. It calculates various metrics to evaluate the projects including regular payback period, discounted payback period, net present value (NPV) at different cost of capital rates, crossover rate, and modified internal rate of return (MIRR). The key findings are: - Project B has a shorter regular and discounted payback period. - If the projects are independent, both should be undertaken as both have positive NPV. - At a 5% cost of capital, Project A has a higher NPV and should be undertaken if mutually exclusive. - At a 15% cost of capital, Project B has a higher

Uploaded by

Anthony Singogo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views12 pages

Assignment 4

The document discusses investment project evaluation for two projects, Project A and Project B. It calculates various metrics to evaluate the projects including regular payback period, discounted payback period, net present value (NPV) at different cost of capital rates, crossover rate, and modified internal rate of return (MIRR). The key findings are: - Project B has a shorter regular and discounted payback period. - If the projects are independent, both should be undertaken as both have positive NPV. - At a 5% cost of capital, Project A has a higher NPV and should be undertaken if mutually exclusive. - At a 15% cost of capital, Project B has a higher

Uploaded by

Anthony Singogo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Copperbelt University

Directorate of Distance Education and Open Learning

Assignment 4

Anthony Singogo

SIN: 22900601

Master’s in business administration (General)

GBS 621: Corporate Finance

Dr. Izidin El Kalak

2023-11-14
1
Assignment

Your division is considering two investment projects, each of which requires an up-front

expenditure of $25 million. You estimate that the cost of capital is 10% and that the

investments will produce the following after-tax cash flows (in millions of dollars):

Year Project A Project B

1 5 20

2 10 10

3 15 8

4 20 6

1. What is the regular payback period for each of the projects?

Payback = number of unrecovered cost


Years prior to + at start of year
Full recovery Cash flow during the recovery year

Payback

Project A
Year 0 1 2 3 4
Cashflow $ (25.00) $ 5.00 $ 10.00 $ 15.00 $ 20.00
Cumulative
CF $ (25.00) $ (20.00) $ (10.00) $ 5.00 $ 25.00
2
Assignment

Payback=2+10/15

2.67 Years 2.67 Years

Project B

Year 0 1 2 3 4

Cashflow $ (25.00) $ 20.00 $ 10.00 $ 8.00 $ 6.00

Cumulative

CF $ (25.00) $ (5.00) $ 5.00 $ 13.00 $ 19.00

Payback=1+5/10

1.5 Years 1.5 Years

Recommendation: with a regular payback evaluation Project B with 1 year and 6

Months would be selected as opposed to Project A with a 2.67 Year.

2. What is the discounted payback period for each of the projects?

Payback

Project A

Year 0 1 2 3 4

Cashflow $ (25.00) $ 5.00 $ 10.00 $ 15.00 $ 20.00


3
Assignment

Discounted CF $ (25.00) $ 4.55 $ 8.26 $ 11.27 $ 13.66

Cumulative Discounted

CF $ (25.00) $ (20.45) $ (12.19) $ (0.92) $ 12.74

Payback=3+$0.92/13.66

3.07 Years 3.07 Years

Project B

Year 0 1 2 3 4

Cashflow $ (25.00) $ 20.00 $ 10.00 $ 8.00 $ 6.00

Discounted CF $ (25.00) $ 18.18 $ 8.26 $ 6.01 $ 4.10

Cumulative Discounted

CF $ (25.00) $ (6.82) $ 1.45 $ 7.46 $ 11.55

Payback=1+$6.82/8.26

1.83 Years $ 1.83 Years

Using discounted cash flows, Project B maintains the shorter payback period, hence if

Project A and B mutually exclusive Project B would be selected over Project A.


4
Assignment
3. If the two projects are independent and the cost of capital is 10%, which

project or projects should the firm undertake?

Project A

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow after tax 5.00 10.00 15.00 20.00

Cost of Capital 10%

PV 4.55 8.26 11.27 13.66

SUM OF PV 37.74

INITIAL OUTLAY (25.00)

PV 12.74

Project B

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow 20.00 10.00 8.00 6.00


5
Assignment
Cost of Capital 10%

PV 18.18 8.26 6.01 4.10

SUM OF PV 36.55

INITIAL OUTLAY (25.00)

PV 11.55

If the two Projects are independent the firm should undertake both Project A and Project

B because NPV for both Projects exceed zero or they all have a positive NPV.

4. If the two projects are mutually exclusive and the cost of capital is 5%, which

project should the firm undertake?

Project A

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow after tax 5.00 10.00 15.00 20.00

Cost of Capital 5%

PV 4.76 9.07 12.958 16.454


6
Assignment
SUM OF PV 43.24

INITIAL OUTLAY (25.00)

PV 18.24

Project B

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow 20.00 10.00 8.00 6.00

Cost of Capital 5%

PV 19.05 9.07 6.91 4.94

SUM OF PV 39.96

INITIAL OUTLAY (25.00)

PV 14.96

Provided that Project A and Project B are mutually exclusive, then the firm should a

project with a higher NPV, in this case it is Project A.


7
Assignment
5. If the two projects are mutually exclusive and the cost of capital is 15%, which

project should the firm undertake?

Project A

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow after tax 5.00 10.00 15.00 20.00

Cost of Capital 15%

PV 4.35 7.56 9.863 11.435

SUM OF PV 33.21

INITIAL OUTLAY (25.00)

PV 8.21

Project B

Year 0 1 2 3 4

Initial outlay (25.00)

Cash flow 20.00 10.00 8.00 6.00


8
Assignment
Cost of Capital 15%

PV 17.39 7.56 5.26 3.43

SUM OF PV 33.64

INITIAL OUTLAY (25.00)

PV 8.64

The firm is recommended to undertake Project B with NPV 8.64 higher than NPV 8.21

for Project A.

6. What is the crossover rate?


9
Assignment
NPV Profile
Discount rate NPV of A NPV of B

0.00 25.00 25.00

0.05 18.24 14.96

0.10 12.74 11.55

0.15 8.21 8.64

0.20 4.44 6.13

0.25 1.27 3.95

0.30 (1.41) 2.04

NPV PROFILE
30.00
25.00
20.00
15.00
NPV

10.00
5.00
-
(5.00) 0.00 0.05 0.10 0.15 0.20 0.25 0.30
Discount rate

NPV of A NPV of B

Using the graph, the crossover rate is 12.4%

7. If the cost of capital is 10%, what is the modified IRR (MIRR) of each project?

At 10% cost of capital. Using excel Project A MIRR= (C6:G7, B8, B8) = 22%
10
Assignment

At 10% cost of capital. Using excel Project B MIRR= (C17:G18, B19, B19) = 21%

References

Ehrhardt, M. (2017). Corporate finance: A focused approach (6th Ed.). Boston, MA:

Cengage Learning. ISBN 9781305637108.


11
Assignment

You might also like