The document describes the forward and backward pass computations for a construction project using the critical path method. It lists the activities in the project, their durations, predecessors, and calculations for the early start, early finish, late finish, and late start of each activity. It identifies activity A to V as being on the critical path and includes a precedence table outlining the activities, descriptions, durations, and predecessor relationships.

Uploaded by

Alcris Carino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views7 pages

COMPUTATIONS

The document describes the forward and backward pass computations for a construction project using the critical path method. It lists the activities in the project, their durations, predecessors, and calculations for the early start, early finish, late finish, and late start of each activity. It identifies activity A to V as being on the critical path and includes a precedence table outlining the activities, descriptions, durations, and predecessor relationships.

Uploaded by

Alcris Carino
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

COMPUTATIONS

FORWARD PASS COMPUTATION


FORMULA FOR FORWARD PASS:
EF = ES + D

ACTIVITY A
A-ES=0
EF=0+2=2

ACTIVITY A
B- ES=2
EF=2+4=6

ACTIVITY A
C- ES=6
EF=6+2=8

ACTIVITY A
D- ES=8
EF=8+12=20

ACTIVITY A
E- ES=8
EF=8+4=12

ACTIVITY A
F- ES=20
EF=20+3=23

ACTIVITY A
G- ES=23
EF=23+3=26

ACTIVITY A
H- ES=26
EF=26+2=28

ACTIVITY A
I- ES=28
EF=28+12=40

ACTIVITY A
J- ES=40
EF=40+4=44

ACTIVITY A
K- ES=44
EF=44+1=45

ACTIVITY A
L- ES=40
EF=40+2=42

ACTIVITY A
M- ES=45
EF=45+3=48

ACTIVITY A
N- ES=42
EF=42+10=52

ACTIVITY A
O- ES=52
EF=52+8=60

ACTIVITY A
P- ES=60
EF=60+2=62

ACTIVITY A
Q- ES=62
EF=62+8=70

ACTIVITY A
R- ES=62
EF=62+8=70
ACTIVITY A
S- ES=70
EF=70+10=80

ACTIVITY A
T- ES=80
EF=80+2=82

ACTIVITY A
U- ES=82
EF= 82+12=94

ACTIVITY A
V- ES= 94
EF= 94+2=96
BACKWARD PASS COMPUTATION
FORMULA FOR BACKWARD PASS:
LS = LF – D
FORMULA FOR FLOAT:
F = LF - EF
V-LF=96
LS=96-2=94
FLOAT FOR V
F=96 – 96 =0
U- LF=94
LS=94-12=82
FLOAT FOR U
F=94-94=0

T- LF=82
LS=94-2=92
FLOAT FOR T
F=94-82=12
S- LF=80
LS=80-10=70
F=80-80=0
R- LF=80
LS=80-8=72
F=80-70=10
Q- LF=70
LS=70-8=62
F=70-70=0
P- LF=62
LS=62-2=60
F=62-62=0
O- LF=60
LS=60-8=52
F=60-60=0
N- LF=52
LS=52-10=42
F=52-52=0
M- LF=60
LS=60-3=57
F=60-48=12
L- LF=42
LS=42-2=40
F=42-42=0
K- LF=52
LS=52-1=51
F=52-45=7
J- LF=51
LS=51-4=47
F=51-44=7
I- LF=40
LS=40-12=28
F=40-40=0
H- LF=28
LS=28-2=26
F=28-28=0
G- LF=26
LS=26-3=23
F=26-26=0
F- LF=23
LS=23-3=20
F=23-23=0
E- LF=20
LS=20-4=16
F=20-12=8
D- LF=20
LS=20-12=8
F=20-20=0
C- LF=8
LS=8-2=6
F=8-8=0
B- LF=6
LS=6-4=2
F=6-6=0
A- LF=2
LS=2-2=0
F=2-2=0

CRITICAL PATH
A,B,C,D,F,G,H,I,L,N,O,P, S, Q,U,V

PRECEDENCE TABLE
ACTIVITY DURATIO PREDECESSO
ACTIVITY DESCRIPTION
MARK N R
A MOBILIZATION 2
B PURCHASE OF MATERIALS 4 A
C SITE CLEARING AND GRADING 2 A,B
D LAY-OUT AND EXCAVATION 12 B,C
E PREPARATION OF FORMS AND REBARS 4 B,C
F CONCRETING OF FOOTINGS 3 D,E
G CONCRETING OF COLUMNS 3 E,F
H CONCRETING OF WALL FOOTINGS 2 E,F,G
I INSTALLATION OF CHB WALLSINTERIOR & EXTERIOR() 12 E,G,H
J ROUGHING-IN OF PLUMBING AND ELECTRICAL 4 G,I
K CONCRETING OF SLAB ON FILL 1 I,J
L CONCRETING OF ROOF BEAMS 2 G,I
M INSTALLATION DOOR JAMBS AND WINDOW FRAMES 3 I,J,K
N INSTALLATION OF ROOF FRAMING SYSTEMS AND ROOFING 10 I,L
O PLASTERING AND FLOOR TOPPING WORKS 8 I,K,N
P INSTALLATION OF DOORS AND WINDOWS 2 M,N,O
Q TILE WORKS 8 N,O,P
R CEILING WORKS (FRAMING & CEILING) 8 N,O,P
S CLOSET AND CABINET WORKS 10 N,O,P,Q
T INSTALLATION OF PLUMBING AND ELECTRICAL FIXTURES 2 O,Q,R,S
U PAINTING WORKS 12 N,O,P,Q,R,S,T
V CLEAN-UP AND DEMOBILIZATION 2 U