Bill of Quantities & Price Schedule - Civil & Structure Works
Bill of Quantities & Price Schedule - Civil & Structure Works
Sub
Description of Items Amount
Head
1 EARTHWORK 3,589,558
9 DISMANTLING WORK -
b Discount NIL
c vat included
Note: The Reinforcement Steel, Cement, Coupler and Wooden door frames shall be supplied by
the Client Free of Cost.
Bill Of Quantities Price Schedule
1.1.1 All kinds of soils for all leads and lifts cum. 18108 75 1,358,100
Excavation shall be payable only for vertical cut up to the outer edge of foundation
lean concrete as indicated in drawings through out the pit depths. Cost of extra
excavation required for working space, supporting side shuttering of foundations
and retaining walls and that required for making slopes for stability of excavation
shall be deemed to be included in the rate quoted. (Note: The Line & levels in the
drawings shall be strictly followed and excess excavation if any shall be made good 0 -
by contractor free of cost as per the instructions of the Owner) To organize the
space for stacking of excavated earth for using the same in back filling will be
responsidility of the contractor only.
1.2.1 All kinds of soils for all leads and lifts cum. 2200 135 296,993
1.3 Excavation in over areas or foundation trenches from existing natural ground
0 -
level
1.3.1 Earth work in excavation in foundation trenches, Columns pits etc. upto a
depth/width of 3 mtr. from existing natural ground level and stacking the
excavated material within the site or adjacent plots including dressing of bottom,
sides strutting, timbering, shoring, trimming of sides dewatering, all leads and lifts, 0 -
incidentals, etc. complete with ramming of bottom, surface preparation as per
specifications to receive the PCC.
Excavation shall be payable only for vertical cut up to the outer edge of foundation
lean concrete as indicated in drawings for all depths. Cost of extra excavation
required for working space, supporting side shuttering of foundations and retaining
walls and that required for making slopes for stability of excavation shall be
deemed to be included in the rate quoted. (Note: The Line & levels in the drawings
shall be strictly followed and over excavation if any shall be made good by 0 -
contractor free of cost as per the instructions of the Owner) To organize the space
for stacking of excavated earth for using the same in back filling will be
responsidility of the contractor only.
1.4.2 Supply selected/ approved earth brought from outside the site and filling the
same in plinths, back of retaining walls, foundations and trenches and spreading in
landscaping and other location as directed by the Project Manager and shall be
done in layers, not exceeding 20cm in depth and consolidating each deposited
layer by mechanical means, ramming and watering as per specifications including
transportation, cost of soil, royalty, loading, unloading, carriage to dumping spot
and all incidentals at all depths and levels, for all leads and lifts complete (Net cum. 0 250 -
consolidated area fill volume will be computed from the initial and final levels.
Volume in slopes, embankments etc. will be computed applying appropriate
formula, as per CPWD specification).
1.8 Dewatering 0 -
Dewatering of basement excavation with Pump ( the quoted rate shall including Per
providing detail design and getting it approved from the Architect / PMC,all piping, hour/per
equipments, running cost like disel, operators etc. all required for total operation.) 0 18 -
Horse
Power
Project:________________ 2 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
1.9 Soling 0 -
a. Providing, laying, ramming and compacting dry rubble stone hardcore /soling in
required consolidated thickness in sub base to required levels and lines with first
quality rubble of 90-45mm in stone aggregate including stone screening 13.2mm
size and finishing /blinding the surfaces with murrum including watering, Cum 13 2,400 31,200
consolidated in layers of 30 cm with vibratory compactor etc. complete as per
specifications, drawings and as directed by the Project Manager.
Total : 1 : 3,589,558
2.3.1 Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, pedestals / bases
cum 1335 3,800 5,073,000
of coloum, wall foundations grade slab etc.
2.3.2 Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, folded
plate stairs and landings, lintel and floor beams, girders (deep beams), RCC bands,
cantilever projections, slab of tank, arches, other non-structural elements etc. cum 3127 3,800 11,882,600
2.3.3 Columns, pillars, piers, abutments, posts and struts,wall, offset and projection of
cum 913 4,000 3,652,000
columns, etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness) cum 694 4,000 2,776,000
2.3.5 Parapets, planters, facias, fins, vertical projection of balconies, pergolas, copings,
cum 47 3,900 183,300
cills etc. (for all heights as shown in the drawing)
2.3.6 Cornics, moulding, bands, corbeling strips etc. cum 7 3,950 27,650
Extra for add or deduct for using Richer or leaner mix in place of M-25
0 -
2.4 Concrete.
2.4.1 M-20 instead of M-25 cum 0 40 -
2.4.2 M-30 instead of M-25 cum 157 80 12,560
2.4.3 M-35 instead of M-25 cum 180 120 21,600
2.4.4 M-40 instead of M-25 cum 300 160 48,000
2.4.5 M-45 instead of M-25 cum 20 200 4,000
2.4.6 M-50 instead of M-25 cum 0 240 -
2.5 Extra over item 2.3 for using RMC (Brought from outside the site) instead of
0 -
M-25 . The rate shall be inclusive cost of cement.
2.5.1 M20 grade concrete cum 0 2,000 -
2.5.2 M25 grade concrete cum 0 2,250 -
2.5.3 M30 grade concrete cum 0 2,500 -
2.5.4 M35 grade concrete cum 0 2,750 -
2.5.5 M40 grade concrete cum 0 3,000 -
2.5.6 M50 grade concrete cum 0 3,250 -
2.6 Centring and shuttering 0 -
2.6.1 Approved Marine plywood shuttering and centring for structural concrete work in
locations called for including strutting, propping, bracing, bolting, wedging, casing,
striking, removal etc. complete for any size, section, thickness. Props shall consist
of well designed steel pipes adequately braced (wooden ballies as props shall not 0 -
be permitted). The item to include centering and shuttering at all heights and levels.
Allow for forming grooves, drip course, chamfers, cut-outs, openings etc. where
called for and for dressing with approved shuttering oil to prevent adhesion.
Unexposed concrete surfaces subsequently left untreated (in the condition
obtained on removal of form work) shall not constitute exposed concrete work and
shall be measured under this item only. Irregular shapes with sides which may not
0 -
be perpendicular to each other for shapes not conforming to rectangle or square
shall not be paid separately. including cost of shuttering and staging material
(quoted rate to include all staging upto any height).
a. Foundation, raft slabs, raft beams, plinth beam, pedestrals/ bases of columns
sqm 636 400 254,400
grade slab etc.
b. Retaining Walls, water tank wall, shear wall and lift wall (any thickness) sqm 5228 415 2,169,620
c. Suspended floors, roofs, landings, balconies, stairs and landings, slabs of water
tank, ramp slabs, lintels, beams, floor beams, girders, cantilever beams, deep sqm 24404 450 10,981,800
beams, ramp beams, arches etc..
d. Columns, pillars, piers, abutments, posts and struts, offset and projection of
sqm 8872 415 3,681,880
columns, etc.
e. Shelves in kitchen/ pantries and toilets etc sqm 0 400 -
Project:________________ 3 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
f. Parapets, Planters, vertical fins, balcony facias, projections, pergolas as per the
sqm 108 450 48,600
shape and profiles indicated in the drawings.
g. Extra over item no. a to f above for circular, semi circular vertical surfaces for all
sizes upto a mean radius not exceeding 1 meters. (shuttering for curved surfaces
with radius greater than 1 meter shall be treated as flat shuttering and paid under sqm 0 200 -
respective items).
h. Cornices, moulding , bands , corbelling, strips etc. sqm 0 450 -
i. Folded plate staircase steps sqm 0 550 -
2.7 Reinforcement steel 0 -
Providing and Laying and fixing in position steel reinforcement ( Fe 500 ) in all
reinforced concrete work, including straightening, cutting, removal of loose rust by
wire brush and coating with cement slurry, bending, hoisting, laying in position to
the shape and profile required at all levels and heights as per drawing and design
and/ or as directed, The rate shall include cost of binding wire and fixing of couplar
and chairs, spacers which will not be measured separately for payment. 0 -
Quantity of steel as per drawing and with authorised overlaps only shall be
measured and paid for. ( Only Reinforcement steel and couplar will be supplied
free of cost by Client)
b. Providing and fixing precast cement concrete ( M -15 grade) drain cover panels,
cum 0 5,500 -
fixed to MS flat as shown in the drawing or as called complete
Total : 2 : 47,522,510
3 MASONARY WORK 0 -
(Quoted Rates are for all heights, all depths, all levels, including basement to roof
(mumty) & all leads and lifts, including racking curved or circular masonary work, 0 -
racking of brick work should be 10mm)
3.1 Brick work in foundation 0 -
3.1.1 Providing and constructing brick masonry using selected quality burnt clay FPS
bricks of class designation 75 in foundation and plinth laid in cement mortar 1:6 (1
cement : 6 coarse sand) mix, joints finished, flush/ raked to 6mm depth including cum 197 4,250 837,250
scaffolding, curing complete as per specification and drawing or as directed by
Project Manager.
3.2 Brick work in superstructure 0 -
3.2.1 Providing and constructing brick masonry of thickness 230 mm or more in
basement & super structure for any shapes, fins, projections, in shafts, under
counter / platform / cupboards, using selected quality burnt clay FPS bricks of class
designation 75 laid in cement mortar 1:6 (1 cement :6 coarse sand) mix, joints cum. 1836 4,350 7,986,600
finished, flush/ raked to 6mm depth including scaffolding, curing complete as per
specification and drawing or as directed by Project Manager.
ALTERNATE ITEM: 0 -
3.2.1 Providing and laying flyash brick work using two hours fire rated flyash bricks in
a super structure above plinth level in cement mortar 1:6 ( 1 cement : 6 coarse sand )
including, curing, joints finished flush/raked to 12 mm depth,scaffolding cum. 0 -
etc.complete as directed by PM.
3.3 Same as item no. 3.2 (a.) above but using machine made bricks in place of
cum. R/O 3,900 -
FPS bricks
3.4 Half brick work 0 -
3.4.1 Providing and constructing half brick masonry using selected quality burnt clay FPS
brick of class designation 75 in super structure laid in cement mortar 1:4 (1
cement : 4 coarse sand) mix, joints finished, flush / raked to 6mm depth as directed
by Project in charge,the rate shall be including placing of 2 Nos 6mm dia. M.S. bars sqm 6572 680 4,468,960
at every third coarse , scaffolding, curing, complete as per specification and
drawing or as directed by Project in charge.
ALTERNATE ITEM: 0 -
3.4.1 Providing & laying Flyash brick work using two hours fire rated flyash bricks in half
a bricks walls in super structure above plinth level in cement mortar 1:4 ( 1 cement :4
coarse sand ) including joints finished flush/raked to 6 mm depth as work proceeds
including steel reinforcement (2 Nos of 6mm dia ) at every fourth course, cleaning
and soaking the bricks at least for 6 hours before use, curing for 7 days etc. sqm 0 650 -
complete at all heights / depth and for all leads.(MS Reinforcement to be provided
by the Contractor within the quoted rates). complete as directed by PM.
4 WATER PROOFING 0 -
(Quoted Rates are for all heights, depths, levels, leads and lifts)
The operations describe below are only indicative & the item is to be executed as
per technical/ manufacturer's specification. 0 -
Testing shall be done by ponding water (150mm depth) for 72 hours.
Note: (The Water proofing work must be executed by an approved specialised
Agency. The Contractor shall give a 10 years guarentee as per instruction of the 0 -
Project Manager).
4.1 Tapecrete water proofing 0 -
Providing and laying composite built up waterproofing in the toilets/ kitchen/
pantry etc. comprising of three coats of Tapecrete or equivalent polymer, each
coat admixed with cement in the proportion 1:2 (one part tapcrete and two parts
cement) over a primer coat of neat cement sturry admixed with impermeable
chemical CH-9. After the second coat of tapecrete, all corners, edges, joints of
0 -
pipes with concrete / masonry should be sealed with epoxy putty. The
waterproofing treatment is to be laid underneath all sanitary pipes on the base and
taken up onto the verticals upto a level of minimum 300mm above the finished toilet
floor level including providing and fixing of PVC spout.
4.1.1 12mm thick protective plaster 1:4 (1 cement : 4 coarse sand) over treated surface
etc complete. (Quoted rate to include grouting of RCC surface for any cracks/ sqm. 1927 400 770,800
fissures)
Project:________________ 4 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
4.1.2 Providing and laying waterproofing treatment to the internal surface of water tank
with five coats of Tapecrete or equivalent water proofing comprising of four slurry
coats of Tapecrete polymer admixed with cement in the proportion 1:2 (one part
Tapecrete or equivalent and two parts cement), one putty coat of Tapecrete
admixed with silica powder and cement applied on the entire surfaces of the water
tanks. After the second coat of tapecrete or equivalent all corners, edges, joints of sqm 767 511 391,937
pipes with concrete etc should be sealed with epoxy putty. The Tapecrete or
equivalent treatment shall be applied directly on the smooth RCC surfaces over a
primer coat of neat cement slurry admixed with impremeable chemical.
From outside:- Two coats of tapecrete or equivalent polymer, each coat admixed
with cement in the proportion 1:2 (one part tapecrete or equivalent and two parts
cement) over a primer coat of neat cement sturry admixed with impermeable
chemical CH-9. After the first coat of tapecrete or equivalent, joints of concrete sqm 1181 480 566,880
should be sealed with epoxy putty and shall be neatly plastered with cement mortar
(1:3) admixed with Acrylic Chemicals of 12 to 15 mm thick.
The item also include providing and making khurrahs 450mm x 450mm with
average minimum thickness of 50mm cement concrete 1:2:4 (1 cement : 2 coarse
sand : 4 graded stone aggregate of 20 mm nominal size) finished with aluminium
foil and 12mm cement plaster 1:3 (1 cement : 3 coarse sand) and a coat of neat sqm 755 550 415,250
cement rounding the edges and making and finishing the outlet complete. (Plan
area will be measured and paid)
4.3.1 Add or deduct for extra or less thickness of brick bat coba waterproofing cum 0 2,854 -
4.4 Deck Slab Waterproofing 0 -
Providing and laying Terrace Garden roof waterproofing with the following
specification including cleaning of the RCC slab top surface. (Actual surface area 0 -
treated shall be measured & paid for)
A layer of bitumenous primer. 0 -
Alayer of hot refined mineral asphalt. 0 -
A layer of Polymeric Polyethylene membrane felt of 1mm thickness with 75mm
0 -
and 100mm side and end laps respectively.
A layer of hot refined mineral asphalt. 0 -
A layer of Polymeric Polyethylene membrane felt of 1mm thickness with 75mm
0 -
and 100mm side and end laps respectively.
A layer of hot refined mineral asphalt. 0 -
A layer of Polymeric Polyethylene membrane felt of 1mm thickness with 75mm
0 -
and 100mm side and end laps respectively.
Vertical: A layer of polymeric polyethylene membrane felt, a layer of Geo-Textile
and a layer of hessian felt type 3 grade 1, each layer laid in hot asphalt over a coat
of bituminous primer with 75mm and 100mm side and end laps respectively. sqm. 1909 650 1,240,850
Project:________________ 5 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
5.1.1 Providing and laying 250mm x 250mm x 25mm thick chequered grey precast
cement concrete tile of approved shape over 25mm average thick base mortar of
mix 1:4 (1 cement : 4 Coarse sand) finished with flush pointing in cement mixed sqm 460 627 288,420
with pigment to match the shade of tiles in approved pattern, cutting, curing etc.
complete as per design & drawings.
Basic rate - 250 per sqm 0 -
5.1.2 Extra over item 6.1.1 of chequered tile flooring above for demarcation arrows with
sqm 0 128 -
red colour precast concrete tiles etc complete.
5.2 Glazed tile 0 -
Providing and fixing commercial quality white glazed ceramic tiles of size 200 x 200
mm & minimum thickness 5mm (floor, walls, jambs etc.) on 12mm thick cement
plaster 1:3 (1 cement:3 coarse sand) and jointed with white cement slurry including sqm. 767 579 444,093
cutting, curing etc. complete in all respect as per drawings.
Total : 5 : 0 4,066,573
6.1.3 Extra for providing and fixing of PVC mesh at the junction of rcc and brick and in
Rmt -
places of condutes work will be charged extra.
6.2 Ceiling plaster 0 -
Providing and applying 6mm thick plaster to RCC slab in cement mortar 1:4 (1
cement : 4 fine and coarse sand in equal proportion) finished smooth including
scaffolding, curing, making grooves at desired location etc. complete as per sqm 9938 145 1,441,010
drawing.
6.3 20 mm cement plaster in two layer -External Plaster 0 -
Providing and applying 20 mm thick plastering on external walls, columns, beams ,
pergola beams and any projections, plaster bands as per drawing etc. in two layers
base layer 14 mm thick of cement mortar 1:5 (1 Cement : 5 coarse sand) and top
layer 6 mm thick 1:4 ( 1 cement : 4 fine sand) including cost of mixing water proof
compound to be applied for both coats, finished to line and level, including all
leads, lifts, scaffolding and curing complete. The rate is inclusive of forming of drip
moulds as with all lead and lift and as directed by Engineer in charge including sqm 11048 350 3,866,800
providing and fixing in position galvanised expanded metal mesh 20 gauge at
junctions of concrete and masonry and other locations as called for including fixing
with GI nails. Fixing approved column / , plaster band and cornices as called for
etc., complete at all levels
Project:________________ 6 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
8.0 MISCELLANEOUS 0 -
(Quoted Rates are for all heights, depths, levels, leads and lifts) 0 -
8.1 Structural Steel 0 -
Supplying, fabricating, assembling, hoisting / erecting and fixing in position at all
heights and with all leads, structural steel works of MS rolled sections (angle,
channel, beams, flats, tees, insert plates, bolts etc.) all as per structural drawings
0 -
and as per detailed specifications (for materials & workmanship) in the situations
described hereinafter including:
Note: The contractor shall submit fabrication drawings for work involved based on
construction drawings (that may be issued during construction period) for approval
by the Project Manager.
The fabrication work shall start only after approval of the fabrication drawings. Any
change required in the fabrication drawings shall be carried out at no extra cost.
Fabrication shall be in a perfect Architectural workmanship manner and as
provided in Section V & VI of IS 800 & IS 7215.
Welding shall be carried out by qualified welders. kg. 0 100 -
Electrodes for welding, the procedure, selection, test and inspection shall confirm
to provisions in IS 816, IS 818, IS 822, & IS 833.
Erection/ hoisting shall commence only after passing of fabricated parts by the
Project Manager.(Basic rate Rs. 48/Kg)
8.3.2 Extra over item 8.3.1 of rolling shutter for providing MS flexible grill of 8mm dia
round bars. (The area of flexible grill provided shall be measured for payment) sqm. 0 500 -
8.6.1 Dumb bell with central bulb (150mm wide, 6mm thick) rmt 0 254 -
8.6.2 as above but 230 mm wide & 9mm thick. rmt 0 363 -
8.6.3 as above but 300 mm wide & 9mm thick. rmt 0 497 -
8.7 Expansion joint AND CORE CUTTING 0 -
8.7.1 Providing and fixing armour board for expansion joints between column, beam,
slab and walls etc. as per manufacturers specification and recommendation. 0 -
Project:________________ 7 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
b. 50 x 12mm Sectional size. rmt 0 1,120 -
c. 25 x 12mm Sectional size. rmt 0 700 -
8.7.4 Supplying and fixing in position in recess or on surface the following size of 16/14
SWG MS conduit including cost of cutting all chases & filling the surface with
cement mortar and providing all accessories such as tees, bends, Junction boxes 0 -
with metallic covers complete as required.
a. 25 mm rmt 0 198 -
b. 32 mm rmt 0 239 -
c. 40 mm rmt 0 289 -
d. 50 mm rmt 0 363 -
8.7.5 Item same as above for using PVC conduits instead of MS conduit. 0 -
a. 25 mm rmt 0 74 -
b. 32 mm rmt 0 116 -
c. 40 mm rmt 0 149 -
d. 50 mm rmt 0 198 -
8.7.6 Providing and fixing before casting circular/hexagonal M.S. sheet ceiling fan box
with clamp of internal dia. 140 mm , 73 mm height, 3mm thick rim, top and bottom
lid of 1.5 mm M.S. Sheet. Lids shall be screwed into M.S. box by means of 3mm Nos 0 200 -
round headed screws, clamps shall be made of 12mm dia. M.S. bar bent to shape
as per standard drawing with over all length as 80 cm.
8.80 Puddle Flanges 0 -
Providing & fixing Galvanised or plastic coated water bar (Puddle Flange) threaded/
flanged ends as the case may be, upto 1200 mm long of the following diameter
8.8.1 fabricated from G.I. (IS:1239 Heavy class or IS:3589 -6 mm wall thickness) pipe. 0 -
[Pipe make-'MSL or eq.']
a. 25 mm dia each 2 437 874
b. 50 mm dia each 2 717 1,434
c. 80 mm dia each 2 1,245 2,490
d. 100 mm dia each 2 1,723 3,446
e. 150 mm dia each 2 2,610 5,220
f. 200 mm dia each 2 4,590 9,180
8.9 PVC sleeves 0 -
Providing and fixing UPVC sleeves (6kg / sqm) properly fixed in wall, column,
8.9.1 0 -
beams, floor and top slab of following diameters:
a. 50 mm outlet dia 300 to 500 mm long each 0 200 -
b. 75 mm outlet dia 300 to 500 mm long each 0 275 -
c. 110 mm outlet dia 300 to 500 mm long each 0 350 -
d. 160 mm outlet dia 300 to 500 mm long each 0 400 -
e. 200 mm outlet dia 300 to 500 mm long each 0 450 -
8.9.2 Extra for additional length of UPVC sleeves (6kg / sqm). 0 -
a. 50 mm outlet dia Rmt 0 218 -
b. 75 mm outlet dia Rmt 0 305 -
c. 110 mm outlet dia Rmt 0 508 -
d. 160 mm outlet dia Rmt 0 798 -
Project:________________ 8 of 9
Bill Of Quantities Price Schedule
(Tower 1B+GF+14)
Sr.
Description of Items UOM Qty. Rate Amount
No.
8.10 Fire seals 0 -
Providing and sealing with fire rated selars by promaseal expansion joint strip
0 -
installed as per manufacturer (promat) specification.
FS50 (50mm thick) Rmt. 0 497 -
8.11 Welding of reinforcement steel 0 -
Welding steel reinforcement of any diameter for laps, with insert plates as per
specifications at all locations as called for including the cost of all materials, labour, 0 -
tools and tackles and processes complete.
per cm
8.11.1 Bult welding weld 0 20 -
length
per cm
8.11.2 Point Welding weld 0 6 -
length
8.12 Expansion Fasteners 0 -
Supplying and fixing expansion fasteners including testing for fixing into already
8.12.1 constructed structure (quoted rate to include design & testing of fasteners for its 0 -
performance).
a. 8mm dia - standard length each 0 243 -
b. 10mm dia - standard length each 0 365 -
c. 12mm dia - standard length each 0 486 -
Item same as 2.11.1 but using Chemical Resin Fasteners instead of expansion
8.12.2 Fasteners (quoted rate to include design & testing of fasteners for its performance). 0 -
Except RCC -
Total : 9 : 0 0
Total 87,223,626
Project:________________ 9 of 9