Daily Report Sample
Daily Report Sample
TILAHUN ABEBE GC
OF/TAGCON/ ECD/001
Title: Issue №:
DAILY REPORT Page №:
1
Page 1 of 1
UNDERGRADUATE
Refer
1 STUDENTS DORMITORY 2,583,027,891.59 1,320,000.00 73,681,960.65 625,495.59 74,307,456.24 2.88% 47.4% 1,490,017..32 2,170.00 311,524.49 20,429.60 100,170.00 3,050.83 62,549.56 - 499,894.48 125,601.11 20% Profit
BUILDING justification
TOTAL 1,320,000.00 73,681,960.65 2,170.00 311,524.49 20,429.60 100,170.00 3,050.83 62,549.56 - 499,894.48 20.08% 20.08% Profit
Company name:
40*890
Company name:
Company name:
In cement mortar - - - - -
01 Concealed from view m3 286.58 474,284.11 1.5 2,457.67 288.06 476,741.78
02 Exposed face for further finish m3 - - - - -
- - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR - 474,284.11 2,457.67 - 476,741.78
Total Amount Birr 37,107,050.55 263,840.16 37,370,890.71
Company name:
TILAHUN ABEBE GC
Title:
Company name:
In situ concrete - - - - -
01 Plain blinding concrete C-5 m3 318.39 1,910,327.25 0.20 1,188.00 318.59 1,911,515.25
Reinforced sub structure concrete - - - - -
Use ordinary Portland cement - - - - -
N.B.C-20/25 is for C-25, 25/30 is for C-30 - - - - -
informer standared
- - - - -
02 C-20/25 in footing &Ramp footing m3 1,350.22 9,154,501.77 12.32 83,536.38 1,362.54 9,238,038.15
03 C-25/30 In foundation columns&Ramp colum m3 56.22 395,765.92 - 56.22 395,765.92
04 C-20/25 in Grade beams &Ramp beams m3 27.49 186,375.42 - 27.49 186,375.42
05 C-20/25 in ground floor slab m3 - - - - -
06 C-20/25 in ramp slab m3 - - - - -
07 C-25/30 in shear wall &Ramp shear wall m3 1.58 10,709.01 - 1.58 10,709.01
08 C-25/30 in retaining wall footing pad for Ramp m3 - - - - -
09 C-20/25 in Entrance steps - - - - -
Reinforced super structure concrete - - - - -
Use ordinary Portland cement - - - - -
10 C-25/30 in elevation column m3 - - - - -
11 C-20/25 in beams & lintle m3 - - - - -
12 C-20/25 in stair case m3 - - - - -
13 C-20/25 in suspended floor & roof slab m3 - - - - -
14 C-25/30 in shear wall m3 - - - - -
Form work - - - - -
Sub structure normal finish to:- - - - - -
15 In footing & Ramp footing m² 2,055.22 1,829,148.91 - 2,055.22 1,829,148.91
16 In foundation columns & Ramp column m² 517.15 460,259.05 - 517.15 460,259.05
17 In Grade beams &Ramp beams m² 323.58 287,981.75 - 323.58 287,981.75
18 In Entrance steps m² - - - - -
19 In shear wall m² - - - - -
20 Suspended ramp slab& Side - - - - -
Super structure normal finish to:- m² - - - - -
21 Elevation column m² - - - - -
22 Beams & lintle m² - - - - -
23 In shear wall m² - - - - -
24 Stair case m² - - - - -
25 Suspended floor & roof slab - - - - -
N.B Duct openig for mechanical, electrical & sanitery - - - - -
have to be checked with AR drawing before - - - - -
executing the Reinforcment for slab and must be - - - - -
done accordind to AR drawing). - - - - -
- - - - -
Reinforcement steel bar - - - - -
Sub structure kg - - - - -
26 Diameter, 24 mm kg 19,755.71 1,916,304.12 - 19,755.71 1,916,304.12
27 Diameter, 20 mm kg 26,907.63 2,610,039.71 - 26,907.63 2,610,039.71
28 Diameter, 16 mm kg 59,164.52 5,738,958.09 403.31 39,121.22 59,567.83 5,778,079.31
29 Diameter, 14 mm kg 2,971.01 288,188.34 - 2,971.01 288,188.34
30 Diameter, 12 mm kg 1,613.46 156,505.27 - 1,613.46 156,505.27
31 Diameter, 10 mm kg 16,838.47 1,633,331.73 472.05 45,789.27 17,310.53 1,679,121.01
32 Diameter, 8 mm 14,554.12 1,411,750.12 - 14,554.12 1,411,750.12
Super Structure kg - - - - -
33 Diameter, 24 mm kg - - - - -
34 Diameter, 20 mm kg - - - - -
35 Diameter, 16 mm kg 6,183.43 599,793.10 - 6,183.43 599,793.10
36 Diameter, 14 mm kg 391.44 37,969.95 - 391.44 37,969.95
37 Diameter, 12 mm kg - - - - -
38 Diameter, 10 mm kg 5,614.49 544,605.79 - 5,614.49 544,605.79
39 Diameter, 8 mm - - - - -
Concrete ancillaries - - - - -
Expansion & construction Joint m - - - - -
40 In 10 mm thick chip wood depth 10 cm. m - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU
Company name:
- - - - -
TOTAL TO SUMMARY ……… BIRR 29,172,515.31 169,634.87 29,342,150.18
04. MASONRY WORK - - - -
- - - - -
Stone wall - - - - -
In cement mortar - - - - -
01 Concealed from view m3 30.61 50,661.62 4.5 7,373.03 35.07 58,034.64
02 Exposed face for further finish m3 - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 50,661.62 7,373.03 58,034.64
Total Amount Birr 33,833,132.52 177,007.90 34,010,140.42
Company name:
TILAHUN ABEBE GC
Title:
Company name:
11 Hard core 25cm thick m² - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 2,561,792.82 41,542.20 2,603,335.02
- - - - -
- - - - -
03. CONCRETE WORK - - - - -
In situ concrete - - - - -
01 Plain blinding concrete C-5 m3 - - - - -
Reinforced sub structure concrete - - - - -
Use ordinary Portland cement - - - - -
N.B.C-20/25 is for C-25, 25/30 is for C-30 - - - - -
informer standared
- - - - -
02 C-20/25 in footing &Ramp footing m3 - - - - -
03 C-25/30 In foundation columns&Ramp colum m3 - - - - -
04 C-20/25 in Grade beams &Ramp beams m3 - - - - -
05 C-20/25 in ground floor slab m3 - - - - -
06 C-20/25 in ramp slab m3 - - - - -
07 C-25/30 in shear wall &Ramp shear wall m3 - - - - -
08 C-25/30 in retaining wall footing pad for Ramp m3 - - - - -
09 C-20/25 in Entrance steps - - - - -
Reinforced super structure concrete - - - - -
Use ordinary Portland cement - - - - -
10 C-25/30 in elevation column m3 - - - - -
11 C-20/25 in beams & lintle m3 - - - - -
12 C-20/25 in stair case m3 - - - - -
13 C-20/25 in suspended floor & roof slab m3 - - - - -
14 C-25/30 in shear wall m3 - - - - -
Form work - - - - -
Sub structure normal finish to:- - - - - -
15 In footing & Ramp footing m² - - - - -
16 In foundation columns & Ramp column m² - - - - -
17 In Grade beams &Ramp beams m² - - - - -
18 In Entrance steps m² - - - - -
19 In shear wall m² - - - - -
20 Suspended ramp slab& Side - - - - -
Super structure normal finish to:- m² - - - - -
21 Elevation column m² - - - - -
22 Beams & lintle m² - - - - -
23 In shear wall m² - - - - -
24 Stair case m² - - - - -
25 Suspended floor & roof slab - - - - -
N.B Duct openig for mechanical, electrical & sanitery - - - - -
have to be checked with AR drawing before - - - - -
executing the Reinforcment for slab and must be - - - - -
done accordind to AR drawing). - - - - -
- - - - -
Reinforcement steel bar - - - - -
Sub structure kg - - - - -
26 Diameter, 24 mm kg - - 1,421.37 137,872.57 1,421.37 137,872.57
27 Diameter, 20 mm kg 822.92 79,823.02 - 822.92 79,823.02
28 Diameter, 16 mm kg 1,032.60 100,161.73 - 1,032.60 100,161.73
29 Diameter, 14 mm kg - - - - -
30 Diameter, 12 mm kg - - 53.95 5,232.76 53.95 5,232.76
31 Diameter, 10 mm kg - - - - -
32 Diameter, 8 mm - - - - -
Super Structure kg - - - - -
33 Diameter, 24 mm kg - - - - -
34 Diameter, 20 mm kg - - - - -
35 Diameter, 16 mm kg - - - - -
36 Diameter, 14 mm kg - - - - -
37 Diameter, 12 mm kg - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU
Company name:
38 Diameter, 10 mm kg - - - - -
39 Diameter, 8 mm - - - - -
Concrete ancillaries - - - - -
Expansion & construction Joint m - - - - -
40 In 10 mm thick chip wood depth 10 cm. m - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 179,984.75 143,105.34 323,090.09
Hard core
B/n axis A2-A4/Aa-Ac
1 / 5 6.75
3.80
128.25 m2
128.25 m2
Form work For GB
1 / 5 12.70 On axis B1,B2,B3/Ba-Bd
0.40
25.40 m2
25.40 m2
Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
Lean concrete
On axis Bd/B5-B6(massonry)
1 / 1 6.60
0.60
0.05
0.20 m3
0.20 m3
Massonery work
1 / 1 6.60 On axis Bd/B5-B6
1.35
0.50
4.46 m3
4.46 m3
Concrete for Pad
On axis C3/Cc
1 / 1 3.70 F3
3.70
0.90
12.32 m3
12.32 m3
Company Name:
1 / 2 15.70
3.00
2.45
230.79 m3
230.79
1 / 2 15.70
3.00
2.45
230.79 m3
230.79
Docment No
L CONTRACTOR
Issue SUB CONTRACT PAYMENT
VERSITY
pit excavation
On axis C1&C2/Ca-Cd 16.65
3.95
m3
Disposal
m3
No No of member Diametr s of Bars
Description Bar No. Dia(mm) Length of bar ɸ8 ɸ10 ɸ12 ɸ14 ɸ16 ɸ20 ɸ24
Block C(B) Gread beam reinforcement
GB1 - - - - - - -
top 16 10.37 3 1 2 - - - - 62.22 - -
16 8.67 3 1 2 - - - - 52.02 - -
16 7.64 3 2 2 - - - - 91.68 - -
16 11.05 3 1 2 - - - - 66.30 - -
bottom 16 8.64 3 1 2 - - - - 51.84 - -
16 6.93 3 1 2 - - - - 41.58 - -
16 7.675 3 3 2 - - - - 138.15 - -
16 7.54 3 1 2 - - - - 45.24 - -
negative
bar 14 3.16 2 1 2 - - - 12.64 - - -
14 3.74 2 1 2 - - - 14.96 - - -
stirup 8 1.66 259 1 2 859.88 - - - - - -
8 1.66 66 1 2 219.12 - - - - - -
- - - - - - -
GB2 top 16 11.77 4 1 2 - - - - 94.16 - -
16 7.27 3 1 2 - - - - 43.62 - -
16 7.64 3 2 2 - - - - 91.68 - -
16 11.045 3 1 2 - - - - 66.27 - -
negative
bar 14 3.16 2 1 2 - - - 12.64 - - -
14 4.67 2 1 2 - - - 18.68 - - -
bottom 16 8.595 4 1 2 - - - - 68.76 - -
16 6.89 3 1 2 - - - - 41.34 - -
16 7.68 3 3 2 - - - - 138.24 - -
16 7.54 3 1 2 - - - - 45.24 - -
stirup 8 1.66 260 1 2 863.20 - - - - - -
8 1.66 66 1 2 219.12 - - - - - -
- - - - - - -
GB3 top 16 7.95 3 1 2 - - - - 47.70 - -
bottom 16 7.9 3 1 2 - - - - 47.40 - -
stirup 8 1.36 46 1 2 125.12 - - - - - -
8 1.36 13 1 2 35.36 - - - - - -
- - - - - - -
GB4 top 16 11.02 3 1 2 - - - - 66.12 - -
16 4.66 3 1 2 - - - - 27.96 - -
negative
bar 14 4.67 2 1 2 - - - 18.68 - - -
bottom 16 7.89 3 1 2 - - - - 47.34 - -
16 8.14 3 1 2 - - - - 48.84 - -
stirup 8 1.66 89 1 2 295.48 - - - - - -
8 1.66 23 1 2 76.36 - - - - - -
- - - - - - -
GB5 top 16 9.12 3 1 2 - - - - 54.72 - -
16 7.64 3 1 2 - - - - 45.84 - -
16 11.045 3 1 2 - - - - 66.27 - -
bottom 16 5.62 3 1 2 - - - - 33.72 - -
16 7.675 3 2 2 - - - - 92.10 - -
16 7.54 3 1 2 - - - - 45.24 - -
stirup 8 1.66 159 2 2 1,055.76 - - - - - -
8 1.66 41 1 2 136.12 - - - - - -
- - - - - - -
GB6 top 16 11.395 3 1 2 - - - - 68.37 - -
16 7.64 3 3 2 - - - - 137.52 - -
16 11.045 3 1 2 - - - - 66.27 - -
16 7.89 3 1 2 - - - - 47.34 - -
bottom 16 6.93 3 1 2 - - - - 41.58 - -
16 7.68 3 3 2 - - - - 138.24 - -
16 7.54 3 1 2 - - - - 45.24 - -
8 1.66 265 1 2 879.80 - - - - - -
stirup 8 1.66 67 1 2 222.44 - - - - - -
- - - - - - -
GB7 top 16 7.245 6 1 2 - - - - 86.94 - -
negative
bar 14 2.01 4 1 2 - - - 16.08 - - -
14 2.81 4 1 2 - - - 22.48 - - -
bottom 16 9.295 3 1 2 - - - - 55.77 - -
16 5.19 3 1 2 - - - - 31.14 - -
stirup 8 1.66 74 1 2 245.68 - - - - - -
8 1.66 20 1 2 66.40 - - - - - -
- - - - - - -
GB8 top 16 9.45 3 1 2 - - - - 56.70 - -
2 - - - - - - -
negative
bar 14 1.96 2 1 2 - - - 7.84 - - -
14 2.81 2 1 2 - - - 11.24 - - -
16 9.4 3 1 2 - - - - 56.40 - -
bottom 8 1.56 48 4 2 599.04 - - - - - -
stirup 8 1.56 13 2 2 81.12 - - - - - -
- - - - - - -
GB9 top 16 5.15 3 1 2 - - - - 30.90 - -
2 - - - - - - -
bottom 16 5.1 3 1 2 - - - - 30.60 - -
8 1.26 26 1 2 65.52 - - - - - -
stirup 8 1.26 8 1 2 20.16 - - - - - -
- - - - - - -
GB10 top 16 5.15 3 1 2 - - - - 30.90 - -
16 5.1 3 1 2 - - - - 30.60 - -
bottom 8 1.26 27 2 2 136.08 - - - - - -
stirup 8 1.26 8 1 2 20.16 - - - - - -
- - - - - - -
GB11 top 16 7.095 6 1 2 - - - - 85.14 - -
2 - - - - - - -
negative
bar 14 1.86 4 1 2 - - - 14.88 - - -
14 2.81 4 2 2 - - - 44.96 - - -
2 - - - - - - -
bottom 16 9.14 3 1 2 - - - - 54.84 - -
16 5.04 3 1 2 - - - - 30.24 - -
2 - - - - - - -
stirup 8 1.26 78 6 2 1,179.36 - - - - - -
8 1.26 21 3 2 158.76 - - - - - -
- - - - - - -
TotaL Length (m) 756.00 - - 19.51 288.63 - -
wt/mL(kg/m) 0.395 0.617 1.208 1.578 2.466 3.551
TotaL weight (kg) 298.62 - - 23.57 455.46 - -
No of member Diametr s of Bars
Description Bar No. Dia(mm) Length No of bar ɸ8 ɸ10 ɸ12 ɸ14 ɸ16 ɸ20 ɸ24
Block C(C) Gread beam reinforcement
GB1 top 16 7.05 4 10 2 - - - - 564.00 - -
bottom 16 9.14 4 5 2 - - - - 365.60 - -
16 5.04 4 5 2 - - - - 201.60 - -
stirup - - - - - - -
10 1.4 77 5 2 - 1,078.00 - - - - -
10 1.4 27 5 2 - 378.00 - - - - -
- - - - - - -
GB2 top - - - - - - -
- - - - - - -
- - - - - - -
bottom - - - - - - -
- - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 169 1 2 - 574.60 - - - - -
10 1.7 57 1 2 - 193.80 - - - - -
- - - - - - -
GB3 top - - - - - - -
- - - - - - -
bottom - - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 165 1 2 - 561.00 - - - - -
10 1.7 56 1 2 - 190.40 - - - - -
- - - - - - -
GB4 top - - - - - - -
bottom - - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 127 1 2 - 431.80 - - - - -
10 1.7 43 1 2 - 146.20 - - - - -
- - - - - - -
GB5 top - - - - - - -
bottom - - - - - - -
stirup 10 1.4 20 1 2 - 56.00 - - - - -
10 1.4 8 1 2 - 22.40 - - - - -
- - - - - - -
GB6 top 16 9.17 4 1 2 - - - - 73.36 - -
bottom 16 9.17 4 1 2 - - - - 73.36 - -
stirup - - - - - - -
10 1.4 51 1 2 - 142.80 - - - - -
10 1.4 18 1 2 - 50.40 - - - - -
- - - - - - -
TotaL Length (m) - 765.08 - - 255.58 - -
wt/mL(kg/m) 0.395 0.617 1.208 1.578 2.466 3.551
TotaL weight (kg) - 472.05 - - 403.31 - -
Length No of NO OF Total No. of
Location Type Dia (m) No of bar member BLOCKS bars Ø 8 mm Ø 10 mm Ø 12 mm Ø 14 mm Ø 16 mm
For mat - - - - -
Bottom bar 24 8.17 46 1 1.0 46 - - - - -
a./5(Cb-Cd) 24 8.03 46 1 1.0 46 - - - - -
24 6.30 136 1 1.0 136 - - - - -
KZ bar 12 2.70 90 1 1 90 - - 243.00 - -
Total Length - - 60.8 - -
Unit Weight 0.40 0.62 0.89 1.21 1.58
Total Weight 0.00 0.00 53.95 0.00 0.00
Ø 20 mm Ø 24 mm
- -
- 375.59
- 369.15
- 856.80
- -
- 400.4
2.47 3.55
0.00 1,421.37
Company name:
TILAHUN ABEBE GC
Title: Page №:
DAILY REPORT Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
Reporting Date:-27/04/2015
DELIVERED
Utilized QTY Expense Amount Balance Amount to
S.No Material Description Unit Balance Unit Price Amount TO
ISSUED this day This day date
DATE
S.No Description of Work Name of Sub contractor Unit Qty Unit Price Amount Remark
TILAHUN ABEBE GC
OF/TAGCON/ ECD/001
Title: Page №:
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
3 daily Lbour 90 -
5 Cabo 200 -
6 carpenter 8 400 -
7 A.carpenter 250 -
8 Time keeper 8 -
Total 2,170.00
Company name:
TILAHUN ABEBE GC
Reporting Date:-27/04/2015
2 Drill TAGC 8 -
TILAHUN ABEBE GC
Title: Page №:
DAILY REPORT Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC
DAILY REPORT
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC
Indirect Expens Reporting Date:-27/04/2015
Title:
JUSTIFICATION RECORD
4 Project Performance/Out
Put Related
Consultant Related
6 Other Factors
Sign:___________________
Date:-
TILAHUN ABEBE GENERAL CONTRACTOR
Reporting Date:-27/04/2015
Major Problems
generator problem
labours shortage due to
holyday
Other issues
Other issues
Sub Total
Other issues
Sub Total
Sub Total
ABEBE GENERAL CONTRACTOR
Reporting Date:-27/04/2015
Description of Main works not Unexecuted Amount
executed+D14:D19D14:D25
Sign:___________________
Date:-
% from Total
Plan
________
Description of Problems
Encountered
-
We build dreams !
Document №:
OF/TAGC/ ECD/42
Issue №: Page №:
1 Page 1 of 1
Remedial measure
taken by the project (if Remark
any)
-
-
Sign:___________________
Date:-
Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
TAKEOFF SHEET Issue No
. EXCAVATION & EARTH WORK
Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
TAKEOFF SHEET Issue No
. EXCAVATION & EARTH WORK