Daily Report Sample

1) The daily report provides an update on progress for the Undergraduate Students Dormitory Building project in Debre Birhan, Ethiopia. 2) As of April 27, 2015, 74,307,456.24 birr or 2.88% of the total contract value has been completed to date. 3) Yesterday's work included 1,490,017.32 birr of direct labor, 311,524.49 birr on materials, and other expenses totaling 499,894.48 birr.

Uploaded by

zenichbad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
219 views43 pages

Daily Report Sample

1) The daily report provides an update on progress for the Undergraduate Students Dormitory Building project in Debre Birhan, Ethiopia. 2) As of April 27, 2015, 74,307,456.24 birr or 2.88% of the total contract value has been completed to date. 3) Yesterday's work included 1,490,017.32 birr of direct labor, 311,524.49 birr on materials, and other expenses totaling 499,894.48 birr.

Uploaded by

zenichbad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 43

Company name: Document №:

TILAHUN ABEBE GC
OF/TAGCON/ ECD/001
Title: Issue №:
DAILY REPORT Page №:
1
Page 1 of 1

Project:UNDERGRADUATE STUDENTS DORMITORY BUILDING

Location: Debre Birhan

Consultant : ETHIOPIAN CONSTRUCTION DESIGN & SUPERVISION

Contractor :Tilahun Abebe GC


Reporting Date:-27/04/2015
Todate Executed as Indirect
Current TOTAL Daily Next DAY Direct Man Machinery over head Indirect(pitty
TOTAL CONTRAT Today Planned of Todate Executed Material Sub Contract Total profit/Loss
Executed PROGRESS progress Plan power and Equipment cost ( 10 %) cash)
Previous Period Man Major
Project Remark
power Problems

Performance Daily Daily Daily Daily Daily Daily Daily


AMOUNT Amount Amount Amount Amount Amount Daily Expense Amount %
in % Expense Expense Expense Expense Expense Expense Expense

UNDERGRADUATE
Refer
1 STUDENTS DORMITORY 2,583,027,891.59 1,320,000.00 73,681,960.65 625,495.59 74,307,456.24 2.88% 47.4% 1,490,017..32 2,170.00 311,524.49 20,429.60 100,170.00 3,050.83 62,549.56 - 499,894.48 125,601.11 20% Profit
BUILDING justification

TOTAL 1,320,000.00 73,681,960.65 2,170.00 311,524.49 20,429.60 100,170.00 3,050.83 62,549.56 - 499,894.48 20.08% 20.08% Profit

Prepared By:-ZENA HABTE Checked By:- Getachew Approved By: FIKREMEDIN .K

Prepared by___________ Approved by___________


ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:

40*890

Title: todate 8=previous9 todate9=previous 10

PROJECT:UNDERGRADUATE STUDENTS DORMITORY BUILDING


CLIENT: Ato Tilahun Abebe Gc
Location: Debre Birhan
Excuted Major Activities
Reporting Date:-27/04/2015
Contract previous Current todate
Item No Item Description
Unit Qty Amount Qty Amount Qty Amount
A. Substructure - - - - -
02. EXCAVATION & EARTH WORK - - - - -
- - - - -
Excavation - - - - -
(All excavation according to the attached
soil report & note - - - - -
given on structural drawing) - - - - -
Bulk excavation - - - - -
- - - - -
01 Not exceeding 1.5m m3 - - - - -
- - - - -
02 Ditto over 1.5m but not exceeding 3.0m m3 - - - - -
- - - - -
Pit & Trench excavation after reduced
bulk level - - - - -
- - - - -
04 Pit not exceeding 1.5 m m3 871.57 26,147.15 - 871.57 26,147.15
05 Ditto over 1.5m but not exceeding 3.0m m3 34,846.32 1,045,389.60 - 34,846.32 1,045,389.60
- - - - -
Trench excavation - - - - -
06 Not exceeding 1.5m m3 324.98 12,999.30 - 324.98 12,999.30
- - - - -
Fill - - - - -
- - - - -
Compaction fill shall be every 20 cm thick - - - - -
attains a minimum of 95% proctor density - - - - -
07 Selected borrowed fill m3 3,490.48 1,500,908.06 - 3,490.48 1,500,908.06
08 Selected Excavated fill from site m3 1,585.36 269,510.85 - 1,585.36 269,510.85
09 Disposal m3 16,595.70 2,489,354.78 - 16,595.70 2,489,354.78
- - - - -
Sub Base - - - - -
10 100 mm thick crushed aggregate m3 - - - - -
11 Hard core 25cm thick m² 1,874.34 3,148,891.20 128.25 215,460.00 2,002.59 3,364,351.20
- - - - -
TOTAL TO SUMMARY ……… BIRR 8,493,200.92 215,460.00 8,708,660.92
- - - - -
- - - - -
03. CONCRETE WORK - - - - -
In situ concrete - - - - -
01 Plain blinding concrete C-5 m3 102.29 613,730.40 - 102.29 613,730.40
Reinforced sub structure concrete - - - - -
Use ordinary Portland cement - - - - -
N.B.C-20/25 is for C-25, 25/30 is for C-30
informer standared - - - - -
- - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:

02 C-20/25 in footing &Ramp footing m3 1,105.13 7,492,759.37 - 1,105.13 7,492,759.37


03 C-25/30 In foundation columns&Ramp colum m3 78.47 552,434.08 - 78.47 552,434.08
04 C-20/25 in Grade beams &Ramp beams m3 163.90 1,111,208.44 - 163.90 1,111,208.44
05 C-20/25 in ground floor slab m3 - - - - -
06 C-20/25 in ramp slab m3 - - - - -
07 C-25/30 in shear wall &Ramp shear wall m3 - - - - -
08 C-25/30 in retaining wall footing pad for Ramp m3 - - - - -
09 C-20/25 in Entrance steps m3 - - - - -
Reinforced super structure concrete - - - - -
Use ordinary Portland cement - - - - -
10 C-25/30 in elevation column m3 62.14 437,432.16 3.31 23,316.48 65.45 460,748.64
11 C-20/25 in beams & lintle m3 - - - - -
12 C-20/25 in stair case m3 - - - - -
13 C-20/25 in suspended floor & roof slab m3 - - - - -
14 C-25/30 in shear wall m3 - - - - -
Form work - - - - -
Sub structure normal finish to:- - - - - -
15 In footing & Ramp footing m² 1,397.92 1,244,148.36 - 1,397.92 1,244,148.36
16 In foundation columns & Ramp column m² 327.82 291,757.80 - 327.82 291,757.80
17 In Grade beams &Ramp beams m² 1,069.36 951,733.96 25.40 22,606.00 1,094.76 974,339.96
18 In Entrance steps m² - - - - -
19 In shear wall m² 11.70 10,413.00 - 11.70 10,413.00
20 Suspended ramp slab& Side m² - - - - -
Super structure normal finish to:- - - - - -
21 Elevation column m² 651.39 579,736.18 - 651.39 579,736.18
22 Beams & lintle m² 87.16 77,572.40 - 87.16 77,572.40
23 In shear wall m² 27.60 24,564.00 - 27.60 24,564.00
24 Stair case m² - - - - -
25 Suspended floor & roof slab m² - - - - -
N.B Duct openig for mechanical, electrical & sanitery - - - - -
have to be checked with AR drawing before - - - - -
executing the Reinforcment for slab and must be - - - - -
done accordind to AR drawing). - - - - -
- - - - -
Reinforcement steel bar - - - - -
Sub structure - - - - -
26 Diameter, 24 mm kg 14,650.67 1,421,114.62 - 14,650.67 1,421,114.62
27 Diameter, 20 mm kg 32,100.53 3,113,751.48 - 32,100.53 3,113,751.48
28 Diameter, 16 mm kg 51,071.30 4,953,915.65 - 51,071.30 4,953,915.65
29 Diameter, 14 mm kg 1,957.58 189,884.80 - 1,957.58 189,884.80
30 Diameter, 12 mm kg 1,534.89 148,884.20 - 1,534.89 148,884.20
31 Diameter, 10 mm kg 23,278.91 2,258,054.63 - 23,278.91 2,258,054.63
32 Diameter, 8 mm kg 6,432.33 623,935.64 - 6,432.33 623,935.64
Super Structure - - - - -
33 Diameter, 24 mm kg - - - - -
34 Diameter, 20 mm kg 2,054.1780 199,255.27 - 2,054.18 199,255.27
35 Diameter, 16 mm kg 6,244.22 605,689.51 - 6,244.22 605,689.51
36 Diameter, 14 mm kg 414.11 40,168.40 - 414.11 40,168.40
37 Diameter, 12 mm kg - - - - -
38 Diameter, 10 mm kg 12,344.55 1,197,421.21 - 12,344.55 1,197,421.21
39 Diameter, 8 mm kg - - - - -
Concrete ancillaries - - - - -
Expansion & construction Joint - - - - -
40 In 10 mm thick chip wood depth 10 cm. m - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 28,139,565.53 45,922.48 28,185,488.01
04. MASONRY WORK - - - -
- - - - -
Stone wall - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:
In cement mortar - - - - -
01 Concealed from view m3 286.58 474,284.11 1.5 2,457.67 288.06 476,741.78
02 Exposed face for further finish m3 - - - - -
- - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR - 474,284.11 2,457.67 - 476,741.78
Total Amount Birr 37,107,050.55 263,840.16 37,370,890.71

Company name:

TILAHUN ABEBE GC

Title:

DAILY REPORT BLOCK A


PROJECT:UNDERGRADUATE STUDENTS DORMITORY BUILDING
CLIENT: Ato Tilahun Abebe Gc
Location: Debre Birhan
Excuted Major Activities
Reporting Date:-27/04/2015
Contract Todate 28/previous 29 Current 29 Todate 29
Item No Item Description
Unit Qty Amount Qty Amount Qty Amount
A. Substructure - 0 - - -
02. EXCAVATION & EARTH WORK - - - - -
- - - - -
Excavation - - - - -
(All excavation according to the attached - - - - -
soil report & note
given on structural drawing) - - - - -
Bulk excavation - - - - -
- - - - -
01 Not exceeding 1.5m m3 6,977.43 209,322.96 - 6,977.43 209,322.96
- - - - -
02 Ditto over 1.5m but not exceeding 3.0m m3 - - - - -
- - - - -
Pit & Trench excavation after reduced bulk level - - - - -
- - - - -
04 Pit not exceeding 1.5 m m3 8,742.50 262,274.91 - 8,742.50 262,274.91
05 Ditto over 1.5m but not exceeding 3.0m m3 2,712.19 81,365.68 - 2,712.19 81,365.68
- - - - -
Trench excavation - - - - -
06 Not exceeding 1.5m m3 100.94 4,037.40 - 100.94 4,037.40
- - - - -
Fill - - - - -
- - - - -
Compaction fill shall be every 20 cm thick until it - - - - -
attains a minimum of 95% proctor density - - - - -
07 Selected borrowed fill m3 2,972.11 1,278,009.06 - 2,972.11 1,278,009.06
08 Selected Excavated fill from site m3 - - - - -
09 Disposal m3 18,499.64 2,774,945.59 - 18,499.64 2,774,945.59
- - - - -
Sub Base - - - - -
10 100 mm thick crushed aggregate m² - - - - -
11 Hard core 25cm thick m² - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 4,609,955.60 - 4,609,955.60
- - - - -
- - - - -
03. CONCRETE WORK - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:
In situ concrete - - - - -
01 Plain blinding concrete C-5 m3 318.39 1,910,327.25 0.20 1,188.00 318.59 1,911,515.25
Reinforced sub structure concrete - - - - -
Use ordinary Portland cement - - - - -
N.B.C-20/25 is for C-25, 25/30 is for C-30 - - - - -
informer standared
- - - - -
02 C-20/25 in footing &Ramp footing m3 1,350.22 9,154,501.77 12.32 83,536.38 1,362.54 9,238,038.15
03 C-25/30 In foundation columns&Ramp colum m3 56.22 395,765.92 - 56.22 395,765.92
04 C-20/25 in Grade beams &Ramp beams m3 27.49 186,375.42 - 27.49 186,375.42
05 C-20/25 in ground floor slab m3 - - - - -
06 C-20/25 in ramp slab m3 - - - - -
07 C-25/30 in shear wall &Ramp shear wall m3 1.58 10,709.01 - 1.58 10,709.01
08 C-25/30 in retaining wall footing pad for Ramp m3 - - - - -
09 C-20/25 in Entrance steps - - - - -
Reinforced super structure concrete - - - - -
Use ordinary Portland cement - - - - -
10 C-25/30 in elevation column m3 - - - - -
11 C-20/25 in beams & lintle m3 - - - - -
12 C-20/25 in stair case m3 - - - - -
13 C-20/25 in suspended floor & roof slab m3 - - - - -
14 C-25/30 in shear wall m3 - - - - -
Form work - - - - -
Sub structure normal finish to:- - - - - -
15 In footing & Ramp footing m² 2,055.22 1,829,148.91 - 2,055.22 1,829,148.91
16 In foundation columns & Ramp column m² 517.15 460,259.05 - 517.15 460,259.05
17 In Grade beams &Ramp beams m² 323.58 287,981.75 - 323.58 287,981.75
18 In Entrance steps m² - - - - -
19 In shear wall m² - - - - -
20 Suspended ramp slab& Side - - - - -
Super structure normal finish to:- m² - - - - -
21 Elevation column m² - - - - -
22 Beams & lintle m² - - - - -
23 In shear wall m² - - - - -
24 Stair case m² - - - - -
25 Suspended floor & roof slab - - - - -
N.B Duct openig for mechanical, electrical & sanitery - - - - -
have to be checked with AR drawing before - - - - -
executing the Reinforcment for slab and must be - - - - -
done accordind to AR drawing). - - - - -
- - - - -
Reinforcement steel bar - - - - -
Sub structure kg - - - - -
26 Diameter, 24 mm kg 19,755.71 1,916,304.12 - 19,755.71 1,916,304.12
27 Diameter, 20 mm kg 26,907.63 2,610,039.71 - 26,907.63 2,610,039.71
28 Diameter, 16 mm kg 59,164.52 5,738,958.09 403.31 39,121.22 59,567.83 5,778,079.31
29 Diameter, 14 mm kg 2,971.01 288,188.34 - 2,971.01 288,188.34
30 Diameter, 12 mm kg 1,613.46 156,505.27 - 1,613.46 156,505.27
31 Diameter, 10 mm kg 16,838.47 1,633,331.73 472.05 45,789.27 17,310.53 1,679,121.01
32 Diameter, 8 mm 14,554.12 1,411,750.12 - 14,554.12 1,411,750.12
Super Structure kg - - - - -
33 Diameter, 24 mm kg - - - - -
34 Diameter, 20 mm kg - - - - -
35 Diameter, 16 mm kg 6,183.43 599,793.10 - 6,183.43 599,793.10
36 Diameter, 14 mm kg 391.44 37,969.95 - 391.44 37,969.95
37 Diameter, 12 mm kg - - - - -
38 Diameter, 10 mm kg 5,614.49 544,605.79 - 5,614.49 544,605.79
39 Diameter, 8 mm - - - - -
Concrete ancillaries - - - - -
Expansion & construction Joint m - - - - -
40 In 10 mm thick chip wood depth 10 cm. m - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:
- - - - -
TOTAL TO SUMMARY ……… BIRR 29,172,515.31 169,634.87 29,342,150.18
04. MASONRY WORK - - - -
- - - - -
Stone wall - - - - -
In cement mortar - - - - -
01 Concealed from view m3 30.61 50,661.62 4.5 7,373.03 35.07 58,034.64
02 Exposed face for further finish m3 - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 50,661.62 7,373.03 58,034.64
Total Amount Birr 33,833,132.52 177,007.90 34,010,140.42

Company name:

TILAHUN ABEBE GC

Title:

DAILY REPORT BLOCK B


PROJECT:UNDERGRADUATE STUDENTS DORMITORY BUILDING
CLIENT: Ato Tilahun Abebe Gc
Location: Debre Birhan
Excuted Major Activities
DAILY REPORT BLOCK B
Contract Todate 28/previous 29 Current 29 Todate 29
Item No Item Description
Unit Qty Amount Qty Amount Qty Amount
A. Substructure - 0 - - -
02. EXCAVATION & EARTH WORK - - - - -
- - - - -
Excavation - - - - -
(All excavation according to the attached
- - - - -
soil report & note
given on structural drawing) - - - - -
Bulk excavation - - - - -
- - - - -
01 Not exceeding 1.5m m3 11,412.26 342,367.67 230.79 6,923.70 11,643.05 349,291.37
- - - - -
02 Ditto over 1.5m but not exceeding 3.0m m3 - - - - -
- - - - -
Pit & Trench excavation after reduced bulk level - - - - -
- - - - -
04 Pit not exceeding 1.5 m m3 2,216.93 66,507.98 - 2,216.93 66,507.98
05 Ditto over 1.5m but not exceeding 3.0m m3 602.99 18,089.82 - 602.99 18,089.82
- - - - -
Trench excavation - - - - -
06 Not exceeding 1.5m m3 - - - - -
- - - - -
Fill - - - - -
- - - - -
Compaction fill shall be every 20 cm thick until it - - - - -
attains a minimum of 95% proctor density - - - - -
07 Selected borrowed fill m3 - - - - -
08 Selected Excavated fill from site m3 - - - - -
09 Disposal m3 14,232.18 2,134,827.35 230.79 34,618.50 14,462.97 2,169,445.85
- - - - -
Sub Base - - - - -
10 100 mm thick crushed aggregate m² - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:
11 Hard core 25cm thick m² - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 2,561,792.82 41,542.20 2,603,335.02
- - - - -
- - - - -
03. CONCRETE WORK - - - - -
In situ concrete - - - - -
01 Plain blinding concrete C-5 m3 - - - - -
Reinforced sub structure concrete - - - - -
Use ordinary Portland cement - - - - -
N.B.C-20/25 is for C-25, 25/30 is for C-30 - - - - -
informer standared
- - - - -
02 C-20/25 in footing &Ramp footing m3 - - - - -
03 C-25/30 In foundation columns&Ramp colum m3 - - - - -
04 C-20/25 in Grade beams &Ramp beams m3 - - - - -
05 C-20/25 in ground floor slab m3 - - - - -
06 C-20/25 in ramp slab m3 - - - - -
07 C-25/30 in shear wall &Ramp shear wall m3 - - - - -
08 C-25/30 in retaining wall footing pad for Ramp m3 - - - - -
09 C-20/25 in Entrance steps - - - - -
Reinforced super structure concrete - - - - -
Use ordinary Portland cement - - - - -
10 C-25/30 in elevation column m3 - - - - -
11 C-20/25 in beams & lintle m3 - - - - -
12 C-20/25 in stair case m3 - - - - -
13 C-20/25 in suspended floor & roof slab m3 - - - - -
14 C-25/30 in shear wall m3 - - - - -
Form work - - - - -
Sub structure normal finish to:- - - - - -
15 In footing & Ramp footing m² - - - - -
16 In foundation columns & Ramp column m² - - - - -
17 In Grade beams &Ramp beams m² - - - - -
18 In Entrance steps m² - - - - -
19 In shear wall m² - - - - -
20 Suspended ramp slab& Side - - - - -
Super structure normal finish to:- m² - - - - -
21 Elevation column m² - - - - -
22 Beams & lintle m² - - - - -
23 In shear wall m² - - - - -
24 Stair case m² - - - - -
25 Suspended floor & roof slab - - - - -
N.B Duct openig for mechanical, electrical & sanitery - - - - -
have to be checked with AR drawing before - - - - -
executing the Reinforcment for slab and must be - - - - -
done accordind to AR drawing). - - - - -
- - - - -
Reinforcement steel bar - - - - -
Sub structure kg - - - - -
26 Diameter, 24 mm kg - - 1,421.37 137,872.57 1,421.37 137,872.57
27 Diameter, 20 mm kg 822.92 79,823.02 - 822.92 79,823.02
28 Diameter, 16 mm kg 1,032.60 100,161.73 - 1,032.60 100,161.73
29 Diameter, 14 mm kg - - - - -
30 Diameter, 12 mm kg - - 53.95 5,232.76 53.95 5,232.76
31 Diameter, 10 mm kg - - - - -
32 Diameter, 8 mm - - - - -
Super Structure kg - - - - -
33 Diameter, 24 mm kg - - - - -
34 Diameter, 20 mm kg - - - - -
35 Diameter, 16 mm kg - - - - -
36 Diameter, 14 mm kg - - - - -
37 Diameter, 12 mm kg - - - - -
ATO TILAHUN ABEBE BILL OF QUANTITU

Company name:
38 Diameter, 10 mm kg - - - - -
39 Diameter, 8 mm - - - - -
Concrete ancillaries - - - - -
Expansion & construction Joint m - - - - -
40 In 10 mm thick chip wood depth 10 cm. m - - - - -
- - - - -
TOTAL TO SUMMARY ……… BIRR 179,984.75 143,105.34 323,090.09

Total Amount Birr 2,741,777.57 184,647.54 2,926,425.11


Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
TAKEOFF SHEET Issue SUB CONTRACT PAYMENT

Project UNDER GRADUATE STUDENTS DORMITORY BUILDING


Location DEBRE BERHAN

Owner DEBRE BIRHAN UNIVERSITY


Consultant CONSULTANT:
Contractor

Hard core
B/n axis A2-A4/Aa-Ac
1 / 5 6.75
3.80
128.25 m2
128.25 m2
Form work For GB
1 / 5 12.70 On axis B1,B2,B3/Ba-Bd
0.40
25.40 m2
25.40 m2
Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR

TAKEOFF SHEET Issue SUB CONTRACT PAYMENT

Project UNDER GRADUATE STUDENTS DORMITORY BUILDING

Location DEBRE BERHAN

Owner DEBRE BIRHAN UNIVERSITY


Consultant CONSULTANT:
Contractor

Lean concrete
On axis Bd/B5-B6(massonry)
1 / 1 6.60
0.60
0.05
0.20 m3
0.20 m3
Massonery work
1 / 1 6.60 On axis Bd/B5-B6
1.35
0.50
4.46 m3
4.46 m3
Concrete for Pad
On axis C3/Cc
1 / 1 3.70 F3
3.70
0.90
12.32 m3
12.32 m3
Company Name:

TIlAHUN ABEBE GENERAL CONTRACTOR


TAKEOFF SHEET

Project UNDER GRADUATE STUDENTS DORMITORY BUILDING


Location DEBRE BERHAN

Owner DEBRE BIRHAN UNIVERSITY


Consultant CONSULTANT:
Contractor

1 / 2 15.70
3.00
2.45
230.79 m3
230.79

1 / 2 15.70
3.00
2.45
230.79 m3
230.79
Docment No
L CONTRACTOR
Issue SUB CONTRACT PAYMENT

STUDENTS DORMITORY BUILDING

VERSITY

pit excavation
On axis C1&C2/Ca-Cd 16.65
3.95

m3
Disposal

m3
No No of member Diametr s of Bars
Description Bar No. Dia(mm) Length of bar ɸ8 ɸ10 ɸ12 ɸ14 ɸ16 ɸ20 ɸ24
Block C(B) Gread beam reinforcement
GB1 - - - - - - -
top 16 10.37 3 1 2 - - - - 62.22 - -
16 8.67 3 1 2 - - - - 52.02 - -
16 7.64 3 2 2 - - - - 91.68 - -
16 11.05 3 1 2 - - - - 66.30 - -
bottom 16 8.64 3 1 2 - - - - 51.84 - -
16 6.93 3 1 2 - - - - 41.58 - -
16 7.675 3 3 2 - - - - 138.15 - -
16 7.54 3 1 2 - - - - 45.24 - -
negative
bar 14 3.16 2 1 2 - - - 12.64 - - -
14 3.74 2 1 2 - - - 14.96 - - -
stirup 8 1.66 259 1 2 859.88 - - - - - -
8 1.66 66 1 2 219.12 - - - - - -
- - - - - - -
GB2 top 16 11.77 4 1 2 - - - - 94.16 - -
16 7.27 3 1 2 - - - - 43.62 - -
16 7.64 3 2 2 - - - - 91.68 - -
16 11.045 3 1 2 - - - - 66.27 - -
negative
bar 14 3.16 2 1 2 - - - 12.64 - - -
14 4.67 2 1 2 - - - 18.68 - - -
bottom 16 8.595 4 1 2 - - - - 68.76 - -
16 6.89 3 1 2 - - - - 41.34 - -
16 7.68 3 3 2 - - - - 138.24 - -
16 7.54 3 1 2 - - - - 45.24 - -
stirup 8 1.66 260 1 2 863.20 - - - - - -
8 1.66 66 1 2 219.12 - - - - - -
- - - - - - -
GB3 top 16 7.95 3 1 2 - - - - 47.70 - -
bottom 16 7.9 3 1 2 - - - - 47.40 - -
stirup 8 1.36 46 1 2 125.12 - - - - - -
8 1.36 13 1 2 35.36 - - - - - -
- - - - - - -
GB4 top 16 11.02 3 1 2 - - - - 66.12 - -
16 4.66 3 1 2 - - - - 27.96 - -
negative
bar 14 4.67 2 1 2 - - - 18.68 - - -
bottom 16 7.89 3 1 2 - - - - 47.34 - -
16 8.14 3 1 2 - - - - 48.84 - -
stirup 8 1.66 89 1 2 295.48 - - - - - -
8 1.66 23 1 2 76.36 - - - - - -
- - - - - - -
GB5 top 16 9.12 3 1 2 - - - - 54.72 - -
16 7.64 3 1 2 - - - - 45.84 - -
16 11.045 3 1 2 - - - - 66.27 - -
bottom 16 5.62 3 1 2 - - - - 33.72 - -
16 7.675 3 2 2 - - - - 92.10 - -
16 7.54 3 1 2 - - - - 45.24 - -
stirup 8 1.66 159 2 2 1,055.76 - - - - - -
8 1.66 41 1 2 136.12 - - - - - -
- - - - - - -
GB6 top 16 11.395 3 1 2 - - - - 68.37 - -
16 7.64 3 3 2 - - - - 137.52 - -
16 11.045 3 1 2 - - - - 66.27 - -
16 7.89 3 1 2 - - - - 47.34 - -
bottom 16 6.93 3 1 2 - - - - 41.58 - -
16 7.68 3 3 2 - - - - 138.24 - -
16 7.54 3 1 2 - - - - 45.24 - -
8 1.66 265 1 2 879.80 - - - - - -
stirup 8 1.66 67 1 2 222.44 - - - - - -
- - - - - - -
GB7 top 16 7.245 6 1 2 - - - - 86.94 - -
negative
bar 14 2.01 4 1 2 - - - 16.08 - - -
14 2.81 4 1 2 - - - 22.48 - - -
bottom 16 9.295 3 1 2 - - - - 55.77 - -
16 5.19 3 1 2 - - - - 31.14 - -
stirup 8 1.66 74 1 2 245.68 - - - - - -
8 1.66 20 1 2 66.40 - - - - - -
- - - - - - -
GB8 top 16 9.45 3 1 2 - - - - 56.70 - -
2 - - - - - - -
negative
bar 14 1.96 2 1 2 - - - 7.84 - - -
14 2.81 2 1 2 - - - 11.24 - - -
16 9.4 3 1 2 - - - - 56.40 - -
bottom 8 1.56 48 4 2 599.04 - - - - - -
stirup 8 1.56 13 2 2 81.12 - - - - - -
- - - - - - -
GB9 top 16 5.15 3 1 2 - - - - 30.90 - -
2 - - - - - - -
bottom 16 5.1 3 1 2 - - - - 30.60 - -
8 1.26 26 1 2 65.52 - - - - - -
stirup 8 1.26 8 1 2 20.16 - - - - - -
- - - - - - -
GB10 top 16 5.15 3 1 2 - - - - 30.90 - -
16 5.1 3 1 2 - - - - 30.60 - -
bottom 8 1.26 27 2 2 136.08 - - - - - -
stirup 8 1.26 8 1 2 20.16 - - - - - -
- - - - - - -
GB11 top 16 7.095 6 1 2 - - - - 85.14 - -
2 - - - - - - -
negative
bar 14 1.86 4 1 2 - - - 14.88 - - -
14 2.81 4 2 2 - - - 44.96 - - -
2 - - - - - - -
bottom 16 9.14 3 1 2 - - - - 54.84 - -
16 5.04 3 1 2 - - - - 30.24 - -
2 - - - - - - -
stirup 8 1.26 78 6 2 1,179.36 - - - - - -
8 1.26 21 3 2 158.76 - - - - - -
- - - - - - -
TotaL Length (m) 756.00 - - 19.51 288.63 - -
wt/mL(kg/m) 0.395 0.617 1.208 1.578 2.466 3.551
TotaL weight (kg) 298.62 - - 23.57 455.46 - -
No of member Diametr s of Bars
Description Bar No. Dia(mm) Length No of bar ɸ8 ɸ10 ɸ12 ɸ14 ɸ16 ɸ20 ɸ24
Block C(C) Gread beam reinforcement
GB1 top 16 7.05 4 10 2 - - - - 564.00 - -
bottom 16 9.14 4 5 2 - - - - 365.60 - -
16 5.04 4 5 2 - - - - 201.60 - -
stirup - - - - - - -
10 1.4 77 5 2 - 1,078.00 - - - - -
10 1.4 27 5 2 - 378.00 - - - - -
- - - - - - -
GB2 top - - - - - - -
- - - - - - -
- - - - - - -
bottom - - - - - - -
- - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 169 1 2 - 574.60 - - - - -
10 1.7 57 1 2 - 193.80 - - - - -
- - - - - - -
GB3 top - - - - - - -
- - - - - - -
bottom - - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 165 1 2 - 561.00 - - - - -
10 1.7 56 1 2 - 190.40 - - - - -
- - - - - - -
GB4 top - - - - - - -
bottom - - - - - - -
- - - - - - -
stirup - - - - - - -
10 1.7 127 1 2 - 431.80 - - - - -
10 1.7 43 1 2 - 146.20 - - - - -
- - - - - - -
GB5 top - - - - - - -
bottom - - - - - - -
stirup 10 1.4 20 1 2 - 56.00 - - - - -
10 1.4 8 1 2 - 22.40 - - - - -
- - - - - - -
GB6 top 16 9.17 4 1 2 - - - - 73.36 - -
bottom 16 9.17 4 1 2 - - - - 73.36 - -
stirup - - - - - - -
10 1.4 51 1 2 - 142.80 - - - - -
10 1.4 18 1 2 - 50.40 - - - - -
- - - - - - -
TotaL Length (m) - 765.08 - - 255.58 - -
wt/mL(kg/m) 0.395 0.617 1.208 1.578 2.466 3.551
TotaL weight (kg) - 472.05 - - 403.31 - -
Length No of NO OF Total No. of
Location Type Dia (m) No of bar member BLOCKS bars Ø 8 mm Ø 10 mm Ø 12 mm Ø 14 mm Ø 16 mm

For mat - - - - -
Bottom bar 24 8.17 46 1 1.0 46 - - - - -
a./5(Cb-Cd) 24 8.03 46 1 1.0 46 - - - - -
24 6.30 136 1 1.0 136 - - - - -
KZ bar 12 2.70 90 1 1 90 - - 243.00 - -
Total Length - - 60.8 - -
Unit Weight 0.40 0.62 0.89 1.21 1.58
Total Weight 0.00 0.00 53.95 0.00 0.00
Ø 20 mm Ø 24 mm

- -
- 375.59
- 369.15
- 856.80
- -
- 400.4
2.47 3.55
0.00 1,421.37
Company name:

TILAHUN ABEBE GC
Title: Page №:
DAILY REPORT Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY

Reporting Date:-27/04/2015

DELIVERED
Utilized QTY Expense Amount Balance Amount to
S.No Material Description Unit Balance Unit Price Amount TO
ISSUED this day This day date
DATE

1 rebar dia 8 kg 95.65 -


1 rebar dia 10 kg 472.05 95.65 45,153.03
2 rebar dia 12 Kg 53.95 95.65 5,160.05
3 rebar dia 14 Kg 95.65 -
4 rebar dia 16 Kg 403.31 95.65 38,577.63
5 rebar dia 20 Kg 95.65 -
6 rebar dia 24 Kg 1,421.37 95.65 135,956.82
7 plywood used -
8 morale 5cm x 7cm Pcs 162.50 -
13 Eucalipts dia 10 pcs 104.35 -
14 Eucalipts dia 8 pcs 100.00 -
15 Eucalipts dia 12 pcs 175.00 -
17 nail dia 10 kg 144.35 -
18 nail dia 12 kg 10.00 144.35 1,443.48
20 nail dia 9 kg 144.35 -
21 nail dia 8 kg 144.35 -
21 nail dia 6 kg 144.35 -
22 blake wire 1.5 mm kg 200.00 -
23 blake wire 2.5 mm roll 5,000.00 -
24 Agregate 0.2 m3 14.7 451.87 6,660.40
25 Sand m3 12.14 878.25 10,660.66
26 Benzine li 3 56.00 168.00
27 Nafita li 35.05 -

28 Re used nail kg 6.00 55.00 330.00


29 CEMENT QTL 69 490.00 33,987.87
30 NASTRO PCS 50.00 -
31 STRING ROLL 2.00 65.00 130.00
32 Play Wood Pcs 1,100.00 -
33 Purline 5x7 pcs 162.5 -
34 Parker pcs 34.50 -
35 Sayntific calculater 977.50 -
36 Punta 150.00 -
37 Jesso Bag 150.00 -
38 Gas Oil li 517 59.44 30,730.48
39 massonary 5.9 432.00 2,566.08
40 selected material 40% from quarry &60 %from site m3 232.22 -
311,524.49 -
Company name: Document №:

TILAHUN ABEBE GC OF/TAGCON/ ECD/001

Title: Issue №: Page №:


DAILY REPORT 1 Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC
Reporting Date:-27/04/2015

Sub-Contractor Expense report

S.No Description of Work Name of Sub contractor Unit Qty Unit Price Amount Remark

Pit & Trench excavation after reduced


1 bulk level Ato Wasihun m3 100 -

2 lean works Seid Legesse m3 35.00 -

4 concrete work Seid Legesse m3 3.31 350.00 1,159.20


5 FORM WORK Seid Legesse M2 25.40 90.00 2,286.00
6 Rebar work Seid Legesse Kg 3.75 -
7 Hard core Seid Legesse M2 128.25 50.00 6,412.50
8 massonary work Seid Legesse m3 1.48 500.00 742.50

10 lean works DANIEL m2 0.20 35.00 6.93


11 concrete work DANIEL m3 12.32 350.00 4,312.35
13 FORM WORK DANIEL m3 90.00 -
14 Rebar work DANIEL kg 875.37 3.75 3,282.62
15 massonary work DANIEL m2 4.46 500.00 2,227.50
16 hardcore DANIEL m2 -
17 rebar work block B Kg 1,475.31 3.75 5,532.42

Total Amount 20,429.60


Company name: Document №:

TILAHUN ABEBE GC
OF/TAGCON/ ECD/001

Title: Page №:

DAILY REPORT Page 1 of 1


PROJECT:UNDER GRADUATE STUDENTS DORMITOR

LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY

CONTRACTOR : TILAHUN ABEBE GC


Direct Labor Expence

Employee's Working Daily


No Position Qty Amount Signature
Name Hour Salary

1 daily Lbour 8 180 1 180.00

3 daily Lbour 90 -

4 daily Lbour 250 -

5 daily Lbour 8 250 5 1,250.00

5 Cabo 200 -

6 carpenter 8 400 -

7 A.carpenter 250 -

8 Time keeper 8 -

9 Ass Store 8 180 1 180.00

10 Data Collector 8 180 2 360.00

Concrete pump operater


11 Ass 8 200 1 200.00

Total 2,170.00
Company name:

TILAHUN ABEBE GC

Title: Issue №: Page №:


DAILY REPORT
1 Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY

Reporting Date:-27/04/2015

Plate Issued Unit


No Equipment Number Owner Ship HRS Down Idle Fuel Price/Hr Amount Remark

1 plywood Cutter TAGC 8 15.00 120.00

2 Drill TAGC 8 -

3 vibrator(1) TAGC 8 50.00 400.00


4 vibrator(2) TAGC 0.5 7.5 50.00 400.00
5 vibrator TAGC 8 -
6 water pump TAGC 8 125.00 1,000.00
7 water pump TAGC 8 125.00 1,000.00
8 water pump Rental 8 125.00 1,000.00
9 concrete pump (1)SN TAGC 2 6 625.00 5,000.00
10 concrete pump (2)DS TAGC 8 625.00 5,000.00
11 Generator(1) 90 kv TAGC 2 8 0 125.00 250.00
12 Generator(2) TAGC 8 0 200.00 - maintenance
13 Generator(3) TAGC 8 200.00 1,600.00
12 Excavator(DOSAN) TAGC 8 1400.00 11,200.00
13 Total E TAGC 5 3 700.00 5,600.00
14 Mixer 750 (1) TAGC 1.5 6.5 100.00 800.00
15 Mixer 750 (2) TAGC 8 100.00 800.00
16 Mixer 750 (3) TAGC 8 100.00 800.00
17 Mixer 750 (4) TAGC 8 100.00 800.00
18 compactor jumper TAGC 8 100.00 800.00
17 Mixer 350 litre TAGC 8 -
18 roller compactor TAGC 0.5 7.5 1250.00 10,000.00
19 Excavater(CAT) TAGC 5 3 1700.00 13,600.00
20 loder TAGC 2.5 5.5 1250.00 10,000.00
21 Dump truck1 TAGC 8 0 -
22 Dump truck2 TAGC 8 0 625.00 5,000.00
23 Dump truck3 TAGC 8 0 625.00 5,000.00
24 Dump truck4 TAGC 8 0 625.00 5,000.00
25 Dump truck5 TAGC 8 0 625.00 5,000.00
26 Dump truck6 TAGC 8 0 625.00 5,000.00
27 water truck TAGC 8 0 625.00 5,000.00
28 minibus Rental 8 0 145.83 1,166.67
Total Amount(Birr) 100,170.00
Company name:

TILAHUN ABEBE GC

Title: Page №:
DAILY REPORT Page 1 of 1
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC

Indirect Expense report Reporting Date:-27/04/2015


Seq.No Name Position Basic Salary Daily Rate No of Days Payment / day

1 FIKREMARIAM Project manager 38,058.00 1,268.60 1.00 1,268.60


2 Getachew costruction engineer 0.00 1.00 0.00
3 Zena habte Office Engineer 20,000.00 666.67 1.00 666.67
4 Amanuel Eticha Office Engineer 3,558.22 118.61 1.00 118.61
5 Getenet Mola G/Forman 9,000.00 300.00 1.00 300.00
6 Birhanemeskel Teketaye Data Collector 3,000.00 100.00 1.00 100.00
7 temesgen Surveyor 3,969.00 132.30 1.00 132.30
8 habtamu Accountant 4,800.00 160.00 1.00 160.00
9 Beza Goshu Casher 3,500.00 116.67 1.00 116.67
10 Abebe store keeper 5,639.70 187.99 1.00 187.99
- -

Total Amount (Birr) 3,050.83


Company name:
TILAHUN ABEBE GC
Title:

DAILY REPORT
PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING
LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC
Indirect Expens Reporting Date:-27/04/2015

No Material unit Rate Qty

1 cement loading unloading bag -


2 printer toner fill pcs -
3 for fuel filtro(pickup) ls -
4 break oil -
daily labour for other
5 works(benzine and fuel boy ) ls -
6 shofer fee ls -
7 Break oil lit -
8 differential tap ps -
9 motor oil lit -
10 material loading unloading -
11 test fee for RE LS -
12 inventory count -
13 marker pkt -
14 vibrator screw -
15 vibrator relay -
16 Grease (9 kg)excavator KG -
17 Grease (9 kg)mixer KG -
18 socket pcs -
19 hose dumptruck pcs -
20 electric wire 2.5 m -
Daprator washing(pick up) and tyre
21 maintenance -
22 pick up maintenance -
23 pick up traffick police penality -
24 highligter -
25 traffic police penalty -
26 uhu -
27 file box -
28 For chain key pcs -
29 plastic hose for fuel -
30 hose maintenance -
31 mixer maintenance -
32 scan -
33 DL -
34 water hose -
35 tyre(pick up) ls -
36 screw(blon and dado) -
37 photocopy -
38 maintenance(water truck+pickup) -
39 nail -
40 pikup parking -
41 fuel filtro -
42 battery charge -
43 connector dia6 -
44 compressor mastenfesha -
45 connector and fuez -
46 cemnt -
47 battery charge -
48 cabo -
49 guard hand light -
50 concrete pump (kalemedari) -
51 shoe(bot chama) -
52 PPR FOR PUMP -
53 compressor -
54 pick up maintenance -
55 BREAKER 32 AMP PCS -
56 NASTRO PCS -
57 TEFLON PCS -
58 STATIONARY FOR RE LS -
59 pen pkt -
60 plastic rope brush -
61 note book pcs -
62 flash disck for Re pcs -
63 copy ls -
64 jeso pcs -
65 nail 12 PKT -
66 nail 10 PKT -
66 water tanker(steel) pcs -
67 A4 paper pcs -
68 pick up break ls -
69 wifi modem for RE no -
perdime for employees & driver
70 Incentive ls -
71 first aid -
72 wire m -
73 divider pcs -
74 largo -
75 roller meter -
76 meter hand -
77 hospital fee -
78 Generator maintenance -
79 Water pump rent Pcs -
80 Fuel for pikup -
81 JIRA TIBO(12 INCH) PCS -
82 black wire roll -
83 wter pump rent ls -
84 grease brush pcs -
85 jerican pcs -
86
Total -
Company name:
ጥላሁን አበበ ጠቅላላ ስራ ተቋራጭ

Title:
JUSTIFICATION RECORD

PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDIN


LOCATION:DEBRE BERHAN
CLIENT: DEBRE BIRHAN UNIVERSITY
CONTRACTOR : TILAHUN ABEBE GC
Location :

oor Work Progress(Loss of Planned Progress or an Executed

Sr. no Credible Reason For Not


Performing as Per Plan

Requested Budget Delay


1 Related

2 Equipment & Machinery


Related breack down
Direct Labor Related
3 (Site Employed)

4 Project Performance/Out
Put Related

Consultant Related
6 Other Factors

Total Unexecuted Amount

Sign:___________________
Date:-
TILAHUN ABEBE GENERAL CONTRACTOR

TUDENTS DORMITORY BUILDING


EBRE BERHAN
RHAN UNIVERSITY
LAHUN ABEBE GC
tion :

Reporting Date:-27/04/2015

Major Problems

generator problem
labours shortage due to
holyday

Other issues

Other issues
Sub Total

Other issues

Sub Total
Sub Total
ABEBE GENERAL CONTRACTOR

Reporting Date:-27/04/2015
Description of Main works not Unexecuted Amount
executed+D14:D19D14:D25
Sign:___________________
Date:-
% from Total
Plan
________
Description of Problems
Encountered
-

We build dreams !
Document №:

OF/TAGC/ ECD/42

Issue №: Page №:

1 Page 1 of 1

Remedial measure
taken by the project (if Remark
any)
-
-

Sign:___________________
Date:-
Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
TAKEOFF SHEET Issue No
. EXCAVATION & EARTH WORK

PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING CONSULTANT:


LOCATION:DEBRE BERHAN CONTRACT AMOUNT:
CLIENT: DEBRE BIRHAN UNIVERSITY
BLOCK NO.: C
No L/W/D Sum Description No L/W/D Sum Description

Company Name:
Docment No
TIlAHUN ABEBE GENERAL CONTRACTOR
TAKEOFF SHEET Issue No
. EXCAVATION & EARTH WORK

PROJECT:UNDER GRADUATE STUDENTS DORMITORY BUILDING CONSULTANT:


LOCATION:DEBRE BERHAN CONTRACT AMOUNT:
CLIENT: DEBRE BIRHAN UNIVERSITY
BLOCK NO.: C
No L/W/D Sum Description No L/W/D Sum Description