PROJECT PROPOSED WAREHOUSE FLOOR AREA 540 SQM

LOCATION PAWILI, CAMARINES SUR TOTAL COST 4,557,994 PESOS


OWNER MR. EUGENE LEE COST /SQM 8,441 PESOS/SQM
SUBJECT BILL OF QUANTITY & ESTIMATE

UNIT TOTAL
ITEMS SCOPE OF WORKS QTY UNIT
RATE AMOUNT
A. GENERAL REQUIREMENTS
1.00 Mobilization 1.00 lot 50,000.00 50,000.00
2.00 Permit and Licenses
a. Building Permit
BY OWNER
b.Occupancy Permit
c. Municipality Contractors tax
SUB-TOTAL 50,000

B. CIVIL-STRUCTURAL WORKS
1.00 Excavation works 237.64 m3 300.00 71,292
a. Footing
F1 160.00 m3 500.00 80,000
b. Tie beam
FTB 129.30 m3 500.00 64,650
c. Wall Footing
WF-1 77.64 m3 500.00 38,820
2.00 Backfilling 121.77 m3 300.00 36,532
3.00 Soil Poisoning 0.00 m3 120.00 -
4.00 Gravel Bed (G1) 81.22 m3 1,500.00 121,833
5.00 Disposal/Haul-out of Construction debris 37.65 m3 200.00 7,529
SUB-TOTAL 420,656

C. REBARS (Grade 40)


1.00 Foundation
1.1 Isolated Footing (F1)
16mm 696.00 kg 55.00 38,280
#16 tie wire 512 kg 75.00 38,400
2.00 2.1 Wall Footing (WF)
2.2 10mm 300 kg 55.00 16,500
2.3 16mm 300 kg 55.00 16,500
2.4 #16 tie wire 100 kg 75.00 7,500
2.5 Fabrication & installation 1908 kg 10.00 19,080
3.00 Columns
3.1 All Columns
3.2 10mm 622 kg 50.00 31,111
3.3 16mm 2100 kg 50.00 105,000
3.4 #16 tie wire 2688 kg 60.00 161,280
3.5 Fabrication & installation 7318 kg 10.00 73,182
4.00 Slab on grade (SOG)
4.10 10mm 100 kg 50.00 5,000
4.20 12mm 4694 kg 50.00 234,700
4.30 #16 tie wire 1414 kg 60.00 84,864
4.40 Fabrication & installation 6208 kg 10.00 62,084
5.00 Lintel beams
5.1 10mm 50.00 kg 50.00 2,500.00
6.00 Beam/Suspended Slab
6.1 10mm 99.00 kg 50.00 4,950.00
6.2 12mm 50.00 kg 50.00 2,500.00
6.3 16mm 189 kg 50.00 9,450.00
6.4 Fabrication & installation 338 kg 10.00 3,380.00
7.00 Counter top
7.1 12mm 0.00 kg 50.00 -
8.00 Stairs
8.1 10mm 0.00 kg 50.00 -
8.2 12mm 0.00 kg 50.00 -
9.00 Walls
9.1 10mm 1653 kg 50.00 82,630
10.00 Sagrod
10.1 10mm 50.00 kg 50.00 2,500
SUB-TOTAL 1,001,391

D. FORMWORK
1.00 Foundation 725.04 sqm 250.00 181,260
1.1 F1 (1.5x1.5x.30)
2.00 Wall Footing
2.1 WF-1
3.00 Columns 192.00 sqm 250.00 48,000
3.1 C1 (0.3X0.3)
Beam/girders
3.2 Tie beam 1.00 sqm 250.00 250
3.3 Roof beam 1.00 sqm 250.00 250
3.4 Lintel beams 1.00 sqm 250.00 250
4.00 Slab 50.00 sqm 250.00 12,500
4.1 SOG
4.2 Counter top 2.00 sqm 250.00 500.00
5.00 Lintel beams
SUB-TOTAL 243,010

E. CONCRETING
1.00 Foundation
1.1 F1 (1.5x1.5x.30) 13.60 cum 1,700.00 23,120
2.00 Tie beam - -
2.1 FTB 4.86 cum 1,700.00 8,262
3.00 Wall Footing 1.69 cum 1,700.00 2,873
4.00 Columns -
4.1 C1 (0.3X0.3) 14.40 cum 1,700.00 24,480
5.00 Slab - -
5.10 SOG 54.00 cum 1,700.00 91,800
6.00 Lintel beams - -
6.10 Doors 1.00 m3 1,700.00 1,700
0.10 Windows 1.00 m3 1,700.00 1,700
7.00 Beam/Girders 5.00 -
7.10 B1 4.86 cum 1,700.00 8,262
8.00 Stairs 0.00 cum 1,700.00 -
SUB-TOTAL 162,197

F. ROOFING

1.00 Angular Bar - 3" x 3" x 3/16" 4290.48 kg 55.00 235,976


2.00 Angular Bar - 2 1/2" x2 1/2" x 3/16" 224.05 kg 55.00 12,323
3.00 1/2' round bar with turnbuckel 1.00 lot 15,000.00 15,000
4.00 C - Purlins - 2" x 4" x 2.0 mm 3321.00 kg 55.00 182,655
5.00 Pre-painted Gutter, GA 24(0.701mm) x 2.44m 128.00 ln/m 250.00 32,000
6.00 Pre-painted Metal Roofing Sheet Ga. 26 x 2.44m 540.00 sqm 300.00 162,000
7.00 Steel Fabrication & installation labor 7836.53 kg 20.00 156,731
8.00 Roof Installation labor 540.00 sqm 20.00 10,800
9.00 Erection & dismantling of scaffoldings 540.00 sqm 50.00 27,000
SUB-TOTAL 834,484

G. MASONRY
1.00 CHB Laying - -
1.1 Interior 36.30 sqm 600.00 21,779
1.2 Exterior 768.00 sqm 700.00 537,600

2.00 PLASTERING - -
2.1 Interior 72.60 sqm 800.00 58,076
2.2 Exterior 1536.00 sqm 800.00 1,228,800

SUB-TOTAL 1,846,255
area
TOTAL COST STRUCTURAL 4,557,994 540