Name and address of

Sl. Voltage Length of the Line Value of Order Date of Commissioning / Taking
the Order placing Order No. & Date Name of the line Scope of work
No. Class (in Km) (in lacs) Over / Completion
authority
47 CSPTCL, Raipur 02-04/P&P/Supply/ Line/Ord/ TR- Nagri to Indagaon (Deobhog) 132kV Km 68.000 2161.65 05.09.2022 Survey, Foundation, Erection, Stringing
18/27/2390 and 02-04/ P&P/ Dist Gariyabandh. DCSS including Supply of all materials e.g. - Towers,
Constn.Charges/ Line/ Ord/TR- Bolts & Nuts, Tower Accessories, Conductor,
18/27/2388 both dtd 07.02.2020 Earthwire / Line Hardwares etc.

48 PGCIL,Gurgaon CC-CS/91-NER/ TWT-2469/ i) Phulbari – Ampati Line - 132kV D/C Km 49.870 6368.27 23.09.2022 Survey, Foundation, Erection, Stringing
1/G4/NOA-I/5843 & CC-CS/ 91- COMPLETED including Supply of all materials e.g. - Towers,
NER/TWT-2469/1/G4/ NOA- ii) MLHEP – Khlerihat at Bolts & Nuts, Tower Accessories, Conductor,
II/5844 both dtd 29.06.2016 (for Mynkre Line Earthwire / Line Hardwares etc.
PackageTW02)

49 PGCIL,Gurgaon NOA No.CC-CS/91-NER/TWT- Tower Packages TW01 220kV D/C Km 129.348 14758.44 14.09.2023 & 14.12.2023 Survey, Foundation, Erection, Stringing
2468/1/G4/NOA-I/5841 & CC- Associated with NER Power including Supply of all materials e.g. - Towers,
CS/91-NER/TWT-2468/1/G4/ System Improvement Project Bolts & Nuts, Tower Accessories, Conductor,
NOA-II/5842 both dtd (Inter-State: Meghalaya) - Earthwire / Line Hardwares etc.
29.06.2016 ( for Package TW01) (i)- 220kV D/C Killing
(Byrnihat) - 86.208 Kms and
(ii)- 220kV Mawngap-New
Shillong Transmission Line -
43.140 Kms &
(iii)- OPGW Live Line links -
484 Km

TOTAL ===> 1987.772 81988.350