CONSTRUCTION PLANNING
NQF LEVEL 2
(12010042)
TIME: 3 HOURS
MARKS: 100
3. Number the answers according to the numbering system used in this question
paper.
6. ALL the abbreviations and symbols must comply with the latest National
Building Regulations and ALL relevant SANS (SABS) codes.
1.2 Give TWO reasons why national building regulations should be adhered to
when building. (2)
[7]
2.1 Indicate whether the following statements are TRUE or FALSE. Choose the
answer and write only 'True' or 'False' next to the question number
(2.1.1–.1.5) in the ANSWER BOOK.
2.1.3 For a house to be perfectly square, the diagonal length across the
area of a square house should be the same.
2.1.4 A two peg method is used to find the level difference of two places.
2.2 Explain how you would use a levelling instrument to calculate horizontal
distance from the instrument to another point using the stadia hairs. (4)
Explain how you would set out this on the ground. Use rough sketches to
illustrate. (6)
2.4 Give FOUR disadvantages of using a water level for levelling. (4)
2.5 A reading of 950 is taken at a point B using a level. Then a reading to the
benchmark 1 300 is taken with the level in the same position.
What will the elevation be of point B given the elevation of the benchmark is
100 meters above sea level? (4)
2.6 FIGURE 1 below shows a Vernier calliper which is used to obtain dimensions
of objects too small to measure accurately.
Name the SIX parts of the Vernier calliper marked from 1–6 respectively.
FIGURE 1 (6)
[29]
QUESTION 3: FOUNDATIONS
3.1 Explain why a site soil investigation is recommended before building a new
structure. (3)
3.2 Explain the cases where raft foundations become the best option. (4)
4.1 Give ONE word/term for each of the following descriptions by choosing a
word/term from the list below. Write only the word/term next to the question
number (4.1.1–4.1.5) in the ANSWER BOOK.
4.1.4 The beam that is held and supported at one end only
4.3 FIGURE 2 below shows a vertical section through one side of a cantilever
beam fixed wall. Reproduce the drawing in your ANSWER BOOK and
indicate the area where tension and compression is located.
FIGURE 2 (2)
C
B
D
A
FIGURE 3 (4 × ½) (2)
4.5 Explain the difference between a point load and uniform distributed load. (2)
4.5 How would one differentiate between plane frames and space frames? (2)
4.7 Name the TWO kinds of loads that cause a five hinge and a four hinge failure
of arches. (2)
[18]
5.1.4 25 mm³ to m³
5.2.1 Force
5.2.3 Current
5.2.4 Energy
5.2.5 Power
(5 × 1) (5)
[10]
6.1 Calculate the concrete needed for a strip footing 600 mm × 200 mm all
around. (3)
6.3 Calculate the litres of paint needed to paint both inside and outside. (2)
[10]
7.1.1 Brick
7.1.2 Stone
7.1.3 Insulation
7.1.5 Screed
(5 × 1) (5)
7.2 What do the following symbols or abbreviations on a building plan stand for?
7.2.1 RWP
7.2.2 BIC
7.2.3 SP
7.2.4 HR
7.2.5 SWP
7.2.6 FFL
(6 × 1) (6)
7.4 Name the TWO drawings on a building plan needed to set out a new building. (2)
[16]
TOTAL: 100