Afpam10 219 v6

Download as pdf or txt
Download as pdf or txt
You are on page 1of 126

BY ORDER OF THE AIR FORCE PAMPHLET 10-219, VOLUME 6

SECRETARY OF THE AIR FORCE 1 FEBRUARY 2006


Certified Current, 8 March 2012
Operations

PLANNING AND DESIGN OF


EXPEDITIONARY AIRBASES

NOTICE: This publication is available digitally on the AFDPO WWW site at:
http://www.e-publishing.af.mil.

OPR: HQ AFCESA/CEXX Certified by: HQ AFCESA/CEX


(Lt Colonel Kent H. Nonaka) (Colonel Thomas D. Quasney)
Pages: 126
Distribution: F

This volume provides deployment information to allow civil engineers and logistics planners to plan for,
design, establish and sustain expeditionary airbases. When used in conjunction with Volume 5 of this
pamphlet series, theater and wing planners, advance echelon (ADVO N) team members and deploying
expeditionary engineers will have the basic tools re quired to identify and employ consistent standards
across the service components for infrastructure development, security and sustainment support for expe-
ditionary bases. This volume is not intended to provide a definitive design or layout applicable for every
type of deployment. It is intended to provide theplanning criteria and background necessary to: (1) Deter-
mine what facilities are required to support Air Force, Joint and Coalition deployments supporting Aero-
space Expeditionary Force (AEF) mi ssions; (2) Identify forces, equipment and resources required to
provide adequate support fa cilities; (3) Understand the factors that affect transition between initial and
temporary standards; (4) Sustain facility operations through redeployment and reconstitution. Ensure that
all records created as a result of processes prescribed in this publication are maintained in accordance with
AFMAN 37-123, Management of Records, and disposed of in accor dance with the Air Force Records
Disposition Schedule located at https://webrims.amc.af.mil.

Chapter 1— INTRODUCTION 7
1.1. References, Abbreviations, Acronyms and Terms. ................................................... 7
Figure 1.1. Southwest Asia Bare Base Support Facilities. .......................................................... 7
1.2. Purpose. ...................................................................................................................... 7
1.3. Scope. ......................................................................................................................... 8
1.4. Background. ............................................................................................................... 8
Figure 1.2. 1980s Cold War Overseas Basing. ........................................................................... 8
Figure 1.3. Permanent Overseas Basing in 2005. ....................................................................... 9
Figure 1.4. Overseas Basing Supporting Global War on Terrorism – 2005. .............................. 9
2 AFPAM10-219V6 1 FEBRUARY 2006

Figure 1.5. Air Force 2005 World Wide Deployed Presence. .................................................... 10
1.5. Base and Construction Standard Terminology and Definitions. ............................... 10
Figure 1.6. Main Operating Bases in Southwest Asia. ................................................................ 10
1.6. Planning for Initial Standard Expeditionary Airbases. .............................................. 10

Chapter 2— AIR EXPEDITIONARY FORCE BARE BASE PLANNING


AND DEVELOPMENT 12
2.1. Overview. ................................................................................................................... 12
Figure 2.1. Tent City during Operation ENDURING FREEDOM. ............................................ 12
2.2. AETF Force Modules. ............................................................................................... 12
2.3. Force Modules. .......................................................................................................... 13
Figure 2.2. AETF Force Module Phased Deployment. ............................................................... 13
2.4. Bare Base Terminology, Definitions and Types. ....................................................... 14
2.5. Construction Standards Definitions and Terminology. ............................................. 15
Figure 2.3. Initial Construction Standard at FOB in Afghanistan. .............................................. 16
Figure 2.4. Temporary Construction Standards for Lodging. ..................................................... 17
2.6. Expeditionary Airbase Development and Planning Process. ..................................... 17
2.7. Operations and Maintenance (O&M). ....................................................................... 19
2.8. Expeditionary Facilities and Beddown Sets. ............................................................. 19
2.9. Better Deployable Facilities. ...................................................................................... 19
2.10. Transportability Issues versus Developmental Timelines. ........................................ 19
Table 2.1. Mission Support to Various Deployment Sets. ......................................................... 20
2.11. Airlift Limitations versus Developmental Timeline. ................................................. 20
2.12. Real World Transport/Logistics Lessons Learned ..................................................... 20
Figure 2.5. Sealift of Military Equipment. .................................................................................. 21
2.13. Mission Considerations. ............................................................................................. 21
2.14. Influence of Base Type and Location. ....................................................................... 21
Figure 2.6. Joint Forces Airbase in Bosnia. ................................................................................ 22
Figure 2.7. Various Construction Standards in Bosnia. .............................................................. 23
2.15. Developmental Timeline Considerations. .................................................................. 23
Figure 2.8. BEAR Sets Supporting a Force Module Beddown. .................................................. 24
2.16. Engineering Considerations. ...................................................................................... 24
AFPAM10-219V6 1 FEBRUARY 2006 3

2.17. Survey, Expeditionary Site Mapping (formerly GeoReach) and Other Information
Based Plans. ............................................................................................................... 24
2.18. Airfield Surveys and Operational Data Collection. ................................................... 25
2.19. Priority Requirements During Planning. ................................................................... 26
2.20. Coalition or Host Nation Support Capabilities and Limitations. ............................... 27
2.21. Mine/UXO Presence. ................................................................................................. 28
2.22. Considerations for Joint Operations Beddowns. ........................................................ 28
2.23. Support Plans. ............................................................................................................ 29
Figure 2.9. MREs vs. Mobile Kitchen Trailer. ............................................................................ 30
2.24. Expeditionary Combat Support (formerly Base Operating Support). ....................... 30
2.25. Command and Control Relationships. ....................................................................... 30

Chapter 3— PLANNING FOR BASE OPERATING AND SUPPORT FACILITIES 31


3.1. Overview. ................................................................................................................... 31
Figure 3.1. Bare Base Sighted Alongside Host Nation Facilities. .............................................. 31
3.2. Purpose. ...................................................................................................................... 31
3.3. Facility Standards for Base Camps. ........................................................................... 31
3.4. Force Protection and Safety. ...................................................................................... 31
3.5. Authorized and Required Facilities. .......................................................................... 32
Table 3.1. Levels of Protection – Expeditionary and Temporary Structures. ............................ 33
Table 3.2. Expeditionary Airbase Construction Standards in Theater.
(MOB Guidelines – Refer to Atths 4, 5 & 6 for detailed info). ............................... 34
Table 3.3. AAFES Contingency Facility Requirements Planning Matrix. ................................ 43
Table 3.4. MOB, FOL, and FOB Facility Authorization Guidance. ......................................... 44
3.6. Facility Construction Standards. ................................................................................ 45
3.7. Utilities. ...................................................................................................................... 47
3.8. Electric Power. ........................................................................................................... 47
3.9. Environmental Control (Heating/Air Conditioning). ................................................. 48
3.10. Potable Water Recommendations. ............................................................................. 49
3.11. Waste Treatment Plant. .............................................................................................. 49
3.12. Personnel Support. ..................................................................................................... 49
3.13. Planned Upgrades. ..................................................................................................... 50
3.14. Manpower Utilization and Task Assignment. ........................................................... 50
4 AFPAM10-219V6 1 FEBRUARY 2006

Table 3.5. Contingency Task Execution Resources. .................................................................. 51


3.15. Air Force Basic Expeditionary Airfield Resources (BEAR). .................................... 51
Figure 3.2. Typical BEAR Tent City. ......................................................................................... 52
Figure 3.3. BEAR 150 (Swift BEAR) Assets. ............................................................................ 53
3.16. Army Force Provider Resources. ............................................................................... 53
Figure 3.4. US Army Force Provider Set. ................................................................................... 53
Figure 3.5. Force Provider Containerized Latrine and Shower Facilities. .................................. 54
3.17. Navy Camp 750 Resources. ....................................................................................... 55
Table 3.6. Air Force, Army and Navy Basic Beddown Sets. .................................................... 56

Chapter 4— BARE BASE UTILITIES DEVELOPMENT 58


4.1. Overview: ................................................................................................................... 58
4.2. Problems and Solutions. ............................................................................................ 58
Figure 4.1. Typical BEAR Utility Assets. ................................................................................... 58
4.3. Potable Water. ............................................................................................................ 58
4.4. Latrine/Sanitation Facilities. ...................................................................................... 59
Figure 4.2. Expeditionary Latrines during Contingency Operations. ......................................... 59
4.5. Electrical Development: ............................................................................................ 60
4.6. Conclusion. ................................................................................................................ 60

Chapter 5— SECURITY AND FORCE PROTECTION DEVELOPMENT 61


5.1. Overview. ................................................................................................................... 61
Figure 5.1. Security Forces Providing Perimeter Security. ......................................................... 61
5.2. Force Protection Planning. ......................................................................................... 61
Figure 5.2. PSAB Airbase (Before and After Buildup). ............................................................. 62
Figure 5.3. Expeditionary Airbase in Afghanistan. ..................................................................... 63
5.3. Classification of Threats. ........................................................................................... 64
Table 5.1. EAF Airbase Threat Matrix. ..................................................................................... 64
Table 5.2. Airbase Defense Threat Levels. ................................................................................ 64
Figure 5.4. Infrared Sensor Security System Installed on Base Perimeter. ................................ 65
Figure 5.5. Surveillance from Over Watch Tower. ..................................................................... 66
5.4. Security Forces Base Defense CONOPS. .................................................................. 67
AFPAM10-219V6 1 FEBRUARY 2006 5

5.5. Force Protection and Safety. ...................................................................................... 68


5.6. Minimum Force Protection Design Standards. .......................................................... 68
Table 5.3. Minimum Standoff Distances & Separation for Exped. & Temp. Structures. ......... 70
Figure 5.6. Standoff Distances and Separation for Expeditionary and Temporary Facilities. .... 71
5.7. Threat Specific Standards. ......................................................................................... 71
5.8. Siren Warning System (Giant Voice). ....................................................................... 72
5.9. Mines, Improvised Explosive Devices and Unexploded Ordnance. ......................... 73
Table 5.4. Neutralization and Detection Methods for UXOs. ................................................... 74
Figure 5.7. Explosive Potential and Evacuation Distances. ........................................................ 75

Chapter 6— FACILITIES UPGRADE, SUSTAINMENT AND MAINTENANCE 77


6.1. Overview. ................................................................................................................... 77
6.2. Transition to Temporary Standard, Semi-Permanent and Permanent Facilities. ....... 77
Figure 6.1. Prince Sultan Airbase – Enduring Presence Construction Standard. ........................ 77
6.3. Normal Transition to Temporary Facilities. .............................................................. 78
6.4. Funding Transition and Beddown Construction. ....................................................... 78
6.5. Other Authorities and Sources of Funding. ............................................................... 79

Chapter 7— REDEPLOYMENT AND RECONSTITUTION 81


7.1. Overview. ................................................................................................................... 81
7.2. Transition. .................................................................................................................. 81
Figure 7.1. Recovery of BEAR Assets. ....................................................................................... 81
7.3. Redeployment. ........................................................................................................... 82
7.4. General Considerations for Redeployment and Reconstitution. ................................ 82
7.5. Reconstitution of BEAR Assets. ................................................................................ 82
7.6. Recovery. ................................................................................................................... 83
7.7. Civil Engineering Support of Transition Operations. ................................................ 83
7.8. Redeployment Scheduling, Validation and Transport. .............................................. 84
7.9. Redeployment Requirements Validation. .................................................................. 84
7.10. Environmental Requirements. ................................................................................... 85
7.11. Conclusion. ................................................................................................................ 85

Chapter 8— CONTRACT AUGMENTATION PROGRAMS 86


8.1. Overview. ................................................................................................................... 86
6 AFPAM10-219V6 1 FEBRUARY 2006

8.2. Air Force Guidance on Contractors in Theater of Operations. .................................. 86


8.3. Air Force Contract Augmentation Program. .............................................................. 88
8.4. Ancillary Capabilities. ............................................................................................... 92
8.5. Materiel Support. ....................................................................................................... 93
8.6. General. ...................................................................................................................... 93
8.7. Logistics Civil Augmentation Program (LOGCAP). ................................................ 94
8.8. US Navy Contingency Construction Capabilities (CONCAP). ................................. 95
8.9. Conclusion. ................................................................................................................ 95
8.10. Forms Adopted. ......................................................................................................... 96

Attachment 1— GLOSSARY OF REFERENCES AND SUPPORTING INFORMATION 97

Attachment 2— RECOMMENDED CE UTC BASED ON MISSION REQUIREMENTS 109

Attachment 3— MAIN OPERATING BASE AUTHORIZED FACILITIES/


CONSTRUCTION STANDARDS 111

Attachment 4— FORWARD OPERATING BASE AUTHORIZED FACILITY/


CONSTRUCTION STANDARDS 124

Attachment 5— FORWARD OPERATING LOCATION AUTHORIZED FACILITY


STANDARDS 126
AFPAM10-219V6 1 FEBRUARY 2006 7

Chapter 1

INTRODUCTION

1.1. References, Abbreviations, Acronyms and Terms. Related publications, abbreviations, acronyms
and terms used in this volume are listed in Attachment 1.

Figure 1.1. Southwest Asia Bare Base Support Facilities.

1.2. Purpose. This volume was developed to provide deployment informa tion, which will allow engi-
neers and logistic planners to pl an for, design, establish and sustai n Aerospace Expeditionary Force air-
bases. When used in conjunction with Volume 5 of this series, theater and wing planners, advance echelon
(ADVON) team members and deploying units’ expeditionary engineers will have the basic tools required
to identify and employ consistent standards and expectations across the service components for infra-
structure development, security and sustainment support for expeditionary bases. This volume is not
intended to provide a definitive de sign or layout applicable for every type of deployment. Rather, it is
intended to provide the planning criteria and background necessary to:
1.2.1. Determine what facilities are required to support Air Force and joint service deployments con-
ducted for Aerospace Expeditionary Forces operations.
1.2.2. Identify what forces, equipment and resources are required to provide adequate support facili-
ties.
1.2.3. Understand the factors that affect transition between initial and temporary standards.
1.2.4. Sustain facility operations within conditions that require a range from austere to initial to tem-
porary standard.
8 AFPAM10-219V6 1 FEBRUARY 2006

1.3. Scope. The materials in this volume are most helpful when used as an update to bare base planning.
It updates bare base planning criteria to consider various Expeditionary Aerospace Force (EAF) deploy-
ment strategies used to support theater of operations (TO) locations. It provides: planning, design, layout
and construction considerations based on force deployment; additional information on deployment time-
lines; expected facility requireme nts along the timeline; information on tailoring of forces and support
packages; and lessons learned based approaches to sustaining facilities and utilities.

1.4. Background. Prior to 1989, the Air For ce was postured a gainst one primary threat, the Soviet
Union. Much of our force was fo rward deployed and if called to fight, would do so from home base or
would deploy to a well-established, permanently manned facility. While our mobility forces deployed in
support of humanitarian operations, our combat forces generally did no t deploy away from well-estab-
lished bases.

Figure 1.2. 1980s Cold War Overseas Basing.

1.4.1. As permanent forward ba sing was lost, more rapidly deployable, U.S.-based forces were
required to assume greater responsibilities to support operations. The ability to project power quickly
across the globe was becoming mo re of a requirement. In the 1990s , while the number of Air Force
wings and personnel were being reduced, the requi rements for support of operations abroad were
increasing.
1.4.2. Since the Gulf W ar, deployment of both combat and support forces has increasingly been to
more austere forward locations – this has become a way of life for the Air Force. The Air Force stood
up numerous expeditionary bases in much the same way that the Navy and Marines approached expe-
ditionary basing. This approach to deployments led to the Air Fo rce reorganizing under the Expedi-
tionary Aerospace Force construct in January 200 0. To support the EAF construct, Aerospace
Expeditionary Forces (AEFs) are formed that operationally link ge ographically separated units into
ten AEFs, each with a designated lead wing. There are also five mobility lead wings designated to pro-
vide global mobility and a constant flow of vital supplies, equipment and other resources from the
United States and allied nations into a theater of operations.
AFPAM10-219V6 1 FEBRUARY 2006 9

Figure 1.3. Permanent Overseas Basing in 2005.

Figure 1.4. Overseas Basing Supporting Global War on Terrorism – 2005.

1.4.3. This publication provides guidance for planning and developm ent of expeditionary airfields
that support associated missions in accordance with Joint Publication 4-04, Joint Doctrine for Civil
Engineering Support. This publication also addresses expeditionary airfield development planning for
the orderly and efficient management, development of land, facilities and infrastructure. The goal is to
take the intent and guidance of Air Force and joint infrastructure and installation regulations and apply
10 AFPAM10-219V6 1 FEBRUARY 2006

them to expeditionary operations. This publication is not intended to address all aspects of expedition-
ary airfield planning. For instance, the combatant commander specifies the construction standards for
expeditionary facilities under his responsibility. These standards are established to ensure that projects
support the commander’s intent and concept of operations.

Figure 1.5. Air Force 2005 World Wide Deployed Presence.

1.5. Base and Construction Standard Terminology and Definitions. Wi t h i n e x p e d i t i o n a r y a n d


long-term operations, there are four types of base camps: forward op erating locations (FOL), forward
operating base (FOB), main operating base (MOB) and intermediate staging base (ISB).

Figure 1.6. Main Operating Bases in Southwest Asia.

1.6. Planning for Initial Standard Expeditionary Airbases. Today’s EAF mobility concept of "light,
lean and lethal" requires rapid deployment. An AEF wing, group, squadron or unit may deploy to an aus-
tere bare base location that has a runway, taxiways, parking ramp and a source of water that can be made
potable. The deployment has often been accomplished with smaller, tailored Unit Type Code (UTC) pack-
ages and with a mix of aircraft. An austere forward airbase's runway, taxiways and parking ramp may not
AFPAM10-219V6 1 FEBRUARY 2006 11

be adequate to meet the requirement for all planned deployed forces; additional engineering forces, such
as the Air Force’s Rapid Engineer Deployable H eavy Operations Response Squadron Engineers (RED
HORSE), or the Navy’s Construction Battalions (CBs or Seabees) or Army Combat Heavy Engineers,
may be required to provide repairs, upgrading and/or expansion to allow full, planned mission use. The
location may also have limited vertical facilities and utilities that can be used, but may have to be repaired
prior to occupancy for its final intended purpose. Ma ny locations may have to re ly on air mobility f or
most or all support. Besides having to use tailored UTC packages for aircraft and personnel, support pack-
ages may have to be further tailored to make them lighter. Some support operations may have to initially
exist as austere, while waiting for resource and logistics capability to robust facilities. Engineers at austere
locations need to plan for increased reliance on expedient expeditionary construction techniques to ensure
mission accomplishments while wa iting for upgrades. D evelopmental delays are usually related to
early-on, airlift-only logistics support for the forward location being dedicated to joint operational support
of other services, such as Army a nd Marine units and special operations forces. Expedient facilities may
be the fill-in method for operating in initial austere locations. Guidance on expedient engineering methods
can be found in AFPAM 10-219, Volume 7, Expedient Construction Methods.
12 AFPAM10-219V6 1 FEBRUARY 2006

Chapter 2

AIR EXPEDITIONARY FORCE BARE BASE PLANNING AND DEVELOPMENT

2.1. Overview. During the last decade of the Twentieth Century, the US military witnessed many transi-
tions: an end to th e Cold War, semi-permanent overseas basing with stateside reinforcement; Operation
DESERT SHIELD prepositioning along with mass transportation and large scale deployment; low inten-
sity conflicts ruled by geopolitical diplomacy and limited military for ces; joint and coalition peacekeep-
ing forces; deployments for military actions other than war; and EAF operations to support rapid, global
deployment. Operation DESERT SHIELD is considered a classic case for lar ge-scale joint deployment
and Global Reach-Global Power force projection to bare bases. Still, DESERT STORM demonstrated that
there were many expeditionary combat support issues to be resolved to im prove global deployments.
Rapid and continually evolving operational a nd beddown requirements dur ing Operation ENDURING
FREEDOM (OEF) and Operation IRAQI FREEDOM (OIF) drove the Air Force to the Air Expeditionary
Task Force (AETF) force module concept of operations. This concept provides clearer planning guidance
for opening and establishing airbases in an expeditionary environment. Engineering planners must con-
sider GMTF CONOPS, mission requirements, climate, host nation capabilities, anticipated operational
duration and airfield and facilities conditions during all phases of the five force modules.

Figure 2.1. Tent City during Operation ENDURING FREEDOM.

2.2. AETF Force Modules. Force modules provide the framework to systematically present capability
to rapidly open an airfield, establish operational capability and conduct air operations thereafter. A force
module is defined as a grouping of combat and e xpeditionary combat support UTCs wi th accompanied
supplies and required non-unit resuppl y and personnel necessary to sust ain forces for a minimum of 30
days. Elements of force modules ar e linked together or are uniquely identified so that they may be
extracted from or adjusted as an entity in the Joint Operations Planning and Execution System (JOPES)
databases to enhance flexibility and usefulness of the operations planning and execution process. Force
modules provide planners a simple methodology for matching specific personnel and equipment for spe-
cific mission requirements.
AFPAM10-219V6 1 FEBRUARY 2006 13

2.3. Force Modules. Force modules help standard ize the planning and execution of how forces are
employed and ensure a repeat able and effective process. The five force modules are open the airbase,
command and control, establish the airbase, generate the mission and operate the airbase. Figure 2.2.
provides a graphic representation of force module deployment.

Figure 2.2. AETF Force Module Phased Deployment.

2.3.1. Open the Airbase. This force module will normally arrive first and assess the airbase for estab-
lishment of airfield operating pa rameters, command and control a nd supporting host-nation support
capabilities. It contains a small force (150 personnel) to provide the capability for: command and con-
trol, force protection, cargo and passenger handli ng, logistics, communications, airfield operations
and establishing minimum operatin g strip, force accountabil ity and reception and beddown of fol-
low-on modules. The capabilities in the module should rapidly establish an initial operating capability
(IOC) in approximately 36 hours from arrival of forces.
2.3.1.1. This module contains capabilities to open an airbase regardless of the follow-on mission
support requirements for a specific mission, airframe or weapons system.
2.3.1.2. Open the airbase forces will also provide the capabil ity to plan the layout for follow-on
airbase infrastructure. These forces may be supporting other service co mponents or coalition
allies. Operations may be flying or non-flying, combat or non-combat or any combination thereof.
This module will most likely deploy in the C minus timeframe. Some portions of this module may
depart when the airfield is minimally capable of supporting the follow-on forces. As the forces
assigned to this module are completing their mission, forces from establish the airbase module are
assuming their responsibilities in addition to extending the airfield’s existing capabilities.
2.3.2. Command and Control (C2). The C2 module contains the capabilities to establish an air expe-
ditionary wing command and control structure and is estimated to be at IOC in approximately 16
hours after arrival of forces. This module assumes command of the airbase from the initial elements of
the open the airbase module and establishes permanent secure and non-secure communications capa-
bilities.
2.3.2.1. This module contains the capabilities to establish initial maintenance group, mission sup-
port group, operations group and me dical group staffs. This initial capability will be rounded out
once the establish the airbase and operate the airbase modules arrive. Secure communications
and intelligence are key capabilities to establishing control.
2.3.2.2. This module begins at some point on or after C-0 and must be in place prior to any com-
mand elements leaving from the open the airbase force module.
14 AFPAM10-219V6 1 FEBRUARY 2006

2.3.3. Establish the Airbase. This module contains the capabilities to support most missions or
weapon systems. Together with the open and generate modules, it provides the airfield’s earliest capa-
bility to execute its assigned mission.
2.3.3.1. The establish the airbase module will provide capabilities to build and modify existing
and deployed infrastructure (petroleum, oils and lubricants (POL), munitions storage and operat-
ing sites, maintenance shelters, tents, electrical), command and control mission specific forces,
expand to 24-hour day/night mission operations, e nhance force protections, communications and
airbase operations as necessary. This module initiates on or after C-0 and overlaps the ef forts of
the open module. The effectiveness of this modu le is dependent upon integration with open the
airbase and generate the mission modules. The module is estimated to be at IOC in approximately
10 days.
2.3.3.2. This module contains forces that increase exped itionary airfield capabilities to support
expanded and sustainment operations. This includes: lodging, finance, aerial port, infrastructure,
emergency response (fire crash rescue, medical, security forces, safety and EOD), personnel sup-
port for contingency operations (PERSCO) and communications.
2.3.4. Generate the Mission. This force module contains the capabilities to conduct the desired mili-
tary and mission effects required by the combatant commander. This module combines two subordi-
nate force modules: a Core UTC package (CUP) a nd a mission platform package. The CUPs contain
the lead aviation package and dir ect aviation support (e.g. maintena nce, munitions, etc) associated
with the aviation capability. CUP titles usually identify the type of aircraft deployed. The mission plat-
form package contains combat support capabilities that support th e aviation package (e.g. weather ,
intelligence, operations support, maintenance supervision and communications).
2.3.4.1. The mission support elements of this forcemodule may begin to flow before C+0 day and
will overlap the open and establish modules. Mission generation is not achievable without integra-
tion of open, C2 and establish modules. This module is intended to conduct operations within 36
hours of initial arrival and will be at IOC in approximately 80 hours from the start of the open the
airbase module.
2.3.4.2. The ability of this force module to reach IOC is heavily dependent on the strategic flow
of resources and the deployment of mission aircraft and operators.
2.3.5. Operate the Airbase. This module contains the mission support capabilities needed to achieve
full operating capability. Forces in this module make initial operating capabilities more robust and can
sustain mission generation forces for up to 30 days.
2.3.5.1. The module provides capabilities to enhance force protection, cargo handling, quality of
life activities (chaplain, fitness, library, health care, feeding and sheltering) and reach-back capa-
bilities (supply, U.S. mail, military pay). This module begins to flow on or after C+2 and reaches
closure on or before day C+14. The module is estimated to be at IOC approximately 7 days from
arrival.
2.3.5.2. The operate the airbase module begins the transition from austere and initial construction
standards to temporary construc tion standards as directed by mission duration and combatant
commander requirements.

2.4. Bare Base Terminology, Definitions and Types. A bare base is defined as a location with a func-
tional runway, taxiway, parking areas and a source of water that can be made potable. The location was
AFPAM10-219V6 1 FEBRUARY 2006 15

chosen to make the base capable of supporting all assigned and supporting aircraft and provide mission
essential resources in a timely an d combat effective manner. These resources would include logistical
support and service to the infrastructure composed of people, facilities, equipment and supplies. This bare
base concept requires prepackaged mobile facilities, utilities and support equipment that can be rapidly
deployed and installed. Expeditionary airbases are de fined by the level of infrastructure, development,
operational duration and missions that are present or will be deployed to the area. By combining the type
of airbase with the outlined facilities standards listed later in this chapter , the CE planne r can greatly
reduce the time required to identify, validate and source requirements for various locations. The various
types of expeditionary airfields include forward operating location, forward operating base, main operat-
ing base, intermediate staging area and warm base.
2.4.1. Forward Operating Location (FOL). FOLs are airfields utilized for short-term, operationally
defined missions such as counter -drug or combat search and rescue (CSAR) and have very limited
facilities and amenities. A FOL is normally an austere location requiring very little engineering effort
to execute mission requirements.
2.4.2. Forward Operating Base (FOB). FOBs are airfields used to support tactical, CSAR and recon-
naissance operations without establishing full support facilities. FOBs may be used for an extended
duration. Support by a main operating base will be required to provide backup support for a forward
operating base.
2.4.3. Main Operating Base (MOB). Main operating bases are normally occupied by a wing or larger
population (550 personnel or more), are continuously operated and posses in-place Air Expeditionary
Wing (AEW) command structures, robust expeditionary combat su pport (ECS) and logistics func-
tions.
2.4.4. Intermediate Staging Base (ISB). An ISB is a location or airfie ld used to stage forces prior to
inserting combat forces into the forward theater of operations. Du ring OIF, the US Ar my utilized
Doha, Kuwait as a staging an d positioning area for the 4 th Infantry Division prior to the initiation of
combat operations in Iraq. ISBs have lar ge transient cargo and personnel requirements and normally
require greater planning factors for cargo ramps and ECS to accommodate large throughput of assets.
2.4.5. Warm Base. A warm base is defined as a prepositioned lo cation where initial beddown infra-
structure development and prepositioning of assets has occurred th at allow for the rapid deployment
of personnel and weapons systems to an expeditionary location. During OEF and OIF, the Air Force
heated up bases at Masira h Island, Al Udeid, Seeb and Thumrait to enable the rapid mobilization of
hundreds of aircraft and thousands of personnel.

2.5. Construction Standards Definitions and Terminology. The combatant commander specifies the
construction standards for all facilities in theater. These standards are established to ensure that facilities
meet mission requirements while minimizing the engineering effort expended for planning and standard-
ize quality of life throughout the theater of operation. The following definitions expand those established
in JP 4-04 and define the construction standards of bare bases and their minimum facility requirements.
2.5.1. Expeditionary Standard Airbase. An expedition ary standard airbase is a subset of the initial
standard defined in Chapter 1. They are design ed and constructed on an expedient basis, using
organic and service provided equipment and systems and/or host nation resources to support mission
durations of up to 90 days. Focus will be on providing support, faciliti es and infrastructure systems
16 AFPAM10-219V6 1 FEBRUARY 2006

necessary to move, receive and beddown deploying forces. Expeditionary standards would be seen at
short term FOL and FOB locations.
2.5.2. Initial Standard Airbase. An initial standard airbase is designed and constructed on an expedi-
ent basis and is characterized by austere facilities requiring minimal engineering effort to initiate mis-
sion operations. They are intended for use by opera tional units upon arrival in theater for a limited
time ranging up to 6 months. Initial standard facilities may require replacement by more substantial or
durable facilities during the course of operations. The Air Force developed BEAR kits to support ini-
tial standard expeditionary airbase deployments. Initial standards would most likely be seen at FOL,
FOB and initial operations at MOB and ISB locations.

Figure 2.3. Initial Construction Standard at FOB in Afghanistan.

2.5.3. Temporary Standard Airbase. For deployments that are expected to last up to 24 months and
where Military Construction Program permanent facilities (or even semi-permanent facilities) are not
required, temporary standard facilities should be programmed. Temporary standards are characterized
by minimum facilities requiring additional engineering effort above that required for initial standards.
Temporary standard airbases provide for sustained operations above the requirements of initial stan-
dards at locations where a lo ng-term presence is not anticipated. The temporary standards may be
used from the start of an operation or as an upgrade from initial standards, if directed by the Combat-
ant Commander for mission requireme nts. Temporary standards should increase the efficiency of
operation, safety, durability, morale and health standards for deployed personnel. For command and
critical facilities, modular and/or K-Span style fac ilities can be constructed wi th buried water lines,
overhead and/or buried electrical distribution, lighting on poles, buried sewer lines, collection tanks
and pumping systems. Dormitories and some administrative functi ons may receive hard floors and
walls, or be upgraded or replaced with modular facilities as base growth and mission duration require.
General requirements are found within Joint Chief of S taff guidance and are depicted in Figure 2.4.
Theater commanders may vary standards as the situation, forces and location dictates.
AFPAM10-219V6 1 FEBRUARY 2006 17

Figure 2.4. Temporary Construction Standards for Lodging.

2.5.4. Enduring Presence Construction S tandard. For deployments that are anticipated to last longer
than two but less than 10 years, semi-permanent standards should be planned, programmed and exe-
cuted. Semi-permanent standards ar e designed and constructed with finishes; materials and syste ms
selected for moderate energy efficiency; maintenance and life cycle costs. Semi-permanent construc-
tion standards may be utilized as initial beddown standards when directed by the component combat-
ant commander. Semi-permanent construction projects may exceed local base civil engineer and wing
authority levels.
2.5.4.1. CE planners must be extremely knowledgeable abou t AF programming, funding and
authority levels when planning for semi-permanent locations . Ensure proper coordination with
theater level CE planners an d MAJCOM CE program director ates prior to initiating any
large-scale construction.
2.5.4.2. Enduring presence construction standards are normally set by ag reements between the
host nation and the United S tates and may incl ude permanent or semi-permanent construction
standards. These agreements will often outlin e conditions and standards the US military must
adhere to while constructing on host nation property as well as cost sharing initiatives that may be
put in place to al leviate the expense to US operations. Semi-permanent airbases should be con-
structed with a prime emphasis on sustainment and survivability.
2.5.5. Warm Base Standards. Warm bases are designed and constructed with finishes, materials and
systems selected for sustaining a mobilization base within the theater of operations. A warm base may
be a separate facility with a contract caretaker f unction or a surge area collocated with an operating
base. Warm bases are positioned to be rapidly heated up through execution of task order contract line
items in the contractor caretaker contract. Current AF pol icy dictates that CE UTCs be deployed to
augment the contractor to ensure base camp is erected to US standards.

2.6. Expeditionary Airbase Development and Planning Process. The airbase development process
has four main components: antiterrorism and force protection, facility requirements, master planning and
construction management.
2.6.1. Antiterrorism and Force Protection (AT/FP). AT/FP and physical security concerns are critical
to the development of expeditionar y airbases and long-term military cam ps. Incorporating AT/FP
requirements into site pl anning, selection, and layout is a cr itical and often difficult process. It is
essential that CE and Securit y Forces planners work together to establish a realistic and executable
18 AFPAM10-219V6 1 FEBRUARY 2006

AT/FP plan to protect US personnel and AF assets. This partnership will ensure that the AT/FP plan is
an integrated design consistent with the airbase initial and long-range development plans.
2.6.1.1. Essential to the base camp planning effort is the early identification of the AT/FP require-
ments. Addressing AT/FP concerns early helps to ensure that site location and layout is compatible
with FP operations and mission accomplishment. Early development of AT/FP and physical secu-
rity requirements also helps to reduce both construction and manpower costs. It is easier and more
cost effective to establish security measures during the planning process than it is to apply AT/FP
and physical security requirements, after the fa ct. AT/FP measures must be considered and
included at all stages of beddown planning and base development.
2.6.1.2. IAW DOD Instruction 2000.16 ( DOD Antiterrorism Standards) and DOD 2000.12H
(DOD Antiterrorism Handbook) standards for construction of new facilities have been developed
to counter possible terrorist threats. These cons truction standards have specific requirements for
such measures as standoff distance, perimeter barriers and building construction. These minimum
standards must be incorporated into the construction of all facilities rega rdless of the identified
threat. Planners must ensure th at they reference command specific publications regarding force
protection instructions. CENTAF, USAFE, SOUTHAF and PACAF all have supplemental instruc-
tions regarding FP construction standards. C ontact your theater level A7/CE planner for more
information.
2.6.2. Facility Requirements. The combatant comma nder establishes the base camp facility require-
ment standard for the theater of operations by operation order (OPORD) fragmentary order. This order
describes standards upon which components and subordinate units develop master plans for mission,
mission support, base a nd community support facilities and requi red utilities. These standards are
intended to provide the combatan t commander’s expectations to component commanders for base
camp living and operating conditions.
2.6.3. Master Planning. Master pla nning provides an integrated strategy for constructing and main-
taining required facilities while right-sizing budge ts, equipment sets and the CE UTC(s) required to
support expeditionary operations. The level of deta il of the base camp mast er plan depends on the
maturity of the location, the speed at which the operational need for a base camp develops and the
expected length of stay. Master plans for expeditionary or initial standard camps may be simply a
sketch of the camp, while master plans for temporary or enduring pr esence camps will include fully
engineered construction plans based on complete surveys. Beddown and base planners should ensure
they utilize and comply with gui dance provided in UFC 4-010-01, Design: DOD Minimum Antiter-
rorism Standards for Buildings, and with UFC 3-260-01, Design: Airfield and Heliport Planning and
Design, when planning for AEF bases.
2.6.3.1. Theater level planners will establish a process to develop, approve and implement base
master plans. For joint a nd coalition bases, this mechanism must include representation from all
affected service components or coalition allies if applicable.
2.6.3.2. Using the established process, component commanders w ill develop base master plans
for intermediate staging and main operating airbases. Planning utilizing semi-permanent and per-
manent construction requires coordination and approval from your numbered air force and major
command programs directorate and civil engineer.
AFPAM10-219V6 1 FEBRUARY 2006 19

2.6.3.3. Theater level or major command Engineer and Servi ces experts can provide technical
support and guidance for expeditionary airbase development if planning is occurring at the unit
level.
2.6.4. Construction Management. Executing units will track the development of base construction in
accordance with the master plan priorities and report progress in accordance with instructions pub-
lished by the A7/CE directorate.

2.7. Operations and Maintenance (O&M). Effective operations and maintenance programs will maxi-
mize the life expectancy of base temporary facilit ies at minimum cost to the government. As the opera-
tional situation develops, more pe rmanent structures and facilities ma y replace temporary facilities and
structures. Airbase units will follo w service regulations for the operatio ns and maintenance of facilities
and may hire civilian contractors to manage and operate the base support mission if the operational situa-
tion permits.

2.8. Expeditionary Facilities and Beddown Sets. Detailed listing for expedi tionary facilities and bare
base beddown assets can be found in AFPAM 10-219 Volume 5, Bare Base Conceptual Planning Guide,
and AFH 10-222 Volume 1, Guide to Bare Base Development, and AFH 10-222 Volume 2, Guide to Bare
Base Assets.

2.9. Better Deployable Facilities. Facilities and equipment used after Viet Nam have been improved to
make them more deployable and livable. Major improvements were made to meet logistical and mission
requirements for increased deployability for mission and base support packages, with the greatest strides
occurring in the two decad es between Viet Nam and Desert Shield. The post- World War II and K orea
Gray Eagle kits were heavy and bulky and required excessive man-hours to position and erect. Additional
equipment was added, but repackaged into sizes that are more manageable. This effort created the small
550-person Harvest Eagle packages of the early 1970s. Likewise, lar ger deployment kits were tested,
which led to the 1970s Harvest Bare packages. Harvest Bare was refi ned, but testing led to the purchase
of new equipment in the mid-1980s such as the Ha rvest Falcon system. The Harvest Falcon packages
were fielded to allow deployment support for a 3,300-person wing and up to 55,000 personnel total.

2.10. Transportability Issues versus Developmental Timelines. While more user and mission friendly
bare base beddown packages have evolved, the packages are still not light and small enough to allow
rapid deployment by the current fl eet of large frame transports. Table 2.1. shows the typical number of
aircraft missions required to s upport the deployment of the s tandard sets (without passengers aboard).
Additional missions may be required if additional site preparation is required. The erection of many cur-
rent deployment packages are also man-hour intens ive. This limits their application by smaller numbers
of personnel that deploy to a site on an ADVON or predeployment team, who must perform site surveys.
Also, the current Housekeeping sets are difficult to break up for use by small teams that require some ini-
tial short-term facilities. Given time for shipment and erection, these assets provided good support during
the initial phases of a deploymen t to Southwest Asia. During the fi rst few weeks of Operation DES ERT
SHIELD deterrent efforts, the tonnage required fo r initial air and ground fo rce projection shipments
depended on air transport. The air transport system was totally choked in spite of many prepositioned civil
engineer assets in country or in USAFE and some personnel faced austere conditions. However, time lines
for Desert Storm actually allowed about 95 percent of the transferred force-buildup tonnage to be sent by
sealift. Keep in mind that the disparity in missions between the legacy (Harvest) sets and the BEAR sets
is due in part to the light/lean nature of BEAR and that BEAR has optional a ssets that are added only as
20 AFPAM10-219V6 1 FEBRUARY 2006

needed (e.g. ROWPUs, MAAS, revetmen t kits, various dome shelters, et c). These assets are sometimes
referred to as BEAR playbook options.

Table 2.1. Mission Support to Various Deployment Sets.


Type of Set C-130 Missions C-17 Missions C-5 Missions
Harvest Falcon (HF) Housekeeping 45 14 7.5
HF Industrial Operations 79 16 13.2
HF Initial Flightline 162 40 27
HF Follow-on Flightline 13 3 2.2
Total HF Missions 299 73 49.9
Harvest Eagle Housekeeping 19 6.3 3.2
Harvest Eagle Utility 13 4.3 2.2
Total HE Missions 32 10.6 5.4
BEAR 150 Housekeeping - 1 -
BEAR 550 Initial Housekeeping - 6 -
BEAR 550F Housekeeping - 5 -
BEAR Industrial Operations - 7 -
BEAR Initial Flightline - 7 -
BEAR Follow-on Flightline - 2 -
Total BEAR Missions - 28 -

2.11. Airlift Limitations versus Developmental Timeline. To meet current AEF taskings, air transport
may be the only method of delivery for several months --this is recognized by all services. T o meet their
needs, the Army developed the Force Provider deployment packages, which evolved from a cross-version
of Harvest Falcon-type assets packaged in Harvest Eagle-size packages. The Air Force has tested lighter
weight, more streamlined Harvest Falcon kits that address the phasing required to reach more remote, aus-
tere bases when these locations are airlift constrained. The Air Force is also developing and programming
replacement shelters and deployable electrical, water and sewerage sy stems that are lighter and more
deployable. The next decade is slated to see many improvements and changes to the deployment packages
to allow rapid beddown of forces to meet the full spectrum of contingency deployments. The programs for
managing and updating bare base a ssets now fall under the BEAR pr ogram. When possible, planners
should investigate the opportunity of utilizing sealift, convoys and railways to move large assets and free
up airlift.

2.12. Real World Transport/Logistics Lessons Learned : During Operation ALLIED FORCE (OAF)
in Yugoslavia and Kosovo, RED HOR SE units in Europe were able to mobilize prepositioned heavy
equipment and beddown assets from Italy and move them via sealift and rail. On every occasion, the
assets arrived ahead of equipment and resources that were prioritized as critical assets and moved via air-
lift. The great advantage to sea and rail is the elimination of weight constraints that occur when moving by
air. Due to severe lack of Class IV construction material in Albania, Army and Navy teams had problems
erecting billeting, showers, latrines and other expeditionary combat support requirements. Within 7 days
of arrival at Albania, RED HORSE had shipped in over 632 short tons of h eavy equipment embedded
with plywood, geo-textile materials, hand tools and other critical construction assets that were not being
moved due to airlift limitations. Coordination and lo cation of opportune sealift through Military Traffic
AFPAM10-219V6 1 FEBRUARY 2006 21

Management Command (MTMC) took three days. The shipment includ ed environmental control units
(ECU), bundles of AM-2 mat, expeditionary shower/shave and latrine sets. Task Force Hawk had been on
the ground three weeks but it was not until the arrival of the RED HORSE assets that they received sani-
tary and hygiene facilities and ear th-moving heavy equipment. CE and RED HORSE planners coordi-
nated this effort outside of the prioritization of the OAF movement center and tactical airlift control center
(TACC).

Figure 2.5. Sealift of Military Equipment.

2.13. Mission Considerations. Requirements for changes in depl oyment packages are driven by AEF
mission considerations. To meet AEF rapid deployment, full-spectrum global commitments, some restric-
tions may have to be imposed for initial mission planning, such as:
2.13.1. Compression requirements for initial deployment timelines.
2.13.2. Restrictive limits on the number of support personnel on the ground during the initial 3 to 14
day periods.
2.13.3. Limited initial flow of equipment and support packages, as well as spreading out follow-up
packages over more airlift missions.
2.13.4. Sending selected mission support UTCs in prior to C+0 Day to ready the base.
2.13.5. Employing joint concepts of support and deployment with Air National Guard, Air Force
Reserve Command, Army, Marine and Navy forces.
2.13.6. All of these may be considered upfront to meet theater commander air superiority and support
campaigns. Finally, the total number of transport aircraft available may be the critical factor for the-
ater locations that are landlocked, have no accessible or ne arby seaports, or lack road or other avail-
able land routes.

2.14. Influence of Base Type and Location. Typical AEF mission planning considerations will depend
in a large part on the type and location of the depl oyment airbases. Mission timelines for initial support
force and equipment UTCs will be different for each of the following situations.
22 AFPAM10-219V6 1 FEBRUARY 2006

2.14.1. Austere airfields for support of missions by special oper ational forces, A-10s, MC- and
AC-130s and special operations and attack helicopters, where the initial arriving aircraft may be lim-
ited to C-17s and C-130s.
2.14.2. Large, former Soviet-bloc airfields that require some repair of hangars, maintenance facilities,
utilities and pavements, but can s upport all types of aircraft and te nt city beddowns and can be par-
tially supported with contracts, trucked-in supplies and modular facilities.
2.14.3. Recovered, enemy commercial and military ai rfields that have ether been denied during
enemy retrograde or coalition ai r and ground bombardment. These were the predominant airfields
occupied during the 2002-2003 OEF and OIF.
2.14.4. Typical bare bases, which can accompany initial fighters, transports (both military airlift and
Civil Reserve Air Fleet) and helicopter missions, but may have limited modes of supply and transport.
2.14.5. Large airbases with a full mix of aircraft and support facilities from numerous military ser-
vices or countries and supportable by several modes of transportation and supply.

Figure 2.6. Joint Forces Airbase in Bosnia.


AFPAM10-219V6 1 FEBRUARY 2006 23

Figure 2.7. Various Construction Standards in Bosnia.

2.15. Developmental Timeline Considerations. Based on the Air Force Chief of S taff's Sight Pictures
and the Agile Combat Support (ACS ) Global Military Task Force (GMTF) program to implement AEF
deployments, the timelines for deployment are e nvisioned through a force mo dule approach. The Air
Force requires any upgrade of the bare base assets to be modular, scaleable and to meet the needs for fol-
low-on set consistency, maintaining full flying operational support and providing theater interoperability.
2.15.1. Timeline Goals. The typical timeline goal for a 3300-person beddown is fourteen days, with
initial flying operations achieved by C+72 Hours and sustainment operations phasing in after fourteen
days. In order to meet a full mi ssion capability within C+14 days, open the base efforts must be
planned to provide equipment and resources in response to mis sion and manning requirements that
allow for immediate build-up and beddown upon arrival at the expeditionary airbase.
2.15.2. Force Modules and BEAR Asse ts. To meet the timelines for force module IOC, BEAR sets
are packaged to more closely align with the goal of the force modules. For instance, BEAR sets are
streamlined for weight and TEMPE R tents are being replaced with more readily deployable systems
that are simpler to erect with fewer personnel (the Small Shelter System was widely deployed during
OEF and OIF). The overall packagin g allows use without major tail oring to meet smaller mission
deployments or beddowns for joint operational support of other branch of service forces. These con-
cepts are depicted in Figure 2.8., which shows both the strategic roadmap force module timeline and
the conceptual modules for a BEAR package that would meet the requirements of deployment.
24 AFPAM10-219V6 1 FEBRUARY 2006

Figure 2.8. BEAR Sets Supporting a Force Module Beddown.

2.15.3. One major planning consid eration is plugging in an open the airbase module (team) prior to
C+0 Day to begin beddown. With an open the airbase beddown package, which provides short-term
austere shelter and basic hygiene, a beddown team would initiate beddown with either a tailored Har-
vest Eagle system or BEAR system (when fully adopted). For ci vil engineers, the open the airbase
team could include a combination of RED HORSE, Prime BEEF and 49 th Material Maintenance
Group (49 MMG) BEAR team personnel to prepare the site, erect and install facilities, equipment and
some utilities. For locations that are not in higher threat areas, planning for these types of bases should
consider use of one of the contractor augmen tation programs for early beddown opera tions. These
programs are the Air For ce Contract Augmentation Program (AFCAP ), the Army Logistics Civil
Augmentation Program (LOGCAP) and the Navy Contingency Construction Capability (CONCAP).
These are covered more broadly in Chapter 8 of this volume.

2.16. Engineering Considerations. Most of the engineering pla nning factors and detailed mechanical
procedures for calculating requirements are covered in AFPAM 10-219, Volume 5. These civil engineer
considerations are based primarily on AEF lessons learned.

2.17. Survey, Expeditionary Site Mapping (formerly GeoReach) and Other Information Based
Plans. Deploying units and theater planners must have good information on what is at a location and
available nearby. Developing a bare base support plan requires accurate information. Knowing what mis-
sions will be present is a major factor in determin ing what should be included and the amount of detail
required. Experience with OAF, OEF, and Operation NOBLE ANVIL has shown that AEF missions can
be much more fluid than previous Air Force depl oyments, usually because ot her services and partner
nation military services are involved.
2.17.1. When there is a requirement to support new contingency missions, there may not be a specific
operation plan (OPLAN) that provide s specific details for the location. Rather, an operations plan in
AFPAM10-219V6 1 FEBRUARY 2006 25

concept form (CONPLAN) may have to be used to deter mine basic requirements. Whether an
OPLAN or CONPLAN is used, an all-services, Timed-Phased Force and Deployment Data (TPFDD)
is required that is associated with the base. The TPFDD database will contain all forces (except possi-
ble specifics on special operations forces) and the deployment timing required to deploy in support of
an OPLAN or CONPLAN.
2.17.2. Problems can develop when all potential missionsare not well defined; when this occurs, civil
engineer planners must make assumptions based on the best information available with respect to total
mission requirements. Theater AD VON teams, through the Expediti onary Site Survey Process
(ESSP), may have surveyed the site and created an Expeditionary Site Mapping comprehensive instal-
lation picture (CIP) with GPS located survey inputs. Some of the more specific requirements for
potential mission support of an airfield may be available from site surveys conducted by Air Mobility
Operations Groups (AMOG), Tanker Airlift Control Elements (TALCE), Contingency Response
Groups (CRG), Special Tactics Teams (STTs) and previously completed Base Support Plans (BSPs)
or theater Civil Engineer Support Plans (CESPs). It is imperative that A7 or theater level CE planners
have the appropriate security clearance level for joint and AF war plan efforts.
2.17.3. With the exception of support to special operations forces, you should be able to obtain and
review (before going on the surv ey) the TPFDD to deter mine the basic deployment forces that will
drive the population-based requirements. Examples of basic information are the number of aircraft by
type, the total base population and the phased basepopulation over time, transient forces and expected
duration of the operation.
2.17.4. Good sources of information are operations plans, base maps, aerial photographs, construc-
tion drawings, past site surveys, data contained in intelligence office documents, information from a
previously deployed unit and in formation from the theater, Aerospace Expeditionary Force Center
(AEFC), or MAJCOM staffs. Until Expeditionary Site Mapping has reached full maturity, civil engi-
neers need to obtain both un classified and classified information as best they can for each initial
deployment. When replacing a deployed unit, incoming civil engineers should use the SECRET Inter-
net Protocol Router Network (SIPRNET) and s ecure telecommunications to determine what may
really be required to replace the current force for sustainment operations.

2.18. Airfield Surveys and Operational Data Collection. The success of an expeditionary airfield is
directly related to the c ondition of the runway. This is reflected in the effort the Combined Force Air
Component Commander (CFACC), Combined Force Land Component Command (CFLCC) and various
organizations put into the deploymen t of numerous pavement evaluation teams. In light of limited and
constricted transportation into many of these areas, it is critical that planners identify the correct require-
ment and task the appropriate team. The following teams and their capabilities are listed to assist in this
selection.
2.18.1. AFCESA Pavement Evaluation Team. The AFCESA Pavement Evaluation Team is governed
by AFI 32-1041, Airfield Pavement Evaluations. The AFCESA Pavement Evaluation program
focuses on airfield support to MAJCOM/NAF/CFACC and bases by providing the following services
for both peacetime and contingency operations:
2.18.1.1. Develop pavement guidance and criteria.
2.18.1.2. Perform airfield structural pavement evaluations.
2.18.1.3. Perform airfield frictional characteristics (skid) evaluations.
26 AFPAM10-219V6 1 FEBRUARY 2006

2.18.1.4. Provide technical support to the MAJCOM and bases.


2.18.2. Tanker Airlift Control Elements (TALCE). Air Mobility Command (AMC) trained, equipped
and tasked airfield evaluation teams perform site surveys to determine airfield suitability for aircraft
operations. TALCE units are ta sked through HQ AMC-TACC/ XOPM, Scott AFB, DSN 779-3071.
Airfield surveys are published on AMC IMT 174, Ai rfield Survey, and are used to update Airfield
Suitability and Restrictions Report (ASRR). ASRRs include airfield geometry assessment, naviga-
tional aids (NAVAID), hazards to flight determinations, aircraft parking area aprons, pavement flow
capabilities, and maximum (aircraft) on ground (MOG) capacity.
2.18.3. Global Assessment Teams (GAT) were created by AMC during OEF to serve as the advance
planning team for AMOG/TALCE units. GATs establish austere initial airfield operations. GATs are
tasked through HQ AMC-TACC/XOPM, Scott AFB, DSN 779-3071.
2.18.4. Contingency Resp onse Groups (CRG) are a first-in, mu lti-discipline force that secure and
establish airfield operations. CRG are comprised of Security Forces, Initial Airlift Support, Civil
Engineering and Communications. CRG are positioned and equipped for short-term operations and
deployment. CRGs are tasked through the Unified Combatant Command and equipped to complete
airfield surveys as detailed on AMC Form 174.
2.18.5. RED HORSE units are mobile, heavy construction squadrons that are equipped to provide air-
field assessment and repairs.
2.18.6. Special Tactics Teams (STT) are Special Operations team s used to survey and certify
semi-prepared airfields, landing zones and assault strips via AF Forms 3822 a nd ASRR. Surveys
include geometrics, NAVAIDS, hazards to flight, semi-prepared airfield load bearing capability. STT
are tasked by the 720th Special Tactics Group at Hurlburt Field, Florida, DSN 579-4250.
2.18.7. Expeditionary Site Survey Process (ESSP) standardizes the process of producing airfield sur-
vey data and providing decision makers with reli able and substantive mission planning information.
ESSP deploys survey teams of high trained individuals to perform pavement evaluation, full spectrum
threat assessment, airfield suitability reports and beddown surveys with LOGCAT/Expeditionary Site
Mapping integration. The director ate of logistics readiness (HQ US AF/ILG) is responsible for Air
Force ESSP policy and guidance, while the MAJCOM logistics plans function provides oversight for
all expeditionary site surveys in their AOR. Additional information on ESSP roles and responsibilities
can be found in AFI 10-404, Base Support and Expeditionary Site Planning.
2.18.8. The National Geospatial -Intelligence Agency (NGA; form erly the National Imagery and
Mapping Agency or NIMA) has completed surveys of all airfields worldwide. During Operations
NOBLE ANVIL, OAF, OEF and OIF planners utilized these surveys for beddown planning purposes.
This proved risky since less than 1% of structural data is taken fr om true technical information. The
majority of facility capacity and capability is estimated from imager y taken of similar airfields or is
taken from reports of airfield managers. This data may be skewed by host nations for political or eco-
nomic reasons. NGA information provides a good initial baseline and satellite imagery for initial plan-
ning.

2.19. Priority Requirements During Planning. Based on lessons learned, it is very important to iden-
tify those items, which must be in the initial support packages, but are not normally included. If a standard
deployment package flows as establis hed in the TPFDD and a site survey shows that there is a critical
need to have another package compon ent arrive earlier, then this is a major concern that should be ele-
AFPAM10-219V6 1 FEBRUARY 2006 27

vated. Heavyweight, large-cube items, such as construction equipment, fire trucks and dump trucks, have
been left on a ramp at an intermediate aerial port or back at a theater's prepositioned-storage site awaiting
airlift support when transportation flows are airlift constrained. Based on the mission, surveys must deter-
mine if initial beddown activities can be accomplishedwithout a large amount of site preparation. If initial
beddown efforts require these assets, then alternate procedures, scheduling or support may be required to
allow this to happen. Actions must be coordinated between theater planners, the AEF wing and United
States Transportation Command (USTRANSCOM). Here is an example.
2.19.1. A former Soviet base now controlled by a partner nation will be used for a force beddown. If
you just looked at aerial photos and used old Soviet-era intelligence reports, the base would appear to
have an adequate runway, taxiway and ramp, as well as a water source and so me damaged flightline
buildings that can be eas ily repaired. However, a site survey might show that the base is on a
rock-hard, rocky surface that has toxic environmental spills affecting some areas of the ground surface
and water sources. Wh ile expedient repairs to existing facilities are practical, they would require
structural work and for safety reasons, these efforts would have to be completed prior to occupancy.
2.19.2. If the deployment buildup were to be phased in over several months, the base could be devel-
oped without deploying additional up-front resources. However, if a 3300-person bare base were
required by C+23 Day, then the TPFDD would have to be ad justed. Deployment packages should be
tailored to reflect Prime BEEF UT Cs as one of the initial teams arriving with AFCAP (or other con-
tractors) and RED HORSE personnel to: clean up or contain the spil l, conduct more arduous surface
preparations, repair the flightline buildings and possibly drill a well, provide additional reverse osmo-
sis water purification units (ROWPU) or supply an alternative means for obtaining drinking water.

2.20. Coalition or Host Nation Support Capabilities and Limitations. A host nation (HN) is a nation
where US military personnel are deployed by government invitation or international agreement. A partner
nation is a nation where US military personnel deploy by government invitation or international agree-
ment and their military forces may be participants under a military agreement or treaty. A host nation's
resources, assets and facilities may exist at the location and may be available for use or support. Theater
and State Department sources, such as military liaison offices or partner nation military personnel on sta-
tion, can sometimes provide valuable information on host nation capabilities and information on: con-
tracts, sources of supply, availability of equipment and materials (as well as an idea of the cost to do
business) and points of contact w ith the local government. Another im portant piece of information per-
tains to the willingness of a host nation to provide facility and utility support and joint use of assets.
2.20.1. The availability of HN s upport may enable CE units to reduce support and transportation
requirements by securing formal and informal agreements with HN authorities. Contact your wing or
theater judge advocate for guidance prior to entering into any agreements or interpretation of existing
agreements. The Joint Forc es Commander (JFC) usually establishes a single office to serve as the
executive agency to manage and coordinate host nation support during wartime. Airbase and Air
Component Command representatives use this of fice, according to JFC re gulations and guidelines,
when entering into any formal agreement with HN authorities.
2.20.2. Units that deployed in support of OEF found that conducting smaller humanitarian and civic
assistance (HCA) support projects for local communiti es often improved the overall ability to obtain
local resources and labor for on-base work. Even when there are few local resources, it is good to con-
duct humanitarian efforts to improve the political climate in terms of host nation support for the loca-
tion and effort. It is important that outgoing civil engineers orient, familiarize and even introduce their
28 AFPAM10-219V6 1 FEBRUARY 2006

replacement to key local and re gional government points of contact. Even with the willingness of
local officials to support deployment ef forts, sometimes there are economic or physical constraints
that affect use of the deployment site.
2.20.3. When leasing of land is a problem, deployed AEF units have found that Army Contingency
Real Estate Support Teams (CRESTs) can often provide support in-the ater. CRESTs can obtain
longer-term leases, provide needed continuity when dealing with local of ficials and landowners and
have more contracting authority than Air Force contracting. Your theater civil engineer staff can facil-
itate CREST assistance.

2.21. Mine/UXO Presence. Many bare bases have been esta blished through long-term government
agreements with traditional treaty or agreement allies/partners; the bases were readied with peacetime
construction programs. AEF deployments within a theater's area of responsibility (AOR) must often rely
on use of airfields or airports that have been ma de available on a short-term basis and often may have
been exposed to ethnic, sectarian, or regional violence. When this is the case, opening the airfield and the
surrounding airfield environment for base beddown usually becomes a much greater problem and danger-
ous situation due to mine fields and UXOs.
2.21.1. Air Force and other service EOD teams usually have to enter the location first and start clear-
ing the runway and the areas adjacent to it, the taxi ways and aprons. Initial forces can then land, of f-
load equipment and stay in any adjacent area that has been cleared of mines and UXOs. However ,
actual layout of the base, construction of outlying and nearby defensive fighting positions, positioning
and erection of shelters and running of utilities becomes a slow process as EOD teams clear each area
one portion after another. This usually requires mine detection and safing or demolition and identifi-
cation, as well as safing and disposal or demolition of UXOs.
2.21.2. Mines or UXOs that have been rendered safe by in-place demolition will also require subse-
quent leveling and grading of the craters. For areas with many mines, additional equipment may be
required from Army, British, or combat engineers from other capable countries with mine dozers/
plows or flails. Again, additional site preparations may be required to recover the areas where plows
had to be used.
2.21.3. With these basic precautions, beddown can proceed within cleared areas for erection of facil-
ities and surface layout of utilities. However, burying utilities can be a very slow process. Mines and
UXOs located below the surface (especially in areas subject to flooding with drifting soil/sand), could
explode when hit or uncovered by tr enching for utilities. EOD teams ma y have to scan or sweep for
additional UXOs and mines directly along the pathways for utility trenching.

2.22. Considerations for Joint Operations Beddowns. Do not assume that another service is preparing
the support plan or is planning to take on the base operating support responsibility. Do not assume that the
Air Force or another service will be in charge when you arrive. Air Force and Army lessons learned from
initial AEF deployments to remote, joint service bases showed that the initial command structures at these
locations were often too fluid for anyone to be in charge during the initial beddown operations, and the
overall command and control of th e location could change several times from initial beddown through
sustainment. Changes in base missi ons cause extraordinary increases in personnel and the need for sup-
port services and facilities. Unit deployment planners must work with theater civil engineers and planners
to identify locations that will be used for major staging operations. Duri ng OEF, some bases expanded
from an expected 300 persons to over 7,000 persons.
AFPAM10-219V6 1 FEBRUARY 2006 29

2.23. Support Plans. When an airfield had no previous survey for beddown requirements, the first units
in need to know what other units are coming so they can determine the general size and layout of the base.
For sizing purposes only, base planners should consid er as a contingency scenario that unit departures
may overlap with unit arrivals and that both may have to operate on the base for some time. They should
also take into account that expedient sanitation facilities may have to be used initially, which can create
the need for additional land area. Finally, joint service may also mean that partner nation military forces
are employed at the location besides just US Army , Navy or Marine units. Beddown planners must be
given the full picture on who will be at the location and when theywill serve. Ideally an expeditionary site
mapping-based theater CESP or AEF BSP would include a base layout, which would address all missions
and be coordinated by other stakeholder service branches. This is rare. More frequently, the initial AEF
civil engineer force will arrive at a location and have to report to the interim, ranking AF officer (such as
the TALCE commander). This is becaus e the initial forces from other services at joint service bases are
often combat forces, whic h do not have base construction resp onsibility. Careful consideration during
planning must be given to servi ce munition operation/storage requirements because of their as sociated
explosive safety quantity distance (ESQD) arcs which limit available beddown areas.
2.23.1. When TPFDD based informat ion is used for initial beddow n planning and layout, develop
support plans and layouts to take into account all the beddown resources that will be used that are
compatible. Until Air Force Harvest Falcon systems and Army Force Provider systems become
interoperable for utilities (either through changes in the utility systems or c onversion kits), like sys-
tems may have to be grouped with specific personnel (i.e., Army with Force Provider). Unless there is
adequate room to separate serv ices for independence of efforts, plan on siting in common groupings
as much as possible (to allow connection of compatible utility systems), such as billeting and support
service areas, maintenance and industrial areas, flightline areas, medical facilities and separated muni-
tions areas. If other services' engi neers or planners are present, use their knowledge and skills when
developing the layout, as they shoul d be more familiar with their se rvice's requirements. Army engi-
neers can be valuable when planning for sustainment, as many have an automated beddown program
(i.e. Theater Construction Management System) that provides basic de signs and bills of material for
various types of construction, facilities and standards.
2.23.2. While Air Force units have ta ken some pressure for wanting to provide quality of life living
standards and facilities too early in base development, other services have faced the problem of not
identifying early enough clearly defined living standards for base camps and staging bases. Theater
commanders should have identified acceptable living standards to plan for during initial deployments.
2.23.3. Many joint service bases are supposed to bepurple suit operations with shared responsibilities
for base operations support. In other cases, one service may open the base and maintain responsibility,
or take over the responsibility for all support. The TPFDD addresses the requirement for support of an
airbase and/or base camp. In some cases, it is essential that other services provide or augment initial
key bare base skills, such as fire protection, bio-environmental, utilities (water and waste), power gen-
eration and environmental (pest management). When the TP FDD requires the Air Force to be sup -
ported by these personnel early on in the deploymen t, AEF civil engineers and planners should
contact the other services’ units and coordina te arrival schedules to ensure that the other services’
engineers can be there as schedul ed in the TPFDD. Be aware that often these engineering personnel
would not be mobilized early enough for initial support, since they typically arrive when their service
accepts responsibility for base operating support. There absence could delay beddown of facilities and
utilities or cause crucial delays in overall beddown.
30 AFPAM10-219V6 1 FEBRUARY 2006

Figure 2.9. MREs vs. Mobile Kitchen Trailer.

2.24. Expeditionary Combat Support (formerly Base Operating Support). ECS includes the provi-
sion of supplies, vehicle maintenance, civil engineering support, services support (including food service,
billeting, laundry, mortuary affairs, recreation centers and fitness centers), communications, security and
general administrative support. During AEF deployments for OEF, it became evident that there was a
basic difference in the ECS concept of operation between the Air Force and the Army.
2.24.1. AEFs deploy as a wing (or a portion of a wi ng with groups and squadrons from other bases)
and form an AEW. Air Force ECS is integral with the wing structure.
2.24.2. The Army has combat engineers and support personnel to support mobile combat operations,
but they do not perform the ECS function. The Army has various support battalions that provide sta-
tionary base operating support, but most of these are reserves. For combined base camps/airfields ini-
tially supported by the Air Force a nd partner nation engineers, Army units often could not take over
ECS until all preparations were in place.
2.24.3. Check deployment orders to en sure that theater planners have addressed base operating sup-
port and transfer of responsibility. Start early on in the deployment to track and account for resources
to ensure that equipment/assets can be reassigned during transfer of responsibility. In some cases, an
Air Expeditionary Group may have to remain at the location to support Air Force personnel and mon-
itor/control equipment/asset accounting.

2.25. Command and Control Relationships. When the deployed location is designated as a numbered
AEW, whether or not the expeditionary civil engineer squadron is primarily from one base or is composed
of numerous units or individuals, it is important that all Air Force civil engineers are formed together (and
billet together) as a unit. This t ype relationship may be harder to enforce when civil engineer forces
include Air Force, Army/Navy/Marine (i.e., other service branches), or international personnel assigned
for support of the airbase. The best policy is to integrate similar forces into one designated work-tasking
unit, whether the unit is a blue, purple, or plaid suite operation, not withstanding any possible need to sep-
arately billet by service/nation.
AFPAM10-219V6 1 FEBRUARY 2006 31

Chapter 3

PLANNING FOR BASE OPERATING AND SUPPORT FACILITIES

3.1. Overview. The Army, Navy, Air Force and Marines each have differing standards for base Operating
Support. This chapter establishes planning guidelines, authorizations and standards for contingency bases
at various stages of development.

Figure 3.1. Bare Base Sighted Alongside Host Nation Facilities.

3.2. Purpose. To provide definitions and st andards for facilities, utili ties and personnel support within
forward operating locations, forward operating bases, main operations and intermediate staging area air-
bases.

3.3. Facility Standards for Base Camps. During the evolution of a con tingency airbase, infrastructure
and facilities will progress from initial to semi-permanent construction standards depending on mission
requirements and operational duration. Definition and de scription of authorized end-state facility con-
struction standards are listed in Table 3.2., pages 3-4 through 3-6. The Component Commander of
CFACC has the authority to establish expeditionary airbases at any construction standard based on opera-
tional requirements and resource availability. AF guidance on authorized facility requirements and stan-
dards is listed later in this chapter (Expeditiona ry Airbase Development Matrix) and in AFH 32-1084,
Facility Requirements. This guidance applies to al l base camps, regardless of the stage of development.
The matrix clarifies the desired construction quality for each facility at various stages of development. It
is understood that meeting these standards will be a progressive effort. Theater and MAJCOM CE staffs
will strive to meet the standards contained in this chapter as quickly as the operational, resource and coor-
dination (programming, approval and funding for semi-per manent and permanent standards) situation
allows.

3.4. Force Protection and Safety. Antiterrorism force protection and p hysical security in the expedi-
tionary environment present unique challenges to planners, engineers and security forces. The threat type,
32 AFPAM10-219V6 1 FEBRUARY 2006

severity and desired level of protection are the primary considerations when selecting AT/FP and physical
security measures. These considerations will be used to identify vulne rabilities, reduction measures and
the siting of facilities. In the expeditionary envi ronment, important security planning factors include:
availability of existing facilities, types of struct ures, existing natural or man-made features, types and
quantity of indigenous construction materials, avai lable real estate and ot her base infrastructure.
Pre-existing buildings will be renovated to meet DOD, AF and CFACC force protection and security stan-
dards. These standards will provide guidance for devel oping strategies to mitigate the effects of specific
aggressor tactics, defined levels of protection and ef fects on building costs of applying those measures.
Specific force protection measures and planning considerations are detailed in Chapter 7 of this volume.
3.4.1. UFC 4-010-01, Design: DOD Minimum Antiterrorism Standards for Buildings, outlines the
threat level and construction requ irements for facilities in both expeditionary and permanent bases.
Table 3.1. is extracted from UFC 4-010-01 to give the CE planner an idea of the required level of AT
construction standards and the impli cations of the various standard s for expeditionary construction.
These factors will allow the CE planner to adequately brief the combined forces commander or theater
planner on ramifications of progr amming and funding for construction at various levels. Ultimately,
the component commander, with the guidance of his staff civil engineer, will be responsible for defin-
ing construction standards for their various bases as outlined in Chapter 1 of this publication.
3.4.2. Levels of protec tion are described in Table 3.1., Table 3.2. and Table 3.3.. These standards
provide a low level of pr otection for billeting and primary gathering buildings because of the higher
concentration of personnel and attractive nature of the target. The effects of utilization of various stan-
dards of protection can be mitigated by add itional active and pa ssive measures such as increased
standoff distances, perimeter fencing, alarming etc. The impact of increased AT standards results in
significant improvement to the facility and person nel survivability but co mes at the expense of
increased funding, beddown execution timelines and res ources. These must be balanced to meet the
CC’s mission requirements.

3.5. Authorized and Required Facilities. As part of the deployment planning and base beddown pro-
cess outlined in AFPAM 10-219 Volume 5, it is imperative to ensure that limited resources are applied to
prioritized mission requirements. The bottom line during planning is that there will never be enough space
and assets to make everyone happy and give them what they think they deserve. In light of this, it is up to
the civil engineer planners and mission support group planners to ove rsee the planning board and mini-
mize conflict. Table 3.2. provides some basic guidelines on facility authorization at different contingency
locations to better facilitate some of the facility utilization planning.
AFPAM10-219V6 1 FEBRUARY 2006 33

Table 3.1. Levels of Protection – Expeditionary and Temporary Structures.


Level of Protection Potential Structural Damage Potential Injury
Below AT Standards Severely damaged. Frame Majority of personnel suffer
collapse/massive destruction. fatalities.
Little left standing
Very Low AT Standards Heavily damaged. Major Majority of personnel suffer
portions of the structure will serious injury. There are likely to
collapse (over 50%). A be a limited number of fatalities
significant percentage of (10-25%)
secondary structural members
will collapse (over 50%).
Low AT Standards Damaged – unrepairable. Some Majority of personnel suffer
section of the structure may significant injuries. There may
collapse or lose structural be few fatalities (<10%).
capacity (10-20% of structure)
Medium AT Standards Damaged – repairable. Minor to Some minor injuries, but no
major deformations of both fatalities are likely.
structural members and
non-structural elements. Some
secondary debris will be likely
but the structure remains intact
with collapse unlikely.
High AT Standards Superficially damaged. No Only superficial injuries are
permanent deformation to likely.
primary and secondary structural
members or non-structural
elements.
Table 3.2. Expeditionary Airbase Construction Standards in Theater. (MOB Guidelines – Refer to Atths 4, 5 & 6 for detailed info).

34
EXPEDITIONARY STANDARD. Characterized by extremely austere facilities requiring minimal engineer effort to initiate operations. Intended for limited operational
duration (< 90 days). Intended for operational personnel and resources only. Support and supply operations to be maintained by host unit at support MOB or ISB.
INITIAL STANDARD. Characterized by austere facilities requiring minimal engineer effort. Intended for immediate operational use by units upon arrival for a limited
operational duration (up to 6 months). May require replacement by more substantial or durable facilities during the course of operations and mission growth.
TEMPORARY STANDARD. Characterized by austere facilities requiring additional engineer effort above that required for initial standard facilities. Intended to
increase efficiency of operations for use up to 24 months. Provides for sustained operations. Replaces initial standard where mission requirements dictate. Temporary
standards may be used initially if directed by the combatant commander.
ENDURING PRESENCE STANDARD. Characterized by well-developed facilities & infrastructure requiring additional engineer effort above that required for
temporary standard facilities. Intended to increase operational efficiency for use over 24 months. Provides for sustained operations through more durable construction
materials, better energy conservation systems, & master planning efforts. Requires programming, funding, design, & construction management through theater C7 or
MAJCOM A7.
WARM BASE STANDARD. Characterized by well developed infrastructure requiring additional engineer effort for opening the airbase. Intended to increase speed of
beddown by requiring erection of prepositioned tents, resources and assets. Maintained by caretaker organization (military unit or civilian contract). Warm bases are
identified and established by the theater C7 and/or MAJCOM/NAF A7.

AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT


FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Site Work As required to Minimal clearing and Clearing and grading for Engineered site Engineered site Clearing and grading for
support beddown grading as required for facilities sites including preparation, including preparation, including facility sites including
(dependent upon mission requirements. drainage, revetments of paved surfaces for paved surfaces for vehicle drainage, revetments for
site, local and Heavy equipment very petroleum, oil and lubricants vehicle traffic areas traffic areas and aircraft petroleum, oil and lubricants,
climate). limited at expeditionary and ammo storage and and aircraft parking, parking, building ammo storage, and aircraft
standard bases. aircraft parking; aggregate building foundations foundations and concrete parking; aggregate for heavily

AFPAM10-219V6 1 FEBRUARY 2006


for heavily used hardstands; and concrete floor floor slabs with masonry or used hardstands; and soil
and soil stabilization. slabs. pre-engineered building stabilization
systems.
Billeting E1-E5 = 80 NSF Tents/Host Nation Tents (may have wood Wood frame structures, Wood frame structures, Concrete pads for tents.
E6/E7 = 130 NSF facilities when available. frames and flooring). re-locatable structures modular and/or masonry/
O1/O2 =130 NSF and modular building prefabricated structures.
E8 = 160 NSF systems.
O3/O4 = 160 NSF
E9 = 256 NSF
O5/O6 =256 NSF
O7+ = 512 NSF
DV/VIP = 2,944
NSF per base
AFPAM10-219V6 1 FEBRUARY 2006
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Dining Facility 860 NSF per 1,000 Tents/Host Nation Tents (may have wood Wood frame structures, Wood frame structures, Concrete pads for tents.
assigned personnel facilities when available. frames and flooring). re-locatable structures modular and/or masonry/
and modular building prefabricated structures.
systems.
Electricity Refer to AFPAM Tactical generators: high Tactical generators: high and Non-tactical or Local power primary and Local power with generator
10-219 Volume 5, and low voltage low voltage distribution commercial power and secondary service with back-up
Attachment 7 for distribution. high or low voltage buried utilizes and
planning guidance distribution generator back-up
Shower Facilities 1 Shower head per Tents/Host Nation HF/FP shower shave units HF assets, HN facilities Modular/package units Concrete pads for tents with
20 Personnel facilities when available and HN facilities when and modular/package upgrading to permanent in-place underground utility
(Minimum) HF/FP; shower/shave sets available with above ground units with underground facilities with underground distribution and collection
when available. utilities and wastewater utilities. utilities. systems
storage tanks.
Potable Water 15 gallons per Bottled water and/or local ROWPU purification of Limited distribution to Water points, wells, HN Water points, wells, host
person per day. supply. water points, wells or other hospitals, dining halls primary distribution and/or nation primary distribution
potable water production and and other large users. other potable water and/or other potable water
pressurized water production & pressurized production and pressurized
distribution systems. water distribution systems. water distribution systems.
Non-Potable Water Generation of 15.5 Local source (wells, host Local source (wells, host Local source (wells, Local source (wells, host Local source (wells, host
gallons per person nation utility lines). nation utility lines). HN utility lines). nation utility lines). nation utility lines).
per day.
Cold storage Dependent upon on Portable refrigeration Portable refrigeration with Refrigeration installed Refrigeration installed in Not Applicable
base food with freezer units for freezer units for medical, in temporary permanent, masonry or
preparation, medical, food and food and maintenance structures. PEB buildings.
medical, and related maintenance storage. storage.
requirements. Refer
requirement to
theater level
planning section.
Latrines 1 Toilet per 15 Burnout/Slit latrines and Chemical units, HF/FP HF/FP Latrine units Wood frame structures, Concrete pads for tents with
personnel Host Nation facilities Latrine Units and associate upgrading to modular/ modular and/or masonry/ underground utilities.
(Minimum). support equipment. package units with prefabricated structures
underground utilities with underground utilities.
and collection.

35
36
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Sewage Disposal Organic equipment, Organic equipment, Waterborne to austere Wastewater collection and Wastewater collection and
and Treatment evaporative ponds, leech evaporative ponds, pit or treatment facility – treatment system via host treatment system via host
fields, pit or burnout burnout latrines, lagoons for priorities are hospitals, nation infrastructure or nation infrastructure or
latrines. hospitals and sewage lift dining halls, purchased package units. purchased package units.
stations. bathhouses,
decontamination sites
and other high volume
users.
Airfield pavement * Refer to AFJMAN Tactical surfacing, Tactical surfacing, including Conventional Conventional pavements. Conventional pavements.
32-8013 Volume 2. including matting, matting, aggregate, soil pavements.
aggregate, soil stabilization and concrete
stabilization and concrete pads.
pads.
C130/C17 Runway Refer to AFJMAN Stabilized Earth Stabilized Earth Conventional Conventional pavements Conventional pavements
32-8013 Volume II pavements
C130/C17 Taxiway Refer to AFJMAN Stabilized Earth Stabilized Earth Conventional Conventional pavements Conventional pavements
32-8013 Volume 2 pavements
C130/C17 Parking Refer to AFJMAN Stabilized Earth Stabilized Earth Conventional AM-2 Matting Conventional pavements
Apron 32-8013 Volume 2 pavements
C5/Tanker/747 Refer to AFJMAN Conventional Pavements Conventional Pavements Conventional Conventional pavements Conventional pavements
Runway 32-8013 Volume 2 pavements
C5/Tanker/747 Refer to AFJMAN Conventional Pavements Conventional Pavements Conventional Conventional pavements Conventional pavements
Taxiway 32-8013 Volume 2 pavements

AFPAM10-219V6 1 FEBRUARY 2006


C5/Tanker/747 Refer to AFJMAN Conventional Pavements Conventional Pavements Conventional Conventional Pavements Conventional pavements
Parking Apron 32-8013 Volume 2 pavements
Aviation HF-FP Tents HF-FP Clamshells Prefabricated/ Clamshells to Concrete pads for tentage
Maintenance Pre-engineered Hangar pre-engineered steel and and/or clamshells
facilities concrete hangar facilities.
Helipad 1 lighted pad per Stabilized earth Concrete Concrete Concrete Concrete
base (minimum);
refer to AFJMAN
32-8013 Vol 2.
Fuel Storage Refer to theater Bladders Bladders Bladders and steel Metal tanks and permanent Concrete pads and
Fuels planner for tanks installed steel distribution containment berms for
space requirements. lines and dispensing points bladders
AFPAM10-219V6 1 FEBRUARY 2006
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Munitions Storage Refer to theater Stabilized earth with blast Gravel pads with blast Gravel pads with blast Concrete pads with blast Concrete pads with blast
Area (MSA) Munitions planner protection berms with protection berms with protection berms and protection berms and protection berms and
for storage space perimeter concertina perimeter concertina fence perimeter concertina perimeter chain-link fence. perimeter chain-link fence.
requirements. fence and guards and guards. fence. Guard house, Guard house, with secure Guard house, with secure
with secure ECP ECP equipped with counter ECP equipped with counter
equipped with counter mobility barriers. mobility barriers
mobility barriers.
Squadron Each flying Tents (Tier I), HF/FP Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
Operations Facilities squadron is Expandable Shelter wood frames and flooring) re-locatable structures modular and/or masonry/
authorized 10,000 * Assets and GP Shelters and modular building prefabricated structures
systems
Office Space (Open Per person Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
Plan layout with E1-E6 = 60 NSF wood frames and flooring) re-locatable structures modular and/or masonry/
10% added for E7 = 90 NSF and modular building prefabricated structures
common areas) E8/O1-O3 = 110 systems
NSF
E9/O3 CC = 100
NSF
O4-O5 = 150 NSF
Office Space E9/O3 CC = 100 Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
(Private Offices NSF wood frames and flooring) portable structures and modular and/or masonry/
when mission, space O4-O5 = 150 NSF modular building prefabricated structures
and assets allow,) O5-O6 CC = 200 systems
NSF
E9 SEA = 200 NSF
07+ = 300 NSF
Squadron HQ 1,536 NSF per Tents (Tier II/III, may Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
Facilities Squadron have wood frames and wood frames and flooring) portable structures and modular and/or masonry/
flooring), HF GP Shelters modular building prefabricated structures
or Expandable Units systems
AEW Wing HQ Maximum Tents (Tier II/III, may Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
Facilities allowance of 5,376 have wood frames and wood frames and flooring) portable structures and modular and/or masonry/
NSF per base flooring), HF GP Shelters modular building prefabricated structures
or Expandable Units systems

37
38
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Office Space for Use above listed Tents (Tier II/III, may Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete Pads for Tents
Headquarters, JTF, office allowances have wood frames and wood frames and flooring) portable structures and modular and/or masonry/
NAF or CFACC plus an additional flooring), HF GP Shelters modular building prefabricated structures
equivalent 40% space or Expandable Units systems
authorization for
storage, conference
rooms, copiers etc.
Storage Facilities As identified by user Unit Tents Tents (Tier II/III, may have MILVAN/CONEX Masonry/Pre-engineered Pre-Engineered Warehouses
requirements wood frames and flooring) Steel Warehouses (Usually
housing prepositioned
assets)
Vehicle Maintenance 1,480 sq ft per HF-FP Tents (Tier I) Tents (Tier II/III, may have Clamshell/Modular Clamshell to permanent Concrete pads for tents and
Group with 640 SF wood frames and flooring) facility with repair bays modular, masonry or repair yards
associated admin pre-engineered building
office space
Vehicle Hard Stands As required to Stabilized Earth Gravel Concrete Concrete Concrete
accommodate
supported equipment
Wash Racks 45’ x 100’ flat rack Not Authorized Gravel Gravel Elevated wash rack on Gravel/Concrete pads
with oil and water concrete pad with oil and
separator water separator with
re-claimer
Medical Facilities Refer to theater Units Tents (Tier I) HF-FP Facilities Wood frame structures, Wood frame structures, Concrete Pads for Tents

AFPAM10-219V6 1 FEBRUARY 2006


Medical Planner for portable structures and modular and/or masonry/
specific Guidance modular building prefabricated structures
systems
MWR Warehouse 1 NSF per person Not Authorized Not Authorized Tents Wood frame structures, Concrete Pad for tents
modular and/or masonry/
prefabricated structures
Supply Warehouse Dependent upon HF-FP Warehousing HF-FP Facilities Wood frame structures, Wood frame structures, Concrete Pads for Tents
equipment density assets portable structures and modular and/or masonry/
and mission modular building prefabricated structures
requirements systems
Individual 1 NSF per assigned HF-FP Facilities Wood frame structures, Wood frame structures, Concrete Pads for Tents Concrete Pads for Tents
Equipment Issue base personnel portable structures and modular and/or
(IEU) modular building systems masonry/prefabricated
structures
AFPAM10-219V6 1 FEBRUARY 2006
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Fitness Center 3 NSF per person None Tents (Tier II/III, may have HF-FP Tents to Wood Wood frame structures, Concrete Pad for tents
wood frames and flooring) frame and/or modular modular and/or masonry/
structures prefabricated structures
Field House Large enough to Not Authorized Tents (Tier II/III, may have HF-FP Tents to Wood Wood frame structures, Concrete Pad for tents
accommodate full wood frames and flooring) frame and/or modular modular and/or masonry/
sized basketball structures prefabricated structures
court (50’x94’)
Recreation Pavilion 1 Court per 1,000 Not Authorized Not Authorized HF-FP Tents to Wood Wood frame structures, Concrete Pad for tents
assigned frame and/or modular modular and/or masonry/
structures prefabricated structures
Running Track 1 outdoor trail (2 Not Authorized Not Authorized Dirt track upgraded to Paved asphalt track Graded Dirt Track
miles in length) is paved
authorized when
local antiterrorism
and force protection
situation allows
Athletic Fields Each MOB is Not Authorized Not Authorized Open fields graded to Open Fields with fencing, Open fields with lights
authorized 2 sand support requirement area lighting and support
volleyball courts, 2 structures
horseshoe pits,
paved outdoor
basketball court (1/2
court), MOBs with
over 2,000 assigned
personnel are
authorized a 2nd set
Community Activity 2,400 NSF per 1,000 Not Authorized Tents (Tier II/III, may have HF-FP tents to wood Wood frame structures, Concrete pad for tents
Center personnel assigned wood frames and flooring) frame and/or modular modular and/or masonry/
structures prefabricated structures
Theater Authorized where Tents (Tier I) Tents (Tier II/III, may have Wood frame or metal Masonry, Metal Concrete pad for tents
base population wood frames and flooring) prefabricated structure prefabricated buildings
exceeds 1,000
personnel (capacity
not to exceed 500
personnel)
Chapel 1,624 NSF per 1,000 Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
assigned personnel wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems

39
40
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Perimeter/Security As required based on Concertina Wire Triple Standard concertina Triple Standard Chain link fence with barb Triple Standard concertina
Fence base Force wire concertina with counter wire outriggers and vehicle with counter mobility berms
Protection plan and mobility berms barriers
threat assessment
Security Forces Interior SF = 145 Not Authorized Tents (Tier II/III, may have HF-FP tents to wood Wood frame structures, Concrete pad for tents
Working Dogs NSF per dog (to wood frames and flooring) frame and/or modular modular and/or masonry/
Kennels include kitchen, tack structures prefabricated structures
room). Interior dog
run = 36 NSF per
dog
Exterior Dog Run =
48 NSF per dog
Perimeter/Security As required based on Gen sets, light carts and Gen sets, light carts and Pole mounted Pole mounted hardwired Pole mounted hardwired
Lighting base Force Remote area lighting Remote area lighting hardwired lights security lights with lights
Protection plan and systems (RALS) systems (RALS) centralized control systems
threat assessment
Guard Towers As required based on Not Authorized Not Authorized Standard SF design Standard SF design Standard SF design
base Force
Protection plan and
threat assessment
Entry Control Point As required based on Guards and vehicles or Berms, serpentine with HESCO Barriers, HESCO Barriers, enclosed Chain link entry fence/gate
base Force equipment used as counter concrete barriers and vehicle enclosed or covered or covered vehicle search with vehicle barriers and
Protection plan and vehicle barriers barriers with search pit vehicle search area and area and search pit, covered entry control vehicle
threat assessment search pit, concrete concrete and vehicle search pit

AFPAM10-219V6 1 FEBRUARY 2006


barriers and vehicle barriers with minimal
barriers with minimal guard building with latrine
guard building with and electronic controls
portable latrine (perimeter cameras, motion
facilities alarms, etc.) guard building
Detainee Retention Tents with concertina wire Tents with concertina wire Wood frame structures Wood frame structures Tents with concertina wire
Facility perimeter fencing perimeter fence and over with chain link with chain link perimeter perimeter fence and over
watch towers perimeter fencing with fencing with triple strand watch towers
triple strand barb wire barb wire outriggers and
outriggers and over over watch guard towers
watch guard towers
Education Center/ 1,710 NSF per 1,000 Not Authorized Tents (Tier II/III, may have HF-FP tents to wood Wood frame structures, Concrete pad for tents
Library assigned personnel wood frames and flooring) frame and/or modular modular and/or masonry/
structures prefabricated structures
AFPAM10-219V6 1 FEBRUARY 2006
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
Post Office 1,710 NSF per base Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Field Exchange See Table 3.3. Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Field Exchange/ See Table 3.3. Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
Warehouse wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Barber Shop See TTable 3.3. Not Authorized Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Food Concession See Table 3.3. Not Authorized Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
Stands wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Food Concession See Table 3.3. Not Authorized Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
Dining Area wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Alteration, Pressing, See Table 3.3. Not Authorized Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
Laundry wood frames and flooring) portable structures and modular and/or masonry/
modular building prefabricated structures
systems
Fire Refer to DODI Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
60556.6 and AR wood frames and flooring) portable structures and modular and/or masonry/
420-90 modular building prefabricated structures
systems
EOD 300 NSF per person Tents (Tier I) Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for Tents
with attached wood frames and flooring) portable structures and modular and/or masonry/
covered vehicle modular building prefabricated structures
storage (enclosed in systems
extreme
environments) Refer
to AFMAN 91-210

41
42
AUTHORIZA- EXPEDITIONARY INITIAL TEMPORARY SEMI-PERMANENT
FACILITY WARM BASE
TION < 90 Days <6 Months <24 Months < 5 Years
DRMO 1 NSF per assigned Tents (Tier I) Tents (Tier II/III, may have Prefabricated Metal/ Prefabricated Metal/ Concrete pads for Tents
person wood frames and flooring) Modular building with Modular building with
Gravel storage yard Gravel storage yard
DRMO Storage Yard 2 NSF per 1,000 Gravel Lot Gravel Lot Gravel Lot Asphalt Lot Asphalt Lot
assigned personnel
Roads/Streets As required by base Stabilized Earth Gravel Asphalt with Concrete Asphalt with concrete Asphalt with concrete
(Primary) layout turnouts turnouts turnouts
Roads/Streets As required by base Stabilized Earth Stabilized Earth Gravel Asphalt with concrete Asphalt with concrete
(Secondary) layout turnouts turnouts
Personnel Flight 1,024 SF per base Tier I Tents Tents (Tier II/III, may have Prefabricated Metal/ Prefabricated Metal/ Concrete pads for tents
Operations (MPF) wood frames and flooring) Modular building with Modular building with
Gravel storage yard Gravel storage yard
Morgue 512 SF per AEW Tier I Tents Tents (Tier II/III, may have Prefabricated Metal/ Prefabricated Metal/ Concrete pads for tents
with refrigerated wood frames and flooring) Modular building with Modular building with
storage space Gravel storage yard Gravel storage yard
Finance Operations 1,024 SF per base Not Authorized HF/FP Assets (Expandable Prefabricated Metal/ Prefabricated Metal/ Concrete pads for tents
with a 5’x 8’ shelters) Modular building with Modular building with
cashiers cage and 8’ Gravel storage yard Gravel storage yard
x 9’ vault
Communications Each AEW is Tents (Tier II/III, may Tents (Tier II/III, may have Wood frame structures, Wood frame structures, Concrete pads for tents
Facilities and authorized a Comm have wood frames and wood frames and flooring); portable structures and modular and/or masonry/
Network Control and NCC secure flooring), HF GP Shelters authorized the following: modular building prefabricated structures;

AFPAM10-219V6 1 FEBRUARY 2006


Centers compound. Basic or Expandable Unit; FE6 Compound fence systems; authorized the following:
allowance guidelines authorized the following: Gravel Parking lot authorized the FE6 Compound fence
are (Base on FE6 Compound fence Security Lighting following: Gravel Parking lot Security
population): Gravel Parking lot FE6 Compound fence Lighting
<1,500 = 2,944 NSF Security Lighting Gravel Parking lot
1,500-3,000 = 4,736 Security Lighting
NSF
3,000-5,000 = 6,208
NSF
5,000< = 91,52 NSF
NOTE: *. Squadron operations facilities authorizations replace any per person NSF authorization for admin space for HQ OSS, Weather Ops and Mission Planning.
Table 3.3. AAFES Contingency Facility Requirements Planning Matrix.

AFPAM10-219V6 1 FEBRUARY 2006


Stock Number of Retail
Number of Retail Food Court Laundry/ Barber Beauty Shop Exterior
Room/ Food Concessions
Personnel Area Seating Alterations Shop (sq ft) Min Bazaar
Storage Conces (400 sq ft
Assigned (sq ft) (sq ft) (sq ft) (sq ft) 250 Female Area
(sq ft) sions per)
0-1000 4,243 2,090 1
700
1001-1500 6,365 3,135 1 400 1
525
1501-2000 8,487 4,180 2 250 1,500
1,400
2001-2500 10,609 5,224 2
2501-3000 12,730 6,270 3
2,100
3001-3500 14,852 7,315 3 800 2
3501-4000 16,973 8,360 4 2800
725
4001-5000 21,217 10,450 4 3500 500 2,500
5001-6000 25,460 12,540 4 4200
6001-7000 29,704 14,629 4 4900
7001-8000 33,947 16,720 4 5600 1,000 3
8001-9000 38,190 18,810 4 6300 750 1,080 3,000
9001-10,000 42,434 20,889 4 7000

NOTES:
CE will be required to provide adequate HVAC support for facilities based on Table 3.2. construction authorizations.
CE will be required to provide Facility Security (Door Locks) for semi-permanent or modular facilities.
Facilities require 220 volt power for lighting, registers and refrigerators in retail, service and food operations.
Concession may require electrical, ECU and water hookups for initial operations.

43
44 AFPAM10-219V6 1 FEBRUARY 2006

Table 3.4. MOB, FOL, and FOB Facility Authorization Guidance.


Main Operating Forward Operating
FACILITY Forward Operating Airbase
Airbase Location

YES (Paved primary and YES (gravel primary and YES (gravel primary and
Roads
secondary) secondary) secondary)

DFAC YES YES NO

Billeting YES YES YES

Latrines and Septic Systems YES YES YES

Shower YES YES YES

Office YES YES YES

Warehouse YES NO NO

SCIF YES NO NO

Finance and Personnel


YES YES (operationally defined) NO
Support Operations

Postal Facility YES NO NO

Laundry Collection/
YES YES NO
Distribution Point

Helipad YES YES YES (operationally defined)

Runway and Taxiway YES YES NO

Aviation Fuel YES YES (operationally defined) NO

Squadron Operations Building YES YES NO

Aviation Maintenance YES YES (operationally defined) NO

Communications
YES YES (operationally defined) NO
Compound/NSC

Medical YES YES (Aid Stations) MEDICS

Vehicle Maintenance YES YES NO

Ground Fuel YES YES NO

Hazardous Waste Collection


YES YES NO
Point

Hazardous Materials
YES NO NO
Warehouse

Parking Lots YES YES YES (operationally defined)

Kennel YES Operationally Defined YES (operationally defined)

Morgue YES NO NO

DRMO YES NO NO
AFPAM10-219V6 1 FEBRUARY 2006 45

Main Operating Forward Operating


FACILITY Forward Operating Airbase
Airbase Location

Wash Rack YES NO NO

Fire Protection YES YES YES (operationally defined)

Training Facilities YES NO NO

SF Facility YES YES NO

Cold Storage YES YES NO

Chapel YES YES NO

Education Center YES NO NO

Barber/Beauty Shop YES NO NO

Alteration/Pressing Shop YES NO NO

AAFES YES YES YES

AAFES Warehouse YES NO NO

Fitness Center YES YES YES

Field House/Multipurpose
YES YES NO
Facility

Athletic Fields YES YES NO

Community Activity Center YES YES YES

Multi-Purpose Theater YES NO NO

MWR Warehouse/
YES NO NO
Maintenance Facility

AFN Manned Operations YES NO NO

AFN Unmanned Operations YES YES NO

Wing HQ Building YES YES YES

3.6. Facility Construction Standards. Table 3.3. provides guidance on the authorized facility construc-
tion standards as defined by mission duration and weapons systems requirements. Construction standards
are detailed in Chapter 2 of this volume. The component commander may authorize any construction
standard for beddown and bare base construction, as long as it conf orms to Air Force programming and
funding authorization and guidelines as listed in AFIs 32-1021, -1022, -1023 and Chapter 6 of this vol-
ume.
3.6.1. Billeting Standards. Initial billeting standards for all con tingency bases is ut ilization of host
nation facilities, BEAR or Force Provider tentage utilizing the pla nning factors listed later in this
chapter for space requirements. Depending on mission requirements and airbase operational duration,
housing may be improved to modular facilities or semi-permanent style dormitories. Theater level CE
planning staffs will dictate the level and speed of billeting upgrades based on the CF ACC’s mission
requirements. It is critical that the theater and continge ncy base engineers plan for a surge billeting
46 AFPAM10-219V6 1 FEBRUARY 2006

capability to respond to changes in war plans and base mission requirements. To accommodate popu-
lation surges/transients, expeditionary airbases will maintain the ability to house 110% of its total nor-
mal population at all times. If the base is utilizing temporary or semi-permanent construction standard
billets (SEA huts, modulars, etc.) surge capacity may be accomplished through utilization of available
BEAR or Force Provider tentage.
3.6.2. Rotary Wing Aviation Facilities. Helicopter landing and parking pads may initially be S tabi-
lized Earth or AM-2 Matting to prevent foreign object damage (FOD). Landing/parking pads will be
upgraded to concrete or asphalt with adequate grounding rods an d tie-downs. Treat all soil in the
immediate area of the pads to reduce FOD. Pla ce HESCO bastions or similar materials around hot
arming pads to minimize damage from accidental mi ssile discharge. At a minimum, outfit one heli-
copter-landing pad on each base camp with landing lights for reduced visibility operations.
3.6.3. Maintenance Facilities Planning Consider ations. The responsible component shall provide
appropriate aircraft maintenance structures in accordance with the number/type of aircraft supported.
Coordinate with theater or deploying Logistics/Maintenance planner for facility requirements.
3.6.4. Medical Facilities Planning Considerations. Develop plans for health clinics, dental clinics and
hospitals in coordination with the responsible component Health Facility Planning Office. Design and
construct medical facilities in accordance with the responsible operational command’s standards. The
Air Force has developed multiple deployable medical treatment facilities (MTFs) to treat and evacu-
ate casualties under all conditions. The Expeditionary Medical Support (EMEDS) system is composed
of more than 170 equipment a nd personnel building block UTCs to meet the spec trum of medical
response needs. EMEDS is deployed in expandable components and its facilities range in size from
four bed holding areas to 114-bed theater hospitals able to treat a population at risk of over 5000 per-
sonnel. See Volume 5 of this pamphlet series fo r detailed civil engineer support requirements for
expeditionary medical facilities.
3.6.5. Transportation Maintenance Facilities. The responsible comp onent will design and construct
vehicle maintenance facilities. The vehicle maintenance facilities will evolve as the base camp
matures to support the mission.
3.6.5.1. Maintenance Facilities. The facility should be equipped with environmental control units
and electricity when the operational situation allows.
3.6.5.2. Fuel Truck Parking. Secondary containment pads are required for fuel truck parking. The
containment pads will be equi pped with a collection sump an d grounding rods for parked fuel
trucks.
3.6.6. Hazardous Waste Accumulation Points. Construct hazardous waste accumulation points IAW
the Overseas Environmental Baseline Guidance Document (OEBGD). Responsible Component Com-
manders may authorize additional ac cumulation points as required. Each base will designate a base
engineer responsible for all hazardous material management and hazardous waste collection and dis-
posal.
3.6.7. Solid Waste Disposal. Solid Waste Disposal will be in accordance with the OEBGD. The
responsible component will authorize the environmentally-appropriate method of disposal of solid
waste such as use of incineration or use of landfills.
3.6.8. Fuel Storage. Above ground fuel tanks are authorized for the storage of bulk fuels at long term
camps. When fuel bladders are necessary, site them according to the OEBGD.
AFPAM10-219V6 1 FEBRUARY 2006 47

3.6.9. Munitions Storage Areas (MSA). Construct MSA in accordance with the responsible compo-
nent’s guidance. Munitions storage areas will have containment berms, a fenced and lighted perimeter,
graveled access roads and lightning protection. Store ammunition in protective structures that are not
in contact with the ground (i.e. on wooden pallets or on concrete foundations).
3.6.10. Kennels. Where military working dogs are authorized for an operation, the responsible com-
ponent will provide kennel facilities to sustain the operation. Kennel facilities will evolve as the base
camp matures to include environmental controls, electrical service and exercise yard.
3.6.11. Mortuary Affairs. Morgues will be in accordance with the standards in Joint Publication 4-06,
Joint Tactics, Techniques and Procedures for Mortuary Affairs in Joint Operations. Regardless of the
type of base camp, privacy screens will be installed around the entire morgue facility.
3.6.12. Distinguished visitor (DV) and guest quarters. Main operations and logistics hub base camps
will have DV and guest quarters.

3.7. Utilities. Design utility systems based on current applicable military handbooks, technical manuals
and guidance. Refer to Attachment 3 (Base Camp Development Matrix) for the recommended facilities
for each level of base camp development.

3.8. Electric Power.


3.8.1. Electrical Grid Development. As the base camp matures, and where economically supportable
and practicable, connect base camp power grids to commercial power. Smaller or remote base camps
that cannot be economically connected to a commercial power grid should install central power plants
with the capacity to support 12 5% of the peak electrical demand in accordance wit h component
requirements. During planning phase, give careful consideration to desired electrical system end-state
as outlined in the utilities portion of Attachment 3 (paragraph A3.36.1.4.).
3.8.2. When the operational situation does not allow a central power plant, then the base camp will
use distributed generators of sufficient capacity to support peak electrical demand loads in accordance
with component requirements. Back up generators should be installed within the base camp. The
placement, types and numbers will be dependent upon the operational situation.
3.8.3. Considerations for Electrical Grid/Load Planning. In the planning phase for the base camp elec-
trical grid, the electrical load for the following numbers and types of equipment must be calculated to
ensure an adequate electrical power supply/grid is constructed:
3.8.3.1. Environmental Control Units (Heating/Air Conditioning).
3.8.3.2. Communications and Automation Equipmen t. Communications equipment, computers
and airfield control measures are critical for electrical load calculation. Ensure planning encom-
passes charging requirements for battery operated computers and computer base equipment.
3.8.3.3. Dining Facility Electrical Equipment. Refer to theater/base Services planner for detailed
load information.
3.8.3.4. Billeting. Deployed AF personnel carry a great deal of electronic equipment not origi-
nally planned for under the BEAR deployment concept. It is common for senior enlisted personnel
and officers to deploy with pers onal laptops and other electronic equipment. Ensure these are
taken into consideration when outlining electric al requirements. During upgrades, it has become
common practice to include small refrigerators, television, VCR/DVD players, game consoles and
48 AFPAM10-219V6 1 FEBRUARY 2006

computers even in expeditionary tent city environments. The CE planner must be prepared for this
level of electrical load as soon as resources and mission effectiveness allow.
3.8.4. Maintenance Facilities.
3.8.5. Force Protection Measures (Exterior Lighting/Electrified Fencing).
3.8.6. Morale, Welfare and Recreation (MWR) Activity Devices and Lighting. Tent cities normally
have a central MWR tent that is comprised of television/theater equipment, gaming consoles,
increased computer equipment and other functions. Coordination with the theater/base theater planner
will enable the CE planner to ad equately cover the electrical needs and increm ental growth of these
facilities during base upgrades.
3.8.7. Civilian Contract Power. Depending on the operational situation, civilian contracts can be used
to procure, operate and maintain electrical power as the base camp passes beyond the Expeditionary
and Initial phases of development.

3.9. Environmental Control (Heating/Air Conditioning). As the base camp matu res, the responsible
component will provide environmental control units to supported facilities/units based on operational and
environmental needs. The type, method and standard of environmental control will be determined by the
following criteria:
3.9.1. Operational situation.
3.9.2. Climate. During OEF numerous northern expediti onary bases in the theater of operation were
delivered pallets of ECUS in the late fall months that were unable to produce the heating required
(standard Harvest ECUs utilized a heat strip that was only functional to 25 degrees Fahrenheit) while
more southern bases went without, even though the daily temperatures were still exceeding 90 degrees
Fahrenheit. The CE planner must understand the cap abilities and limitations of equipment requested
to ensure our limited assets are sourced for the proper location.
3.9.3. Type/function of facility/base camp.
3.9.4. Maturity of facility/base camp. Unless extreme climactic conditions or equipment requirements
arise, it does not make sense to waste limited airlift to deploy envi ronmental control units to Initial
Standard expeditionary bases (<90 days).
3.9.5. Base camps will utili ze existing installed environmental c ontrol systems if economically and
environmentally feasible.
3.9.6. The following priority list fo r deployment of environmental control units is provided to assist
CE planners in doling out these assets. This list serves as a guideline for both theater planners execut-
ing dozens of beddowns or the ba se planner prioritizing on ground assets for installation. ECUs
should be installed in the following priority:
3.9.6.1. Command/Control/Communications and Automation facilities.
3.9.6.2. Medical facilities.
3.9.6.3. Billeting.
3.9.6.4. Dining facilities.
3.9.6.5. Dog kennels.
AFPAM10-219V6 1 FEBRUARY 2006 49

3.9.6.6. MWR facilities.

3.10. Potable Water Recommendations.


3.10.1. Base Engineers should tie into local municipalities where it is economically feasible, and con-
ditions meet health and force pr otection standards. The installati on of a water purification station
should be considered during the initial planning for the base camp and be part of the start up costs for
the base camp.
3.10.2. Installation of wells for pot able water is recommended. A minimum of two wells per camp,
one primary and one back up, within the boundaries of the base camp are recommended. Planning will
include the drilling of all wells at the same time to reduce mobilization costs. If economically feasible,
plan and install water storage di stribution systems. Additional wells may be drilled within the base
camp boundaries, if the situation allows, if additional capacity is required.
3.10.3. Well-drilling should be contracted through civilian markets where it is economically feasible
and conditions meet force protec tion requirements. RED HORSE units or Army Combat Engineers
have well-drilling capabilities that will need to be requested, sourced and prioritized through the the-
ater engineering planning function.
3.10.4. Transported or bottled water should be used only during the early stages of a contingency
operation and should be used as a long-term potab le water source only if no alternate sources are
available. One major lesson learne d by planners is that bottled water places a huge burden on the
logistics procurement and theater ai rlift planners. CE planners need to be aware that the decision to
utilize bottled water will re sult in the loss of daily airlift for other equipment and resources if local
suppliers cannot be located and certified to US standards.

3.11. Waste Treatment Plant. The initial assessment for a base camp should plan for wastewater treat-
ment based on a minimum of 110% projected size of the camp to include coalition forces and local nation-
als. Coordinate with local contracting and environmental offices to determine if connection to a municipal
wastewater treatment plant is economically feasible and environmentally sound. Containerized wastewa-
ter treatment plants are available through civilian contracts and should be considered when appropriate
and connection to municipal plants is not allowed. Expeditionary ba ses in Northern Iraq were able to
source and install a containerized wastewater treatment for under $700,000 in 60 days.

3.12. Personnel Support. Upgrade personnel support facilities to increase support services and provide
a safer working environment. The recommended levels of support (as listed in Attachment 3, Base Camp
Development Matrix) are to apply to all base camps. The level of personnel support will evolve as the
base camp matures and operational requirements change.
3.12.1. Dining Facilities. The dining facility may change as the base matures. The long term dining
facility will have electric lighting, environmental control units as operationally feasible and adequate
electrical connections. If civilian contractors are used, establish an occupational medicine program for
health screening. Ensure that local national ki tchen staff is provided ad equate space for cleaning,
latrine and changing areas.
3.12.2. Each base camp will have a nondenominationa l religious support facility, sized according to
the base population. The structure, as operationally feasible, will have electrical lighting, environmen-
tal control units and fixed electri cal connections. The responsible base commander will provide ade-
50 AFPAM10-219V6 1 FEBRUARY 2006

quate office space for chaplains to conduct privileged communications, adequate storage space and
side areas for private devotions. Coordination with theater/base chaplain planner will further define
their requirement.
3.12.3. Fire Protection. The responsible component commander will provide Fire and Emer gency
Response Services IAW DODI 6055.6 and National Fire Protection Association (NFPA) 403, Stan-
dard for Aircraft Rescue and Fire Fighting Services at Airports.

3.13. Planned Upgrades. The basic requirement to support mission full oper ational capability (FOC)
within a set timeline determines the AEF facility beddown timeli nes. Meeting the FOC and beddown
timelines (as well as providing an acceptable level of force protection, readiness capabilities, fire protec-
tion and critical support facilities ) drives TPFDD re-engineering and UTC restructuring. AEF bare base
support must be lighter, leaner and faster. The following matrix is provided to assist CE and contingency
airbase planners to provide initial requirements for minimum operations. Upgrades from initial to tempo-
rary standards should be planned and implemented as soon as mission and resources allow.

3.14. Manpower Utilization and Task Assignment. CE planners need to review anticipated deploy-
ment duration and mission re quirements to determine the best utiliz ation of limited active duty, AFRES
and ANG civil engineer personnel to ensure that the areas where they are deployed and utilized are appro-
priate for blue suit operations. Table 3.5. lists some standard contingency tasks and provides general guid-
ance for potential task execution resources to limit deployed man-days for CE personnel.
AFPAM10-219V6 1 FEBRUARY 2006 51

Table 3.5. Contingency Task Execution Resources.


EXPEDI- SEMI-
Personnel INITIAL TEMPORARY
TIONARY PERMANENT WARM BASE
Tasking <6 Months <24 Months
< 90 Days < 5 Years
Solid Waste Field Field Field Incinerator Field Incinerator Field Incinerator
Incinerator or Incinerator or or landfill or or landfill or or landfill or
landfill landfill civilian contract civilian contract civilian contract
removal and removal and removal and
disposal disposal disposal
Medical Field Field Incinerator/ Incinerator/ Incinerator/
Waste Incinerator Incinerator Civilian Contract Civilian Contract Civilian Contract
removal and removal and removal and
disposal disposal disposal
Hazardous Removal from Removal from Civilian Contract Civilian Contract Civilian Contract
Waste Site to central theater IAW removal and removal and removal and
collection OEBGD disposal disposal disposal
location
Facility Military Military Military Engineer Military Engineer Military units
Engineers Engineer Units Engineer Units Units or Civilian Units or Civilian transferring to
Contract Contracts Civilian
Contracts
Fire Military Fire Military Military or Military or Civilian Fire
Fighting Fighters Firefighters Contract Civilian Contract Civilian Fighters
Fire Fighters Fire Fighters
Snow Military Units Military Units Military or Military or Civilian Contract
Removal Civilian Contract Civilian Contract

3.15. Air Force Basic Expeditionary Airfield Resources (BEAR). BEAR UTCs are aggregated into
sets or packages that provide ECS capabilities. Note that sets may be further broken down into sub-UTCs
or involve less than full-set deployments. Bare base equipment allowance standards are found in AS 158
(Harvest Falcon); AS 159 (Harvest Eagle); AS 157 (BEAR); and AS 429, Part N for tr aining assets.
Below is a brief description of current BEAR sets. For a more detailed description of the set contents refer
to Volume 5 of this pamphlet series and AFH 10-222 Volume 2.
52 AFPAM10-219V6 1 FEBRUARY 2006

Figure 3.2. Typical BEAR Tent City.

3.15.1. BEAR 150 Housekeeping Set (also known as Swift BEAR). The set supports a maximum of
150 personnel for approximately fi ve days. Sets include austere sh elters, field latrine for basic
hygiene, 60kW generators, power distribution panels, environment control units (ECU), light carts,
and forklift support.
3.15.2. BEAR 550 Initial Housekeeping Set. These sets contain bare base assets for billeting, power
production/distribution, water distribution, messing capability, hygiene, camp lighting and environ-
mental control. The BEAR 550I can be tasked in one of two ways, ei ther as a parent UTC or by any
combination of its sub-UTCs. The BEAR 550I also includes expeditionary combat support infrastruc-
ture such as chapel, CE/base maintenan ce facilities and tactical field exchange. BEAR 550 sets
include assets sufficient to support 550 personnel.
3.15.3. BEAR 550 Follow-On Set. Thes e sets augment the 550 Initial set and include additional bil-
leting, hygiene, power production/distribution, water distribution, camp lighting and environmental
control.
3.15.4. BEAR Industrial Operations Set. An infrastructure set that provides various sized shelters as
facilities for supply, CE, vehicle operations/maintenance, packing and crating, etc. This package sup-
ports up to 3,300 personnel (e.g. six BEAR 550 housekeeping sets).
3.15.5. BEAR Initial Flightline Set. The set pr ovides initial flightline support for one squadron of
fighter aircraft. The assets include aircraft hangars, avionics shops and general purpose functions. The
set also provides additional power production, latrines and ECUs.
3.15.6. BEAR Follow-on Flightline Set. This set supports an additional aircraft squadron by adding
an additional aircraft hangar and medium sized sh elters for power/non-powered aircraft generation
equipment (AGE).
3.15.7. BEAR has additional optional UTCs for deployment on an as needed basis. Ther e are 16
major UTCs available including Reverse Osmosis Water Purification Units (ROWPU), self-help laun-
dry, concertina wire, water syst em freeze protection, desert cam ouflage nets/poles, AM-2 matting,
emergency airfield lighting and mobile aircraft arresting systems.
AFPAM10-219V6 1 FEBRUARY 2006 53

Figure 3.3. BEAR 150 (Swift BEAR) Assets.

3.16. Army Force Provider Resources. Force Provider is the Army’s base camp support system, similar
to the Air Force BEAR system. Force Provider was de veloped in response to lessons learned from the
1991 Gulf War. During Operation De sert Storm the Army realized that its base beddown and operating
support facilities contained only rudimentary messing and hygiene f acilities and actually hampered mis-
sion accomplishment and troop morale.

Figure 3.4. US Army Force Provider Set.

3.16.1. The Force Provider (FP) mission is to give frontline soldiers a respite from the rigors of duty.
Each Force Provider Company consists of six platoons which can support 550 soldiers separately.
Combining all six modules allows support for 3,300 soldiers. The modules can operate as stand-alone
beddown or as a modular and scalable tent city to support as large a deployment as assets are avail-
able. Each 550+ module provides the following:
54 AFPAM10-219V6 1 FEBRUARY 2006

3.16.1.1. Climate controlled billeting for 600 personnel (550 soldiers and 50 FP maintainers).
3.16.1.2. Food preparation and service capabilities for 1,650 A-ration meals per day.
3.16.1.3. Showers ( 24 stalls with water for 10 minute show ers per person per day) and latrine
facilities (24 toilets, four urinals and eight sinks).
3.16.1.4. Containerized laundry system capable of 200 pounds of laundry per hour.
3.16.1.5. MWR Facilities.
3.16.2. FP sets are containeri zed for transport via land, sea or air , military or civilian movement. A
550+ FP set is packaged in 103 TRICONS (Three ISO Containers).

Figure 3.5. Force Provider Containerized Latrine and Shower Facilities.

3.16.3. A 550+ module requires the following consumable resources:


3.16.3.1. 90kW of continual power that can be provided by organic FP generator capabilities.
3.16.3.2. Module generators require 3,137 gallons of JP8 fuel per day.
3.16.3.3. 150 gallons of standard MOGAS per day.
3.16.3.4. Production/distribution infrastructure for 25,000 gallons of potable water per day.
3.16.3.5. Storage and distribution capacity for 40,000 gallons of grey wastewater per day.
3.16.3.6. Storage/treatment and/or removal of 3,000 gallons of black wastewater per day.
3.16.3.7. Solid waste/refuse disposal.
3.16.4. Set-up for the 550+ module requires the following:
3.16.4.1. 10-15 acres of land (dependant upon terrain and security posture).
3.16.4.2. Site preparation, utilizing a combat heavy battalion, to produce a level, graded site (5%
of less grade), access roads, security berms, equipment yards and storage aprons require the fol-
lowing time:
AFPAM10-219V6 1 FEBRUARY 2006 55

3.16.4.2.1. Good Location. Expect fo rty eight (48) hours for site preparation, eight (8) days
for erection. A good location is defined as a site with flat terrain, limited ground cover/brush,
stable soil, existing roads and adequate site drainage.
3.16.4.2.2. Fair Location. Expect seventy-two (72) hours for site preparation, nine (9) days for
erection. A fair location is define d as a site with uneven terrai n, lots of underbrush and trees,
partially stable soils, some roads and moderate drainage work required.
3.16.4.2.3. Poor location. Expect ni nety-six (96) hours for site preparation, 10 days for erec-
tion. A poor location is defined as a site with rough, hilly terrain, dense underbrush and trees,
no roads, unstable soil and extensive grading required for site drainage.
3.16.5. The erection, maintenance and sustainment of the Force Provider set requires the following:
3.16.5.1. Appropriate elements of the corps or theater Army for finance, legal, personnel, admin-
istrative services, security and supplemental transportation support
3.16.5.2. A heavy combat e ngineer battalion (or Air Force, Navy or contract equivalent) for site
preparation.
3.16.5.3. An Engineer fire fighting team (or other service equivalent) and fire truck for structural
responses.
3.16.5.4. A utilities team for utilities operations.
3.16.5.5. A Quartermaster supply company for potable water.
3.16.5.6. A resident unit ministry team for religious support to attached units.
3.16.5.7. An Engineer prime power battalion for power generation support.

3.17. Navy Camp 750 Resources. Navy Camp 750 sets provide comp lete living facilities and expedi-
tionary combat support to 750 personnel. Details are listed in Table 3.6.
56 AFPAM10-219V6 1 FEBRUARY 2006

Table 3.6. Air Force, Army and Navy Basic Beddown Sets.
US Air Force US Army US Navy
BEAR 550 Housekeeping Set Force Provider Camp 750
(550 Person Set) (550 Person Set) (750 Person Set)
Stand alone warm-weather, personnel Assembled by task-organized Quarter Provides complete living facilities for
support package master Company 750 personnel (75 Officers, 613 enlisted,
62 person complement)
Setup varies depending on mission. Setup of standard module: 63 Setup (initial) within one day, followed
Typical PRIME BEEF complement of personnel take 120 hours to complete by additional improvements over 2-5
Lead and Follow team can achieve initial (varies depending on required site days.
operational capacity (IOC) within preparation, climate, lay down
72-hours. configuration and personnel
experience levels.

Billeting Subsystem Billeting Subsystem Billeting


Small Shelter System/TEMPER (48) TEMPER Tents (44) GP Medium Tents (62)
Environmental Control Units (72)

Admin Facility Subsystem Admin Facility Subsystem Admin Facilities


Small Shelter System (4) TEMPER Tents (6) GP Medium Tents (3)
GP Medium Tents (1) – Dispensary

Shower Subsystem Shower Subsystem Shower


Small Shelter System (2) TEMPER Tents (6) 12-head shower unit (6)
6 stalls w/2 shower heads ea/12 sinks (2) Portable shower/shave stands
M-80 Water Heater (1)

Laundry System Laundry System Laundry


Self-Help Laundry (optional) Portable Water System (1) Container ISU 90; washer/dryer (2)
Blackwater Containment (1) Modular GP Tent (2)
3,000 gallon storage tank and pump
(optional)

Latrine Latrine Latrine


Small Shelter System (2) Containerized Latrine 4-hole burnout head and Latrine (15)
Field Latrine w/6 seats & 2 sinks (2) 24 toilets, four urinals and eight sinks

Water Storage/Distribution System Water Storage/Distro System Water Storage/Distribution


550-person Water Distribution System 20K-gal collapsible tank (4) Waste Water Leach Field (3)
(1)
20K-gallon Water Bladder (2) Pressure tank assembly Sanitary Sewer, 300’ (7)
3K-gallon Water Tank(5) 400-gal tank with mobile chiller (4) Water Treatment Unit (2)
Expansion Tank Assembly (4) Water Storage (30K-gal) (2)
AFPAM10-219V6 1 FEBRUARY 2006 57

US Air Force US Army US Navy


BEAR 550 Housekeeping Set Force Provider Camp 750
(550 Person Set) (550 Person Set) (750 Person Set)
Hyperchlorination Unit (4) Water Distribution Line, Portable (2)
Food Service Food Service Food Service
550 Kitchen (SPEK) (1); TEMPER Tent (4) Bakery Plant Field Portable Tent (1)
Medium Shelter (Messing Facility) (1) 600-cf Refrigerator (2) GP Medium Tent – Garbage Storage (1)
Convection double-oven (2) Field Mess Galley (1)
Stand-mounted griddles (2)
30-gallon braising pan (2)
20-gallon steam kettle (2)
5-Pan Opening Steam Tables,
equipment and accessories (2)

Power Generation and Distribution Power Generation Power Generation


Generator, 30kw, MEP-805 (2) Tactical Quiet Generators (3) Power Plant, 2-60kW w/fuel tanks (1)
Generator, 60kW, MEP-806 (3) 500-gal collapsible tank w/liner Electrical Distribution Line (11)
Generator, 920kW MEP-PU-810A (2) Power Gen/Distro System (1) Power Distribution Center (18)
Primary Cable Skid (2)
Secondary Distribution Center (10)
Primary Switching Center (1)
Light Cart (2)

Bulk Fuel Storage/Distribution Bulk Fuel Storage/Distribution Refueling/Maintenance Facilities


Fuel bladder, 10,000-gal (2) 10K-gal collapsible tank (2) 3K gallon pillow tanks/filling station (2)
Berm liner assemblies (2) Maintenance Facilities (FSTFS) (1)
Fuel Spill Kit Storage/Supply (40’ x 100’) Tent (1)
500-gallon Drum (12)
Forward Area Refueling Equipment

Base Support/MWR Facilities MWR Facilities


Small Shelter (7) TEMPER Tents (3)

Mortuary Gray water Collection System


Small Shelter System (1)

Camo Nets/Pole Sets (2)


58 AFPAM10-219V6 1 FEBRUARY 2006

Chapter 4

BARE BASE UTILITIES DEVELOPMENT

4.1. Overview: The provision of water, electricity and removal and treatment of wastewater are critical
to the success of deployed military operations and AF CE mission requirements. This chapter will outline
some general utility issues. Greater detail on planning and installing de ployed utility systems is outlined
in AFPAM 10-219 Volume 5 and AFH 10-222, Volume 1.

4.2. Problems and Solutions. Recent bare base operations during OAF, OEF and OIF have highlighted
a number of utility limitations and challenges faced by deployed expeditionary engineering units. Theater
and unit level engineer planners and leadership can alleviate many of these problems by understanding the
cause and effects of these limitations.

Figure 4.1. Typical BEAR Utility Assets.

4.3. Potable Water. During Operations Southern and Northe rn Watch deployed USAF personnel and
base camp operations used bottled water as the primary source of potable water for personal consumption.
This evolution from production-based potable water supplies resulted from very liberal assistance-in-kind
(AIK) agreements between the Gulf States of Kuwait, Turkey and Saudi Arabia and Air Force personnel
operating within the theater. In these agreements, the host nation agreed to supply numerous consumable
resources to include potable water at no char ge to the US government. As personnel rotated through the
CENTAF AOR, bottled water became part of the understood deploya ble concept of operations. This
dependency upon bottled water caused a number of problems during OEF and OIF.
AFPAM10-219V6 1 FEBRUARY 2006 59

4.3.1. Water supply for the personnel at an OEF base in Afghanista n was provided by bottled water
flown in from centr al supply points in Qata r and Kuwait. Two months into the mission with over
1,000 personnel on the ground, the CE water shop was treating 15,000 gallons of city water per day .
The base utilized the treated water for laundry, dining, cleaning and hygiene requirements but would
not utilize it for personal consumption. The treated city water was rated safe by the base Bioenviron-
mental Engineer yet the base was still flying inroughly 10,000 bottles of water per day to support base
personnel. This consumed critical airflow for other mission assets since water was always prioritized
at the top position for intra-theater airlift.
4.3.2. While experiencing shortfalls in engineering heavy equipment, maintenance supplies and qual-
ity of life improvements, the base was losing approximately two C-130 flights per day to the mindset
that AF personnel must drink bottled water. Since this mindset was prevalent at over 17 expeditionary
bases in the AOR it had a significant effect on available airlift. Mission requirements eventually led to
many bases, such as Bagram, Kanda har, and Jacobabad to switch over to ROWPU treated water for
consumption when the base population surged beyond the AF’s ability to purchase, marshal and ship
enough bottled water to support base populations in remote areas.
4.3.3. Theater engineering planners need to be ready to advocate for the judicious use of bottled water
for initial operations and conversion to other sources as quickly as possible to increase overall mission
effectiveness.

4.4. Latrine/Sanitation Facilities. Poor sanitation and hygiene has significantly impacted military cam-
paigns throughout history. Figure 4.4 shows examples of latrine facilities used by Air Force expeditionary
forces during the OAF, OEF and OIF. Many of the austere and initial standard facilities were utilized for
extended periods while theater level planners attempted to source and transport Harvest Falcon or Force
Provider assets to alleviate conditions that did not meet minimum AF operating and hygiene standards.

Figure 4.2. Expeditionary Latrines during Contingency Operations.

4.4.1. In this day and age of modern technology, airlift and continued improvements in bare base asset
technologies, AF expeditionary engineers can still expect to be faced with a wide-range of sanitation
and latrine options while bedding down US and coalition troops. Numerous bare base beddowns dur-
ing OAF, OEF and OIF required USAF engineers to construct field expedient latrines, urine trenches,
latrines with burnout pots and other creative solutions to handle a very real sanitation problem.
60 AFPAM10-219V6 1 FEBRUARY 2006

4.4.1.1. Base engineers need to en sure that they focus on comple ting basic expedient latrine and
sanitation construction techniques during field exercises, and ensure personnel understand the
importance of planning for and marking the location of waste collection areas, slit trench locations
and other waste disposal areas to ensure future excavation does not expose these areas.
4.4.1.2. Shower Facilities . Although very important to hygiene, sanitation and quality of life,
shower facilities do not represent the critical requirement that latrines do. Recent operations have
shown that shower/shave kits will be bumped by hi gher priority assets for daily intra-theater air-
lift. Deploying AF engineers should plan for the requirement to construct a field expedient shower
facility with limited Class IV material available on the local market. If showers are a high priority
of your deploying team, the engineers need to pack for it.
4.4.2. Deployed units often experienced host nation (HN) infrastructure limitations when attempting
to expand base facilities for new missions and the associated infrastructure required: sewage treatment
and gray water disposal, solid waste management programs. These types of limitations are greatly
improved where the US and HN force have created a favorable political climate that creates opportu-
nities for service contracts, land leases and utility supplies. The CE planner must take local economy,
political relations and other outsid e influences into cons ideration when trying to solve the problem.
Normal deployment systems/methods for sewage treatment and waste disposal may not be possible
when an existing airfield is used for an AEF deployment. Surrounding populations and structures may
simply prevent some expansions and existing utility systems may already be overtaxed or incapable of
handling the additional load from a small military city dropping in on their doorstep.
4.4.3. Deployment planning may have to consider use of purchased or leased package treatments sys-
tems, construction of in termediate holding tanks to allow storage of s ewage and wastewater for
removal to a more remote treatment site and construction, repairs and upgrades to an existing utility
system before tying into it. AF CAP (or other contract augmentation programs) may be required to
provide resources and labor or RED HORSE may be required to construct large tanks or bury pipe-
lines.

4.5. Electrical Development: Development of electrical requiremen ts, upgrades and planning factors
can be found in AFPAM 10-219 Volume 5.

4.6. Conclusion. Air Force engineers, planners and deployed personnel need to address sanitation and
hygiene requirements early in the planning and beddown process. Silver Flag and CE training focuses on
the importance of this, yet we often still fall short in real world deployments. Historically during deploy-
ments, more personnel require medical assistance due to sanitation related illnesses than due to combat
injury.
AFPAM10-219V6 1 FEBRUARY 2006 61

Chapter 5

SECURITY AND FORCE PROTECTION DEVELOPMENT

5.1. Overview. Security and protection of Air Force assets in an expeditionary lo cation is of critical
importance to all organizations on the base. Although the Security Forces Commander operates the base
Force Protection plan, it cannot be a ccomplished without active participation of CE planners and crafts-
men. AEF planners should have mo re information/intelligence on lo cation threats when planning for
deployments to austere locations when compared to s tandard bare bases. Austere, forward locations are
usually much closer to battle areas or areas of heightened terrorist threat. Units that deploy will have much
more to consider when they arrive on station and some of their initial actions may include verifying the
threat situation rather than starting site layout. Consider the following subjects when you deploy to higher
threat areas.

Figure 5.1. Security Forces Providing Perimeter Security.

5.2. Force Protection Planning. For civil engineers, force protection roles and responsibilities have var-
ied greatly since 1950.
5.2.1. During the Cold War, the Air Force CONOPS was to operate from established main operating
bases with hardened shelters and facilities, as we ll as numerous buildings with chemical overprotec-
tion. Army personnel surrounded these bases for ground defense and air defense with Patriot batteries.
Depending on the theater, the threat ranged from attack by enemy special operations forces and sabo-
teurs, larges scale air and ground attac ks and conventional and chemical missile and rocket a ttacks.
Security force protection ranged from fortified bunkers, robust perimeter security and alarmed facility
and base access.
5.2.2. During Operation Desert Storm the Air Force was able to activate some bases with Royal Saudi
Air Force (RSAF) hardened facilities and chemi cal protection. The majority of Air Force operations
were conducted from bare base, expeditionary airfields with Ha rvest Falcon systems or temporary
shelters, which were not chemically protected. Ar my forces and resources were still utilized to pro-
vide ground defense and anti-aircraft/anti-missile air defenses for AF bases. Rudimentary facility
hardening was accomplished with sa ndbags, concrete barriers and various constructed revetments.
Due to air and naval superiority, the major threat became chemical and biological attacks by missiles
and terrorists, as well as conventional attacks by terrorists. Enemy special force units and teams were
62 AFPAM10-219V6 1 FEBRUARY 2006

still a threat, but they had limited long-range capability to attack most bare bases. AF Security Forces
personnel created force protecti on plans based on multiple fighting positions, roving patrols and
mobile alarm systems. Chemical, biological and radiological detection was still relatively rudimentary
utilizing passive monitoring systems (M-8/M-9 tape ) and often fell to Re adiness teams that were
ill-equipped, lacked the adequate situation intelligence and resource s to adequately protect in what
could have been a significantly contaminated environment.

Figure 5.2. PSAB Airbase (Before and After Buildup).

5.2.3. Recent AEF deployments have relied on Harvest Eagle and Harvest Falcon assets, along with
Army Force Provider assets. Revetments have ranged from expedient sandbag to Concertainer sys-
tems. Weapon threats tend to be grenades, mortars, mines, rockets and missiles; shoulder fired
anti-aircraft missiles and small ca nnons. While the threat is usually from explosives, there is the
chance that chemical or biological agents could be used in war heads or even in ground dispersal
devices. Force protection is a major concern when there is a high probability of terrorist, saboteur, or
insurgent attacks, especially when the planned b are base airfield is at an existing commercial airport
near a town. When airfields ar e surrounded by populated areas, it fo rces in- and outbound aircraft to
fly over towns and there is a greater threat of a successful shoot down of coalition aircraft.
5.2.3.1. Force protection plans for expeditionary airbases (EAB) of this type should consider the
use of defensive fighting positions, roving patrols, remote area detectio n alarms and other mea-
sures to secure the flightline and the surrounding area to the greatest extent possible.
5.2.3.2. Large frame aircraft used for troop rotation and resupply are easier and more inviting tar-
gets to enemy forces and their protection places an even greater strain on our security forces per-
sonnel. Fighting positions must be used along with portable alarm systems and detection fields.
Protective measures and patrols must be extended as far past the runway clear zones as possible to
prevent targeting of the slower, heavier aircraft on approach and take off.
AFPAM10-219V6 1 FEBRUARY 2006 63

Figure 5.3. Expeditionary Airbase in Afghanistan.

5.2.4. Civil Engineer and Security Force pla nners must coordinate fo rce protection requirements,
help establish protection zones, reinforce fighting positions, clear or establ ish obstacles and harden
the perimeter in some locations to ensure maximum utilization of resources. Beddown and planning
should take into account the force protection needs at their inception to prevent problems during exe-
cution. It may be necessary to construct berms and revetments arou nd critical assets and to bury or
cover utilities.
5.2.5. AEF deployments for OEF e xperienced planned and unplanned growth, which required addi-
tional land and resources. Every change that increases the base footprint usually requires changes and
extensions to force protection measures. Some areas with exposed fuel transfer pipelines may have to
be buried or placed between berms or shallow trench es to provide additional protection. The same
holds true for utility lines. Whil e electrical cables should normally be buried, if host nations prohibit
burying or the ground surface is solid rock, then you should plan to berm and cover or bring in soil and
cover these utilities (except at road crossings where these utilities should always be buried).
5.2.6. When there is a higher risk of terrorist attacks or sabotage , protection of water transfer lines
becomes a concern. In the past, a major concern related to chemical attacks has been the introduction
of agents into a municipa l water supply used by de ployed forces. However, there is also a threat to
water produced by ROWPUs and stored in tanks. Du e to the ready availability of waterline hot-tap-
ping tools, PVC or soft/ductile water transfer pipes can be tapped under pressure within minutes. Then
a chemical poison or bi ological agent could be introduced with a hand pump. Provide planning
assumptions for protective measures such as roving patrols and/or burying the lines, especially for any
areas that are not readily observable.
5.2.7. To meet the threat of an airborne chemical attack, planning should also consider whether addi-
tional areas of the base will have to be cleared to create saf e areas for contamination control ar eas
(CCA). Planners should consider possible approach/departure routes for the base and CCAs based on
the topography and prevailing winds. Planners should understand that open areas, which can be used
as potential CCAs, may f urther limit the available la nd on a base. If this is the case, notify theater
64 AFPAM10-219V6 1 FEBRUARY 2006

planners that contingency real estate support teams (CREST) or theater contracting officers may have
to take action to lease additional land prior to deployment.

5.3. Classification of Threats. CE planners need to be able to characterize and define the various threats
faced in an expeditionary location to greater partner with the force protection planning group at both the
theater and base level. The Air Force has developed amatrix to define the varying levels and threats posed
to an expeditionary airbase (Table 5.1. and Table 5.2.). Greater detail on these and other potential NBCC
threats may be found in AFMAN 10-2602 Chapter 2, Sections 2-4 through 2-12.

Table 5.1. EAF Airbase Threat Matrix.


Low Intensity Medium Intensity High Intensity
EAF Threat Level I EAF Threat Level II EAF Threat Level III
Ground Irregular forces Military Special Ops Regular Infantry Assault
Terrorists Sabotage
Penetrating threats Standoff/Long range
munitions threat
Air Conventional Airdropped Enemy offensive Theater Ballistic Missile
munitions counter-air operations (e.g. SCUDs)
Chemical/ Contamination of food & Localized Chemical Base wide CW
Biological water Warfare (CW) agent contamination
contamination
Information, Physical and virtual attack on Disruption of reach back Radio Frequency Weapons
Command & IT systems, networks and capability and computer Hack of the Network
Control connectivity connectivity (SIPR and Disabling of Networks
NIPR)

Table 5.2. Airbase Defense Threat Levels.


Threat
Example Response
Level
Agents, Saboteurs, sympathizers, terrorists Airbase, wing and unit self-defense and force
I
protection measures
Small tactical units, unconventional Airbase, wing and unit self-defense force
II warfare forces, guerilla groups protection measures with supporting fire from
larger combat units
Large conventional tactical forces, to Requires support of tactical size combat forces
III include airborne, heliborne and major air dependent upon threat
operations

5.3.1. Low-intensity ground threats include utilization of gueri lla style tactics by conventional or
non-conventional military forces (terrorists, insurgents or military) to pene trate base perimeters and
disrupt operations or cause loss of AF personnel or resources. The best defense against a low intensity
ground threat is utilization of a large and mobile security forces presence to provide monitoring of the
base perimeter and controlling base access. Through a number of AF Battle Lab initiatives, the AF has
AFPAM10-219V6 1 FEBRUARY 2006 65

developed a number of electronic upgrades to equip the roving patr ols and augment perimeter secu-
rity. These initiatives include, bu t are not limited to, th e Tactical Automated Surveillance System,
night vision technology, perimeter fence movement detectors, perimeter cameras with central control
and monitoring, and lighter armored vehicles and body armor. The theater and base SF Force Protec-
tion Cell will be able to provide additional information to the CE planner regarding equipment in use
and required CE support of construction and infrastructure to support FP initiatives.

Figure 5.4. Infrared Sensor Security System Installed on Base Perimeter.

5.3.2. Medium-intensity ground threat includes the utilization of enemy Speci al Operations Forces
(SOF), paramilitary, specialized terrorist organizations that attempt base penetrations and operations
disruption through direct attack or standoff weaponry (mortars, rocket s, rocket propelled grenades)
launched from outside the base perimeter. This type of threat is very difficult to defend against since
the primary methodology is to att ack from beyond the perimeter fen ce where US forces may or may
not have authority to engage. Current procedures require the base to work closely with host nation
security and military agencies to provide beyond-the-fence surveillance and around the base (1,200
foot desired) standoff, clear zone to minimize the impact of st andoff weapons. CE personnel may be
called upon to erect counter-mobility berms, install concrete barriers and assist with the construction
of over watch positions and towers. The AF Force Protection Battle Lab is looking into the potential
of fielding other assets to enable the SF personnel to better counter this threat. Contact you base force
protection cell for information.
66 AFPAM10-219V6 1 FEBRUARY 2006

Figure 5.5. Surveillance from Over Watch Tower.

5.3.3. High-intensity ground threats are large scale, organized terrorist or enemy military forces (nor-
mally brigade size or larger) attacks on an airbase. While low and medium intensity ground threats are
the responsibility of the assigned base personnel, high-intensity threats will normally require the
deployment of additional forces to counter the threat. Baghdad International Airport during Operation
Iraqi Freedom was a high-intensity threat area that evolved into a medium thre at area. The AF was
collocated with an Army brigade to provide greater security and alleviate the threat.
5.3.4. Low-intensity air threats are found in slow-moving unmanned aerial vehicles (UAV) or suicide
remote controlled aerial bombs (small remote controlled airplanes, rockets etc). When these are paired
with GPS guidance systems, they become especially lethal. Th ese UAV delivery systems can be
armed with a series of sub-muni tions, cluster bombs and conventi onal weapons, chemical/biological
systems that pose a serious threat to successful mission and airbase operations. Base planners should
strive to increase intelligence collection and coordination, SF interaction with air traffic control (host
nation and coalition). Base CE and SF need to have an adequate bunker and emergency alarm plan to
counter the potential impact of this type of weaponry.
5.3.5. Medium-intensity air threat covers the realm of standard military or terrorist aerial bombing
operations. In this type of envir onment, base CE and SF need to have an adequate bunker and emer-
gency alarm plan to counter the potential impact of this type of attack. Current AF doctrine requires
the AF to establish and maintain theater air superiority to counter this level of threat.
5.3.6. High-intensity air threat en compasses theater ballistic miss iles (SCUDS, intermediate range
ballistic missiles, etc.). The majority of enemies who will possess this technology will be severely
hampered by poor guidance and limited stocks. Th e base should be prepar ed to defend against and
survive lucky hits of conventional or NBC warheads. The base CE a nd SF need to have an adequate
bunker and emergency reaction plan to counter the potential impact of this threat.
5.3.7. Low-intensity NBC threats encompass the potential of chemical or biological contamination of
base water and food suppli es in an effort to sicken or kill the base population and disrupt mission
operation. Current AF operations utilize vaccinations, antibiotics, preventative health maintenance to
counter the effects of contamination. Bases should maintain an emergency supply of bottled water and
meals-ready-to-eat (MREs) as a backup in the event of contamination. Base food and water stocks can
AFPAM10-219V6 1 FEBRUARY 2006 67

be resupplied within a matter of days so stockpiles do not need to beextensive. Base CE water produc-
tion specialists and Biomedical Engineering personnel are responsible for continual testing of the base
water source.
5.3.8. Medium-intensity NBC threats are defined as the localized release of NBC warfare agents with
the intent to immobilize, destroy or degrade US operations. Localized release means the attack con-
taminates parts of a base but falls short of af fecting the entire airbase, resulting in the current
split-mission oriented personal protection (MOPP) concept of ope rations at AF bases worldwide. As
the primary resource for readiness reporting the CE planners must relay heavily on the expertise and
experience found in the CE Readin ess Flights to alleviate this th reat. Intelligence, remote sensors,
emergency response planning and adequate personnel bunkers will assist in minimizing the impact of
this threat.
5.3.9. High-intensity NBC threats ar e defined as an att ack that causes base wi de contamination by
NBC agents. As the primary resource for readines s reporting the CE planners must relay heavily on
the expertise and experience found in the CE Readin ess Flights to alleviate this threat. I ntelligence,
remote sensors, emergency response planning and adequate personnel bunkers will assist in minimiz-
ing the impact of this threat.
5.3.10. Low-intensity command an d control/intelligence, surveillance and reconnaissance (C2ISR)
threats are physical attacks on information, C2 and communications systems infrastructure. To defend
against this, CE, Communications and SF planners need to ensure that key nodes, distribution centers
and relays are installed in the most secure method available. Host nation coordination may be required
for underground installation.
5.3.11. Medium-intensity C2ISR threats are defined as attacks to deny expeditionary forces access to
reach back data and planning capabilities, connectivity to higher headquarters, intelligence organiza-
tions, surveillance, and hacking of US government computer systems by insurgent forces.
5.3.12. High-intensity C2ISR threats are defined as the disruption or destruction of C2ISR systems
through the utilization of electrical or radio waves.

5.4. Security Forces Base Defense CONOPS. Engineers need to understand the defensive CONOPS of
the AF Security Forces to better support physical security requirements. The primary item for AF CE
planners to understand is that AF SF CONOPS dictate that the AF will be responsible for the tactical area
of responsibility (TAOR) and perimeter fence in, while security of the area outside of the base will fall to
other agencies. The following postures are included in AFPD 31-3, Air Base Defense.
5.4.1. During periods of low or mid-level threats (Levels I, II and III), airbase defense forces are pri-
marily responsible for protecting the force from attackers attempting close attack by penetrating
forces and from st andoff attack within the TAOR. The TAOR is the area, which the defense force
commander can control through organic heavy/light weapons fire. The Air Force component will
ensure adequate support is available from the othe r joint components, host nation, coalition, allied
forces, and civilian authorities to meet surveillance and denial needs, such as for the stand-of f threat
beyond the capabilities of the Air Force.
5.4.2. During periods of high-level threat (Level III), airbase defense forces rely on a tactical combat
force (TCF) comprised of other US service components, allied, co alition, or host-nation forces to
ensure the survivability of airbases.
68 AFPAM10-219V6 1 FEBRUARY 2006

5.4.3. Outside the airbase TAOR, US Army, USMC, host nation m ilitary forces, or civilian law
enforcement agencies will have responsibility for security requirements.
5.4.4. US, host-nation, coalition, and civilian law enforcement/security forces will be incorporated
into airbase defense planning and operations to the fullest extent possible.

5.5. Force Protection and Safety. Antiterrorism force protection and p hysical security in the expedi-
tionary environment present unique challenges to planners, engineers and security forces. The threat type,
severity, and desired level of protection are the primary considerations when selecting AT/FP and physical
security measures. These considerations will be used to identify vul nerabilities, reduction measures, and
the siting of facilities. In the expeditionary envi ronment, important security planning factors include:
availability of existing facilities, types of struct ures, existing natural or man-made features, types and
quantity of indigenous construction materials, available real estate, and othe r base infrastructure.
Pre-existing buildings will be renovated to meet DOD, AF , and CFACC force protection and security
standards. These standards will provide guidance to design strategies for mitigating the effects of specific
aggressor tactics, defined levels of protection, and effects on building costs of applying those measures.
Some specific force protection measures are as follows.
5.5.1. Perimeter. Chain link or concertina fences will be employed on the camp perimeter. Whenever
possible, berms and sniper screens will be used to bloc k direct visual access from outside the base
perimeter. Lighted gravel perimete r roads should be installed insi de the perimeter berm. Surveys to
assess alternate access routes should be completed with focus on culverts underneath the perimeter
fence. Culverts should be caged, or otherwise blocked to prevent personnel entry.
5.5.2. Gates. Main gates with covered inspection ar eas are authorized if required by the operational
situation. Barriers will be built to enable the blockage of large vehicles. Gate Guard Shacks should be
equipped with lighting and environmental control units. Tilt bar and swing gates are authorized. Place
weapons clearing barrels inside the gates.
5.5.3. Primary Gathering Facilities. Construct barriers to minimiz e car bomb threats. Use HESCO
bastions, Jersey barriers, or other methods capable of stopping a car or truck. Fence the air condition-
ing intakes to reduce the terrorist threat of introducing gas into duct systems.
5.5.4. Water Sources. Water plants, wells, storage tanks, and bladders will be fenced if a threat to
these facilities exists.

5.6. Minimum Force Protection Design Standards. The most cost-effective solution for mitigating the
effects of an attack is generally to provide distance between facilities and any explosions that might occur.
Unified Facilities Criteria 4-010-01 provides planning standards for expeditionary and temporary struc-
tures, including minimum antiterrorism standards for expeditionary and temporary structures. As is the
case for fixed facilities, the type and severity of the threat along with the desired level of protection will
be the primary considerations in the selection of the anti-terrorism force protection and physical security
measures. These considerations will affect decisions on various issues such as the types of vulnerability
reduction measures and the physical layout of facilities, facility groups and infrastructure. Important fac-
tors in planning security measures in the expeditionary environment include the availability of existing
facilities, the type of structures in which people live and work, existing natura l or man-made features,
type and quantity of indigenous construction materials, available real estate an d layout of utilities and
other base infrastructure. The stan dards in UFC 4-010-01 fo r minimum standoff distances apply to all
AFPAM10-219V6 1 FEBRUARY 2006 69

new and existing expeditionary and temporary structures and is more in depth and has precedence over
guidance outlined in this pamphlet.
5.6.1. Facility Access.
5.6.1.1. Select sites away from public roads or other uncontrolled areas.
5.6.1.2. Maximize use of natural or man-made features to obscu re vision from potential threat
vantage points.
5.6.1.3. Limit vehicle approach speeds.
5.6.1.4. Minimize vehicle access points.
5.6.1.5. Provide an entry control point with a well defined holding area for unauthorized vehicles
and vehicles being searched. The holding area should be outside of prescribed minimum standoff
distance.
5.6.1.6. Separate functi onal areas requiring frequent vehicle access (e.g., ki tchens, industrial
areas, retail areas, refuse collection points) from billeting areas.
5.6.2. Site Characteristics.
5.6.2.1. Maintain good housekeeping by keeping areas within 30 feet of shelters or structures free
of items other than those items that are part of the infrastructure.
5.6.2.2. When possible, position exterior doors so they cannot be easily targeted from the installa-
tion perimeter or uncontrolled vantage points.
5.6.3. Facility Standoff/Separation. Standoff distances are defined as the distance maintained between
a building or portion thereof and the potential location for an explosive detonation. Standoff distances
are based on the assumption that a controlled perimeter will create an opportunity to detect bombs and
explosives before they enter the controlled perimeter. To make them effective planners must clearly
delineate the installation perimeter. This includes fencing, concertina wire, barricades, counter-mobil-
ity barriers, ditches, police tape, or warning signs. The following table and figure highlight and illus-
trate the minimum antiterrorism standards for expeditionary and temporary structures in Annex D of
UFC 4-010-01.
70 AFPAM10-219V6 1 FEBRUARY 2006

Table 5.3. Minimum Standoff Distances & Separation for Exped. & Temp. Structures.
Standoff Distance or Separation Requirements
Applicable
Location Structure Category Applicable level Fabric Covered/ Other Exped. &
Explosive
of Metal frame Temporary
Weight
Protection Structures (1) Structures (1)(2)
(TNT) (3)
Controlled Billeting Low 31 m (102 ft) 71m (233 ft) I
perimeter or
Primary Gathering Low 31 m (102 ft) 71m (233 ft) I
parking roadways
Structure
without a
controlled Very Low 24 m (79 ft) 47 m (154 ft) II
Inhabited Structure
perimeter

Parking and Billeting Low 14 m (46 ft) 32 m (105 ft) II


roadways within a Primary Gathering Low 14 m (46 ft) 32 m (105 ft) II
controlled Structure
perimeter
Inhabited Structure Very Low 10 m (33 ft) 23 m (105 ft) II
Billeting Low 14 m (46 ft) 32 m (105 ft) II
Trash Primary Gathering Low 14 m (46 ft) 32 m (105 ft) II
Containers Structure
Inhabited Structure Very Low 10 m (33 ft) 23 m (75 ft) II
Separation between Low 18 m (59 ft) 18 m (59 ft) III(5)
Structure Groups
Structure Separation between Low 9 m (30 ft) 9 m (30 ft) III(5)
Separation (4) Structure Rows
Separation between Very Low 3.5 m (12 ft) 3.5 m (12 ft) III(5)
Structures in a Row

NOTES:
1. See UFC 4-010-01 for a complete description of these structure types.
2. For container structures refer to UFC 4-010-02 Appendix B.
3. Refer to UFC 4-010-02, for the specific explosive weights (kp/pounds of TNT) associated with designations – I, II, III.
UFC 4-010-02 is For Official Use Only (FOUO).
4. Applies to billeting and primary gathering structures only. No minimum separation distance for other inhabited struc-
tures.
5. Explosive for building separation is defined as an indirect fire (mortar) round at a standoff distance of half the separation
distance.
AFPAM10-219V6 1 FEBRUARY 2006 71

Figure 5.6. Standoff Distances and Separation for Expeditionary and Temporary Facilities.

5.7. Threat Specific Standards. In addition to the minimum standards described above, the DoD Secu-
rity Engineering Manual provides guidance for incorporating additional measures to mitigate specific
threats. That guidance includes design strategies for mitigating the effects of specific aggressor tactics to
defined levels of protection and the effect on building cost of applying those measures.
72 AFPAM10-219V6 1 FEBRUARY 2006

5.7.1. Power Generation and Distribution. Wood or chain link fence will be installed around all gen-
erator, transformer and consolidated generator st ation locations. Enclosing generators in wooden
buildings is not authorized.
5.7.2. Perimeter. Fences, either chain link or con certina, are authorized ar ound the camp perimeter.
Berms and sniper screens are authorized to bloc k vision. Perimeter lights are authorized. A gravel
perimeter road is authorized inside the berm. Culverts underneath the perimeter fence will be caged to
prevent persons from crawling through.
5.7.3. Gates. Covered inspection areas on the main gates are author ized as required by weather con-
ditions. Gates will have lighted, heated, guard shacks. Tilt bar and swing gates are authorized. Locate
clearing barrels inside the gates.
5.7.4. Clearing Barrels. Clearing barr els will be installed at all access control points and outside the
entrances to arms and ammunition storage areas, medical and dinning facilities.
5.7.5. Walkways and decks. Pressure treated, rot-resistant lumber is the standard. If not available, or
cost prohibitive, consider using composite decking material for co nstructing walkways and decks.
Untreated wood can be used if primed and painted. Paint any wo oden walkways with sa nd paint or
other non-slip materials to reduce the chance of slipping, particularly in climates with snow and ice or
extended rainy periods. Provide lighting wherever steps cannot be seen at night.
5.7.6. Buried utilities. The BCE will maintain a database of all buried utilities. No job will be closed
out until new underground utilities have been pr operly documented. No work will commence on a
project until a dig permit has been obtained. Digging permits should also be coordinated for commu-
nication line clearance. Buried utilities will have caution tape at least one foot above the utility lines.
Buried electrical lines will have signs posted at every turn in the line and wherever else needed by the
terrain.
5.7.7. Bunkers. Only bunker designs approved by th e Corps of Engineers, Engineer Research and
Development Center will be constr ucted. Sand bag bunk ers will have the sand bags protected from
solar radiation and the wooden core protected from rot. Design factor is 110% of camp population for
bunkers and fighting positions. No rmal planning factor is that 50% of the population will be on the
perimeter, with 50 % in bunkers.
5.7.8. Guard Towers. Guard towers will be placed so every tower is visible to the immediate towers
on the right and left so there is no dead space on the perimeter. Towers will have heat and light. Tow-
ers will be hardened against small arms and mortar fire.
5.7.9. Constructed fighting positions. Overhead cover design on fighting positions must be approved
by the task force engineer. Fighting positions must be inspected regularly for deterioration. A digging
permit must be coordinated before any construction begins.
5.7.10. Theaters and similar multipurpose facilities. These facilities will have a barrier to minimize a
car bomb threat. Barrier can be a berm, HESCO bastions, Jersey barriers, or other method capable of
stopping a car or truck. Air induction units and other vents will be screened or fenced to reduce terror-
ist threat of gas introduced into the duct systems.
5.7.11. Water Plant. Water plants, wells, storage tanks and bladders will be fenced.

5.8. Siren Warning System (Giant Voice). Force Protection planning should include the installation of
a dual tone warning system that supports voice and tone to alert personnel to local hazards and incidents.
AFPAM10-219V6 1 FEBRUARY 2006 73

The system should be sited to provide clear audible coverage of main work sites and billeting cantonment
areas.

5.9. Mines, Improvised Explosive Devices and Unexploded Ordnance. The strength and capabilities
of the US military make it an unstoppable force in the face of conventional symmetrical warfare. To bal-
ance the battlefield, the enemy has resorted to asymmetrical warfare tactics of small guerilla units armed
with unconventional weaponry. Worldwide attacks over the last decade highlight this: suicide bombers in
market squares, roadside daisy chain explosives along the supply routes in Iraq, booby-trapped facilities
in Afghanistan, and airliners used as bombs during the September 1 1th attacks against New York and
Washington DC. The military planner and bare base beddown engineer mu st be constantly aware of the
threat of passive and active unconventional weapons. During the six months after cessation of major mil-
itary actions during OIF, more US military personnel were killed by unconventional weapons and guerilla
insurgents than were lost during direct combat actions against the Iraqi Army.
5.9.1. A common threat at most expeditionary beddown and airfield sites is the presence of anti-per-
sonnel explosive devices dispersed through enem y forces, insurgent groups or expended coalition
unexploded ordnance. This results in the common EOD mantra to deployed personnel to ST AY ON
THE CONRETE. EOD personnel are e ssential for the clearing, de-min ing and safing of a potential
beddown area. This is particularly critical during the planning and open the base module. If EOD has
not cleared the area, it doesn’t matter how much equipment you have on site, you cannot initiate bed-
down erection. Theater level CE planners must advocate at the planning meetings to ensure that EOD
is present on the survey ADVON team and if require d in the initial cadre of personnel arriving to the
site. The new Airborne Engineer CONOPS incorporates this requirement into its SOP for airfield sur-
veys. During OAF, coalition EOD personnel provided a myriad of sa fing and clearing operations. A
matrix of available methodologies and their advantages and disadvantages is found in Table 5.4.. This
is to serve only as a general information sheet fo r engineer planners. All planning efforts should
include the theater or deploying EOD commander or planner. Air Force engineers must remember that
EOD actions may be completed by other than Air Force personnel.
74 AFPAM10-219V6 1 FEBRUARY 2006

Table 5.4. Neutralization and Detection Methods for UXOs.


*Advantages and Disadvantages of Neutralization and Detection Methods
Neutralization Method Advantages Disadvantages
- Leaves uncleared berms
- Has a rapid clearance rate
- Not C-120 transportable
- Clears AP mines
- Causes severe percussion if AT mine
MCAP Dozer - Clears subsurface, but has not depth
detonates
- Mechanically reliable
- Makes ground susceptible to becoming a
- Clears rough terrain
quagmire
- Slower than the MCAP dozer
- C-130 transportable
- Cause a large dust cloud
Medium Flails - Offer depth control
- Make ground susceptible to becoming a
Ardvark and Hydrema - Clear at a relatively rapid rate
quagmire
- Likely to withstand AT blasts
- Less effective in rough terrain
- Effective for mine extraction and MOUT
- Allow minimal subsurface clearance
Miniflail areas
- Has a slow clearance rate
- Highly transportable
- Has a high probability of neutralization - Not effective against buried munitions
Explosive (if munition is seen) - Requires direct soldier exposure
- Effective for point targets - Not effective for large areas
- Requires special training
- Requires no direct soldier exposure
SMUD - Requires special equipment
- Effective for point targets
- Requires pinpoint detection
Detection Method Advantages Disadvantages
- Not effective for buried munitions
- Easiest method
Visual - Only as good as the observer’s visual acuity
- Can scan large areas
- Requires direct soldier exposure
- Not effective with metal clutter or ferrous soil
- Highly effective for high-metal mines
Metal Detector - Relatively slow
and UXO
- Requires direct soldier exposure
- Relatively slow
- Has a high success rate under ideal
Mine Detection Dog - Affected by environmental conditions
conditions
- Requires intensive training
* NOTE: The advantages and disadvantages shown above are based on the subjective opinion of the author and are
intended to give the reader a comparative analysis of the various clearance methods used in Afghanistan. This is not
intended to be a complete objective analysis.

5.9.2. During OAF, Army Combat Engineering Battalions had to complete extensive explosive clear-
ing operations prior to beddown delaying the es tablishment of stationary beddown operations. At
many locations in Yugoslavia and the Balkans, the Army is still clearing portions of the airfields that
they have been operating on for over 8 years. Smal l insurgent countries have seen a proliferation of
counter-personnel mining operations in an attempt to quell civilian uprisings and keep dictatorial gov-
ernments in power. In every area of the Middle East, Far East, African and Balkans theater of opera-
tions, military personnel will be faced with the task of identifying the counter-personnel mine threat,
presence and remediation of the th reat. Conservative estimates identify over one billion counter-per-
sonnel mines currently deployed throughout the world. Most in areas where location maps no longer
exist.
AFPAM10-219V6 1 FEBRUARY 2006 75

5.9.3. The construction of an improvised explosive device (IED) is simple: modify military ordnance,
initiator/fuse, some plastic explosives and an i ndividual to trigger the explosion. This simplicity
makes it very difficult to eliminate the IED threat.

Figure 5.7. Explosive Potential and Evacuation Distances.


76 AFPAM10-219V6 1 FEBRUARY 2006

1 – Based on the maximum amount of material that could reasonably fit into a container or vehicle. Variations possible.
2 – Governed by the ability of an unreinforced building to withstand severe damage or collapse.
3 – Governed by greater of fragment throw distance or glass breakage/falling glass hazard distance. Distances can be reduced
for personnel wearing ballistic protection. Note that pipe bomb, suicide belt/vest, and briefcase/suitcase bomb are assumed to
have a fragmentation characteristic that requires greater standoff distances than equal amounts of explosives in a vehicle.
4 – Assuming efficient mixing of the flammable gas with ambient air.
5 – Determined by U.S. firefighting practices wherein safe distances are approximately 4 times the flame height. Note that an
LPG tank filled with high explosives would require a significantly greater standoff distance than if it were filled with LPG.
AFPAM10-219V6 1 FEBRUARY 2006 77

Chapter 6

FACILITIES UPGRADE, SUSTAINMENT AND MAINTENANCE

6.1. Overview. This chapter discusses transitioning from s hort-term use temporary expeditionary facili-
ties to semi-permanent and permane nt facilities. It also discusses various funding and programming
requirements for beddown construction.

6.2. Transition to Temporary Standard, Semi-Permanent and Permanent Facilities. Typically the
basis for transition to temporary standard facilities has relied on the Joint Publication 4-04 requirement
that temporary standard fa cilities will be adopted when the deployment is expected to last more than 6
months, then temporary standards will increase usage up to 24 months . The realities of overseas deploy-
ment and the support of theaters and areas of responsibility have required basing to exist for more than 24
months, but usually less than 5 years to be considered as a standard for transition to even more permanent
facilities. When a base will become a main base for operations and logistics support in a theater, the like-
lihood is that diplomatic and military agreements will require semi-permanent and permanent facilities to
be constructed. Sometimes this is with conveyance to the host nation as a grant for basing, while in other
cases the facilities may be conveyed to the host nation with the stipulation that the facilities may be used
again in case of contingencies. When this is the cas e, additional agreements may be required to establish
pre-positioning sites for deployment resources. Depending on the reason for the conflict, the scope of the
work and the length of use, construction may be through O&M or MILCON funding.

Figure 6.1. Prince Sultan Airbase – Enduring Presence Construction Standard.


78 AFPAM10-219V6 1 FEBRUARY 2006

6.3. Normal Transition to Temporary Facilities. Construction and quality of life upgrades should be
programmed and planned as soon as resources and mission expectations allow. If initial beddown mis-
sions are planned for long term US presence than CE planners should initiate and advocate for semi-per-
manent construction standards as soon as resources allow. This will free up critical BEAR assets for
utilization in short term expeditionary, FOB and FOL bases. During the maturation of the mission, bases
may be identified for longer operational requirement s therefore requiring the upgrade of the base con-
struction standards.

6.4. Funding Transition and Beddown Construction. Engineering planners must be aware of funding
and programming requirements for all levels of expe ditionary and contingency beddown and construc-
tion. Attempts to circumvent thes e programming and funding requirement s usually results in significant
delays and paperwork in gaining the appropriate approvals. Although many of the authorities require up
to 30 days of approval and processing, it is quicker than trying to go around the rules. Further details and
decision flow charts for deciding which authorities are appropriate for your requirements can be found in
JP 4-04, Appendix F, pages F-3 through F-5.
6.4.1. Operation and Maintenance (O&M) Funding: The Air Force is authorized to use annual O&M
funds for construction projects less than $750K. This is a peacetime provision that is applicable during
contingencies and emergencies. During combat or designated contingency operations, O&M may be
used under certain circumstances to fund construction projects exceeding these thresholds. The theater
or wing legal office must be consulted prior toexpending O&M funding for contingency construction.
6.4.2. Title 10, USC, Emergency and Contingency Construction: Title 10 USC contains numerous
broad authorities to fund contingency construction.
6.4.3. Section 2803 Emergency Military Construction Authority: Section 2803 authorizes AF leader-
ship to use up to $30M per year of unobligated military construction (MILCON) for projects that can-
not wait for the normal MILCON program submission and approval process. Section 2803 projects
require a 21-day Congressional notification period for members to question the applicability of utiliz-
ing current year funds for the requested project. Planners need to be aware that 2803 funds are current
year MILCON funds currently authorized for another project. If you utilize 2803 funds for a project,
the AF loses a similar project elsewhere to fund the requirement.
6.4.4. Section 2804 Contingency Construction Authority: Section 2804 funding authority allows the
Secretary of Defense to designate a specific military construction program line item amount for con-
tingency construction projects that cannot wait for normal MILCON submission and authorization.
Section 2804 funding normally is less than $10M per year and requires a 21-day Congressional noti-
fication period.
6.4.5. Section 2805 Unspecified Minor Construction: Section 2805 authorizes the AF (and other ser-
vices) a military construction program line item for unspecified minor construction requirements.
Project funded under this authority cannot ex ceed $1.5M. Projects exceeding $500K require a
21-Congressional Notification period.
6.4.5.1. CE construction planners should coordina te with USAF/ILEC to request utilization of
these funds.
6.4.5.2. Exercise related construction (ERC) pr ojects complement and enhance the Chairman
Joint Chief of Staff (CJCS) Joint Training Plan Exercise Program. Projects will be developed to
enhance the effectiveness of exercise activities, reduce overall exercise costs, enhance safety and
AFPAM10-219V6 1 FEBRUARY 2006 79

improve training of engineer forces. ERC may be accomplished by US troops, combined US-host
nation engineer forces, or by contractor (accomplishment by contractor is the least preferred
option). Where an ERC project is planned in a country eligible fo r assistance, an HCA construc-
tion project should be planned in conjunction with the ERC project.
6.4.5.2.1. ERC is defined as an unspecified minor co nstruction project, outside CONUS, in
support of an in-progress or planned CJ CS exercise that results in a faci lity, or facilities that
remain, in any part after the end of the exercise.
6.4.5.2.2. The cost of a single ERC project may not exceed $1,500,000. Each ERC project
must be approved by the Joint Staff and reported to Congress. No construction funds may be
obligated until the appropriate Congressional committees ha ve approved the project or a
21-day waiting period has elapsed from the date of the notifi cation. An ERC project includes
all construction necessary to produce a complete and usable facility. Construction costs can
vary +/- 25% without the requirement to request Joint Staff approval.
6.4.6. Section 2808 Construction Author ity in the Event of a Declarat ion of War or National Emer-
gency: Section 2808 authority can only be granted after a Presiden tial declaration of war or national
emergency. Section 2808 allows the Secretary of Defense to ca rry out any milita ry construction
project for the war or national emergency within the total unobligated military construction program.
Congress must be notified of all 2808 projects but does not require a 21-day delay of authorization of
funding.
6.4.6.1. Section 2808 authority was executed during OEF and OIF. Difficulties gaining access to
authorization of 2808 funds, lega l reviews and differing views of the extent of the authorities
caused delays in executing critical contingency construction projects.
6.4.6.2. Similar to Section 2803 fundi ng, funds are taken from current year authorized construc-
tion projects. Normally, overseas projects are sacrificed to elim inate the cancellation of CONUS
based projects.

6.5. Other Authorities and Sources of Funding.


6.5.1. Burden sharing (T itle 10, USC Section 2350j). This statute provide s authority enabling the
DOD to accept funds from host natio n or foreign governments for bu rden sharing of construction,
supplies and services. Section 2350j funding is complicated by the inclusion of foreign nation invest-
ment and partnering. Additional information of 2350j can be found in JP 4-04 page F-2. Engineering
planners must involve their legal office in the consideration of utilizing this authority.
6.5.2. Economy in Government Act (T itle 31, USC, Section 1535). This statute allows for US Gov-
ernment agencies, outside of the DOD, to fund AF execution of continge ncy construction projects
providing they have the funds and authority to do so. Your legal office is critical in making the deter-
mination of request for utilization of this authority.
6.5.3. Humanitarian and Civic Assistance (HCA) (Title 10, USC, Section 401). Joint force engineers
may work with host nation government agencies to repair or improve infrastructure and public facili-
ties. These authorized and funded projects must fulfill unit training requirements that incidentally cre-
ate humanitarian benefit to the local populace. HCAs are usually planned well in advance and are
usually not in response to disasters, although some have been executed following disasters. Specific
engineer activities for which HCA funds can be us ed include construction of rudimentary surface
80 AFPAM10-219V6 1 FEBRUARY 2006

transportation systems, well drilling, construction of basic sanitation facilities and rudimentary con-
struction and repair of facilities.
6.5.4. Foreign Humanitarian Assistance (FHA). In disaster operations, the UN and the Department of
State’s Office of Foreign Disaster Assistance (U SAID) may generate funded requirements for DOD
assistance. FHA programs focus on the use of DO D excess property, emergency transportation sup-
port, disaster relief, or other support as necessary to alleviate urgent needs in a host country caused by
some type of natural or manmade disaster that might present serious threat to life or great damage to
or loss of property. While other elements of the joint force are focused on immediate FHA, civil engi-
neering support planning may focus on projects that provide expedient shelter for dislocated civilians.
The joint force engineer and staff should work closely with the representatives of the host nation and
US Country Team.
AFPAM10-219V6 1 FEBRUARY 2006 81

Chapter 7

REDEPLOYMENT AND RECONSTITUTION

7.1. Overview. Expeditionary Airbases will transition as the mission and operational requirements
change. Base transition can be either improvement of construction standards as outlined in Chapter 6 or
return of the base back to host na tion ownerships when the US forces depart from the site. This chapter
will focus on base closure and return of the site back to host nation and/or civilian ownership or manage-
ment.

7.2. Transition. Since eventually an expeditionary airbase will transition back to civilian or host nation
control, deployed units should understand the theater level redeployment and reconstitution plan to better
carry out the operational requirem ents for their units. Redeploymen t operations are dependent upon the
combatant commander’s defined mission end state, peacekeeping requirements and host nation support
requirements. Reconstitution is defined as the process of returning deployed fo rces to full operational
readiness, to include personnel actions, training a nd equipment repair and replacement. Redeployment
normally occurs once the combatant commander has de creed that the deployed location will transition
from combat operations to civilian reconstruction or peacekeeping operations.

Figure 7.1. Recovery of BEAR Assets.

7.2.1. Transition operations cover a wide range of requirements that must be met prior to the last US
personnel or US contractor leaving the site. The general rule of thumb to go by is Leave the land and
infrastructure better than you found it.
7.2.2. Base engineers have seen the fallout of leavi ng a base in less than pristine condition when we
redeploy troops to an old s ite and run into the host nation engineer that was left with the clean-up
headache. Engineers will be responsible for the vastmajority of clean-up requirements and in turn will
probably be some of the last troops to leave the site.
82 AFPAM10-219V6 1 FEBRUARY 2006

7.3. Redeployment. Redeployment applies to onward or forward deployment as well as return to home
station. Redeployment planning is essential to an ef fective and efficient return of deployed resources or
forward deployment of combat capability. Redeployment activities need to begin long before a redeploy-
ment order is received. Normally, the planning process begins upon arrival at the deployed location. This
ensures all deployed resources are accounted for and redeployment movement activities comply with host
nation customs requirements. Redeployment is not deployment in reverse. First, fragmented UTCs or unit
line numbers (ULN) are more likely to be incrementally redeploy ed/forward deployed to retain residual
capability at the original deployed location requiring the supportability of remaining forces. Planners need
to plan for the movement of parts of units, UTCs, or ULNs. Secondly, it is common to receive redeploy-
ment orders calling for the rede ployment of fragmented UTCs and UL Ns rather than a reverse TPFD D.
Additionally, due to military, political or diplomatic reasons, redeployment may be far more rapid than the
deployment phase, which makes early-on redeployment planning all the more critical.
7.3.1. During planning commanders must understand that redeployment can be a significant engi-
neering challenge, particularly when terminating overseas contingency operation. Civil engineer oper-
ations support force redeployment through the preparation of facilities for retrograde, completion of
construction projects and the refurbishment and turnover of property and real estate to the host nation.
7.3.2. Additionally, engineers terminate leases and facility contracts, construct wash racks and other
redeployment facilities, prepare collection points and coordinate for the safe disposition of hazardous
cargo. Commanders and civil engineers must be aware of legal consideration involved in these rede-
ployment activities.

7.4. General Considerations for Redeployment and Reconstitution. The situation, condition of assets
and the need for redeployment/reuse will dictate the extent and methods used for recovery and reconstitu-
tion. During deployments, CE teams can anticipate increased loss of equipment, tools and other resources
due to increased utilization and harsh climatic conditions. Your teams should strive to replace worn-out or
destroyed assets as they are lost (prior to redeployment) as in-theater equipment funding is much stronger
than at home equipment accounts.
7.4.1. CE leadership needs to ensure that funds expended are used to replace assets required and not
just desired as nice to haves. There have been numerous instances of deployed teams purchasing the
next greatest technology only to find out that it does not meet their need.
7.4.2. Teams also need to realize that assets purchased in theater to support operational requirements,
that are not listed on you teams equipment supply list (ESL) or Vehicle authorization list (VAL), will
need to be transferred to the incoming team for thei r use. This often occurs when units validate the
purchase of bobcats and gator transports in theater and hope to take them back for use at home station.
This is not practical because if you needed them in the ater so does your replacement. Secondly, at
close to $5,000 per hour for operation of airlift, it is cheaper to buy a new bobcat when you get home.

7.5. Reconstitution of BEAR Assets. Once erected, BEAR assets are operated and maintained primarily
by Prime BEEF and Services personnel. Depending on the situation and the asset, selected 49 MMG per-
sonnel, AFCESA’s CE Maintenance, Inspection and Repair Team (CEMIRT), or a trained theater support
contractor may also assist. The senior on-scene commander, who is normally the AEF/AEW commander,
must appoint a Bare Base Manager (BBM) at each location that is using BEAR. The BBM has custodial
responsibility for the BEAR assets until turned in for redeployment. Redepl oyment planning is a theater
responsibility. Assistance in striking assets is normally requested as needed from the 49 MMG through
AFPAM10-219V6 1 FEBRUARY 2006 83

Air Combat Command’s Logistics Plans office. Reconstitution occurs after the deployment mission
requirement has ended through either force redeploym ent or transition to temp orary or permanent stan-
dard facilities and utilities. Reconstitution usually involves extended operations to clean, inventory; per-
form intermediate- or depot-level maintenance and re pair and repackage assets for shipment or storage.
This effort is normally handled by the asset owner, usually 49 MMG or a theater operating location, or on
a limited basis it ma y include CEMIRT and AFCAP/LOGCAP/CONCAP or theater contractors prior to
shipment for storage.

7.6. Recovery. Unless there has been an attack with damage to the bare base, generally the term recovery
means the dissembling and repacking of BEAR systems for redeployment shipment to another location or
the demobilization and readying of the base for return to the national owners. For facilities such as person-
nel shelters, medical facilities, dining halls and smaller flightline shops, the user, Prime BEEF and logis-
tics personnel generally accomplish this. For larger shelters/hangars this may have to be accomplished by
RED HORSE, 49 MMG tea ms or trained teams from AFCAP/LOGCAP/CONCAP. Theater planners
should consider whether mobile support teams should be established to conduct recovery operations and
conduct user-level maintenance/repair prior to repacking. It may be readily apparent for some assets that
they can be reused without reconstitution. All parties participating in recovery need to make sure that the
designated BBM is properly informed and knows the condition of all assets before making the decision to
redeploy them forward or reutilize in the field. If they are not in a condition to allow for immediate erec-
tion and use for at least another six months, then the items must be identified as requiring maintenance or
identified that additional personnel and supplies may be required for erection and reuse. This is especially
important when the assets are vehicles and equipment items such as generators, high voltage electrical
distribution components, ROWPUs, pumps, bladders, etc., for utility system support.

7.7. Civil Engineering Support of Transition Operations. The deployed engineering squadron is one
of the last teams to leave the contingency airbase. The engineers normally have the main responsibility for
preparing the base for transition to a civilian led task force, military peacekeeping operation, base closure
or return of infrastructure to the host nation. Civil engineer squadrons should be prepared to support the
following transition requirements in addition to normal reconstitution and squadron redeployment priori-
ties:
7.7.1. Termination of base support contracts (refuse, Class IV materials, cleaning etc.).
7.7.2. Preparation of documentation for turnover of facilities and real estate.
7.7.3. Reconstitution of advance bases, staging areas and recovery/inventory and repacking of war
reserve material.
7.7.4. Definition and award of contingency support contracting (AFCAP, CONCAP, or LOGCAP) as
outlined in Chapter 8 of this volume.
7.7.5. Cleanup (in-house or civilian contract) of contaminated sites and waste disposal areas.
7.7.6. Repair of civil infrastructure damaged by US military operations and utilization.
7.7.7. Construction of f acilities required for pr eparing assets for redepl oyment (marshalling yards,
customs yards, wash racks etc.).
7.7.8. Minefield marking and clearance.
84 AFPAM10-219V6 1 FEBRUARY 2006

7.7.9. Port surveys and coordination of port clearance requirements for movement of equip-ment and
assets.
7.7.10. Development and production of topographic, geographic and base utility tabs for future oper-
ations.
7.7.11. Construction of foreign humanitarian assistance and humanitarian civic assistance projects as
defined and negotiated by CREST or the theater engineer and combatant commander.

7.8. Redeployment Scheduling, Validation and Transport. Redeployment is scheduled and prioritized
by the combatant commander’s mission requirements and planning staff. It is imperative that the Combat-
ant Commander maintains the right balance of forces until he no longer requires them for mission accom-
plishment. In an effort to streamline this process, base level units need to have a redeployment plan in
place to be able to adequately schedule and meet redeployment timelines. To support this, the CE planner
needs to understand the process of prioritizing, validating and schedu ling transport, regardless of the
mode of travel.

7.9. Redeployment Requirements Validation. Once a unit has been prior itized for redeployment, the
unit is responsible for confirming readiness posture, movement availability dates and passenger and cargo
details (load lists, weights etc.) to their higher commands, who will verify and prioritize movement sched-
uling.
7.9.1. The supported component commander receives the base reports and merges this into the rede-
ployment TPFDD, and adjusts prioritizations as required.
7.9.2. Once the prioritizations are finalized, the planning cell validates the lift requirements within the
specified TPFDD window of movement for USTRANSCOM movement scheduling.
7.9.3. USTRANSCOM conducts a transportation feasibility review and coordinates unresolved trans-
portation conflicts with the supported comma nder. Once completed, US-TRANSCOM forwards
requirement back to the supported commander as an approved TPFDD that redeploying units use for
scheduling.
7.9.4. Once scheduled the unit will be directed to proceed, IAW flow schedule, to a port of debarka-
tion for airlift back to home station or on to another mission requirement.
7.9.5. Lessons Learned on rede ployment. If a redeploying unit misrepresents its requirements
(weights, passengers, availability, etc.) during the planning phase of this process or fails to adequately
prepare for redeployment, their airlift or transport will be affected and possibly delayed.
7.9.5.1. During OIF and OEF a number of redeploying CE units were frustrated at the inability of
USTRANSCOM and TACC to schedule required airlift on the ap proved rotation dates. During
investigation of the problem, it was discovered that the retu rning units had requested dated
changes on a number of occasio ns, had changed passenger lists and cargo load requirements
necessitating changes to airframes. The best way to ensure that your team gets home as scheduled
is to have a well thought out redeployment plan at the start of the deployment. This should include
passenger manifests (adjusts as the unit gains or loses personnel through combat attrition, injury or
reorganization), anticipated load plans (what did you bring versus what are you brining home) and
rotational requirements (know which passengers and equipment need to go where).
AFPAM10-219V6 1 FEBRUARY 2006 85

7.9.5.2. The USTRANSCOM and TACC scheduling and validation process normally takes a min-
imum of 10 days during normal operational requirements. During contingency operations and
high periods of airlift demand this process can take up to 21 days with continual modifications and
changing mission requirements. As the CE planner or commander, you must keep visibility on the
TPFDD, airflow scheduling valid ation and potential problems. The only guarantee of a flight
home is the day that the TACC scheduler or logistics planner provides a tail number of the aircraft
you are flying home on. During redeployment, your logistics planner is your best friend; constant
coordination and partnering will get your team home.

7.10. Environmental Requirements. The Air Force is committed to maintaining a high level of envi-
ronmental quality during contingency operations. Civil engineers have a special role in helping to meet
this commitment and in full c ompliance with environmental standards. While the degree of complia nce
with these standards is af fected by the location and activities performe d, and may vary during dif ferent
phases of contingencies, the goal is to restore a site to predeployment condition and return it to the host
nation or appropriate agency. Areas of consideration include:
7.10.1. Hazardous waste storage/dis posal, using the DRMO as a dis posal agent, hazardous material
labeling/packaging, mark/map abandoned wastewater facilities, preventing hazardous spills and min-
imizing air/noise pollution.
7.10.2. For detailed information on these and other environmental requirements during redeployment
and reconstitution, see AFH 10-222, Volume 4.

7.11. Conclusion. The end of hostilities, operations or disaster recovery does not mean the end of the
Expeditionary Engineer responsibility. The CE Commander and personnel ne ed to plan to be one of the
last support functions to leave the deployed locations as they will be responsible for recovering the site to
better than its orig inal condition, transfer of ownership of agreed facilitie s and environmental clean-up
and remediation. During OAF, OEF and OIF it was common for the operations and logistics groups at
deployed locations to depart, leaving the Mission Support Group (MSG) Commander or the senior MSG
squadron commander in charge of closing and recovering the base pr ior to redeployment. CE planners
need to start creating a redeployme nt plan during the in itial deployment to ensu re they have adequate
resources identified.
86 AFPAM10-219V6 1 FEBRUARY 2006

Chapter 8

CONTRACT AUGMENTATION PROGRAMS

8.1. Overview. The military is one-third smal ler today than a decade ago ye t averages almost twice the
number of deployments and contingency operations. This operational tempo versus resources highlights a
need to augment operational capa bility throughout the Department of Defense. In the early 1990s, the
DOD created contract augmentation programs or CAP (LOGCAP, CONCAP, and AFCAP). These pro-
grams enabled the military to augment its current capabilities through the contract award of stand-by rapid
response force contracted civilian capabilities. It is not cheap to contract the stand-by rapid response, pro-
fessional expeditionary combat support and construction services of civilian contractors, but during con-
tingency operations it frees up military personnel to complete military missions while civilian contractors
take care of non-military specific requirements.

8.2. Air Force Guidance on Contractors in Theater of Operations. Civilian contractor personnel
accompanying Air Force forces are not combatants and must not be allowed to act as combatants during
Air Force operations. Civilian contractor personnel have historically provided support to fielded military
forces and international law allows for such activities. Therefore, it is Air Force po licy to integrate
increased commercial support to the total force wher ever appropriate while preserving our core compe-
tencies.
8.2.1. The risks must be minimized when deciding to use contractors to provide essential services. In
fact, a uniformed capability should be maintained to provide essential services in the event the opera-
tional environment precludes the use of contractors. AFMAN 10-401, Volume 2, Planning Formats
and Guidance, requires that full consideration of the impactof contractors must be addressed in devel-
oping operational plans. Commanders should limit the designation of essential contract services (IAW
DODI 3020.37, Continuation of Essential DOD Contractor Services During Crisis) to those truly
indispensable to the accomplishment of the unit’s operational mission. Contracts will identify which
services are essential. If the contract has esse ntial services, contractor support requirements must be
integrated fully into the total force structur e and planning to ensure mission accomplishment . Any
determination regarding commercial support must consider the essentia l services that must be main-
tained and the risks associated due to possible contractor non-performance. Again, if contractors can’t
be used to do the job, military personnel must be integrated into the planning process.
8.2.2. Contractors ar e expected to comply with all applicable US and international law. Unless
addressed otherwise by in ternational agreement, contractor personnel are subject to the law of the
nation in which they are lo cated. This means that contractors must be prepared to comply with all
local taxes, immigration requirements, customs fo rmalities and duties, environmental rules, bond or
insurance requirements, work permits and transporta tion or safety codes. The f act that the military
force for which they are performing services enjoys certain exemptions from local law does not mean
contractor personnel are also exempt--generally, contractor personnel are not exempt from local law.
During a declared war, contractor personnel accompanying the armed forces are subject to the crimi-
nal jurisdiction of the military and the Unif orm Code of Military Justice. However, in all circum-
stances contractors are subject to host nation criminal law, unless specifically addressed otherwise by
international agreement. Contractor employees and other civilians accompanying the armed forces
may also be prosecuted by the United States for criminal acts.
AFPAM10-219V6 1 FEBRUARY 2006 87

8.2.3. When contractor personnel are deployed in support of Air Force operations, the Air Force may
provide or make available, under terms and conditions as specified in the contract, force protection
and support services commensurate with those provided to DOD civilian personnel to the extent
authorized by US and host nation law. These services may include but are not limited to medical/den-
tal care, messing, quarters, special clothing, equipment, training, mail and emergency notification. Air
Force units are to provide only t hose goods and services to contract or personnel that are specified in
the terms of the contract when authorized under host nation law or applicable international agreement.
If the Government provides support services to contractor personnel, it may increase the overall cost
to the Government. Planni ng to provide this suppor t to contractors must include a careful review of
host nation law and applicable international agreem ents as well as contract pricing, budget and mili-
tary manpower (reference AFMAN 10-401 , Volume 2). Commanders and the requiring activity will
determine which services are essential and submit requirements, including proposed support services,
to the contracting officer to modify existing contracts. All future contracts will need a determination if
essential services exist and, if necessary , incorporate requirements in the statement of work (SOW).
SOW language should also include applicable deployment requirements, both medical and physical,
and allow for contractor information system interoperability with USAF and/or government informa-
tion systems.
8.2.4. During contingencies that do not constitute international armed conflicts, the status of contrac-
tor personnel accompanying the armed forces is entirely determined by host nation law or applicable
status of forces agr eements, although contractors are seldom included in su ch agreements. During
contingencies that constitute international arme d conflicts, contractor personnel are non-combatant
persons accompanying the armed forces but may be subject to hostile action because of the support
they provide in close proximity to combat forces. Commanders should take care to ensure contractor
personnel are not used in any mann er that would jeopardize their status under international law as
non-combatant persons accompanying the armed for ces. Assuming they have not jeopardized their
status as noncombatants, if cap tured during an international arme d conflict, contractor personnel
accompanying the armed forces are afforded the same protection granted to Prisoners of War (POWs)
under the Third Geneva Convention of 1949.
8.2.5. Air Forc e commanders should not issue firearms to contract or personnel operating on their
installations, nor should they allow contractor personnel to carry personally owned weapons. With the
express permission of the ge ographic combatant commander and in consultation with host nation
authorities, Air Force comma nders may deviate from this prohib ition of firearms only in the most
unusual circumstances (e.g., for protection from bandits or dangerous animals if no military personnel
are present to provide protection).
8.2.6. Air Force commande rs should not issue military garmen ts (e.g., battle dress uniforms or
Gore-Tex jackets) to contractor personnel. Exceptions may be made for compelling reasons such as a
need for chemical protective equipment when the contract requires the G overnment to issue such
items rather than requiring the contractor to provide them to its personnel. Should commanders issue
any type of standard uniform item to contractor personnel, care must be taken to require that the con-
tractor personnel be distinguishable from military personnel with some distinctively colored patches,
armbands, or headgear.
8.2.7. Although many contractor personnel supporting Air Force operations are former military mem-
bers, the contract and commanders must make it cl ear that contractor personnel have no military sta-
tus.
88 AFPAM10-219V6 1 FEBRUARY 2006

8.3. Air Force Contract Augmentation Program. Air Force policy is to in tegrate increased commer-
cial support into the total force wherever appropria te while preserving its co re uniformed competencies
(for complete Air Force policy govern ing contractors in the theater, see Appendix E). In support of this,
the AF has developed the AFCAP concept. The AFCAP contract provides the following support.
8.3.1. Commander Support. AFCAP provides commanders a responsive, force multiplier option to
augment or relieve expeditionary combat support functions participating in military operations other
than war (MOOTW) or small-scale contingencies (SSCs).
8.3.2. Quick Response, Contract Deployment Capability. AFCAP is a contract with extensive world-
wide support capabilities, able to respond in minimal time. Capab ilities focus on temporary contin-
gency skills and/or resources to sustain military forces participating in MOOTW/SSCs or to recover
from a natural disaster, accident, or terrorist attack.
8.3.3. Planning a nd Deployment. The contractor shall provide the personnel, equipment, materials,
services, travel and all other me ans necessary to provide a quick response, worldwide planning and
deployment capability. Planning is expected to be available within the contractor’s program manage-
ment team and other company resources. Deployment capabilities are to be obtained as required for a
site-specific scenario. The capabilities under this contract are intended to support Air Force MOOTW/
SSC activities operating in support of National Command Authority missions, which could include
(but are not limited to) joint or combined United States military forces acting as part of or in concert
with United Nations (UN), North Atlantic Treaty Organization (NATO), multinational force, or other
entities. MOOTW/SSCs may include Air Force required support to na tural disaster relief operations
within and outside CONUS.
8.3.4. Deployment Capabilitie s. The principal effort of this co ntract will be to provide deployment
capabilities generally aligned with Air Force combat suppor t and combat service support functions
associated with expeditionary combat support, to include the Civil Engineer and Services career fields
and to provide logistic support that reduces a dependence on scarce war reserve materiel stockpiles. A
partial list of skills typically required include: carpentry, plumbing, electrical, mechanical (e.g., refrig-
eration, air conditioning, heat, controls, etc.), heavy equipment, paint, power production, food service,
lodging management, recreational services, housekeeping services, laundry plant operation, va rious
utility plant operations (e.g., water, sewage, solid waste disposal, et c.), structural fire protection and
fire crash rescue, unexploded or dnance (UXO) technician (e.g., cl earing sub-scale practice bombs),
emergency management, professional engineering, and project and program management.
8.3.5. Program Management Office. The contractor shall provide the necessary supplies, equipment
and personnel to sustain administrative/management support for the Air Force Contract Augmentation
Program (AFCAP). Minimum requirements include: having a dedicated program management office
within a 25-mile radius of Tyndall AFB, FL, with the capability to develop Rough Order of Magnitude
(ROM) cost estimates and execute individual task orders. This program management of fice shall be
available for support 24 hours a day, 365 days a year.
8.3.6. Types of Response. Because military forces are trained and equipped for rapid deployment and
flexible support for a variety of scenarios, the e xpectation is that initial response to a MOOTW/SSC
will generally be assigned to mi litary forces. As thes e forces establish a ba se(s) of operations and
extended activities are likely to occur , AFCAP relief, augmentation, or expansion are potential
resource options. However, the above statement does not rule out the possibility that AFCAP contract
support may be the initial responder in selected scenarios, particularly small scale, fast moving, iso-
AFPAM10-219V6 1 FEBRUARY 2006 89

lated location scenarios or during worldwide recovery operations. In addition, work may include
MOOTW/SSC backfill support at existing operational Air Force bases within and outside the United
States to augment sustaining forces.
8.3.7. Background. AFCAP represents an initiative to contract for base operating support and tempo-
rary construction capabilities to relieve or augment military support forces and resources involved in
MOOTW/SSCs. MOOTW are described as military actions, except thos e associated with sustained,
large-scale combat operations and SSC is a new term for military operations other than war. These
military actions can be applied to complement any combination of the other instruments of national
power and occur before and after war [Joint Publication 3-07]. Generally, these operations will occur
in a noncombatant, forward deploy ed environment (outside United States territory). However, this
does not eliminate the possibility of natural disaster support or home base backfill sustainment sup-
port in the United States.
8.3.8. Typical Air Force Deployment Locations. With rare exceptions, Air Force deployments are tied
to airfields which typically contain at least some existing buildings and utility infrastructure. There-
fore, deployment support will usually include a variety of operation and maintenance (O&M) require-
ments to fixed, existing real property, as well as providing measures to augment or emplace additional
temporary services and facilities.
8.3.9. Customers. Through the AFCAP Program Manageme nt Office, this contract is established to
support Air Force major commands (MAJCOM) and associated component commanders.
8.3.10. Deployment Capabilities. All expeditionary combat support functions to include but not lim-
ited to the following tasks.
8.3.10.1. Deployed Management/Services Management Cell. Contractor shall establish an on-site
central management cell for (at a minimum).
8.3.10.1.1. Contractor management responsibilities, including scheduling, management plan
updating, supervision, cost control, etc., necessary to assure task order success.
8.3.10.1.2. Contractor and customer work order /job order receipt, processing and control;
logistics/procurement management; contractor command, control and communications and
liaison with the on-site customer.
8.3.10.2. Security. The contractor shall develop and implement OPSEC/COMSEC procedures;
develop and implement internal co ntractor controls to provide physical security protection of
property from theft.
8.3.10.3. Professional Engineering. Th e contractor shall provide home office and/or on-site pro-
fessional architect-engineer services (including foreign sources) appropriate to the task order sce-
nario.
8.3.11. Airfield Support. The contractor shall provide operation, maintenance, repair, installation and
renovation of airfield requirements.
8.3.11.1. Airfield unique facilities such as contro l tower(s), hangars, hard ened aircraft shelters,
NAVAID shelters, etc.
8.3.11.2. Airfield surfaces (includi ng underlying structures) such as runways, taxiways, aircraft
parking ramps, hot cargo pads, grounding points, tie downs, sw eeping, foreign object removal,
90 AFPAM10-219V6 1 FEBRUARY 2006

snow and ice control; implement bird aircraft strike hazard (BASH) recommendations, vegetation
control, soil stabilization, clear zone maintenance (e.g., tree removal), etc.
8.3.11.3. Aircraft arresting syst ems including operation (setup & resets), operator level mainte-
nance, and repair (installation/removal done by others).
8.3.11.4. Lighting including commercially installed high/low voltage, Emergency Airfield Light-
ing Set (EALS), strobes, Pulsed Light Approach Slope Indicator (PLASI), Visual Approach Slope
Indicator (VASI), Precision Approach Path Indicator (PAPI) systems, ball park ramp lighting sys-
tems, foreign systems, etc.
8.3.11.5. Markings/Striping--e.g., runway centerline/edges, taxiway centerlines, hold lines, mag-
netic compass runway orientation numbering, dis tance/barrier markers, touchdown zone stripes,
aircraft parking layouts, etc.
8.3.11.6. Emergency power--e.g., dedicated emergency power for selected critical facilities/infra-
structure (e.g., control tower, lighting, etc.).
8.3.12. Infrastructure Support. Provide operation, maintenance, repair, installation and renovation of
infrastructure requirements. Contract focus will be on providing te mporary methods and materials to
solve tasked requirements (e.g., tents, expandable/portable buildings and modular systems).
8.3.12.1. Facility Su pport. Air Force basi ng typically includes some existing infrastructure so
construction craft personnel skilled in disciplines such as structural, electrical, plumbing, mechan-
ical, fire and security al arms, etc., shall be provided by the contractor as appropriate to the task
order scenario.
8.3.13. Utilities.
8.3.13.1. Electrical dist ribution systems, such as high/low voltage, AC/DC, switching, under-
ground, pole mounted, surface laid, transformers, and converters.
8.3.13.2. Power production, such as receive and distribute commercial power; install and operate
prime generator plant for task order infrastructure and standby generators.
8.3.13.3. Water distribution & storage system, including storage (elevated tanks, bladders, e tc),
pumps, piping (underground, surface laid, etc), valving and metering.
8.3.13.4. Water production and treatment, such as tap commercial sources, drill wells, operate
existing water treatment plants, establish expedient water treatment plant, chlorinate and fluori-
date.
8.3.13.5. Sewage distribution system—e.g. underground, surface laid, va lving, lift stations and
clean outs.
8.3.13.6. Sewage treatment plant—tie into commerc ial system, operate existing plant, develop
expedient treatment (e.g., leach field, lagoon).
8.3.13.7. Steam plant (heat)—operate, maintain and repair.
8.3.13.8. Fire pr otection systems—existing installed systems (e.g., sprinkler, deluge, halon and
standpipe).
8.3.13.9. Support expedient installation of fire protection systems and/or add to existing systems.
8.3.13.10. Natural gas distribution—existing natural gas distribution systems.
AFPAM10-219V6 1 FEBRUARY 2006 91

8.3.13.11. Compressed air system—existing compressed air systems.


8.3.13.12. Propane and/or fuel oil stora ge & distribution systems (heat)—propane and fuel oil
systems.
8.3.13.13. Alarm syste ms—fire and security alarm distribution systems and associated central
monitoring stations.
8.3.13.14. Energy monitoring and control systems (EMCS)—existing system.
8.3.13.15. Storm drainage system.
8.3.13.16. Petroleum, oils, lubricants (POL).
8.3.13.17. Aircraft storage tanks (above- and underground) and bladders.
8.3.13.18. Aircraft POL di stribution system, including hydrant system, manifolds, lines (above-
and underground), pumps and valves.
8.3.13.19. Non-aircraft POL storage—tanks (above- and underground) and bladders.
8.3.13.20. Non-aircraft POL distribution system—dispensers, lines (above- and underground),
pumps and valves.
8.3.13.21. Solid waste management—establish pickup points and appropriate containers, pickup
and transport to landfill or commercial solid waste pickup point.
8.3.13.22. Landfill—establish, operate, maintain, repair and close.
8.3.13.23. Recycle—establish and ope rate a recycling program as appropriate and required by a
specific task order (e.g., paper, plastic, glass, metals, chemicals, etc.).
8.3.13.24. Incineration.
8.3.13.25. Roads/Parking.
8.3.13.26. Paving—all surfaces (asphalt, concrete, etc.), including subsurface structures and strip-
ing.
8.3.13.27. Unimproved (dirt)—stabilization, grading, mud and dust control.
8.3.13.28. Security structures—structures such as chain link fencing, barbed wire fencing, razor
tape, observation towers, defensive fighting positi ons and electrically or hydraulically operated
entry barriers.
8.3.14. Environmental.
8.3.14.1. Permits—support for preparation/submittal.
8.3.14.2. Hazardous material—support for management, inventory/control, ultimate disposition.
8.3.14.3. Hazardous Waste. Perform required management, collection, storage and disposal in
accordance with applicable laws/regulations.
8.3.14.4. Pest/Vegetation Control. Assess needs and apply appropriate agents.
8.3.14.5. Environmental Clean-up. Provide capability to clean up and contain localized environ-
mental spills resulting from MOOTW/SSC activities.
92 AFPAM10-219V6 1 FEBRUARY 2006

8.3.15. Emergency Support Services.


8.3.15.1. Fire protection. Provide full range of fire protection to include fire prevention and haz-
ardous materials response/mitigation support. All fire fighters, to include supervisory levels (e.g.,
fire chief, crew chief, station chief, assistant chief, etc.) must be certified or have equivalent expe-
rience to meet the requirements ou tlined in the appropriate Nati onal Fire Protection Association
professional qualifications standards.
8.3.15.2. Prevention. Develop fire prevention progr ams and promote fire prevention awareness.
Personnel must be certified Fire Inspector I or II, or have equi valent experience to meet the
requirements outlined in the National Fire Protection Association Professional Qualification Stan-
dard 1031, Professional Qualifications for Fire Inspector.
8.3.15.3. HAZMAT. Provide appropriate HAZMAT response capability. Personnel must be
trained and employer certified per Code of Federal Regulations 29 CFR 1910.120 (Q) at the
Awareness, Operations, Incident Command and/or Technician level as appropriate for the specific
task order scenario.
8.3.15.4. Planning. Develop, coordinate and publish site-specific emergency management plans.
Plans must address actions to prepare for, survive during, respond to and recover from local natu-
ral, man-made or technological disasters.
8.3.15.5. Warning systems. Identify requirements, install, operate and maintain an integrated
emergency warning system. The system must provi de standard Air Force notification for person-
nel at risk and recall of disaster response and control personnel.

8.4. Ancillary Capabilities. Provide maintenance, repair, installation and renovation of a variety of
ancillary requirements, such as:
8.4.1. Facility Hardening. Task includes berming, sandbagging, plywood reinforcing, shoring, etc.
8.4.2. Dispersal. Whe re dispersal is required, establish multiple st orage, parking and maintenance
sites.
8.4.3. Obstacles. Includes entry obstacles, delaying obstacles, etc.
8.4.4. Redundancy Measures. Add redundancy to utilities (looped systems), provide spare generators
and add capacity or systems to critical facility air conditioning requirements.
8.4.5. Reconstitution. Tear down, clean, repackage, inventory and turn-in government (including
AFCAP contractor purchased) equipment where and to whom specified by task order or the contract-
ing officer.
8.4.6. Restoration.
8.4.6.1. Remove temporary improvements to facilities, utilities, roads, etc.
8.4.6.2. Perform operations to return land to host nation in required condition.
8.4.6.3. Services (MWR and Services).
8.4.6.4. Provide food service support using field and garrison equipment and facilities. Contractor
furnished equipment may be required. Preparation of up to four meals per day may be required
using A, B and T rations. Distribute operational ra tions such as Meals Ready to Ea t (MRE), as
needed. Contractor shall maintain food accountability using task order prescribed procedures and
AFPAM10-219V6 1 FEBRUARY 2006 93

forms. Personnel working in food service must have current and documented food handlers train-
ing in accordance with AFMAN 34-240, Food Service Program Management.
8.4.6.5. Troop support—order, receive, store, issue, secure, and account for all subsistence to sup-
port food operations. Purchase subsistence direct ly from vendors (US or foreign national) and
transport to the final destination. All purchases must be from sources approved by military public
health as meeting public health standards.
8.4.6.6. Lodging. Provide central lodging processing point for allocation of space for various cat-
egories of personnel (i.e., male, female, officer, enlisted, aircrew, etc.). Operate locator system and
provide housekeeping support. Use space in commercial qua rters or contingency quarters as
directed. Contractor furnished lodging facilities may be required.
8.4.6.7. Laundry. Provide laundry operations to suppor t individual self-help, organizational, and
medical requirements.
8.4.6.8. Fitness. Set up and manage individual and intramural sports activities. Provide, maintain,
and monitor use of fitness equipment, facilities, and programs for strength and cardiovascular con-
ditioning.
8.4.6.9. Recreation. Provide a variety of recreati onal and leisure time activities such as 16 or
35mm movies, VHS videos, tabl e games, tours, equipment ch eck-out, and reading materials
(books, periodicals, newspapers, etc.). Provide electronic library reference material and an assort-
ment of current newspapers.

8.5. Materiel Support.


8.5.1. Mobility/War Reserve Materiel (WRM)—e. g., BEAR, Harvest Falcon and Harvest Eagle
assets.
8.5.2. Erection/Installation. Augment or relieve mil itary forces in the erec tion/installation of mobil-
ity/WRM assets.
8.5.3. Existing Infrastructure. Perform routine operation, maintenance, repair, or renovation, includ-
ing disassembly/reconstitution.
8.5.4. Contingency/Disaster Relief Materiel. Procure, transport and store materiel to support contin-
gency and disaster relief operations. Support may include materiel management, handling and inven-
tory.

8.6. General.
8.6.1. Real Property Leasing. As the task order scenario dictates, th e contractor shall lease existing
facilities and/or land in order to meet task order requirements, but only after explicit written Contract-
ing Officer approval.
8.6.2. Land Clearing and Grubbing. Provide heavy equipment and operators to prepare land for use/
occupancy, including creating and compacting subsurface support structures (base course, sub-base
course, etc.); leveling for airfield surfaces, roads and facilities; sloping for drainage, etc.
8.6.3. Aircraft Gunnery Range Clear ance Operations. Provide active range clearance operations at
service Class A primary training ranges to include collection, inspection, disposal, and removal of all
sub-scale practice bombs and unexploded ordnance.
94 AFPAM10-219V6 1 FEBRUARY 2006

8.6.4. Typical Construction. Typical AFCAP construction requirements are synonymous with initial
and temporary joint servi ce construction standards. The contractor shal l use these standards to help
determine the types of materials and construction techniques to be employed. These construction stan-
dards provide criteria that minimize construction efforts while providing facilities of a quality consis-
tent with the mission requiremen ts, personnel health and safety, and the expected availability of
construction resources. These crite ria can be met by commercial of f-the-shelf building systems that
are rapidly erectable and yet have a life span that exceeds even the temporary standard if that alterna-
tive is cost or operationally effective.
8.6.5. Semi-Permanent and Permanent Construction. The contractor shall be capable of accomplish-
ing semi-permanent and permanent construction. It is imperative that the scope and required specifi-
cations be explicitly call ed out within the defini tion of the task order . These requirements will
generally be accomplished as a turn-key effort.
8.6.6. Backfill Support. MOOTW/SS C support may entail a requirement to augment the sustaining
force at an Air Force base whethe r in CONUS or overseas. This back fill support will not be in the
form of personal services.

8.7. Logistics Civil Augmentation Program (LOGCAP). LOGCAP is authorized by Army Regulation
700-137, Logistics Civil Augmentation Program (LOGCAP). The Department of the Army’s Deputy
Chief of Staff, Logistics (DCSLOG) is the proponent, and the Army Corps of Engineers is the contracting
activity. Its purpose is to use civilian contractors to perform selected services for military forces deployed
to a theater of operations. The support includes trans portation, food service, ice, potable water, laundry,
showers, latrines, refuse removal, contingency equipment, and an unskilled labor pool. The mission state-
ment requires the contractor, on order and within 15 days , to initiate specific logistical and engineering
support for 20,000 arriving troops for up to 180 days.
8.7.1. LOGCAP should be accessed through the Army’s theater level G4/S4 (Logistics and Engineer-
ing) staff or the CFACC Engineer (A7). LOGCAP is managed by the LOGCAP Support Unit (LSU)
in Alexandria, Virginia. If you require direct access or have additional questions on LOGCAP organi-
zation, capabilities, and execution, contact the LSU at: AMCLG-TPU, LOGCAP Support Unit, 5001
Eisenhower Avenue, Alexandria, VA 22333-0001, (703) 617-0556 or call DSN 767-0556.
8.7.2. LOGCAP is primarily designed for use in ar eas where no bilateral or multilateral agreements
exist. However, LOGCAP may provi de additional support in areas with formal host nation support
(HNS) agreements, where other contractors are involved, or where peacetime support contracts exist.
LOGCAP is also availa ble during Continental United States (CONUS) mobilizations to assist the
CONUS support base and help units get ready for war.
8.7.3. LOGCAP includes all pre-planned logistics and engineering/construction oriented contingency
contracts actually awarded. LOGCAP also includes peacetime contracts wh ich include contingency
clauses that provide rapid and responsive capability that augments US forces’ capabilities by meeting
logistics and engineering/construction requirements.
8.7.4. The Army has used contr actors to provide supplies and se rvices during both peacetime and
contingencies dating back to the Revolutionary War. LOGCAP was established on 6 December 1985
with the publication of Army Regulation 700-137, Logistics Civil Augmentation Program. The newly
established program was used in 1988 when the Third United S tates Army requested that the U.S.
Army Corps of Engine ers (USACE) contract out a management plan to construct and maintain two
AFPAM10-219V6 1 FEBRUARY 2006 95

petroleum pipeline systems in S outhwest Asia in support of conti ngency operations. Since its incep-
tion, LOGCAP has supported US Army operations in Rwanda, Haiti, Saudi Arabia, Kosovo, Ecuador,
Qatar, Italy, Southern Europe, Bosnia, Panama, Korea, Kuwait, Afghanistan, and Iraq.
8.7.5. LOGCAP capabiliti es include supply operations, clot hing exchange and repair, mortuary
affairs, billeting, facilities ma nagement, information management, transportation, engineering and
construction, equipment retrograde, laundry, food services, hazardous waste disposal, personnel sup-
port to include MWR, maintenanc e, medical services, power generation and distribution, and other
operations and services.

8.8. US Navy Contingency Construction Capabilities (CONCAP). The Navy's civilian augmentation
program was started to enhance the Naval Facilities Engineering Command's (NAVFAC) ability to
respond to global contingencies. The immediate need was to supplement the capabilities of local com-
manders and regional resources.
8.8.1. CONCAP provides the Navy and Marine Corps with a responsive contracting vehicle ready to
respond to contingencies or natural disasters. It provides for indefinite deliveries and quantities using
a cost-plus-award-fee contract for design, construction and services to support the Navy in war, disas-
ter recovery, and military operations other than war. CONCAP is suitable for those situations in which
the mission parameters exceed normal acquisition timing, there is an aust ere contingency environ-
ment, and facility requirements are not well defined.
8.8.2. The contract calls for a broad range of capabilities in both vertical and horizontal construction
scenarios.
8.8.3. CONCAP helps the Navy stay within its force ceilings and frees uniformed Navy personnel for
contingency operations. The contract specifies what may be required and includes time parameters for
setting up quick, behind-the-lines facility support for troops. It also frees up Seabee s to support the
fight.
8.8.4. CONCAP capabilities include:
8.8.4.1. Horizontal/vertical construction (runways, roads, br idges, causeways, piers, berthing/
messing facilities, depots, warehouses, clinics, field hospitals, operational/maintenance facilities,
communications infrastructure, and ammunition dumps).
8.8.4.2. Specialty construction and engineering (d redging, aerial photography, soils engineering
and surveys, operation of power generation, concrete and asphalt plants, POL facilities, and envi-
ronmental restoration).
8.8.4.3. CONCAP’s primary focus is to support day-to-day operations, construction, and manage-
ment of Navy permanent bases. CONCAP is not a viable alternative for initial standard contin-
gency construction, but can be ut ilized in the event AFCAP or LOGCAP are not available for
large-scale permanent construction requirements at expeditionary beddown locations.
8.8.5. CONCAP has been utilized dur ing requirements in Somalia, Ha iti, and Bosnia; during Hurri-
cane Andrew (October 1995), Hurricane Bertha (July 1996), and Hurricane Fran (September 1996). In
2002, CONCAP built detention facilities at Guantanamo Bay, Cuba.

8.9. Conclusion. The various contract augmentation programs offer the component/theater engineer and
commander various options, other than utilization of limited military reso urces, to complete specified
96 AFPAM10-219V6 1 FEBRUARY 2006

expeditionary combat support services, construction, management, and logistics. The increased cost is
worth the on-call capabilities that the programs offer. All programs must be accessed through the appro-
priate management function: AFCAP through AFCESA, at Tyndall AFB; LOGCAP via LSU in Alexan-
dria, Virginia; and CONCAP through NAVFAC at the Washington Navy Yard in Washington DC.

8.10. Forms Adopted. AMC IMT 174, Air Field Survey; AF IMT 3822, Landing Zone Survey.

DONALD J. WETEKAM, Lt General, USAF


DCS, Installations and Logistics
AFPAM10-219V6 1 FEBRUARY 2006 97

Attachment 1

GLOSSARY OF REFERENCES AND SUPPORTING INFORMATION

References
JP 1-02, DOD Dictionary of Military and Associated Terms
JP 3-07, Joint Doctrine for Military Operations Other Than War
JP 4-04, Joint Doctrine for Civil Engineering Support
JP 4-06, Joint Tactics, Techniques and Procedures for Mortuary Affairs in Joint Operations
DOD 2000.12H, DOD Antiterrorism Handbook
DODI 2000.16, DOD Antiterrorism Standards
DODI 2000.18, DOD Installation Chemical, Biological, Radiological, Nuclear and High-Yield Explosive
Emergency Response Guidelines
DODI 3020.37, Continuation of Essential DOD Contractor Services During Crisis
Manual for Courts-Martial United States (2002 Edition), Appendix 21, Rule 202(a)
AFDD 1-2, Air Force Glossary
AFDD 2-4.4, Bases, Infrastructure and Facilities
AFPAM 10-219V5, Bare Base Conceptual Planning Guide
AFPAM 10-219V7, Expedient Construction Methods (Draft)
AFH 10-222V1, Guide to Bare Base Development
AFH 10-222V2, Guide to Bare Base Assets
AFH 10-222V4, Environmental Guide for Contingency Operations
AFMAN 10-401V2, Planning Formats and Guidance
AFI 10-403, Deployment Planning
AFMAN 10-2602, Nuclear, Biological, Chemical and Conventional (NBCC) Defense Operations and
Standards
AFPD 31-3, Air Base Defense
AFI 31-202, Military Working Dog Program
AFI 32-1021, Planning and Programming Military Construction (MILCON) Projects
AFI 32-1022, Planning and Programming Nonappropriated Fund Facility Construction Projects
AFI 32-1023, Design and Construction Standards and Execution of Facility Construction Projects
AFI 32-1024, Standard Facility Requirements
AFI 32-1041, Airfield Pavement Evaluation Program
AFH 32-1084, Facility Requirements
98 AFPAM10-219V6 1 FEBRUARY 2006

AFMAN 34-240, Food Service Program Management


AFMAN 37-123, Management of Records
AFMAN 91-210, Contract Safety
AR 420-90, National Fire Protection Association Codes
AR 385-64, U.S. Army Explosives Safety Program
AR 700-137, Logistics Civil Augmentation Program (LOGCAP)
DA PAM 385-64, Ammunition and Explosives Safety Standards.
UFC 3-260-01, Design: Airfield and Heliport Planning and Design
UFC 4-010-01, Design: DOD Minimum Antiterrorism Standards for Buildings
UFC 4-010-02, Design: DOD Minimum Standoff Distances for Buildings
USAF War and Mobilization Plan, WMP-1, Annex S
29 CFR 1910.120(Q)
10 USC Sections 2803, 2804, 2805, 2802, 2350j
31 USC Section 1535

Abbreviations and Acronyms


ABD—airbase defense
AC—alternating current
ACH—aircraft hangar
ADR—airfield damage repair
ADVON—advance echelon
AEF—Air and Space Expeditionary Force
AETF—Air Expeditionary Task Force
AEW—Air Expeditionary Wing
AFCAP—Air Force Contract Augmentation Program
AFCESA—Air Force Civil Engineer Support Agency
AFDD—Air Force doctrine document
AFH—Air Force handbook
AFI—Air Force instruction
AFMAN—Air Force manual
AFN—American Forces Network
AFPAM—Air Force pamphlet
AFPD—Air Force policy directive
AFPAM10-219V6 1 FEBRUARY 2006 99

AFRES—Air Force Reserve


AFTH—Air Force theater hospital
AGE—aerospace ground equipment
ALCE—airlift control element
AMOG—air mobility operations group
ANG—Air National Guard
AO—area of operations
AOR—area of responsibility
AR—Army Regulation
ARFF—aircraft rescue and fire fighting
ASP—ammunition supply point
ASRR—airfield suitability and restrictions report
AT/FP—antiterrorism/force protection
BCE—base civil engineer
BEAR—basic expeditionary airfield resources
BRAAT—base recovery after attack
C2—command and control
C3—command, control and communications
CBRNE—chemical, biological, radiological, nuclear and high-yield explosive
CEMIRT—Civil Engineer Maintenance, Inspection and Repair Team
CESP—civil engineering support plan
CFACC—combined force air component commander
CFLCC—combined force land component commander
CFR—crash fire rescue; Code of Federal Regulations
CH—contingency hospital
COB—collocated operating base
COMSEC—communications security
CONCAP—contingency construction capability
CONEX—consolidated express (containers)
CRAF—Civil Reserve Air Fleet
CREST—contingency real estate support team
CRG—contingency response group
100 AFPAM10-219V6 1 FEBRUARY 2006

CSAF—Chief of Staff, Air Force


CSAR—Combat Search and Rescue
cu ft/sec—cubic foot per second
DA—Department of the Army
DC—direct current
DG—distributed generation
DODI—Department of Defense Instruction
EAF—Expeditionary Aerospace Force
ECU—environmental control unit
E-G—engine generator
EMEDS—Expeditionary Medical Support
EOD—explosive ordnance disposal
ESQD—explosive safety quantity distance
ESSP—expeditionary site survey process
FHA—Foreign Humanitarian Assistance
FOB—forward operating base
FOC—full operating capability
FOD—foreign object damage
FOL—forward operating location
FP—Force Provider
gal—gallons
gal/d—gallons per day
gal/m—gallons per minute (also gpm)
GMTF—global mobility task force
GP—general purpose
HCA—Humanitarian and Civic Assistance
HE—Harvest Eagle
HF—Harvest Falcon
HFPO—Health Facilities Planning Office
HN—host nation
hz—hertz
IC—internal combustion
AFPAM10-219V6 1 FEBRUARY 2006 101

IOC—initial operational capability


ISB—intermediate stage base
ISO—International Standardization Organization
JA—Judge Advocate
JCC—Joint Contracting Center
JCS—Joint Chiefs of Staff
JP—Joint Publication
JSP—joint support plan
JTF—joint task force
kW—kilowatt
LN—local national
LOGCAP—Logistics Civil Augmentation Program
MAJCOM—Major Command
MEP—mobile electric power
MILVAN—military van (container)
MOB—main operating base
MOC—minimum operating capability
MOG—maximum (aircraft) on ground
MOGAS—motor gasoline
MOOTW—military operations other than war
MOS—minimum operating strip
MSG—mission support group
MTF—medical treatment facility
MTMC—Military Traffic Management Command
MWR—Morale, Welfare and Recreation
NATO—North Atlantic Treaty Organization
NAVAID—navigational aid
NCC—network control center
NFPA—National Fire Protection Association
NSF—net square feet
OAF—Operation ALLIED FORCE
OEBGD—Overseas Environmental Baseline Guidance Document
102 AFPAM10-219V6 1 FEBRUARY 2006

OEF—Operation ENDURING FREEDOM


OIF—Operation IRAQI FREEDOM
O&M—operation and maintenance
OPLAN—operation plan
OPORD—operation order
OPSEC—operations security
PACAF—Pacific Air Forces
PEB—pre-engineered building
POL—petroleum, oils and lubricants
Prime BEEF—Prime Base Engineer Emergency Force
RALS—Remote Area Lighting System
RDS—records disposition schedule
RED HORSE—Rapid Engineer Deployable Heavy Operational Repair Squadron, Engineer
ROWPU—reverse osmosis water purification unit
SCIF—sensitive compartmented information facility
SEA—Southeast Asia
SF— Security Forces
SIPRNET—SECRET Internet Protocol Router Network
SSC—small scale contingency
STANAG—standardization agreement
STT—special tactics team
SWA—Southwest Asia
SWB—sanitary wall board
TACAN—tactical air navigation
TACC—tactical airlift control center
TALCE—tanker airlift control element
TEMPER—Tent Extendable Modular Personnel
TM—technical manual
TO—theater of operations; also, technical order
TPFDD—time-phased force and deployment data
TPFDL—time-phased force and deployment list
TRANSCOM—Transportation Command
AFPAM10-219V6 1 FEBRUARY 2006 103

TRICON—three isolation containers


UFC—Unified Facilities Criteria
ULN—unit line number
UPH—unaccompanied personnel housing
USACE—United States Army Corps of Engineers
USAFE—United States Air Forces in Europe
UTC—unit type code
UXO—unexploded explosive ordnance
V—volt
VA—volt-ampere
VAL—vehicle authorization list
VASI—visual approach slope indicator
WRM—war reserve materiel

Terms
agile combat support—An Air Force distinctive capability that encompasses the process of cr eating,
effectively deploying and sustaining US military power anywhere—at our ini tiative, speed and tempo.
Includes provisions and protection of air and space personnel, asse ts and capabilities throughout the full
range of military operations. Also called ACS. (AFDD 2-4)
airbase defense—Those measures taken to nullify or reduce the effectiveness of enemy attacks on, or
sabotage of, airbases to ensure that the senior commander retains the capability to accomplish assigned
missions. (AFDD 2-4.1)
airfield damage repair—The process of using construction eq uipment, tools, portable equipment,
expendable supplies and temporary surfacing materials to provide a minimum operating surface through
expedient repair methods. Also called ADR.
Air Force Civil Engineer Support Agency—A field-operating agency lo cated at Tyndall Air Force
Base, Florida. The Contingency Support Directorate (CEX) acts as the Air Fo rce program manager for
base civil engineer contingency response planning. Also called AFCESA.
air strip—An unimproved surface which ha s been adapted for takeof f or landing of aircraft, usually
having minimum facilities. (JP 1-02)
bare base—A base having minimum essential facilities to house, sustain and support operations to
include, if required, a stabilized runway, taxiways, and aircraft parking areas. A bare base must have a
source of water that can be made potable. Other requirements to operate under bare base conditions form
a necessary part of the force package deployed to the bare base. (JP 1-02).
base denial—The destruction or denial of vital airbase resources so the enemy cannot use them against
friendly forces or for his benefit.
104 AFPAM10-219V6 1 FEBRUARY 2006

base development—The improvement or expansion of the resources and facilities of an area or a location
to support military operations.
base recovery after attack—A theater concept of reco vering a base after conv entional attack where
resumption of flying operations is the first priori ty. Other recovery activities may be conducted
concurrently; however, these activities must not impede the resumption of flying operations.
basic expeditionary airfield resources—Facilities, equipment, and basic infrastructure to support the
beddown of deployed forces and aircraft at austere locations; a critical capability to fielding expeditionary
aerospace forces. Also known as BEAR, the resources include tents, field kitchens, latrine systems, shop
equipment, electrical and power systems, runway systems, aircraft shelters, and water distribution
systems needed to sustain operations. Also called BEAR.
chemical defense—The methods, plans, and procedures involved in establishing and executing defensive
measures against attack utilizing chemical agents.
chemical warfare—All aspects of military operations in volving the employment of lethal and
incapacitating munitions/agents and the warning and protective measur es associated with such offensive
operations. Since riot control agents and herbicides are not considered chemical warfare agents, those two
items will be referred to separately or under the broader term "chemical", which will be used to include all
types of chemical muniti ons/agents collectively. The term "chemical warfare weapons" may be used
when it is desired to re flect both lethal and incapacitating mu nitions/agents of either chemical or
biological origin.
collocated operating base—An active or reserve allied airfield de signated for joint or unilateral use by
US Air Force wartime augmentation forces or for wartime relocation of US Air Force in-theater forces.
Collocated operating bases are not US bases. Also called COB.
combined force—A military force composed of elements of two or more allied nations. (JP 1-02)
command and control—The exercise of authority a nd direction by a properly de signated commander
over assigned and attached forces in the accomplishment of the mission. Command and control functions
are performed through an arrangement of personnel, equi pment, communications, facilities and
procedures employed by a commander in planning, directing, coordinating and controlling forces and
operations in the accomplishment of the mission. Also called C2.
Continental United States—United States territory, including the adjacent territorial waters, located
within North America between Canada and Mexico. Also called CONUS.
contingency—An emergency involving military forces caused by natu ral disasters, terrorists,
subversives, or by required military operations. Due to the uncertainty of the situation, contingencies
require plans, rapid respon se and special procedures to ensure the safety and read iness of personnel,
installations and equipment.
contingency plan—A plan for major contingencie s that can reasonab ly be anticipated in the principal
geographic sub areas of the command.
contingency response plan—A base civil engineer plan of action developed in anticipation of all types
of contingencies, emergencies, and disasters.
conventional weapons—A weapon, which is neither nuclear, biological, radiological, nor chemical.
AFPAM10-219V6 1 FEBRUARY 2006 105

convoy—A group of vehicles organized for the purpose of control and orderly movement with or without
escort protection.
country team—The senior, in-country, US coordinating and supervising body, headed by the chief of the
diplomatic mission, usually an ambassador, and composed of the senior member of each represented US
department or agency, as desired by the chief of the US diplomatic mission. (JP 1-02)
decontamination—The process of making any person, objec t, or area safe by absorbing, destroying,
neutralizing, making harmless, or removing, chemical or biological ag ents, or by removing radioactive
material clinging to or around it.
deploy—To relocate a unit, or an element thereof, to a desired area of op erations or to a staging area.
Deployment will be accomplished wi th all required personnel and equipment. Deployment begins when
the first aircraft, personnel, or item of equipment le aves the home base. The fo rce is deployed when the
last component of the unit has arrived.
explosive ordnance disposal—The detection, identification, on-site evaluation, rendering-safe, recovery,
and final disposal of unexploded explosive ordnance. It may also in clude explosive ordnance that has
become hazardous by damage or deterioration. Also called EOD.
explosive ordnance reconnaissance—Reconnaissance involving the investigation, detection, location,
marking, initial identification, and reporting of su spected unexploded explosive ordnance by explosive
ordnance reconnaissance agents, in order to determine further action. Also called EOR.
forward operating base—An airfield used to support tactical operations without establishing full
support facilities. The base may be used for an extended period. Support by a main operating base will be
required to provide backup support for a forward operating base. Also called FOB. (JP 1-02)
Harvest Eagle—The operational name for an air trans portable package of housekeeping equipment,
spare parts, and supplies required for support of US Air Force genera l-purpose forces and personnel in
bare base conditions. Examples of Harvest Eagle equipment are wate r purification units, tents, and
showers. Each kit is designed to provide soft wall housekeeping support for 550 personnel.
Harvest Falcon—The operational name give n to a se lected package of mobile facility, utility, and
equipment assets required to support forces and aircraft under bare base conditions. These WRM assets
are packaged in air transportable sets to include housekeeping, industrial, initial flightline, and follow-on
flightline. Harvest Falcon sets are designed to support increments of 1,100 personnel and squadron size
aircraft deployments.
initial operating capability—The first attainment of the capability to employ effectively a weapon, item
of equipment, or system of approved specific characteristics that is manned or operated by an adequately
trained, equipped, and supported military unit or force.
joint force—A general term applied to a force composed of significant elements, assigned or attached, of
two or more Military Departments operating under a single joint force commander. (JP 1-02)
joint force air and space component commander—The commander within a unified command,
subordinate unified command, or joint task force re sponsible to the establishing commander for making
recommendations on the proper empl oyment of assigned, attached, and made available for tasking air
forces; planning and coordinating ai r operations; or accomplishing su ch operational missions as may be
assigned. The joint force air and space component commander is given the authority necessary to
accomplish missions and tasks assigned by the establishing commander. Also called JFACC. (JP 1-02)
106 AFPAM10-219V6 1 FEBRUARY 2006

joint force land component commander—The commander within a un ified command, subordinate
unified command, or joint task force responsible to the es tablishing commander for making
recommendations on the proper employme nt of assigned, attached, or made available for tasking land
forces; planning and coordinating land operations; or accomplishing such operational missions as may be
assigned. The joint force land co mponent commander is given the authority ne cessary to accomplish
missions and tasks assigned by the establishing commander. Also called JFLCC. (JP 1-02)
joint force sea component commander—The designated, centralized co mmander for all theater sea
operations. Also called JFSCC. (JP 1-02)
joint force special operations component commander—The designated, centralized commander for
all theater special operations. Also called JFSOCC. (JP 1-02)
joint support plan—A plan for the reception and beddown of forces that is collectively developed by the
host nation, the theater in-place spons or, and the affected augmentation unit. The plan outlines all facets
of operations at a colloca ted operating base to include personnel, facilities, and equipment. Also called
JSP.
main operations base—In special operations a base established by a joint force special operations
component commander or a subordinate special operations component commander in friendly territory to
provide sustained command a nd control, administration, and logistical supp ort to special operations
activities in designated areas; also called MOB. (JP 1-02). Also, a base on which all essential buildings
and facilities are erected and organizational and intermediate maintenance capability exists for assigned
weapon systems. The intermediate maintenance capability may be expanded to support specific weapon
systems deployed to the main operating base. Also called main operating base.
military operations other than war—Operations that encompass the use of military capabilities across
the range of military operations shor t of war. These military actions can be applie d to complement any
combination of the other instruments of national power and occur before, during, and after war. (JP 1-02)
military van—(container)—Military-owned, demountable container, conforming to US and international
standards, operated in a centrally controlled fleet for movement of military cargo.
minimum operating strip—A runway which meets th e minimum requirements for operating assigned
and/or allocated aircraft types on a particular airfield at maximum or combat gross weight. (JP 1-02). Also
called MOS.
mobility—A quality or capability of military forces whic h permits them to move from place to place
while retaining the ability to fulfill their primary mission.
net square feet—The floor area in any building or structure. Sometimes referred to as net usable square
feet.
operation plan—Any plan, except for the Single Integrated Operation Plan, for the conduct of military
operations. Plans are prepared by combatant commanders in response to requirements established by the
Chairman of the Joint Ch iefs of Staff and by comm anders of subordinate commands in response to
requirements tasked by th e establishing unified co mmander. Operation plans ar e prepared in ei ther a
complete format (OPLAN) or as a concept plan (CONPLAN). The CONPLAN can be published with or
without a time-phased force and deployment data (TPFDD) file.
a. OPLAN—An operations plan for th e conduct of joint operations that can be used as a basis for
development of an operation order (OPORD). An OPLAN identifies the forces and supplies
AFPAM10-219V6 1 FEBRUARY 2006 107

required to execute the combatant co mmander’s strategic concept and a movement schedule of
these resources to the theater of operations. The forces and supplies are identified in TPFDD files.
OPLANs will include all phases of the tasked operation. The plan is prepared with the appropriate
annexes, appendixes and TPFDD files as described in the Joint Operation Planning and Execution
System manuals containing planning policies, procedures, and formats.
b. CONPLAN—An operations plan in an abbreviated format that would require considerable expan-
sion or alteration to convert it into an OPLAN or OPORD. A CONPLAN contains the combatant
commander’s strategic concept and those annexes and appendixes deemed necessary by the com-
batant commander to complete planning. Generally, detailed support requirements are not calcu-
lated and TPFDD files are not prepared.
c. CONPLAN with TPFDD—A CONPLAN with TPFDD is the same as a CONPLAN except that it
requires more detailed planning for phased deployment of forces. (JP 1-02)
Overseas Environmental Baseline Guidance Document—A set of objective cr iteria and management
practices developed by the De partment of Defense to protect human health and the environment. (JP
1-02). Contains procedures to establish the final governing standards for a particular geographic area or to
provide standards for environmental compliance where no final governi ng standards have been
established. Also called OEBGD.
potable water—Water that is safe for consumption.
Prime BEEF (Base Engineer Emergency Forces)—A Headquarters US Air Force, major command
(MAJCOM), and base-level program that organizes civil engineer forces for worldwide direct and
indirect combat support roles. It assigns civilian employees and military personnel to both peacetime real
property maintenance and wartime engineering functions.
RED HORSE (Rapid Engineer Deployable Heavy Operational Repair Squadron, Engineer—) —
Air Force units that are wartime-structured to pr ovide a heavy engineer capability . They have a
responsibility across the operational area, are not tied to a specific ba se, and are not responsible for base
operation and maintenance. These uni ts are mobile, rapidly deployable, and largely self-sufficient for
limited periods of time.
reverse osmosis water purification unit—A water purification device that uses a series of membranes
to eliminate impurities. It is capable of removing dissolved minerals. Also called ROWPU.
sanitary sewer—A sewage system that carries only domestic sewage.
Standardization Agreement (NATO)—The record of an agreement among several or all of the member
nations to adopt like or similar military equipmen t, ammunition, supplies a nd stores; and operational,
logistic and administrative procedur es. National acceptance of a NA TO allied publication issued by the
Military Agency for S tandardization may be record ed as a S tandardization Agreement. Also called
STANAG.
standoff—A physical distance separation to minimize the damage done by hand-held weapons.
survivability—Capability of a system to a ccomplish its mission in the face of an unnatural (man-made)
hostile, scenario-dependent environment. Surviv ability may be achieved by avoidance, hardness,
proliferation, or reconstitution (or a combination).
108 AFPAM10-219V6 1 FEBRUARY 2006

time-phased force and deployment data—The Joint Operation Planni ng and Execution System
database portion of an operation plan; it contains time-phased force data, non-u nit-related cargo and
personnel data and movement data for the operation plan, including the following:
a. In-place units;
b. Units to be deployed to support the operation plan with a priority indicating the desired sequence
for their arrival at the port of debarkation;
c. Routing of forces to be deployed;
d. Movement data associated with deploying forces;
e. Estimates of non-unit-related cargo and personnel movements to be conducted concurrently with
the deployment of forces;
f. Estimate of transportation requi rements that must be fu lfilled by common-user lift resources as
well as those requirements that can be fulfilled by assigned or attached transportation resources;
also called TPFDD. (JP 1-02)
time-phased force and deployment list—Appendix 1 to Anne x A of the operation plan. It identifies
types and/or an actual unit requir ed to support the operation plan and indicates origin and ports of
debarkation, or ocean area. It may also be generated as a computer listing from the time-phased force and
deployment data. Also called TPFDL. (JP 1-02)
unimproved surface—A takeoff and landing surface that has not been improved through paving with
asphalt, concrete, or other durable substance; for example, a grass or dirt landing strip.
unit line number—A seven-character alphanumeric code that describes a unique increment of a unit
deployment, i.e., advance party, main body, equipment by sea and air, reception team, or trail party, in a
Joint Operation Planning and Execution System time-phased force and deployment data. (JP 1-02)
unit type code—A Joint Chiefs of S taff developed and assigned code, consisting of five characters that
uniquely identify a type unit. (JP 1-02). Also called UTC.
United States Transportation Command—The unified command with the mission to provide strategic
air, land and sea transportation for the Department of Defense, across the range of military operations.
war reserve materiel—Materiel required in addition to primary operating stocks and mobility equipment
to attain the operational objectives in the scenarios authorized for sust ainability planning in the Defense
Planning Guidance. Broad categories are: consumables associated with sortie generation (to include
munitions, aircraft external fuel tanks, racks, adapters, and pylons ); vehicles; 463L systems; materiel
handling equipment; aircraft engines; bare base assets; individual clothing and equipment; munitions; and
subsistence. Also called WRM.
AFPAM10-219V6 1 FEBRUARY 2006 109

Attachment 2

RECOMMENDED CE UTC BASED ON MISSION REQUIREMENTS

Table A2.1. Recommended CE UTCs for One Fighter Squadron Deployment.


Low Threat Medium Threat High Threat
UTC # Personnel Total # Personnel Total # Personnel Total
4FPEA 1 55 55 1 55 55 1 55 55
4FPEP 2 25 50 2 25 50 2 25 50
Traditional CE 105 105 105
4FPFJ 3 2 6 3 2 6 3 2 6
4F9FN 1 1 1 1 1 1 1 1 1
4F9FA 1 1 1 1 1 1 1 1 1
4F9FP 11 6 66 11 6 66 11 6 66
Fire Fighters 74 74 74
4F9DA 1 2 2
4F9DB 1 2 2 2 2 4 2 2 4
4F9DC 2 3 6 7 2 14 11 2 22
Readiness 8 18 28
4F9X1 1 6 6 1 6 6 1 6 6
4F9X2 1 4 4 1 4 4 2 4 8
4F9X3 1 2 2 1 2 2 1 2 2
4F9X9 1 2 2 1 2 2
4F9XA 1 2 2 2 2 4
EOD 12 16 22
Total Personnel 199 213 229

Table A2.2. Recommended CE UTCs for a 2 Fighter Squadron Deployment.


Low Threat Medium Threat High Threat
UTC # Personnel Total # Personnel Total # Personnel Total
4FPEA 1 55 55 1 55 55 1 55 55
4F9EB 1 42 42 1 42 42 1 42 42
4FPEP 2 25 50 2 25 50 2 25 50
4F9AP 1 4 4 1 4 4 1 4 4
Traditional CE 151 151 151
4FPFJ 3 2 6 3 2 6 3 2 6
4F9FN 1 1 1 1 1 1 1 1 1
4F9FA 1 1 1 1 1 1 1 1 1
4F9FP 11 6 66 11 6 66 11 6 66
Fire Fighters 74 74 74
4F9DA 1 2 2
4F9DB 1 2 2 2 2 4 2 2 4
4F9DC 3 2 6 7 2 14 11 2 22
Readiness 8 18 28
4F9X1 1 6 6 1 6 6 1 6 6
4F9X2 1 4 4 1 4 4 2 4 8
4F9X3 1 2 2 1 2 2 1 2 2
4F9X9 1 2 2 2 2 4
4F9XA 1 2 2 1 2 2
EOD 12 16 22
Total Personnel 245 259 275
110 AFPAM10-219V6 1 FEBRUARY 2006

Table A2.3. Recommended CE UTCs for a 3 or More Fighter Squadron Deployment.


Low Threat Medium Threat High Threat
UTC # Personnel Total # Personnel Total # Personnel Total
4FPEA 1 55 55 1 55 55 1 55 55
4F9EB 2 42 84 2 42 84 2 42 84
4FPEP 2 25 50 2 25 50 2 25 50
4F9AP 4 2 8 4 2 8 4 2 8
Traditional CE 197 197 197
4FPFJ 3 2 6 3 2 6 3 2 6
4F9FN 1 1 1 1 1 1 1 1 1
4F9FA 1 1 1 1 1 1 1 1 1
4F9FP 11 6 66 11 6 66 11 6 66
Fire Fighters 74 74 74
4F9DA 1 2 2
4F9DB 1 2 2 2 2 4 2 2 4
4F9DC 3 2 6 7 2 14 11 2 22
Readiness 8 18 28
4F9X1 1 6 6 1 6 6 1 6 6
4F9X2 1 4 4 1 4 4 2 4 8
4F9X3 1 2 2 1 2 2 1 2 2
4F9X9 1 2 2 2 2 4
4F9XA 1 2 2 1 2 2
EOD 12 16 22
Total Personnel 291 305 321
AFPAM10-219V6 1 FEBRUARY 2006 111

Attachment 3

MAIN OPERATING BASE AUTHORIZED FACILITIES/CONSTRUCTION STANDARDS

A3.1. Main Operating Base (MOB) Facilities. MOBs are occupied by a wing or larger unit (US popu-
lation of 500 or more) and are cont inuously operated camps with comma nd, staff and logistic functions.
The standards outlined in this sect ion apply to all MOBs. Since the in itial construction standards consist
mainly of unit organic equipment or bare base depl oyable assets, the discussion below concentrates pri-
marily on temporary construction standards.

A3.2. Roads. Primary roads identified by commanders on ba se camp master plans are authorized for
paving with asphalt. Primary roads ar e considered as major arteries th at support the majority of vehicle
traffic through the base. Concrete turning pads are authorized to prevent damage to asphalt roads. Second-
ary and perimeter patrol roads are to be surfaced with gravel.

A3.3. Dining Facilities. Dining facilities will provide 640 sq ft of dining room space and 320 total sq ft
of kitchen, admin and storage space per 750 assigned personnel. Adequate space for cleaning, latrine, and
clothes changing for local national kitchen staf f will be provided. Sanitary wall board (SWB) or other
waterproof material will be used in the kitchen and latrine areas. Lo ading dock can be concrete, asphalt,
or treated lumber. Portable sanitary hand-washing stations will be located at the entrance of the dining
facility.

A3.4. Lodging Standards. Table A3.1. gives the authorized square footage for unaccompanied person-
nel housing (UPH) space for deployed military personnel, government mission essential civilians, and
assigned DOD contractors. Table A3.2. gives the authorized s quare footage for UPH billeting s pace for
civilians and contractors who are deployed greater than 6 months. Table A3.3. gives the authorized square
footage for UPH billeting space for military personnel deployed greater than six months.

Table A3.1. Contingency Lodging Standards.


Number Per
Number Per
Standard TEMPER
Category Standard Modular
Tent (or equivalent)
(8’ x 20’)
(16’ x 32’)
E1-E5; GS-5 & below, NF 1/2; Civilian WG 1-11 or
6 2
WL 1-5; Contracted Laborers
E6-E7; O1/2; GS 6-9, NF 3;
4 2
Civilian WS 1-7
E8, O3/4; GS 10-12, NF4; 3 2
E-9, O5/6; GS 13-15, NF5 2 1
O7; SES; NF6 1 1
112 AFPAM10-219V6 1 FEBRUARY 2006

Table A3.2. Housing Standards for Long-term Civilian/Contractor Employees (>6 mo.s).
Number Per Standard
TEMPER Tent/SEA hut
Category Container
(or equivalent) (16’ X 32’)
(8’ X 20’)
GS 8 & Below; NF 1/2; 2 Personnel/Room (16’ x 16’)
1
Civilian WG 1-11 or WL 1-5 with 2 Rooms/SEA hut
GS 9-12; NF 3; Civilian WS 1-7; 1 Personnel/Room (8’ x 16’) with
1
Educators Schedule C1-3 4 Rooms/SEA hut
GS 13 & Above; NF4; Educators Schedule 1 Personnel/Room (16’ x 16’)
C4 & Above; D-F, M-O and Teaching with 2 Rooms/SEA hut 1
Principals – Schedule L

Table A3.3. Housing Standards for Long-term Military Personnel (>6 Months).
TEMPER Tent/SEA hut Number Per Standard
Category
(or equivalent) (16’ x 32’) Container (8’ x 20’)
2 Personnel/Room (16’ x 16’) with
E1-E6 1
2 Rooms/SEA hut
E7-E8, WO1/2, CW3/4, 1 Personnel/Room (8’ x 16’) with
1
O1-O4 4 Rooms/SEA hut
1 Personnel/Room (16’ x 16’) with
E-9, CW5, O5-O6 1
2 Rooms/SEA hut
1 Personnel/Room (16’ x 32’) with
O7; SES; NF6 1
1 Room/SEA hut

A3.4.1. The US Army utilizes the S outh-East Asia Hut (SEA hut) as its base module for temporary
and semi permanent construction standard billeting. The SEA hut is a wood framed, elevated building
with exterior covered walkways that is utilized for billeting. SEA Huts are normally grouped together
and are collocated with a latrine and shower huts. Standard SEA huts are 512 square feet, with a stan-
dard SEA hut cluster having five bays and a latrine (2,944 sq ft). SEA hut structures provide a greater
degree of safety and comfort than hard backed GP Mediums or TEMPER tent. SEA huts may be sub-
divided for individual rooms and common areas based on grade/rank of inhabitants. SEA huts provide
an expedient and more cost effective solution than contracted modular facilities as they are easily fab-
ricated by either contract or military labor. SEA huts organized in this manner minimize the distance
personnel are required to walk to shower and latrine facilities and increases unit cohesion by maintain-
ing company, platoon and squad integrity.
A3.4.2. Private (modular or partitioned SEA hut) and semi-private billeting space for the housing of
long-term (exceeding 6 months) government civilian/ all contractor employees and airmen should be
considered at the earliest possible time. The Theat er Engineer (A7) will de termine grade equivalen-
cies for DOD contractor employees. The MSG Commander is delegated the responsibility to resolve
private room availability for long-term civilian/contractor employees and airmen at their assigned air-
base.
AFPAM10-219V6 1 FEBRUARY 2006 113

A3.4.3. All 110/220 volt electric outlets in billeting facilities will be protected by not more than 30
amp ground fault circuit interrupter. Highest protection level will be selected to protect against electric
shock hazard. Where practical, billeting should be c onfigured into clusters with shower, shave and
latrine units collocated within the clusters. Standard 5’ (minimum width) covered walkways should be
provided to allow personnel to walk under cover to latrine units. Sufficient space will be maintained
between facilities to allow fire trucks and other safety vehicles driving space. Carpet is not authorized
in living or office areas.
A3.4.4. Minimum authoriz ed government provided furniture per deployed person (units presently
exceeding this standard are authorized to keep the excess furnishings on hand).
A3.4.4.1. One bed, bunk/single.
A3.4.4.2. One foot locker.
A3.4.4.3. One wall unit with shelves and hanging area.
A3.4.4.4. One desk with chair.
A3.4.4.5. One dresser.
A3.4.4.6. Locally built shelves made of plywood.
A3.4.5. Surge Housing. All base camps will maintain the ability at all times to house 10% of total
population as transients and surges. During surge periods that exceed 10%, Tier II tents (maximum)
will be used for housing. Tier level for tents is as follows.
A3.4.5.1. Tier I consists of GP Medium field tents or equivalent (TEMPER, 16’ x 32’) with ply-
wood floor panels.
A3.4.5.2. Tier II consists of a GP Medium field tent or equivalent (TEMPER) with plywood floor
panels, two electric light outlets, two electrical outlets, and space heaters.
A3.4.5.3. Tier III consists of a GP Medium field tent or equivalent (TEMPER), full wooden frame
for tent, plywood panel sidewalls, raised insulated flooring, four electric light outlets, eight elec-
trical outlets, and Environmental Control Units (ECUs).
A3.4.6. VIP/DV Billets. Each MOB hosting a JTF or Combatant Commander is authorized 2,944 sq
ft (or 6 TEMPER tent equivalent) for VIP/DV billets. All other MOBs are authorized 512 sq ft (or one
TEMPER tent equivalent) for VIP/ DV billets.

A3.5. Latrines and Shower Facilities. Toilet and shower facilities will be lighted, heated and equipped
with hot and cold water . SWB is the preferred wall covering for latr ines. Sheetrock, if used, must be
waterproof, with a waterproof finish for cleaning.
A3.5.1. A shower head/population ratio of 1:10 is the goal for all base camps.
A3.5.2. A toilet/population ratio of 1:10 is the goal for all base camps.

A3.6. JTF, CFACC or equivalent HQ. The size of the HQ is situati on dependent, based on the stan-
dards in Table A3.4. The component commander has approval authority over the final de sign. The HQ
should include, but is not limited to:
A3.6.1. Standard FE-6 Chain Link fence with outrigger.
114 AFPAM10-219V6 1 FEBRUARY 2006

A3.6.2. Gravel parking lots (asphalt parking authorized when mission considerations allow).
A3.6.3. Exterior security lighting that can be turned off using a single emergency switch that is avail-
able to the manned security forces entry control point.
A3.6.4. Sensitive Compartmented Information Facility (SCIF). Constructed to initial standards and
upgraded to comply with Director of Central Intelligence Directive 1/21, SCIF Construction.
A3.6.5. A facility to house the AOC operation.
A3.6.6. Modular/SEA hut style buildings for primary staff offices.
A3.6.7. Communications platforms and shelters.
A3.6.8. Personal protection bunkers.
A3.6.9. Entry control point and guard shacks.

Table A3.4. Utilization Guidelines for Office Space.


PERSONNEL MAXIMUM NSF/PERSON
Private Offices
Brigadier Generals (O7) and above 300
Colonel, O5 Commanders, GS-15, Command CMSgt 200
O5, O4 Commanders, GS-13/14, Wing Command Chief 150
MAJ, O3 Commanders, GS-12, CMSgt (E9), 1st Sergeants (Any Grade) 100
Open Offices
GS-9/11, E8, O1-O3 110
GS-7, E7 90
E1-E6, GS6 and Below 60

NOTES:
- Planning numbers only apply to military units/organizations and personnel. Admin space for MWR and
commercial functions are discussed separately.
- To calculate total building size, add an additional 40% for central files, hallways, storage, copier, mail,
and conference rooms.

A3.7. Supply Warehouse. Each task force is authorized a suppl y warehouse facility. The size of the
facility is dependent upon equipmen t density, base population and cla sses of supply to be supported.
Warehouses are for long-term storage. Military Van (MILVAN) containers are for transportation only.
MILVANs will be unloaded promptly, less than 7 working days, and returned to the transportation system.
Leased MILVANs will never be held for storage or modified; holes cut or parts welded on. Warehouses
will not be used for long-term housing of excess government property. Each wing is authorized a 10,000
sq ft warehouse.
AFPAM10-219V6 1 FEBRUARY 2006 115

A3.8. Individual Equipment Unit (IEU) Warehouse. Each air expeditionary wing is authorized an
IEU with a gravel holding yard with chain link fence. The IEU facility space is authorized at a rate of
1,000 sq ft per 1,000 personnel supported.

A3.9. Finance and Personnel Support. Each air expeditionary wing is authorized a Finance Center and
Military Personnel Flight (MPF) facility. Finance and MPF are each authorized 1,024 sq ft. The Finance
Flight requires a 5’x 8’ pay cage, an 8’x 9’ walk-in vault, and a customer service area.

A3.10. Laundry Collection/Distribution Point. This operation is authorized 512 sq ft of space per 500
authorized users.

A3.11. Air Expeditionary Wing Headquarters (AEW HQ) Facilities. A maximum of 5,376 sq ft of
space is authorized for the AEW HQ. AEW HQ facilities are also authorized the following:
A3.11.1. Gravel parking lots (asphalt parking authorized when mission considerations allow).
A3.11.2. Exterior security lighting that can be tu rned off using a single emer gency switch that is
available to the manned security forces entry control point.
A3.11.3. Modular or SEA hut style facility construction standards.
A3.11.4. Personnel protection bunkers for AEW Group HQ Facilities. A maximum of 3,840 sq ft of
space is authorized for housing the HQ elements of each AEW group command staff (mission support
group, operations group, maintenance group, and medical group). This space is intended to house the
group’s command staff, mailroom, group administrative functions, executive officer, command chief,
first sergeant, and other associated support elements.
A3.11.5. Squadron HQ Facilitie s. Each AEW squadron is authorized a maximum of 1,536 sq ft of
space for the command staf f, administrative office, orderly rooms, conference, storage, and supply
rooms.

A3.12. Aviation Facilities. Runways, taxiways, parking aprons, maintenance areas, and helipads should
be sited, planned, and constructed IA W UFC 3-260-01, Design: Airfield and Heliport Planning and
Design.

A3.13. Helicopter Pads. Helicopter landing and parking pads will initially be AM-2 matting surfaced to
prevent foreign object damage (FOD). Helicopter landing and parking pads will be concrete, with asphalt
aprons. The pads will have adequate grounding rods a nd tie-downs. All soil in the immediate area of the
pads will be planted in grass or gravel large enough not to become FOD. Hot pads will have HESCO bas-
tions or similar material to minimize damage from accidental weapons discharge.
A3.13.1. Lighted Landing Pad. One helicopter landin g pad on each base camp will be outfitted with
nighttime landing lights. This will facilitate landing of helicopters for emergency operations.
A3.13.2. Vehicle Parking Area. An 11,000 sq ft vehicle graveled parking area is authorized for heli-
copter pads. This area is intended for the parking of service and maintenance vehicles associated with
helicopter operations.
116 AFPAM10-219V6 1 FEBRUARY 2006

A3.14. Forward Area Refuel Point. If pipe is used it will be doubl e walled stainless steel with return
line. Aviation quality fuel filters will be used. Pads will be concrete, as will any area where fuel spills are
likely. Blast protection will be installed around the fueling pads.

A3.15. Control Tower. Control tower will be of suf ficient size and height for unobscured vision of the
entire airfield. The tower can be either wood or metal, grounded, with adequate priming and painting to
prevent weather damage and minimize slip hazard in bad weather.

A3.16. Squadron Operations. 10,000 sq ft of space is authorized for Squadron Operations.

A3.17. Aviation Maintenance. Total number of aviation clamshell tents is based on mission require -
ments. Tow ways will be paved from the aprons, hardstands, and helipads to the maintenance clamshell
tents. (Aviation ground vehicle maintenance considered separately under Maintenance Facilities).

A3.18. Helicopter and Aviation Wash Racks. Wash racks for helicopter a nd aircraft are authorized.
The wash racks will ha ve a storage tank and concre te pad with a drainage syst em equipped with an oil
water separator.

A3.19. Communications Compound/Network Control Center (NCC). Each AEW is aut horized one
Communications Compound/NCC. The facility size requirement is dependent upon the wing organization
and supported units and missions. Bases that host JTF or higher level headquarters functions will require
a significantly larger area. Consult theater level CE and communications planners for further direction.
Basic planning guidelines are as follows: up to 1,500 main operating base (MOB) personnel = 2,944 sq ft;
1,500 to 3,000 personnel = 4,736 sq ft; 3,000 to 5,000 personnel = 6,208 sq ft; greater than 5,000 person-
nel = 9,152 sq ft. NCC compounds are authorized the following:
A3.19.1. Standard FE-6 Chain Link fence with outrigger.
A3.19.2. Gravel parking lots (asphalt parking authorized when mission considerations allow).
A3.19.3. Exterior security lighting that can be tu rned off using a single emer gency switch that is
available to the manned security forces entry control point.

A3.20. Expeditionary Medical Support (EMEDS) System. For final planning consult with the theater
medical planner to determine which level of EMED S will be deployed. The la rgest deployed EMEDS
planning factor is for an EMEDS+ 114 theater hospital and staging area. EMEDS+ 114 requires 400-kW
of power, 11,000 gallons of potable water per day, 675 pounds of ice per day, and produces 11,286 gallons
of waste water and 4,500 pounds of solid waste per day. Additional information regarding EMEDS plan-
ning can be found in AFPAM 10-219, Volume 5.
A3.20.1. Special Medical Requirements. The follow ing spaces will include a sink with running hot
and cold water: examination rooms, trauma/treatment rooms, laboratory and dental treatment rooms.
Dental sterilization radiology rooms will require lead shielding appropriate to the type of radiology
equipment utilized. This includes all four walls and servicing door (lead shielded). The minimum
thickness level and specifications for installation may be determined through consultation with the
supporting Health Facilities Planning Office (HFPO) or Preventive Medicine Office. Specific consid-
eration should be given to ensure ventilation from the x-ray development, dental sterilization and lab-
oratory spaces. Finished materials should support infection control measures by incorporating smooth
AFPAM10-219V6 1 FEBRUARY 2006 117

washable surfaces with limited seams throughout. All interior partitions shall be constructed from the
floor to the underside of the ceiling and will not be undercut or left open at the top. Lighting and elec-
trical requirements for each sp ace will be coordinated with HFPO in consideration of existing and
planned medical equipment.
A3.20.2. Air Force Transportable Hospital (AFTH) Location. Locate medical facilities on the base to
support the command’s mission requirements. Consideration should be given to daily sick call opera-
tions and the relative proximity to the troop population and emergency medical operations (evacuation
operations both into and out of th e clinic by ground and air). The st andard base camp clinic will be
sized to meet the medical and dental care expectat ions of the population st ipulated in the operations
order and supported by the medical staff.

A3.21. Maintenance Facilities. Each AEW should strive to consolidate maintenance activities as much
as possible. A facility size at a rate of 1,840 sq ft per AEW Group supported by the facility is authorized.
If a squadron-sized facility is required, then a 1,200 sq ft maintenance facility is authorized. These facili-
ties will be equipped with inside and outside lights, as well as exhaust fans and compressed air.

A3.22. Maintenance (MX) Administration. 640 sq ft of office space is authorized for each MX flight.

A3.23. Maintenance Parking Area. Each MX group is authorized a parking area of a suf ficient size to
accommodate outside maintenance of wing vehicles. Pads should be large enough to accommodate the
largest vehicle maintained plus a recovery vehicle. Maintenance pads for tracked and wheeled vehicles (if
supported by base MX) will be constructed from concrete. Maintenance pads will be located near the unit
maintenance bay, usually as aprons to a consolidated maintenance facility.

A3.24. Fuel Storage. Above ground fuel tanks are authorized for the storage of bulk fuels. Fuel storage
bladders will be phased out as above ground storage tanks become available. Tanks will be constructed
IAW existing environmental regulations and insta lled per manufacturer recommendations. Where it is
necessary to use fuel bladders, they will be sited IAW environmental guidelines and will be surrounded by
a constructed containment structure large enough to contain the maximu m amount of fuel in the bladder
to contain any spillage. Fuel truck parking will have secondary containment pads equipped with a catch-
ment sump and grounding rods.

A3.25. Hazardous Waste Collection Points. Each AEW Group will have a covered hazardous waste
collection point, built on an elev ated pad, to be out of contact w ith ground surface and have permanent
secondary containment system. AEW commanders may authorize additional collection points at bases as
required to support their mission.

A3.26. Hazardous Material Warehouse. Each AEW is authorized a hazardous materials warehouse at
a size rate of 1,000 sq ft per 1,000 assigned personnel.

A3.27. Parking Lots. Parking lots should be constructed usi ng well-graded rock and compacted, with
engineered slope and drainage to minimize weather effects and increase safety. Avoid loose rocks greater
than 30-40. The purpose is to minimize damage to gravel parking lots and to prevent damage to vehicles
from flying rocks. Wooden parking lot stripes are not authorized. Concrete turning pads are authorized for
parking of tracked vehicles. Chain link fences around motor pools are not authorized unless they are part
of the perimeter fence.
118 AFPAM10-219V6 1 FEBRUARY 2006

A3.28. Direct Support Maintenance. Direct Support Maintenance and Allied Trades is authorized
2,050 sq ft per 1,000 MOB personnel supported, including admin space.

A3.29. Kennels. Military working dogs are authorized a lighted, climate controlled kennel and an exer-
cise yard. Kennels will have indivi dual stalls (dog run) for each animal an d a sealed concrete floor for
health reasons and ease of cleaning. Kennel floor drains should be connected to a sewer system. The ken-
nel-planning factor is 145 sq ft per dog, which includes kitchen, tack room and interior dog run, (36 sq ft
per dog). Exterior dog runs should be 48 sq ft per dog, with a connecting guillotine-type door to the inte-
rior dog run. Additional information is located in AFI 31-202, Military Working Dog Program.

A3.30. Morgue. Each morgue is authorized 512 sq ft of workspace an d a refrigeration van. Privacy
screen is authorized around the entire facility.

A3.31. Defense Reutilization and Marketing Office. One recycling facility per task force is authorized
at a size of one sq ft per MOB employee (e.g. soldier, civilian, host country national). It should have con-
crete or asphalt floor capable of handling forklifts.

A3.32. Ammunition Supply Point (ASP). The ASP, if applicable to the base camp, will not house
ammunition in containers. If the mission dictates containers be temporarily used, then only DOD-owned
containers will be used. Any DOD containers used must be a temporary arrangement until bunkers can be
constructed. The ASP will be constructed with bunkers an d space allocations (safety requirements) to
meet the net explosive weight of the planned stored ammunition. Consult theater CE and SFS planners for
additional guidance.

A3.33. Basic Load and Captured Ammunition Holding Areas. Ammunition holding areas will be
constructed in accordance with AR 385-64, U.S. Army Explosives Safety Program, and DA PAM 385-64,
Ammunition and Explosives Safety Standards. Ammunition holding areas will have containment berms, a
fenced and lighted perimeter, graveled access roads and lightning protection for the entire area. Ammuni-
tion will be stored in protective st ructures such as MILVAN containers that are out of con tact with the
ground (on wooden sleepers or on concrete foundations).

A3.34. Wash Rack. Each MOB is authorized at minimum one 45’ long elevated vehicle wash rack, one
100’ flat wash rack and one container wash rack equipped with oil/water separators. Wash racks shall be
designed to fit the largest and heaviest vehicles in the fleet.

A3.35. Fire Protection. Provide Fire and Emergency Response services in accordance with DODI
6055.6, DoD Fire and Emergency Services Program; DODI 2000.18, DoD Installation Chemical, Biolog-
ical, Radiological, Nuclear and High-Yield Explosive Emergency Response Guidelines; AR 420-90,
National Fire Protection Association Codes, and the following standards:
A3.35.1. Fire Departments will be established only at base camps with a population of 1,000 or more
US personnel (permanent residents), or where US Air Force flight operations and/or Army
rotary-wing flight operations dictate based on flightline response requirements. Refer to t heater CE
Fire Planner to dictate requirements as they are based on assigned weapons systems.
A3.35.2. Base camps that do not meet the criteria above will use appropriate portable fire extinguish-
ers. Fire and emergency personnel will be properly trained on the use of extinguishers.
AFPAM10-219V6 1 FEBRUARY 2006 119

A3.35.3. The AOR Fire Chief, in coordination with the theater CE (A7), will determine the type and
number of fire extinguishers required.
A3.35.3.1. For MOBs with fire departments the following applies:
A3.35.3.2. The number and type of fire apparatus for structural and aircraft rescue and fire fight-
ing (ARFF) response will be determined IAW DODI 6055.6, DOD Fire Protection Program, AR
420-90, Fire and Emergency Services, and NFPA Codes.
A3.35.3.3. Fire and emergency services will be available 24 hours a day, seven days a week.
A3.35.3.4. Construction of one fire station per base camp is author ized to be built to house fire
fighters and fire trucks, as recommended by the theater A7 and theater Fire Chief.
A3.35.3.5. Fire fighting facilities will be co-located and fire fighters should live at the fire station
to reduce response time, if appropriate and determined by the theater A7.
A3.35.3.6. One classroom/library is required for firefighting training, fire prevention safety
inspection training, and to maintain regulations, NFPA Codes, International Fire Service Training
Association Training Materials, etc.
A3.35.3.7. Records holding area is required of training, inspections, and fire response activities.
A3.35.3.8. One fire control center per base camp is authorized.
A3.35.3.9. Fire Protection and fire prevention staffing will be in accordance with AR 420-90 and
DODI 6055.6.
A3.35.3.10. For fire fighting pu rposes, base camps are authoriz ed one 5,000-gallon tanker for
water storage. The tanker will be capable of tapping i nto the potable water storage. Centrally
located standpipes for filling the tankers should be adde d to the potable wate r system to fill the
tanker. Manning of ARFF vehicles will be during airfield operational hours.
A3.35.3.11. Due to intrusion and security concerns, SCIF Facilities will use a battery operated fire
alarm and detection system. Central reporting lines and radio transmitted alarms will not broadcast
through the SCIF shielding and/or pose a threat for release of secure compartmental information.

A3.36. Utilities. Utility systems shall be designed based on current applicable military handbooks, tech-
nical manuals and guidance. Engineering calculations will be used to size the system. All utility designs
will be approved by Depu ty Chief of Staff for Engineering (DCSENG), United States Army, Europe
(USAREUR) before construction begins.
A3.36.1. Electric Power. Where economically supportable and practicable, base camp power grids
will be connected to commercial power . Smaller or remote base camps that cannot be economically
connected to the commercial power grid are author ized to construct central power plants capable to
support 125% of camp maximum demand load, or use distributed generators of sufficient capacity to
support maximum demand loads. An economic analysis should be co mpleted to determine the most
cost effective power plant/generator solution. In all cases, critical fa cilities will be identified in the
master plan by the mission support group commander and have back-up generator power. Non-critical
facilities that have stand-alone distr ibuted generators will not have any b ack-up generator power. A
maximum of 10% of total generators (one minimum) serving non-criti cal facilities are authorized as
reserve generators that can be placed in service quickly in case a generator serving a non-critical facil-
ity has a major failure.
120 AFPAM10-219V6 1 FEBRUARY 2006

A3.36.1.1. Determination of appropriate size for generators is not a simple task, as many genera-
tors are typically over-sized for loads served. Sizing of generators shall include an evaluation of
actual and expected loads considering appropriate demand and load diversity factors, along with a
review of any historical demand load data for similar base camps. Engine-generator sets may need
de-rating to account for use of JP -8 fuel (rather than diesel), altitude, temperature and starting
requirements for any large load specialized equipment (e.g., hospital X-ray machines). In many
cases, load banks have been used to ensure adequate performance of under loaded engine-genera-
tor sets. Under loaded engine-generators may operate unsatisfactorily, fail prematurely, and
require more maintenance and overhauls due to excessive formation of carbon deposits in the
engine. The use of load banks and premature engineoverhauls can be avoided if engine-generators
are right-sized for the load. A complete and through analysis of the affected electrical system must
be accomplished to ensure power plant requirements are properly defined. Leasing of generators
for periods greater than six months is generally not cost effective.
A3.36.1.2. Where stand-alone distributed generators are the main power source, they will be sized
so no generator set is loaded less than 50%.
A3.36.1.3. Electrical power systems for the MOBs and forward operating bases can be composed
of sub-transmission lines to main substations; distribution lines to distribution substations; utiliza-
tion lines to distribution transformers; and gene rators to provide emergency, stand-by and/or
prime power for mission base camp facilities. Application of the new Distributed Generation (DG)
Technology other than the matured Internal Combustion (IC) Genset (diesel engines) technology,
maybe considered if economically feasible, environmental impacts and emissions are critical, and
alternative fuels for DG applications are available. DG including IC Gensets allow cogeneration
(combined heat and power). The waste heat from power generation may be recovered and used to
offset costs. Today, the capital cost of an IC Genset is 200-350 $/Kilowatt (kW) rating for diesel
and 400-1000 $/kW for natural ga s. Operations and Maintenan ce (O&M) costs for both types
excluding fuel are 0.01$/kWh/yr. Currently, DGs have high initia l costs; however they are the
future for power generation.
A3.36.1.4. At end state or earlier, electric power supply, transformers 400/208 volts 50 Hertz (Hz)
and/or 230/120 volts 50 Hz should be used in lieu of 208/120 vo lt generators. 50 Hz to 60 Hz
rotating or static (preferred) fre quency converters should be us ed in lieu of 60 Hz generators.
Applicable electrical industry codes, standards, or publications will apply to equipment, materials
and construction covered in th e Base Camp Facilities S tandards. The minimum requirements of
the latest version of NFPA-70, National Electrical Code, and American National Standards Insti-
tute C2, the National Electrical Safety Code, will be met and exceeded when requirements that are
more stringent are specified an d/or directed. These sta ndards provide policy and guidance for
main and forward base camp design criteria and standards for electrical power supply and distri-
bution systems. Requirements of Military Handbook 1191, Medical and Dental Treatment Facility
Criteria, and other medical facilities design office criteria will be considered for power arrange-
ments for medical facilities.
A3.36.1.5. All facilities th at are used for or c ontain housing, office space, or other a reas that
require the use of electric devices and/or equipment will be supplied with sufficient fixed electri-
cal outlets. SEA huts used for housing will have eight fixed duplex electrical outlets. All facilities
that require illumination to perform tasks or in order to provide a safe living, working, or recre-
ational environment will be equipped with sufficient electric lights.
AFPAM10-219V6 1 FEBRUARY 2006 121

A3.36.2. Heating, Ventilation & Air Conditioning (HVAC). At a minimum, all facilities where per-
sonnel live, work or recreate will be provided heating. Install ECUs that provide heating and cooling
capabilities whenever possible. Large facilities such as dining facilities an d expeditionary hospitals
should be provided with central HVAC systems. Camps will utilize installed central heating/cooling
systems where already existing or as economically feasible. Storage areas will only be provided heat-
ing/cooling services as needed to address specific storage requirements of designated facilities types.
When temporary and semi-permanent facilities such as SEA huts utilize ECUs, they will be sized to
ensure delivery of heating/cooling as follows.
A3.36.2.1. The standard for maximum indoor temperature in winter is 68oF and minimum indoor
temperature in summer is 78oF. Temperature strips are installed in administrative areas and living
spaces wherever ECUs are utilized.
A3.36.2.2. Where central heating/cool ing systems are pre-existing or have been installed for all
other facilities (e.g. hangars, recreation centers, gyms, dining facilities, medical facilities, etc) the
support staff will monitor installed thermostatic controls to maintain established temperature stan-
dards.

A3.37. Water. The order of preference for potable water at MOBs is:
A3.37.1. Joint Contracting Center (JCC) will contract to tie into local municipalities if it is economi-
cally feasible and meets Army health and force protection standards. The installation of a water puri-
fying station, such as a UV-60, Transportable Water Purification and Disinfection System, should be
considered in the start up cost.
A3.37.2. Installation of wells for potable water is authorized. Site planning should consider installing
water storage distribution systems if economically feasible. A mi nimum of two wells per camp, one
primary and one for back up are au thorized. The expense of mobilization for drilling equipment rep-
resents a major cost of providing a well. Therefore, local contractors should be hired to perform well
drilling. Additional wells may be dr illed based on the capability of the first two wells to supply the
required amount of water. Wells should be within camp boundaries.
A3.37.3. The least desira ble option is trucking po table water and/or bottle water to the base camp.
The cost of purchasing and maintaining the trucks, along with drivers and the reoccurring cost of bot-
tle water to include purchase, transport, storage, and waste disposal needs should be included in the
initial cost estimate.

A3.38. Wastewater Treatment Plant. The initial assessment for a base camp should have a design for
the installation of a wastewater plan t based on projected population si ze of the camp, to include Allied
forces and local nationals . Coordination with JCC s hould be utilized to dete rmine if connection to a
municipal wastewater treatment plant is economically feasible and environmentally sound. Upgrades to
existing sewage treatment plants are authorized to allow for effective treatment of waste being generated
on that facility. Connection to local waste treatment facilities should be made only if the facilities meet
Army standards. Upgrades will be limited to the expansion of the plant’s current capabilities to handle the
increased daily flows.

A3.39. Quality of Life (QOL) and Personnel Support. Personnel facility su pport for MOBs are
intended to improve the QOL for assigned personnel. On MOBs where commanders have made the deci-
sion to split personnel support, MWR, AAFES services or concessions according to geographic location,
122 AFPAM10-219V6 1 FEBRUARY 2006

the sum of the space allocated for each activity split-based will not exceed the total square footage for that
category of facility as determined below.

A3.40. Chapels. Each base camp is authorized a chapel at a rate 1,624 sq ft of space per 1,000 authorized
user. The structure will have linoleum flooring installed. Design will be nondenominational. Office space
will be provided for the execution of chaplain functions supporting privileged (e.g. confidential) commu-
nications with parishioners.

A3.41. Education Centers, Defense Logistics Agency (DLA), and Military Occupational Specialty
(MOS) Library. A combination education center, DLA, and MOS Library of 1,710 sq ft is authorized for
each 1,000 authorized user assigned to a MOB.

A3.42. Army and Air Force Exchange Services (AAFES).


A3.42.1. Barber/Beauty/Alteration/Pressing Facilities: A barber/beauty shop and alteration/ pressing
facility is authorized for MOBs with a minimum operational duration of 6 months. Barber and beauty
shops can be collocated in the sa me facility. Barber and beauty shops are authorized 240 net square
feet (NSF) per 1,000 authorized users. Alteration and pressing facilities can be collocated in the same
facility, if contractor requirements can be met. Alteration and pressing se rvices are authorized 160
NSF per 1,000 authorized users.
A3.42.2. Field Exchange. All MOBs are auth orized a field exchange with authorized space of 2,800
sq ft per 1,000 authorized us ers. Sufficient electrical connections are authorized to ensure suf ficient,
safe electrical power is available for displays and other requirements.
A3.42.3. Each field exchange warehouse is authorized 1,340 sq ft per 1,000 assigned personnel.
A3.42.4. Each field exchange is authorized 250 sq ft per 1,000 authoriz ed users for administrative
space.
A3.42.5. Loading docks and gravel parking lots for delivery trucks are authorized.
A3.42.6. Food and Service Concessions S tands. The commander will determine what food conces-
sions will be on the post. Each f ood concession is authorized 480 sq ft per 750 authorized users.
Authorized dining/seating space is 375 sq ft per 750 authorized users. One refrigerated cooler, three
freezers, and one dry storage contai ner are authorized per food court. When requested by the local
Command, a specialty food concept is authorized 512 sq ft, which includes seating. Amusement areas
adjacent to the food concession are authorized 150 sq ft per concession fo r equipment setup. The
Army is responsible for providing basic facilities for these concessions, to include utility hookups and
ventilation O&M. AAFES is responsible for the installation a nd maintenance of all AAFES peculiar
items (e.g. cash registers, display shelves and coolers, stoves, and specialty lights).

A3.43. MWR.
A3.43.1. Fitness facilities. Each MOB is authorized a fitness facility at three sq ft per authorized user.
The facility will have rubber floor tiles and male/female latrines.
A3.43.2. Multipurpose Facility. All MOBs are authorized a facility to conduct indoor sports, shows,
or large meetings. The fa cility will have a wooden floor lined for basketball, volleyball, and other
sports activities. If possible, the facility should be able to have an enclosed full size basketball court of
50’X 94’ with eighteen foot (18’) floor to ceiling clearance and a minimum five foot (5’) safety/walk-
AFPAM10-219V6 1 FEBRUARY 2006 123

ing lane surrounding the playing area. Field houses should have fluorescent lighting and climate con-
trol male/female latrines. The field house should have double entry/exit doors.
A3.43.3. Athletic Fields. Each MOB is authorized two sand volleyball courts, two horseshoe pits, a
paved outdoor basketball (1/2 court) court and one outdoor pavilion. Base camps over 2,000 are
authorized a second set.
A3.43.4. Where adequate space exists, multi-purpose athletic field with outdoor lighting suitable for
flag football, softball, soccer, and track activities may be constructed.
A3.43.5. Running trail with workout stations: each MOB is authorized a lighted outdoor running trail
up to two miles in length with up to eight uncovered fitness stations.
A3.43.6. Community Activity Center. Each MOB is authorized a community activity center. The cen-
ter is authorized 2,400 sq ft pe r 1,000 assigned personnel. The facility should have double entry/exit
doors, latrines, and running water. The community activity center and theater will be located in oppo-
site areas of base for force protection issues. The structure will house the communication (cyber cafe)
center with phone center, common area, library, equipment room, TV room, movie room, and video
teleconference room.
A3.43.7. Multi-Purpose Theater. Each MOB with over 1,000 US personnel is authorized one
multi-purpose theater, with a 35’ wide x 25’ deep stage, with steps on both sides and a securable stor-
age area under the stage, two dressing rooms on both sides, with climate control, mirrors, and shelves
to the sides. MOBs with fewer th an 1,000 personnel are not authorized a stage. Facility will be hard
wired with two each 380 volt, 32 amp and 64 amp, 220V power. The theater will be housed in a struc-
ture designed to seat 25% of the base population, or 500 persons, maximum. The theater should have
double entry/exit doors. Seating will be folding metal or plastic chai rs, that can be quickly removed
and the floor space used for formations or transfer of authority movements.
A3.43.8. MWR Warehouse. Each task force is authorized one MWR warehouse facility at 1 sq ft per
personnel supported. Facility is to be used for repair of MWR equipment and for short-term storage of
remote site equipment and seasonal equipment not in use. It is not authorized for long-term storage of
excess MWR equipment.
A3.43.9. American Forces Network (AFN) Services. Each MOB will establish facilities for broadcast
transmission of AFN services. The standard AFN broadcasting pad is a minimum of 300’ X 150’ and
located on the highest point of the perimeter or in the center of the base camp. It includes a housed
power generation/fuel source. Variations for manned/unmanned operations areas as follows:
A3.43.9.1. Manned Operations. The AFN pad will in clude a facility to house a manned af filiate
operation – consisting of studios, offices, and other administrative space up to a maximum of
56’ x 75’ or 4,200 sq ft.
A3.43.9.2. Unmanned Operations. One climate-controlled equipment shelter the size of a stan-
dard SEA hut (512 sq ft) is required.
124 AFPAM10-219V6 1 FEBRUARY 2006

Attachment 4

FORWARD OPERATING BASE AUTHORIZED FACILITY/CONSTRUCTION STANDARDS

A4.1. Forward Operating Bases. A forward operating base (FOB) is defined as a site normally occu-
pied by company-sized units and operated on a continuous basis. The standards found in the main body of
this volume apply to FOBs, except in the following circumstances.

A4.2. Roads. FOBs are authorized gravel on primary and secondary roads.

A4.3. Dining Facilities. Dining facilities are authorized 1,024 sq ft of dining room space and 512 sq ft
for kitchen, admin and storage space per 100 authorized users. Adequate space for cleaning, latrine, and
clothes changing for local national kitchen staff will be provided. Load ing dock, if present, can be con-
crete, asphalt, or treated lumber.

A4.4. Laundry Collection/Distribution Point. A total of 256 sq ft is au thorized for a laundry collec-
tion/distribution point.

A4.5. Aviation Facilities. Helicopter landing and parking pads will be concrete. Bean Bag Lighting Kit
will be available and operational for nighttime flight operations.

A4.6. Communications Compound/Network Control Center. Each FOB is author ized 512 sq f t to
house the base’s communications control operations.

A4.7. Aid Stations. Aid stations are authorized a maximum of 512 sq ft.

A4.8. Transportation Squadron Maintenance Facilities. A maintenance facility of 1,200 sq ft erected


on concrete or asphalt pads are authorized for each company-sized element. The maintenance facility will
be equipped to provide heating, electric lights and compressed air.

A4.9. Maintenance Administration. A maximum of 320 sq ft for of fice space is authorized for each
company-sized element.

A4.10. Fire Protection. Portable fire extinguishers will be available in all buildings and places where
flammable materials are used. The AOR Fire Chief, in coordination with the DPW, will determine the
number of fire extinguishers for eac h facility. The FOB Commander will ensure the occupants are prop-
erly trained in their use.

A4.11. EMEDS. Expeditionary medical facilities expand depending on the size of the population served.
For instance, EMEDS+25 package whic h serves a population of 3,000 to 5,0 00 personnel will require
40,000 sq ft of land area, 200kW of pow er, 1,430 gallons of potable wate r per day, 300 gallons of diesel
fuel per day, 2,500 gallons of gr ey water runoff, and 1,100 pounds of solid wa ste removal per day. See
AFPAM 10-219, Volume 5 for additional information on the beddown of EMEDS and theater hospitals.

A4.12. Utilities.
A4.12.1. Water. Reference water guidelines located in the Utilities Section of MOB standards.
AFPAM10-219V6 1 FEBRUARY 2006 125

A4.12.2. Electric Power: Generator power will continue to be the primary source of remote site
power if commercial power is not available.
A4.12.3. Sewage collection tanks are authorized. However the initial asse ssment for a FOB should
consider installation of a wastewater treatment system. Sewage can be trucked to a suitable wastewa-
ter treatment plant.

A4.13. MWR and Personnel Support.


A4.13.1. Community Activity/Education Center. Each FOB is authorized a community activity/edu-
cation center at a rate of 1,024 sq ft per 150 authorized user, with a minimum size of 1,024 sq ft.
A4.13.2. Fitness center is authorized at a rate of 1,024 sq ft per 150 authorized users with a minimum
size of 1,024 sq ft.
A4.13.3. Barber/Beauty Shop: A barber/beauty shop is authorized for FOBs. Barber and beauty shops
can be collocated in the same facility. Barber and beauty shops are authorized 256 sq ft per 150 autho-
rized users with a minimum size of 256 sq ft.
A4.13.4. Base Exchange. All FOBs are authorized a Field Exchange with authorized space of 512 sq
ft per 150 authorized users w ith a minimum size of 512 sq ft. Suf ficient electrical connections are
authorized to ensure sufficient, safe electrical power is available for displays and other requirements.
A4.13.5. Athletic Fie lds. Each FOB is authorized one sand volley ball court, one horseshoe pit, a
paved outdoor basketball (1/2 court) court, and one outdoor pavilion. Where adequate space exists,
multi-purpose athletic field suitable for flag football, softball, soccer, and track activities may be con-
structed.
A4.13.6. Running Trail. Each FOB is authorized a running trail.

A4.14. Non-Authorized Facilities. The following facilities are not authorized at a FOB.
A4.14.1. Individual Equipment Unit Warehouse.
A4.14.2. Hazardous Materials Warehouse.
A4.14.3. Morgue.
A4.14.4. DRMO.
A4.14.5. Ammo Supply Point.
A4.14.6. Wash Rack.
A4.14.7. Training Facilities.
A4.14.8. Security Forces Law Enforcement S tation (force protection and entry control points are
authorized as required).
A4.14.9. Alteration/Pressing Shop.
A4.14.10. Multi-Purpose Theater.
A4.14.11. MWR Warehouse/Maintenance Facility.
A4.14.12. AFN Manned Operations.
126 AFPAM10-219V6 1 FEBRUARY 2006

Attachment 5

FORWARD OPERATING LOCATION AUTHORIZED FACILITY STANDARDS

A5.1. Forward Operating Locations (FOLs). FOLs are normally used fo r short term, operationally
defined missions (e.g. checkpoints and observation posts) for platoon or squad sized elements and will not
have the level of services the ma in operating airbases and forward operating airbases are authorized.
FOLs will be authorized the following primary services.
A5.1.1. Field expedient slit trenches/urine pipes, portable latr ines, existing host nation facilities or
ablution units if they can be serviced. BEAR or Force Provider latrine, shower and shave units are pre-
ferred over expedient method shower and latrine facilities, if the site will be occupied over the winter
or through periods of extreme inclement weather (such as monsoon season, etc).
A5.1.2. Portable generators or taps into host nation facilities to provide power.
A5.1.3. Heated Tier II tents (16’ x 32’) for living and working space, or modular style containers (8’
x 20’). If containers are used, one container for admin space is authorized. Living space is the same as
base camps.
A5.1.4. One Tier II tent to serve as a recreation room and break room. Modulars are not authorized for
this purpose at FOLs.
A5.1.5. One Tier II tent for a fitness facility. Modulars are not authorized for this purpose at FOLs.
A5.1.6. Airmen personnel support will be accomplished by in-theater higher headquarters, located at
either an FOA or MOA. No facilities are authorized.
A5.1.7. Construct the perimeter fence with concertina wire and other approved force protection mate-
rials.
A5.1.8. Preferred blast protection is HESCO-style expedient blast barriers (interlocking wall 10’ high
and/or berms).
A5.1.9. Gravel parking and walking paths should be constructed from well-graded gravel and com-
pacted. These areas should be free of loose rocks greater than 40 mm in diameter to decrease probable
damage to vehicles and personnel injury.
A5.1.10. EMEDS package supporting up to 500 personnel. This package requires 15,000 sq ft of land
area, 65kW of power, 400 gallons of potable water per day, 700 gallons of grey water runoff, and 180
pounds of solid waste removal per day. See AFPAM 10-219, Volume 5 for additional information on
EMEDS beddown.

A5.2. Additional FOL References. See Attachment 1 for other references related to FOLs.

You might also like