Weld Time - Pass
Weld Time - Pass
Weld Time - Pass
SPECIFICATION: G-1064-23a
Administrative Revisions
Header page 3: Updated the title to match the titles on the other pages.
Section 5.1 B - Replaced the title for G-100,281, “Weld End Forged Fittings for Gas
Piping” with “Butt Weld Fittings for Gas Piping”
Section 24.1 - Added the title for G-11870 “Integrity Assessment and Repair of Steel
Gas Transmission Pipelines Operating at 125 PSIG or More”.
Section 26.2 – Added the title for IP-9 “Requirements for Long Form Written
Procedures and Contingency Plans”
Section 37.0 - Replaced the title for G-100,281, “Weld End Forged Fittings for Gas
Piping” with “Butt Weld Fittings for Gas Piping” Replaced the title for
IP-9, “Requirements for Written Procedures and Contingency Plans”
with “Requirements for Long Form Written Procedures and
Contingency Plans”.
Throughout the document minor grammar revisions were made and units changed for
concurrence.
REVISIONS: (Continued)
1) Cover Page - Added “Course ID” and “Core Group”; revised “Target
Audience” to include Construction.
TABLE OF CONTENTS
13.0 ALIGNMENT...................................................................................................... 19
16.0 PREHEAT.......................................................................................................... 20
36.0 RECORDS......................................................................................................... 30
1.0 SCOPE
This specification covers the welding of piping used in gas, steam, electric and
cable type pipe, and the standards of acceptability for production welds.
All welding parameters and requirements found in the paragraphs and tables of
this specification are derived from the company Welding Procedures and
Qualification Records, referenced in Section 35.0.
New York State - NYCRR Title 16, Part 255, Sections 255.225 through
255.245 and Appendix 14-G.
3.1 All welders and welding procedures shall be qualified in accordance with
Specification G-1065, “Qualification of Welders and Welding Procedures”.
3.2 Each welder shall have in their possession an identification card issued by
the Company which lists the welder's qualification.
5.1 Only steel pipe, fittings, and components conforming to one of the
following Specifications shall be used:
C) S-9035, “Steel Pipe for Steam Mains and Services for the 200 psig
Distribution System”.
5.1 (Continued)
D) S-9036, “Steel Pipe for Steam Mains and Services for the 400 psig
Distribution System”.
E) S-9040, “Steel Socket or Butt Welding Fittings for Use in the 200
and 400 psig Steam Distribution Systems” and approved
component specifications.
5.2 For material with specified minimum yield strength (SMYS) of 70,000 psi,
ONLY material approved by Gas Engineering Major Projects/Transmission
Maintenance may be used. Consult with Gas Engineering Major
Projects/Transmission Maintenance prior to welding any material with
specified minimum yield strength of ≥65,000 psi.
NOTE: Material with a SMYS of 70,000 psi may only be welded to the
same grade material OR to material with a SMYS of 60,000 psi or 65,000
psi.
6.1 15 minutes maximum between "Root Pass" and "Hot Pass" is permitted.
6.2 Once started, the welding of both the root pass and hot pass shall be
continuous until complete.
6.3 The maximum time between completion of the second pass and the start
of the other passes shall not exceed 1 hour. Deviation from this timeframe
requires Engineering approval.
A) Standard joint design and spacing between abutting pipe ends shall
conform to Figure No.1. An optional bevel end preparation of 30
deg, +5 deg, -0 deg may be used.
F) Stop locations for subsequent weld beads shall not coincide with
the start/stop location of the previous bead.
WELD-O-LET
E) Steam may also use the drain, bypass, and blow off connections
depicted in EO-16905-B “Drain, By-pass and Blow-off Connections
for 200 psig and 400 psig Steam Mains”.
B) Backing rings for cable pipe shall be used when the ends of the
pipe to be welded are flared.
D) Backing rings shall be carefully fitted into the end of the pipe with
the pipe end against the chamfer extrusion of the backing ring.
E) The opening in the backing ring shall be located at the three or six
o'clock position.
F) Care shall be taken to ensure that the opening of the backing rings
in welded joints at bends or offsets are not able to interfere with the
pulling of cable.
G) For sleeve joints, the pipe ends shall be reamed to remove all
sharp edges and burrs and leave a 1/8" radius on the inside edge
of the pipe.
8.1 Class E-6010, E-7010 and E-8010 electrodes shall be used as specified in
Tables I, II and III.
8.2 Tables I, II and III are guides for the number of passes, class, and size of
electrodes to be used. Variations in electrode size are acceptable based on
field conditions.
TABLE I - Specified Minimum Yield Strength (SMYS) of Less Than 65,000 psi)
8.2 (Continued)
8.2 (Continued)
9.2 The voltage and amperage range shall conform to Table IV to Table VI.
TABLE IV
WALL THICKNESS 1/4" to 3/4" (inclusive)
And
Specified Minimum Yield Strength (SMYS) of 70,000 psi
Root SMAW E6010 5/32” DCRP 130-180 23-26 Target 4-8 IPM
Hot Pass SMAW E8010 5/32” DCRP 150-180 26-30 Target 4-8 IPM 15 Minutes
Fill SMAW E8010 3/16” DCRP 170-200 26-30 Target 4-8 IPM Max
Cap SMAW E8010 3/16” DCRP 150-200 26-30 Target 4-8 IPM
TABLE V
WALL THICKNESS 1/4" to 3/4" (inclusive)
And
Specified Minimum Yield Strength (SMYS) of 65,000 psi
Root SMAW E7010 5/32” DCRP 105-160 23-30 Target 4-8 IPM
Hot Pass SMAW E8010 5/32” DCRP 105-160 23-30 Target 4-8 IPM 15 Minutes
Fill SMAW E8010 3/16” DCRP 105-160 23-30 Target 4-8 IPM Max
Cap SMAW E8010 3/16” DCRP 105-160 23-30 Target 4-8 IPM
9.2 (Continued)
TABLE VI
WALL THICKNESS 1/4" to 3/4" (inclusive)
And
Specified Minimum Yield Strength (SMYS) of less than 65,000 psi
Root SMAW E6010 5/32” DCRP 120-190 25-70 Target 4-8 IPM
Hot Pass SMAW E7010 5/32” DCRP 120-190 25-70 Target 4-8 IPM 15 Minutes
Fill SMAW E7010 3/16” DCRP 120-190 25-70 Target 4-8 IPM Max
Cap SMAW E6010 3/16” DCRP 120-190 25-70 Target 4-8 IPM
11.2 On pipe sizes larger than 14" OD, two welders shall be used for the root and
hot pass. Filler beads and cap pass may be done by one welder.
12.0 CLEANING
12.2 Prior to fitting the sections together, but after all cutting and end preparation
operations have been completed, the inside and outside surfaces of the pipe
and/or fittings to be welded shall be inspected for corrosion product build up
or debris. If observed, it shall be manually removed before welding.
12.3 Pipe cleaning shall be done by power brush and/or grinding between every
pass.
13.0 ALIGNMENT
13.1 The alignment distance between abutting ends of pipe, and/or fitting =
1/16" ± 1/32".
Line-up clamps are required for piping butt welds greater than or equal to 16”
NPS. When required, either external or internal clamps may be used. Other
methods of alignment may be used with Engineering approval.
15.1 External lineup clamps shall be removed after at least 50% of the root
bead is completed, and uniformly spaced around the circumference of the
pipe.
15.2 When an internal lineup clamp is used, the root bead shall be completed
before releasing clamp tension.
16.0 PREHEAT
A) For all incomplete welds. Welds may be left incomplete; only after
a minimum root and hot passes have been completed.
B) Carbon steel that has a carbon content more than 0.32 percent or a
carbon equivalent (C + ¼ Mn) of 0.65 percent or higher. Other new
materials where the pipe grade or carbon content is unknown shall
be referred to Gas Engineering for advice on preheating and stress-
relief.
17.1 PWHT on pipe welds in material with a SMYS less than 65,000 psi shall
be required for the following:
A) Welds on carbon steel that have a carbon content greater than 0.32
percent or a carbon equivalent (C + ¼ Mn) greater than 0.65
percent.
17.1 (Continued)
B) When conditions exist that would cause the weld to cool at a rate
detrimental to the quality of the weld.
D) For welds on carbon steel pipe with a wall thickness of more than
1-1/4 inches, consult stress relieving requirements with Gas
Engineering.
17.2 When applying PWHT, the temperature shall be monitored to ensure that
a uniform temperature is maintained and that the following PWHT cycle is
followed:
17.2 (Continued)
18.1 Pre-heat the area of the two longitudinal seams to 300º F. (Maintain
temperature during welding.)
18.2 Weld the longitudinal seams on the spherical fitting. Weld only the portion
of the longitudinal seams which are on the spherical part of the fitting. The
ends of the longitudinal seams which are in contact with the pipe are not
to be welded. (Welds to be magnetic particle tested.)
18.3 Pre-heat the area of the first circumferential weld to 300º F. (Maintain
temperature during welding.)
18.4 Weld the first (root) pass for the circumferential weld. (Weld to be
magnetic particle tested.)
18.5 Complete the second (hot) pass for the circumferential weld. (Weld to be
magnetic particle tested.)
18.7 Remove the pre-heat and allow the circumferential weld to cool.
18.8 Follow the same process (18.3 to 18.7) for the second circumferential
weld on the fitting.
19.1 The Field Representative shall decide if weather conditions are suitable
for welding.
20.5 Miter welds shall be fabricated by mitering both ends of the adjoining
pipes equally.
Where back welding is performed, the inside bead shall be run after all outside
welding is completed.
23.2 The ground lead shall not be tack welded to a pipe or appurtenance.
24.1 Arc burns and shallow notches or gouges shall be eliminated by blend
grinding per Specification G-11870 “Integrity Assessment and Repair of
Steel Gas Transmission Pipelines Operating at 125 PSIG or More”.
24.2 Gouges or notches deeper than 10% of the wall thickness of the pipe shall
be cut-out by removing a cylinder of the pipe. See Section 31.0 for the
minimum size of cylinder to be removed.
The sleeve shall be centered over the pipe ends and welded in position in
accordance with Figure No. 7.
26.1 “Prior to starting any task pursuant to this specification, Con Edison Gas
Operations employees must be familiar with any Job Safety Analysis
contained in Con Edison’s Job Safety Analysis (JSA) Library. Any Con
Edison Gas Operations employee preparing a job briefing for any task to
be accomplished pursuant to this specification shall review the JSA
Library to determine if there is a JSA applicable to the task. Any relevant
JSA found in the library shall be discussed during the job briefing for the
task. This provision is only applicable to Con Edison Gas Operations
Employees.”
26.2 Welders must wear proper PPE and follow safe work practices as outlined
in CEHSP S15.00 - "Welding, Cutting, and Other Hot Work Operations".
Welding is prohibited in flammable/combustible atmospheres. Purging
with an inert gas as outlined in IP-9 ”Requirements for Long Form Written
Procedures and Contingency Plans” is an acceptable means of ensuring
that a flammable/combustible atmosphere is not present. Combustible
material must be removed from the vicinity of the welding operation. Any
combustible material in the vicinity of the welding operation that cannot be
moved must be adequately protected by welding blankets, etc.
26.3 Proper welding screens should always be used when welding to prevent
employees and the public from being exposed to ultraviolet light.
26.4 Burning of solid debris or sludge has the potential to release harmful
vapors into the atmosphere, including dioxins if PCBs are present.
Therefore, a visual inspection must be performed prior to flame
cutting/burning pipe to insure there is no solid debris or sludge inside the
pipe. This includes live gas mains as well as previously abandoned
mains. In addition, discovery of debris or sludge in a gas main requires
sampling. If solid debris or sludge is found, stop work, and notify the Field
Representative who will contact EH&S Operations (Gas) for assistance.
26.4 (Continued)
27.1 A complete written record of all welds as to location, date, weld number
and welder identification number shall be prepared by the Field
Representative, for gas mains operating at or above 125 psig. These
records shall be given to Major Projects of Gas Engineering who shall be
responsible for retaining these records. Refer to Records section 36.0 for
records management.
27.2 For gas mains operating at less than 125 psig, the welders shall mark with
a pipe marker adjacent to the weld made, the weld passes the welder
completed. For example: root, hot, filler, or cap.
28.1 For gas mains that will operate less than 125 psig and steam mains,
welders shall inspect their own welds to ensure that the welds have a
clean appearance and are free of cracks, inadequate penetration, burn-
through, or other defects as specified in API 1104 “American Petroleum
Institute Standard for Welding Pipeline and Related Facilities” (20th
Edition)”.
28.2 For gas mains that will operate at 125 psig or more, welds shall be
inspected by a person qualified by experience and training: minimum
Level II inspector or a certified welding inspector (AWS CWI). Self-
inspection of the weld by the welder is prohibited.
30.1 Acceptability of welds shall be based upon G-1070 and API 1104.
30.2 The Chief Gas Transmission Engineer of the Gas Engineering Department
or duly authorized representative may require that test coupons be cut
from welds.
30.3 Welding shall not be done over defects. Defects shall be removed by
grinding. Repaired areas shall be re-radiographed or inspected by the
same means previously used. If the repair is not acceptable, the weld shall
be removed as a cylinder of pipe, see Section 31.0.
Welds or pipe sections with repairs in excess of the preceding limits must be cut
out. The installing organization shall remove cylinders containing the defective
welds or pipe section. Minimum lengths for cylinders are as follows
Note: If the minimum cylinder length cannot be met, consult with Gas
Engineering.
32.1 Except for branch connections and assemblies of standard pipe and
fittings joined by circumferential welds, the design pressure of each
component fabricated by welding, whose strength cannot be determined,
must be established in accordance with paragraph UG-101 of section VIII
of the ASME Boiler and Pressure Vessel Code, Division I (as referenced
in Section 10.3 of the latest edition of Title 16 NYCRR.).
32.2 Each prefabricated unit that uses plate and longitudinal seams must be
designed, constructed, and tested in accordance with the ASME Boiler
and Pressure Vessel Code (as described in Section 10.3 of Title 16
NYCRR), except for:
B) pipe that has been produced and tested under a specification listed
in Appendix 14-B of the latest edition of Title 16 NYCRR;
32.3 Orange-peel bull plugs and orange-peel swages may not be used on
pipelines that are to operate at a pressure of 125 psig or more.
32.4 Except for flat closures designed in accordance with section VIII of the
ASME Boiler and Pressure Vessel Code (as described in Section 10.3 of
Title 16 NYCRR), flat closures and fish tails may not be used on pipe that
either operates at 100 psig or more or is more than 3 inches nominal
diameter.
33.1 Each welded branch connection made to pipe in the form of a single
connection, or in a header or manifold as a series of connections, must be
designed to ensure that the strength of the pipeline system is not reduced,
taking into account the stresses in the remaining pipe wall due to the
opening in the pipe or header, the shear stresses produced by the
pressure acting on the area of the branch opening, and any external
loadings due to thermal movement, weight, and vibration.
34.2 Place halves of fitting around main and tack weld (both sides). Prior to
welding, completion plug shall be removed, and the screw cap shall be
hand tight. Do not install plug until all welding has been completed and the
fitting has cooled.
34.3 Weld longitudinal seams, both sides. Fitting may be turned, so the
longitudinal seams can be welded on top. Both longitudinal seams may
also be welded simultaneously.
34.4 (Continued)
Wrought iron welding shall follow the same welding parameter as stipulated
above for the welding of steel. Wrought iron welding should be kept at a
minimum when possible.
36.0 RECORDS
Any records generated in the course of performing work in accordance with this
specification shall be maintained as required by Corporate Instruction CI-870-1
“Records Management”. Guidance on the retention of Company Gas Operations
records can also be found on the Records Management intranet site.
37.0 REFERENCES
Gas
GEHSI E06.11 Liquids and solids from natural gas mains during main cut-
outs
IP-9 Requirements for Long Form Written Procedures and
Contingency Plans
Steam
EO-16905-B Drain, By-pass and Blow-off Connections for 200 psig and
400 psig Steam Mains
S-9035 Steel Pipe for Steam Mains and Services for the 200 psig
Distribution System
S-9036 Steel Pipe for Steam Mains and Services for the 400 psig
Distribution System
S-9040 Steel Socket or Butt Welding Fittings for Use in the 200 and
400 psig Steam Distribution Systems