The document outlines the planning and organization of an IT network project in 7 phases over 8 days. It involves understanding the project, designing the LAN network and infrastructure, proposing the network and infrastructure, purchasing equipment, implementing the LAN network, testing the network, and preparing tutorials for employees. It also provides a list of 18 hardware items needed for the project, their quantities, manufacturers, unit prices, and total cost. The project will require involvement from IT managers, IT experts, and daily workers at different phases.

Uploaded by

kuku
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views3 pages

C - Coc Documents - Doc Planning and Organizing of The Projec1 Test

The document outlines the planning and organization of an IT network project in 7 phases over 8 days. It involves understanding the project, designing the LAN network and infrastructure, proposing the network and infrastructure, purchasing equipment, implementing the LAN network, testing the network, and preparing tutorials for employees. It also provides a list of 18 hardware items needed for the project, their quantities, manufacturers, unit prices, and total cost. The project will require involvement from IT managers, IT experts, and daily workers at different phases.

Uploaded by

kuku
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Planning and organizing of the project

no Phase of the project Activities to be Duration of Required man Responsibility Remark


performed the activities power
1 Understanding the Looking of the 2 days 3 IT manager
project area of the project
2 Design Design of the LAN 2days 3 IT manager
of network and
infrastructure
3 Propose Propose the 3 days 2 IT manager
networking and
infrastructure
4 Purchase Purchase the IT 5days 3 IT experts and 2 Marketing
network and daily workers manager
equipments
5 Implements Implements of the 8 days 5 IT experts and 3 IT Manager
LAN network of daily workers
Design

6 Test and check Testing of the 2 days 2 IT manager


network device
and installation of
software and
hardware
7 Prepare Tutor Prepare tutor for 2 days 2 IT manager
employee and for
staff
Hardware needed

no Name of hardware Manufacturer Quantity Unit price


or brand
1 computer Dell 790 144 800.00
500GB,16GB
RAM CORE i7
2 Server Hp 1TB HD 3 80000.00
16GB ram
3 ADSL Ethio 1 700.00
telecom
4 RJ-45 Intel 1000 5.00
5 Wall outlet integrated D-link 72 89.00
6 Patch panel D-link 9 1500.00
7 switch D-link 9 2500.00
8 router Cisco 1 55000.00
9 printer Hp LaserJet 9 7000.00
10 crimper Intel 3 60.00
11 Tester D-link 1 500.00
12 rack 6u rack 9 4500.00
13 trunk 25*40mm 75 60.00
14 Utp cable Cat 6e 3roll 3500.00
15 Fisher 6mm Intel 5pack 35.00
16 Screw 6mm Intel 5pack 45.00
17 Puncher - 3pcs 45.00
18 Drill bit 6mm Intel 5pcs 15.00
19 Drill machine Bosch 2pcs 250.00
=