4422-VW-SG-001000000001 - B3-Painting & Coating
4422-VW-SG-001000000001 - B3-Painting & Coating
4422-VW-SG-001000000001 - B3-Painting & Coating
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
HOLD LIST
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
TABLE OF CONTENTS
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
1. PROJECT OVERVIEW
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
2. PURPOSE
The objective of this document is to define the requirements for painting, lining and
coatings for onshore facilities of ADNOC Hail & Ghasha Development Project and CO2
Recovery Project.
3. TERMINOLOGY
3.1 Definitions
3.2 Abbreviations
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
4. REFERENCE DOCUMENTS
The latest versions and amendments of all applicable UAE Legislation and Environmental
Regulations, ADNOC Group Engineering Standards and Specifications (AGES),
COMPANY Occupational Health Management Standards and HSE Regulations, the Hail
& Ghasha Development Project Specifications and Data Sheets, and all relevant
International Codes and Standards on the EFFECTIVE DATE of CONTRACT shall be
used.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
- -
All ASTM, ISO and SSPC standards referenced in AGES SP-07-004 are applicable.
5. ORDER OF PRECEDENCE
Design and engineering for the Facilities shall be undertaken in accordance with
regulations, codes, standards and specifications in the order of precedence stated below:
• UAE Local Laws and Regulations,
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Itemized Includes any tagged valves such as instrument valves (on-off, slide,
Valve etc.), control and safety valves, etc.
Shelf item Shelf Item is any item such as instruments (level gauge, flowmeters,
thermometer, etc.), push button, low voltage motors (< 415 Volt),
cabinets, etc., not covered by other definitions.
Zinc rich Any zinc containing primer, inorganic or organic, in compliance with
primer ISO 12944-5, para. 7.1.2
With Piping includes pipes, fittings, pipe supports and accessory items.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Replace All painting and coating systems shall meet the performance
requirements and the coating systems as specified in this specification
with a minimum environment of Category ,CX, ISO 12944-9.
All offshore requirements shall comply to ISO 12944-9.
With All painting and coating systems shall meet the performance
requirements and the coating systems as specified in this specification
with a minimum environment of Category C5 and having an expected
durability (High) as per ISO 12944-1 and -2.
All coatings for offshore shall comply to ISO 12944-9 and environmental
corrosivity CX.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Replace The SUPPLIER shall perform surface preparation, priming, and finish
painting of the following items including all attachments thereto in
accordance with the painting systems of this specification or their
standard paint specification provided the total paint system has a
minimum corrosion resistance of 2000 hours when tested in accordance
with ASTM B117 and / or ISO 12944-5 Table A6, CX, high durability and
passes the minimum laboratory requirements of ISO 12944-6. Offshore
coating shall comply with 4200 hrs in accordance with ISO 12944-9.
With The SUPPLIER shall perform surface preparation, priming, and finish
painting of the following items including all attachments thereto in
accordance with the painting systems of this specification or their standard
paint specification provided that the proposed paint system:
− has a minimum corrosion resistance of 2000 hours when tested in
accordance with ASTM B117. Copy of the test report released by
independent laboratory shall be provided together with the working
procedure for painting
or
− - is in compliance with C5, high durability (H) as per ISO 12944-1,-
2
Manufacturer's standard systems for items installed indoor shall be in
compliance with C4, high durability (H) as per ISO 12944-1, -2.
Coating for Offshore surfaces shall comply with environmental corrosivity
CX in accordance with ISO 12944-9.
Shelf Items, as defined in Section 6.2 '"Amendment to Table 1.2 List of
Definitions", shall be supplied as per paint system manufacturer standard
in compliance with ISO 12944-2 C5 and expected durability high (H) as per
ISO 12944-1 under the complete responsibility of the VENDOR, painting
procedures shall be submitted to CONTRACTOR for information only. Final
color / RAL shall be as per Project requirements.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
With Only for Static Equipment (Tanks, Drums, Heat Exchangers (S&T),
Reactors, Columns), Main Civil Structural Steel, Site activity for piping and
tanks, the Coating MANUFACTURER’s technical representative shall
submit a periodic report to CONTRACTOR confirming that painting (shop
/ field at site) is being carried out in accordance with their instructions and
quality of workmanship is acceptable to them. This report shall also cover
analysis of technical problems (if any).
Structural steel and piping in the above list do not include packaged units
and machinery.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
(page 30 of 176)
Replace A pre-production test shall be used to qualify all coating procedures using
an appropriate test panel representative of the structure to be painted.
ASTM D4228 can be used as a reference.
With A pre-production test shall be used to qualify all coating procedures using
an appropriate test panel representative of the structure to be painted.
ASTM D4228 can be used as a reference. SUPPLIER / SUB-
CONTRACTOR shall retain the prepared test panel for COMPANY
inspection.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Replace Flame cut areas and weld spatter shall have been ground flush with the
requirements of ISO 8501-3, preparation Grade P3.
With Metallic surfaces to be coated shall comply with ISO 8501-3 grade P2
except for weld spatter and flame cut areas that shall comply with Grade
P3.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
6.21 Amendment to Section 10.3 Protection of Stainless-Steel and CRA Surfaces -2nd
Paragraph
(page 36 of 176)
Replace All uncoated CRA shall be pickled and passivated in accordance to ASTM
A380 after installation on site.
With Pickling and passivation at Site shall be carried out only on weld joint
areas, whereas others CRA surfaces shall be pickled and passivated at
shop (when applicable and required).
With For piping, equipment, steel structures and any machinery installed
outdoor with high impact on the plant reliability and productivity, the SUB-
CONTRACTOR shall schedule a pre-job meeting, to ensure that job
requirements are fully understood.
With Surface preparation for stainless steel (including super duplex stainless
steel) and CRA surfaces shall be sweep blasting as per as per SSPC-SP16
to achieve a 25-40 µm profile.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Replace Holiday detection shall be carried out in accordance with ASTM D5162 on
100% of coated area for external coatings of buried tanks, vessels and
piping.
With Holiday detection shall be carried out in accordance with ASTM D5162 on
100% of coated area for external coatings of buried tanks, vessels and
piping and insulated items coated with non conductive systems (e.g. epoxy-
based coating systems).
6.26 Amendment to Section 14.5 Inspection and Tests Summary- Table 14.1 Inspection
and Tests
(page 51 of 176)
Test Type Method Extent / Frequency Acceptance Criteria
DFT of each coat and of ISO 19840/ 100% of surfaces Specification requirements
complete paint system SSPC-PA2
Total NDFT Spot Checks (1) To be performed on test
<150 micron as panels: Class 0
per ISO 2409
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Replace silica sand, copper slag and steel shot shall not be used
With silica sand, copper, slag, and other refinery slags and steel shot shall not be
used
Replace Surface quality of welds shall be at least equal to or better than NACE
SP0178, Weld Designation D.
With Surface quality of welds shall be at least equal to or better than NACE
SP0178, Weld Designation C. All the welds shall be continuous: spot and
discontinue welds are not permitted. All sharp edges shall be ground to
produce a radius (r > 3 mm) and all imperfections such as skip welds,
delaminations, scabs, slivers and slag shall be corrected prior to and after
abrasive blasting. Other defects shall comply with ISO 8501-3 grade P3.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
6.33 Amendment to Section 26.6 Inspection Acceptance Criteria – Table 26.1 Inspection
Acceptance Criteria for Lining Work
(page 75 of 176)
Replace Suitable abrasives shall be selected from those defined in ISO 8504-2.
With Suitable abrasives shall be selected from those defined in ISO 8504-2
except slags refinery that are forbidden,
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
With:
Service Coating
Item Description Substrate Temperature System
Range Number
All Buried Steel - Piping / Equipment CS - 20°C ≤ T ≤ 60°C A-6
Add the following in Table 1.1 for Item Description - All Buried Steel - Piping / Equipment
(page 93 of 176);
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Add the following in Table 1.1 for Item Description - Insulated - Piping / Pipe Fittings /
Structures / Equipment / Flares (page 94 of 176);
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
3rd Polyurethane 75 µm
With:
Coating
System Substrate Surface Preparation and Blast Profile Coat Generic System
DFT
Number Details
Inorganic Zinc
1st 75 µm
Silicate
Sa 2.5 / SSPC-SP 10 Polyamide Epoxy
A-13 CS 50 µm – 75 µm 2nd 100 µm
MIO
Polyamide Epoxy
3rd 100 µm
MIO
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
Note: The use of the above-mentioned system A-13B shall be endorsed by the intumescent
epoxy Fireproofing Manufacturer and subject to Contractor and Company approval.
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
ABU DHABI NATIONAL OIL COMPANY (ADNOC)
GHASHA CONCESSION PROJECTS
HAIL AND GHASHA DEVELOPMENT PROJECT
PACKAGE 2 – ONSHORE FACILITIES
CONTRACTOR DOC NO:
AGREEMENT NO: 4700021829
4422-VW-SG-001000000001
PAINTING & COATING SPECIFICATION Document class: 2B
APPENDIX-1
This Document is intended for use by ADNOC and its nominated Consultants, Contractors, Manufacturers and Suppliers.
THE CONTENTS OF THIS DOCUMENT ARE PROPRIETARY AND CONFIDENTIAL
Specification
APPROVED BY:
NAME: Abdulmunim
Abdulmunim Saif Al KindyAl Kindy
TITLE: Executive Director PT&CS
EFFECTIVE DATE:
AGES-SP-07-004
REVISION HISTORY
Digitally signed
Reuben byYagambaram
Reuben
Yagam Date:
2021.04.13
baram 14:55:02
+04'00'
Group Projects & Engineering is the owner of this specification and responsible for its custody, maintenance and
periodic update.
In addition, Group Projects & Engineering is responsible for communication and distribution of any changes to
this specification and its version control.
This specification will be reviewed and updated in case of any changes affecting the activities described in this
specification.
DEFINITIONS
“ADNOC Group” means ADNOC together with each COMPANY in which ADNOC, directly or indirectly, controls
fifty percent (50%) or more of the share capital.
“Approving Authority” means the decision-making body or employee with the required authority to approve
Policies & Procedures or any changes to it.
“Business Line Directorates” or “BLD” means a directorate of ADNOC which is responsible for one or more
Group Companies reporting to, or operating within the same line of business as, such directorate.
“Business Support Directorates and Functions” or “Non- BLD” means all the ADNOC functions and the
remaining directorates, which are not ADNOC Business Line Directorates.
“Group COMPANY” means any COMPANY within the ADNOC Group other than ADNOC.
The intranet copy of this document located in the section under Group Policies on One ADNOC is the only
controlled document. Copies or extracts of this document, which have been downloaded from the intranet, are
uncontrolled copies and cannot be guaranteed to be the latest version.
LIST OF FIGURES
APPENDIX FIGURE 6.1 PIPING COLOUR CODING ARRANGEMENT - GAS PROCESSING ..................... 113
APPENDIX FIGURE 7.2 PIPING COLOUR CODING ARRANGEMENT - REFINING ..................................... 120
APPENDIX FIGURE 8.3 EXAMPLE OF APPLICATION OF SAFETY COLOUR AND CODING - ONSHORE
..................................................................................................................................................................... 125
APPENDIX FIGURE 9.4 APPLICATION OF COLOUR IDENTIFICATION SYSTEM - OFFSHORE ............... 144
APPENDIX FIGURE 10.5 LINE NUMBERS - LNG ........................................................................................... 150
APPENDIX FIGURE 13.6 TOUCHDOWN / POSITIONING MARKING CIRCLE - OFFSHORE ...................... 155
APPENDIX FIGURE 13.7 LOCATION OF TOUCHDOWN MARKINGS - CENTRALISED TOUCHDOWN
MARKINGS - OFFSHORE .......................................................................................................................... 156
Introduction
This specification defines the minimum requirements for surface preparation, selection of painting systems and
their application, personnel qualification, inspection and quality control and health, safety and environment
requirements related to surface preparation and paint application.
It applies to all coastal, onshore facilities and offshore facilities.
This specification covers all external surfaces of structures, equipment, machinery, piping, valves, instruments
and accessories, including buried piping / equipment and well casings.
This specification also covers the general design, materials, surface preparation, application, and testing
requirements for lining the internal surfaces of shop and field fabricated tanks, pressure vessels, piping and other
equipment in a shop or jobsite environment.
This specification does not cover the following:
External coating of pipelines.
Coatings for buildings.
Purpose
The materials and procedures specified herein are provided to protect the following:
External surfaces of plant equipment and piping from corrosion and to provide an aesthetically pleasing
environment for operating personnel.
Internal surfaces of plant equipment and piping from corrosion and to prevent the possibility of product
contamination.
The ADNOC Business Unit specifications listed in Section 2.2 shall also be considered part of this specification,
where indicated as applicable in the Purchase Order.
The definitions used throughout this specification are shown in Table 1.2.
REFERENCE DOCUMENTS
ASTM
Standard practice for cleaning, descaling, and passivation of stainless-
ASTM A380
steel parts, equipment, and systems
ASTM B117 Standard practice for operating salt spray (fog) apparatus
ASTM C109 Standard test method for compressive strength of hydraulic cement
mortars (using 2-in. or [50 mm] cube specimens)
ASTM D149 Standard test method for dielectric breakdown voltage and dielectric
strength of solid electrical insulating materials at commercial power
frequencies
ASTM D2240 Standard test method for rubber property - durometer hardness
ASTM D2583 Standard practice for generation of environmental data related to waste
management activities: quality assurance and quality control planning and
implementation
ASTM D4060 Standard test method for abrasion resistance of organic coatings by the
taber abraser
Standard practice for qualification of coating applicators for application of
ASTM D4228
coatings to steel surfaces
ASTM D4285 Standard test method for indicating oil or water in compressed air
Standard test method for pull-off strength of coatings using portable
ASTM D4541
adhesion testers
Standard practice for measuring MEK resistance of ethyl silicate
ASTM D4752
(inorganic) zinc-rich primers by solvent rub
Standard test method for conductimetric analysis of water-soluble ionic
ASTM D4940
contamination of blast cleaning abrasives
Standard practice for conducting a patch test to assess coating
ASTM D5064
compatibility
Standard practice for discontinuity (holiday) testing of nonconductive
ASTM D5162
protective coating on metallic substrates
ASTM D520 Standard specification for zinc dust pigment
Standard practice for cyclic salt fog / UV exposure of painted metal,
ASTM D5894 (alternating exposures in a fog / dry cabinet and a UV / condensation
cabinet)
BS
BS 1710 Specification for identification of pipelines and services
BS 4800 Schedule of paint colours for building purposes
Respiratory protective devices. Continuous flow compressed air line
BS EN 14594
breathing devices. Requirements, testing and marking
BSI PAS 102 Specification for processed glass for selected secondary end markets
ISO
ISO 10005 Quality management - Guidelines for quality plans
Preparation of steel substrates before application of paints and related
ISO 11124 (Parts 1 to 4)
products - Specifications for metallic blast-cleaning abrasives
Preparation of steel substrates before application of paints and related
ISO 11125 (All Parts)
products - Test methods for metallic blast-cleaning abrasives
Preparation of steel substrates before application of paints and related
ISO 11126 (All Parts)
products - Specifications for non-metallic blast-cleaning abrasives
Preparation of steel substrates before application of paints and related
ISO 11127 (All Parts)
products - Test methods for non-metallic blast-cleaning abrasives
Paints and varnishes - Corrosion protection of steel structures by
ISO 12944 (All Parts)
protective paint systems
ISO 14918 Thermal spraying - Qualification testing of thermal sprayers
ISO 1524 Paints, varnishes and printing inks - Determination of fineness of grind
ISO 15741 Paints and varnishes - Friction-reduction coatings for the interior of on-
and offshore steel pipelines for non-corrosive gases
Paints and varnishes - Corrosion protection of steel structures by
ISO 19840 protective paint systems - Measurement of, and acceptance criteria for,
the thickness of dry films on rough surfaces
ISO 2409 Paints and varnishes - Cross-cut test
ISO 2431 Paints and varnishes - Determination of flow time by use of flow cups
ISO 2808 Paints and varnishes - Determination of film thickness
ADNOC Specifications
The ADNOC Business Unit specifications listed shall also be considered part of this specification, where indicated
as applicable in the Purchase Order.
Applicable ADNOC Business Group specifications shall form part of this specification where they are specifically
indicated as applicable in the Purchase Order.
Standard Drawings
None at present.
DOCUMENT PRECEDENCE
The specifications and codes referred to in this specification shall, unless stated otherwise, be the latest approved
issue at the time of contract award.
It shall be the CONTRACTOR's responsibility to be, or to become, knowledgeable of the requirements of the
referenced Codes and Standards.
The CONTRACTOR shall notify the COMPANY of any apparent conflict between this specification, the related
data sheets, the Codes and Standards and any other specifications noted herein.
Resolution and / or interpretation precedence shall be obtained from the COMPANY in writing before proceeding
with the design / manufacture.
In case of conflict, the order of document precedence shall be:
UAE Statutory requirements
ADNOC HSE Standards
Equipment datasheets and drawings
Project specifications and standard drawings
COMPANY specifications
National / International Standards
Design Basis
All painting and coating systems shall meet the performance requirements and the coating systems as specified
in this specification with a minimum environment of Category CX, ISO 12944-9.
All Offshore requirement shall comply to ISO 12944-9.
EXECUTION
Any painting procedures submitted by the SUPPLIER and approved by the CONTRACTOR and COMPANY shall
be considered additional to the requirements of this specification but shall not be considered in lieu of or
substitution for the procedures and requirements stated in this specification.
In case of packaged equipment, electrical equipment and other MANUFACTURER’s standard items, the paint
system shall be suitable for environmental classification of CX as per ISO 12944-2 and ISO 12944-9 for Offshore,
unless otherwise specified by COMPANY.
Application Procedure
A detailed application procedure shall be established by the CONTRACTOR / SUB-CONTRACTOR for
COMPANY approval based on the requirements of this specification. No painting work shall begin before the
application procedure is approved by COMPANY.
The application procedure shall include at the minimum the following information:
Equipment / structure / piping to be coated.
Range of operating temperature of the equipment.
Type of substrate to be coated: carbon steel, stainless steel, galvanized steel, non-ferrous alloy, etc.
Exposure: atmospheric, immersed, buried, under insulation / fireproofing.
Painting system to be used from APPENDIX A2.
Coating products to be used.
Ambient / environmental conditions required for safety and quality of work.
Surface preparation method, including detail of the abrasive intended to be used.
Methods of application and application requirements, including the colour of each coat.
Test and inspections in accordance with Section 14.
MATERIALS
All paints used shall be obtained from Coating MANUFACTURERs approved by the COMPANY.
Equipment and materials specified or referenced by the Coating MANUFACTURER’s name and / or brand name
are intended to describe the type and quality level of the equipment and materials desired and are not intended
to be restrictive or to exclude similar items by other Coating MANUFACTURERs. Alternate equipment and
materials of similar quality or better may be submitted for CONTRACTOR and COMPANY approval.
All material shall be supplied in the Coating MANUFACTURER's original containers, durably and legibly marked
with the description of the contents, colour reference number, batch number, date of manufacture, the shelf-life
expiry date and the Coating MANUFACTURER's name or recognized trademark.
Paints containing heavy metals, such as cadmium, lead, coal tar epoxy or any toxic material to environment /
personnel shall not be used.
Different brands or types of paints shall not be inter-mixed.
The storage and preparation of paints and other coating materials shall be in accordance with the Coating
MANUFACTURER's instructions. Samples for testing the paint being used may be taken by the COMPANY at
Abrasives
Abrasive for use on carbon steel and low alloy steels shall be in accordance with ISO 8504-2. Abrasives shall be
grit manufactured from chilled iron, steel, and malleable iron; non-metallic abrasives such as aluminium oxide
and garnet. Abrasive shall be angular in shape.
Abrasives for use on stainless steel, duplex, super austenitic materials and other CRA surfaces where painting is
required shall be free from chlorides, zinc, and ferrous contamination. Abrasives shall be glass beads, aluminium
oxide and garnet.
All abrasive material to be used shall be approved by COMPANY / CONTRACTOR. Silica sand or other media
producing silica dust shall not be used.
Blasting abrasives shall be dry, clean and free from contaminants that will be detrimental to the performance of
the coating. Abrasives selected shall be suitable for producing the required profile and surface roughness and
have a minimal health impact.
The properties of abrasives used shall meet the requirements of the relevant parts of ISO 11124, ISO 11126-4,
ISO 11126-7, ISO 11126-10, SSPC-AB 1, SSPC-AB 3 and SSPC-AB 4.
Test methods shall be in accordance with the tests specified in ISO 11127.
Each batch of abrasive should be tested from COMPANY approved laboratory to check that the abrasive meets
the requirements as specified in the relevant ISO standard.
The conductivity of abrasive for carbon steel and stainless steels shall be a maximum of 150 µmS/cm.
Conductivity shall be checked at site for each batch and delivery of abrasives.
The COMPANY shall approve the use of alternate abrasive materials after testing and evaluation.
Almandite garnet is an iron aluminium silicate with the chemical formula Fe3Al2(SiO4)3. Other forms of garnet,
such as andradite garnet, which is a calcium iron silicate with the chemical formula Ca3Fe2(SiO4)3, exist but
these garnet abrasives are not covered in ISO 11126.
Selection of Abrasives
Steel or iron grit is commonly used as recyclable abrasives. In general, when steel shot is used, it shall be used
together with steel grit and approved by the COMPANY. The shot content in such a mix shall not exceed 67%.
The abrasives shall be free from oil, grease, moisture, chloride contamination, etc., and supplied with certification
documentation traceable to batches of material. Abrasive (mesh size ranges) sizes to be selected based on the
blast clean profile required.
Effective recycling system of the metallic abrasives shall be provided by the SUB-CONTRACTOR. Conductivity
of the recycled metallic abrasives shall be checked a minimum of two times per shift.
Only approved Garnet shall be used as an abrasive media on Offshore installation. Garnet shall be used for all
site works and yard work where there is no recovery system in place. Garnet used on COMPANY facilities shall
be from Company approved Abrasive MANUFACTURERs.
Garnet Blasting Media used for COMPANY work shall conform to the following requirements:
Compressed Air
The compressed air supply used for abrasive blasting shall be free of water and oil. Adequate separators and
traps shall be provided, and these shall be kept emptied of water and oil and regularly purged. The control of
compressed air cleanliness shall be in accordance with ASTM D4285.
Compressed air temperature shall not exceed 90°C at the blasting nozzle. In addition, the pressure at the nozzle
shall not be below 90 psig / 6.21 barg.
After cooler shall be used during summer to ensure the air is dry. It shall be tested for oil and moisture by blotting
paper test regularly. Oil traps and moisture traps shall be cleaned when required.
Where personal breathing equipment is used, the operator's hood or headgear shall be ventilated by clean cool
air, free from water, oil and any other organic contaminants served through a regulator filter to prevent blasting
residues from being inhaled by the operator. Air supplies must comply as a minimum with BS EN 14594 and the
quality of the breathing air shall be checked regularly.
Paint Materials
Paints for use over stainless steels or nickel alloys shall be free from low melting points (e.g. halides, zinc, etc.)
which might cause embrittlement.
All paints and related materials shall be as identified in the respective Paint Systems.
Primers, mid-coats, and finishes shall be factory tinted, sealed, and labelled. Thinners and solvents shall be as
identified in the Coating MANUFACTURER’s data sheets.
All paint materials shall be used on a first-in, first-out basis.
Polyurethane finishes shall have excellent colour retention and high gloss.
Primer colours shall be Coating MANUFACTURER’s standard colours. Finish colours, except for silicone
aluminium, shall be as noted in the applicable Safety and Identification Colour Coding requirements. For services
above 93°C, if heat stable colours matching specified colours are not commercially available from the Coating
MANUFACTURER’s standard stock, heat stable colours shall be selected regardless of colour match subject to
COMPANY’s choice of standard stock colour.
CONTRACTOR / SUB-CONTRACTOR shall bear responsibility in VOC (Volatile Organic Compounds) emissions
and monitor the use of the solvents as directed by the Coating MANUFACTURER during all paint application.
Paint material supplied / applied shall be from the same Coating MANUFACTURER throughout the coating
system. Different brands or types of paint shall not be inter-mixed
All proposed materials shall be supplied with an infra-red fingerprint and ash content of all components in
accordance with recognised International Standards (see Section 2.1) with the approval documentation. The
COMPANY shall require at least two random samples from each coating product to be taken during the coating
activities and tested at an independent laboratory to confirm that the supplied goods match the proposed products.
The following properties of the components associated with each coating product shall be identified:
An infrared spectrum of the mixed paint components (fingerprint).
Specific gravity of the resin base and curing agent and the mixed paint components (ISO 2811).
Volatile and non-volatile matters in the mixed paint (ISO 3251).
Viscosity of the resin base, curing agent and the mixed paint components (ISO 2431).
Fineness of grind of the mixed paint components, Hegman scale (ISO 1524).
Percentage of zinc by weight (zinc rich primers only), percentage weight in the dry film shall be measured
using test panels.
Percentage of glass flake by weight (glass flake containing coatings only), percentage weight in the dry
film shall be measured using test panels.
For the zinc rich primer, organic or inorganic, the content of zinc dust by weight shall conform the Level
1 of the standard SSPC Paint 20. The zinc dust pigment shall comply with the requirements specified in
standard ASTM D520.
For zinc phosphate primer, based on polyamide cured two pack epoxies. Zinc phosphate content shall
be not less than 20% by weight in the dry film.
Micaceous Iron Oxide epoxy (MIO) pigments shall be minimum 80% weight of total pigmentation being
mainly min. 85% natural laminar ferric oxide (Fe2O3). Volume solid content 80% ±5.
Glass Flake product shall contain glass flake in the cured film not less than 20% of total pigmentation.
Paint System Qualification Tests for each specification shall also be included.
Hazardous Materials
This specification may call for the use of hazardous substances and procedures. Handling for application and the
subsequent disposal of all surface preparation consumables and coating materials specified in this specification
shall conform to all relevant local regulatory requirements and bylaws.
The CONTRACTOR shall ensure that all layers of a coating system and all abrasive blasting materials comply
with any local and / or regional standards or regulations on banned materials such as lead, chromate, crystalline
silica or coal tar. Any coating system shall fully comply with any local and / or regional air quality or VOC levels
or emission standards or regulations.
MSDS’s shall be available for review at sites and shops where coating is applied. All PPE requirements stated in
the MSDS shall be met when working with coatings and solvents.
GENERAL REQUIREMENTS
Steel Preparation
Fabrication should be complete before surface preparation begins. Any prefabrication ‘shop’ primers shall be
removed after fabrication by blasting and the surface shall be blasted to the specified surface cleanliness unless
otherwise agreed with the COMPANY. The method for repair of pitted steel prior to coating application shall be
agreed with COMPANY.
Flame cut areas and weld spatter shall have been ground flush with the requirements of ISO 8501-3, preparation
Grade P3. SUB-CONTRACTOR is responsible for inspecting steel preparation at steelwork reception and for
highlighting any non-conformance to CONTRACTOR.
All mating surfaces of equipment subject to outdoor exposure shall be coated with the full coating system prior to
assembly (saddles, skirts, base plates, bolted components, flanges, etc.).
Pre-Job Meeting
The SUB-CONTRACTOR shall schedule a pre-job meeting to ensure that job requirements are fully understood.
The personnel present at the meeting shall include, but not be limited to, the COMPANY’s and CONTRACTOR’s
representative, the SUB-CONTRACTOR’s representatives, painting engineer, quality control and safety.
If required a technical representative of the Coating MANUFACTURER / SUPPLIER shall be present.
Roles and responsibilities shall be clarified at the pre-job meeting, such as when the COMPANY deals with the
SUB-CONTRACTOR, who are the focal points and how administration procedures are executed.
Technical aspect such qualification of SUPPLIERs / Sprayers, approved application procedures, equipment,
approved Inspection Test Plan (ITP) shall be discussed. It shall be confirmed that all parties have the latest
version of the contract, application procedure, technical specification, approved drawings and ITP.
SURFACE PREPARATION
Items to be Protected
Before abrasive blast cleaning, all equipment which could be damaged by blast, dust or particulate matter shall
be suitably protected by wrapping, taping, or other means to prevent damage. This equipment shall include, but
is not limited to the following:
Bearings
Conduit
Control panels
Control valves
Basic Cleaning
The following cleaning procedure is mandatory for all surfaces before blast cleaning. This cleaning procedure is
also mandatory before applying field coatings over shop coated items and any surface which requires coating.
Dust, dirt and debris shall be removed from the substrate surfaces by high pressure fresh water washing.
Stubborn deposits shall be removed by scrubbing with stiff plastic brushes. The water wash shall continue until
all water-soluble salts are removed from the surfaces.
Prior to paint application the blasted substrate shall be tested for Soluble Salts as per ISO 8502-6 & 9 by Bresle
kit and maximum levels are indicated on each paint system in this specification.
Surface contaminants such as oil, grease, hydrocarbons etc. shall be removed by water based biodegradable
cleaner in accordance with the application data. SUB-CONTRACTOR shall request and obtain Coating
MANUFACTURER’s recommendations for the cleaner concentration, appropriate for the type of surface to be
cleaned.
The degreased surfaces shall be further washed with fresh water to remove all traces of the cleaner chemicals.
Shop Priming
The CONTRACTOR, in case of particular yard conditions, procedures and / or other project requirements, may
use shop-primed steel plates and profiles for the construction of the various items. The shop-priming shall be
performed in accordance with the following requirements:
The surfaces (steel plates, pipes, beams, profiles etc.) shall be cleaned by abrasive blast cleaning in
accordance with standard SSPC-SP 10 / NACE No. 2.
Application of one coat of Inorganic Zinc Ethyl-Silicate shop-primer (prefabrication primer) with DFT of 25
microns.
The shop-primer and the relevant DFT shall conform the standards, cutting and welding procedures and shall be
approved by the competent authority.
The above procedure shall be performed only in shops with automatic equipment both for the steel grit blasting
and for the shop-primer application.
CONTRACTOR shall perform all required checks two times per shift and any malfunction of the equipment and/or
working defects shall be promptly corrected and repaired.
Metallic abrasives shall meet the requirements of ISO 11124 Parts 1 to 4, applicable to the type of abrasive
intended to be used. Tests and controls shall be completed according to ISO 11125 Parts 1 to 7.
Pre-Blast Cleaning
Welded areas shall be cleaned, and ground as needed to remove sharp rough areas. Weld reinforcement removal
is not required, if the reinforcement has rounded edges. Sharp edges, fillets, corners, and weld seams shall be
radiused or smoothed to a minimum of 3 mm. All bolt holes shall be drilled and ground prior to blast cleaning.
The SUB-CONTRACTOR shall give special attention to all weld areas for removal of burrs, weld spatter, weld
flux, slivers indentations, protrusions and other foreign matter to be removed by grinding prior to abrasive blast
cleaning. If grinding is to be carried out after blast cleaning, the ground surface shall be re-abrasive blasted to
restore the specified profile.
Supports for items to be blast cleaned shall have a configuration such that the contact points are as small as
practical to limit surface area covered.
Random salt contamination tests shall be carried out to verify the need or otherwise for solvent detergent washing
(or alternative method) prior to abrasive blast cleaning.
All steel stored in a coastal site or shipped as deck cargo shall be water washed and checked for salt
contamination prior to coating operations. The frequency and nature of these checks shall be sufficient to ensure
the surface cleanliness of the substrate.
Any oil, grease or other contaminants on the working surface shall be removed by solvent cleaning in accordance
with SSPC-SP 1.
Surface Profile
At the beginning of each project, blast cleaned steel sample plates to assess blasting operators shall be prepared
in compliance with the surface preparation requirements in the Procedure Qualification Test (PQT).
The anchor profile shall be measured in accordance with ISO 8503-2 or ISO 8503-5.
For field measurements of surface profile, the following methods may be used:
Replica tape.
Portable micrometre.
Checks on surface profile shall be made on each component of prepared surface and a minimum of 3 times per
blasting operator per day.
PAINTING APPLICATION
Scheduling
Painting shall NOT be applied when:
The ambient temperature is less than 4°C.
The relative humidity is more than 85 percent, except for Inorganic Ethyl Zinc Silicate up to 95%.
The surface temperature is less than 3°C above the dew point.
The metal surface temperature is higher than 50°C except for special paint systems in accordance with
Coating MANUFACTURER’s recommendations / datasheet.
Surface preparation has not been completed or oil, grease, and dust are present on the substrate to be
painted.
Poor weather conditions for painting exist or are expected within two hours of application such as blowing
sand, fog or rain.
Where there is a deposition of moisture in the form of rain, condensation, frost, etc. on the surface.
Where the available light is less than 500 lux.
Painting Application
Surfaces shall be painted with paint systems specified in APPENDIX A1.
Paint shall be applied to dry, clean, prepared surfaces under favourable conditions and in accordance with the
Application Data.
Pigmented and catalysed materials shall be thoroughly mixed using power mixers before being applied. Sticks
shall not be used.
Continuous agitation type spray pots shall be used when applying metal pigmented coatings such as zinc or
aluminium loaded coatings.
A mist coat shall be applied over inorganic zinc primer to avoid surface defects. The SUB-CONTRACTOR shall
exercise necessary care to ensure a smooth and uniform coating is applied over inorganic zinc primer.
Application Checks
12.5.4 Adhesion
The quality of adhesion between the coating system and the steel substrate, and of the adhesion between the
coating layers, shall be measured as follows:
5 MPa for zinc primed coating systems.
7 MPa for non-zinc primed coatings systems.
For coating systems with a maximum total NDFT of 150 µm, a crosscut test in accordance with ISO 2409, Class
O.
Testing shall be completed on fully cured systems according to the Coating MANUFACTURERs
recommendations given in the product datasheet. This shall not be less than 7 days after the application of the
final layer for epoxy systems. Adhesion testing shall be carried out on test plates coated at the same time as the
inspected components.
General Requirements
SUB-CONTRACTOR shall submit a repair procedure for each coating system.
Prior to the application of succeeding coats, all damaged and defective areas shall be repaired to specification
requirements.
Adhesion qualification tests are mandatory and shall be performed to determine the compatibility for each repair
method.
Surface preparation shall wherever possible be carried out by dry blast cleaning. If dry blast cleaning is not
specified or not feasible (e.g. due to limited access, risks of damage to equipment, light gauge steel, the proximity
of electrical components or instrumentation), then power tool to manual cleaning by mechanically operated tools
shall be performed. In this instance, the use of power or mechanically operated tools is subject to COMPANY
approval.
Unless otherwise specified Bristle Blasting, power tooling shall be carried out in accordance with the requirements
of ISO 8504-3 and ISO 8501-1 Grade St 3.
Power tool cleaning (grinding) to Barge metal shall be completed in accordance with SSPC-SP 11, if approved
by COMPANY.
Bristle Blaster power tooling is acceptable for use on small area preparation such as inaccessible areas. Areas
and frequency of use are subject to COMPANY approval.
Compare the degree of cleaning offered by bristle blasting utilizing the pictorial standard issued by the Steel
Structures Painting Council, SSPC-VIS 3.
When bristle blasting technique used for inaccessible area surface preparation, a surface tolerant coating system
shall be applied. The surface tolerant coating system is subject to COMPANY approval.
If the surface being prepared lies adjacent to a coated surface not requiring to be repaired, the surface preparation
shall overlap the coated surface by at least 50 mm. The remainder of existing coated surface shall be adequately
protected with shields or screens to prevent any possible damage to the coating.
Inorganic zinc primer shall not overlap adjacent intermediate and finish coats. Any overlapping shall be removed
with fine grade of emery paper.
Areas with inadequate painting thickness shall be thoroughly cleaned, prepared and additional compatible coats
applied until they meet this specification. These additional coats shall blend in with the final coating on adjoining
areas. Colour match shall be achieved.
General
The COMPANY and CONTRACTOR shall have the right to inspect the paint work at all stages of preparation and
to reject any tools, materials, equipment or work which do not conform to this specification. Before painting
activities commences, the CONTRACTOR shall submit an Inspection and Test plan for COMPANY approval.
CONTRACTOR shall employ a qualified Painting Inspector whose resume shall be approved by the COMPANY.
CONTRACTOR Qualified Inspector shall have either NACE CIP Level-2 (National Association of Corrosion
Engineers), FROSIO Level-2 (The Norwegian Professional Council for Education and Certification of Inspectors
for Surface Treatment) or BGAS-CSWIP Level 2 certification or equivalent and approved by COMPANY.
All items painted by the SUB-CONTRACTOR shall be inspected on arrival. All damaged areas shall be repaired
by SUB-CONTRACTOR / CONTRACTOR. In cases where there is damage of more than 5% of the surface area
not exposing to Barge metal or, the finish coat appearance is not acceptable, COMPANY reserves the right to
instruct CONTRACTOR to rectify the defects in accordance to this specification at no cost to COMPANY.
Minimum inspection intervention points / items shall be included in ITP as minimum.
After Painting
After application of painting, SUB-CONTRACTOR shall verify and document dry film thickness of the primer,
intermediate and finish coats. In accordance with SSPC-PA 2.
Each coat of a system and the complete system shall be visually inspected for adhesion and surface imperfections.
If upon visual inspection, loss of adhesion is suspected or found, an adhesion test shall be made. In all cases,
complete system involving silicone-based paint shall be tested for adhesion by pull-off test method. The adhesion
of the primer to the steel substrate and the inter-coat adhesion of the subsequent coat(s) after curing shall be
determined by the application of either a cross-cut test in accordance with ISO 2409 to maximum grade C2 or a
pull-off test described in ISO 4624, 5 MPa for zinc primer based system and 7 MPa for non-zinc primer system.
TSA coatings applied to blast cleaned steel surface, exhibiting an adhesion of less than 7 MPa shall be rejected.
Each painting system and repair method shall be tested on a test plate for an adhesion qualification test. The test
plate shall be painted at the same time and under same conditions as the production work.
Repairs made in the field shall be documented and re-inspected as outlined above.
General
The Painting CONTRACTOR’s facility and painting equipment shall be qualified prior to starting any production
painting operations.
The qualification program for production and the pre-approval qualification shall include application of TSA coating
of pipe or components, as applicable for the work to be undertaken and shall include all the testing required. Both
of these exercises shall be witnessed by an authorized representative of the COMPANY. Where applicable, it
shall also be witnessed by the CONTRACTOR and any 3rd party inspectors. Where significant changes are been
made in the TSA application process or materials, CONTRACTOR shall demonstrate that the coating will meet
the requirement by providing additional test data on the TSA coating application. Data shall cover both the TSA
application process and materials.
Where requested by the COMPANY or CONTRACTOR, an application trial shall be conducted at the painting
application site. As part of the trial, the painting CONTRACTOR shall coat a sample to demonstrate that the
applicable procedure and quality control will produce coatings that meets the requirements of this specification.
All coatings shall meet the requirements proposed for the system and shall be applied using equipment and
procedures to that used for production coating application.
Bend test:
Each thermal sprayer shall prepare and spray a minimum of three comparison bend test coupons (dimensions
as per SSPC-CS 23.00 / AWS C2.23M / NACE No. 12). The thermal spray bend test coupons shall not be sealed
or top coated. The coating thickness shall be as specified in the specification.
The bend test entails bending at least three thermal spray coated steel coupons through 180° on a 13 mm (1/2
in) diameter steel mandrel.
Should any one of the bend tests fail the acceptance criteria specified in Table 15.1, the thermal sprayer may
make one additional attempt to qualify by spraying and testing a further three coupons. Should any one of these
fail, the sprayer shall be deemed to have failed the qualification test.
Adhesion test:
Each thermal sprayer shall apply TSA at the required thickness onto a test panel (thickness 6 mm (0.25 in), with
a minimum surface area of approximately 1 m² (10.7 ft²). The painted surface shall not be sealed or top coated.
The adhesion strength between the thermal spray coating and the steel substrate shall be measured by means
of a portable, self-aligning, hydraulic controlled adhesion tester in accordance with ISO 4624. The adhesive
between the dolly and the thermal spray coating shall be an epoxy.
A minimum of three pull off adhesion tests shall be conducted. Should any one of the pull off adhesion tests fail
the acceptance criteria in Table 15.1, the thermal sprayer may make one additional attempt to qualify by spraying
and testing a further panel. Should any one of the subsequent pull off adhesion tests fail, the sprayer shall be
deemed to have failed the qualification test.
Sealer:
TSA shall be top coated with a sealer coat to close the TSA porosity following completion of the pull off adhesion
tests, the test panel used shall be sealed with the project sealer material.
The sealer coat shall be selected based on the operating temperature of the TSA coated surface. The sealed
surface area of the thermal spray coated test panel shall be examined holiday testing. The sealed surface shall
show 100% coverage, no holiday and no open pores shall be present at the surface.
Summary of qualification tests and acceptance criteria:
Table 15.2 Test Requirement for TSA Coating During TSA Production Coating
Property Test Method Measurements Acceptance Criteria
Coating Appearance Visual Inspection 100% surface Uniform appearance, no blister,
Barge patches, defects or non-
adhering coating.
Coating Thickness ISO 2808 All surfaces 250 to 500 microns
Coating Adhesion ISO 4624 At least 3 at random > 7 MPa (1000 psig / 68.95 barg)
Single measurements.
Bend Test SSPC-CS 23.00 / At least 3 Minor cracks, with no coating
AWS C2.23M / NACE lifting or spalling.
No. 12
Sealer Visual Inspection and 100% of surface 100% coverage, no open pores
Holiday Test present at the surface / No
holiday.
Coating Repair
The SUB-CONTRACTOR shall produce a painting repair procedure, to be agreed by the COMPANY. Only
qualified painting repair methods shall be used, in compliance with this specification. This repair procedure shall
be verified and approved during the qualification trials. If the thermal spray coating has been mechanically
damaged and Barge substrate metal is observed, the painting shall be repaired, including the local (repair)
application of a new sealer, and / or topcoat, if applicable.
The damaged area shall be pre-cleaned, followed by local blast cleaning to a minimum of Sa 2.5, in compliance
with this specification.
Edges of the remaining existing painting system shall be feathered by abrasive blasting, and the remainder of the
adjacent coated surface shall be properly protected.
Local repair application of thermal spray coating shall follow this specification, including the application of new
sealer and topcoat.
In cases where defect sizes are small, it may be acceptable to use a liquid paint to repair the damage. The
maximum defect size allowable for liquid paint repair shall be 10 cm 2 (1.55 in2). The use of liquid paint repairs
shall be approved by the COMPANY.
Where thermal spray coatings show local surface damage, the area shall be pre-cleaned followed by localised
sweep blasting. The adjacent coated surface shall be properly protected (masking). The locally restored thermal
spray coating, including sealer / topcoat, shall meet the minimum thickness requirements.
Where the sealer or topcoat has been damaged, the surface shall be prepared by abrasion with medium coarse
abrasive until a clean bright surface is visible. Edges of the remaining coating at the location of the repair shall
be feathered. The re-applied sealer / top-coat system shall be compatible with the existing painting system.
General
The implementation of a maintenance painting option for a coating remedial work should be in accordance with
COMPANY policy related to the activities which are undertaken to preserve the integrity or the functionality of
structures, process system and equipment.
Refurbishment
Renovation Procedure
After the complete initially coated surfaces have been pre-cleaned, all surfaces shall be blast cleaned. Carbon
steel and low-alloy steels shall be blasted to the visual standard SSPC-SP 10 / NACE No. 2 at the time of coating.
After the surface preparation, a completely new coating system shall be applied. Renovation shall be considered
if the rusting pattern as described in ISO-4628-3 is pin-pointed over the whole coated area or if the rust grades
are higher than those described under refurbishment.
Stainless Steels
Where coating maintenance to stainless steel surfaces is required, the entire surface shall be thoroughly sweep
blasted to remove flaking and poorly adherent paint and to provide a surface roughness to any well-adhered paint
surfaces. This shall then be followed by the appropriate, compatible maintenance painting system.
GENERAL
This section defines the lining systems intended to be applied to the interior of process / pressure vessels, piping,
tanks and equipment for oil and gas production and processing facilities of COMPANY.
Internal lining of vessels is not permitted when operated at pressure ≥ 50 Barg.
If any requirement or operating parameters not covered in following section, the coating system shall be evaluated
on individual case by case basis by COMPANY.
HANDLING
Preparation for shipment of all lined items shall be in accordance with the Lining MANUFACTURER’s and SUB-
CONTRACTOR’s standards. SUB-CONTRACTOR shall be solely responsible for the adequacy of the
preparation for shipment provisions with respect to materials and application, and to provide equipment at the
destination in ex-works condition when handled by commercial carriers.
Adequate protection of lined equipment and piping shall be provided to prevent mechanical damage and
atmospheric corrosion in transit and at the job site.
Preparation for shipment and packing will be subject to inspection and rejection by COMPANY’s /
CONTRACTOR’s inspectors. All costs of lined equipment occasioned by such rejection shall be to the account
of the SUB-CONTRACTOR.
After inspection and test, equipment or piping shall be completely free of water and dry before start of preparation
for shipment.
EXECUTION
Internal lining shall be with accordance to COMPANY’s approved / qualified lining system. Prior to commence the
internal lining works, CONTRACTOR / SUB-CONTRACTOR shall submit a detail application procedure with
approved lining system.
The SUB-CONTRACTOR is solely responsible for supply of installed and consumable materials, equipment (air
compressor, after cooler, blast cleaning, dehumidifying, ventilation, spray etc.), tools, instruments and labour
(application, supervision, quality control etc.) and each and every item of expense to supply, apply, cure and
check the integrity of the entire lining system in accordance with this specification. Application of the lining system
consists of, by way of example but not by limitation, surface conditioning, degreasing, removal of water solubles,
blast cleaning, priming (if applicable), lining application, full cure and quality checks and any repairs.
All blast cleaning personnel and lining personnel shall be prequalified at least one week prior to start of work.
Each qualified person shall wear an identification badge which shows that he / she has been tested and qualified
to perform the work.
The lining work shall be performed when all the following conditions exist:
All blast cleaning and lining personnel are pre-qualified.
All inspection equipment is ready.
All Referenced Panels are ready and approved by CONTRACTOR and COMPANY.
All specified materials are available on site with suitable storage e.g. air conditioning.
Degreaser
The degreaser shall be water based biodegradable cleaner.
Abrasives
Abrasives shall be composed of clean, hard particles free from foreign substances such as dirt, oil, grease, toxic
substances, organic matter, mill scale, soil and water-soluble salts. The pH of the abrasive materials shall not be
below 6.2. The moisture content of the selected abrasive shall not exceed 0.5 percent by weight. The conductivity
of deionized water extract of the abrasive material shall not exceed 150 micro-siemens/cm.
Abrasive shall be garnet for blast cleaning all surfaces. Steel grit or garnet may be used for blast cleaning tank
floors. Silica sand, copper slag, and steel shot shall not be used.
The abrasive shall be capable of producing the degree of cleanliness and surface profile specified in this
specification.
The particle size of the abrasive shall be 0.1 mm to 1.5 mm.
Equipment
Spray equipment shall be maintained in good working order and shall be comparable to that described in the
Application Data.
Dehumidifying equipment shall be of a sufficient size to provide the required air changes at the temperature and
humidity levels stated in the Application Data.
Compressed Air
All air compressors shall be of a sufficient size to deliver 7 kg/cm 2 at the nozzle. Each compressor shall have two
oil / moisture filters, one located at the compressed air exit of the compressor and one located just before the
after cooler.
Compressed air used for blasting and lining application must be clean, oil free and dry.
The compressed air shall be passed through a dryer package.
Proper functioning of the in-line moisture and oil traps shall be evaluated daily by allowing the air supply
(downstream from the traps) to blow against a clean, white cloth in accordance with ASTM D4285. No moisture
or oil should be deposited on the cloth. If contaminants are detected, the equipment deficiencies shall be corrected,
and the air stream shall be retested. Surfaces determined to have been blasted since the last successful test
shall be degreased and re-blasted with clean air and abrasive. Linings determined to have been applied using
contaminated air shall be removed and new linings applied using clean air.
Lining Materials
Lining materials shall be as stated in APPENDIX A12.
Thinners and cleaners shall be products of the MANUFACTURER of the lining system materials and as
recommended in the Application Data. Cleaners shall not be used as thinners.
GENERAL REQUIREMENTS
Surface Conditioning
SUB-CONTRACTOR shall ensure compliance with the following design guidelines and NACE SP0178 prior to
surface preparation and lining application:
All edges of clips, plates and other items shall be rounded or chamfered to a minimum radius of 3 mm.
All interior welds shall be continuous seal welds.
Dehumidification
Surfaces must be maintained at least 3°C above the dew point, immediately before and during the lining
installation and remain in this condition during curing. To comply with this requirement, dehumidifying equipment
shall be at the site. The capacity of the dehumidifying equipment shall be as recommended by the dehumidifying
equipment Lining MANUFACTURER.
The typical minimum dew point differential specified for holding a blast over an extended period of time is 9 to
14°C with a relative humidity not to exceed 40% to 55%. The CONTRACTOR should refer to SSPC-TR 3 / NACE
6A192 - “Dehumidification and Temperature Control during Surface Preparation, Application, and Curing for
Coatings / Linings of Steel Tanks, Vessels, and Other Enclosed Areas” for guidance. The air temperature, relative
humidity, dew point and steel temperature are to be recorded hourly throughout the duration of the work through
a computerized system as well as verified manually. A detailed method statement on how the CONTRACTOR
proposes to maintain the environmental conditions throughout the duration of the work is to be submitted.
Ventilation
During all blast cleaning operations, ventilation shall be maintained to allow adequate visibility and for safety.
Flexible ventilation ducts shall be used to allow the point of extraction to be reasonably close to the blaster. The
ventilation ducts shall be arranged so that dead spaces do not exist.
Ventilation must be maintained during the entire lining application and continue while the solvent is released from
the lining film during drying. The ventilation system must prevent the vapor concentration from exceeding 10
percent of the lower explosive limit (or less than this if required by the local regulations).
Proper exhaust shall be maintained using ducts of appropriate size at various levels inside the item being lined.
The number of air changes in confined spaces during lining installation and curing shall be 10 air changes per
hour. The forced cross air ventilation shall be maintained during the entire curing period of internal lining after the
application of the lining system.
To minimize dry spray during application, a lower level of ventilation shall be maintained. The number of air
changes shall be determined by the SUB-CONTRACTOR subject to safety considerations.
Provisions shall be made for 24-hour surveillance of any ventilation equipment.
Lighting
In accordance with SSPC-Guide 12 for illumination of industrial painting projects.
Surface Preparation
All Surfaces shall be degreased with a biodegradable water based cleaner. Degreased Surfaces shall be
thoroughly washed to remove any film of the degreaser.
All water-soluble compounds shall be removed by additional washing with potable water. After washing, the
Surfaces shall be tested for water soluble salts with a salt testing kit, approved by COMPANY, in accordance with
ISO 8502-6 & 9, the Bresle method. If the quantity of water-soluble salts is more than 2 micrograms per square
centimetre, washing shall be repeated until the acceptable range of soluble salt is attained.
Surfaces shall be dried with natural ventilation. If forced air is used, the air shall be oil free.
All coatings applied in the shop such as prefabrication shop primers shall be completely removed by blast cleaning.
All Surfaces shall be blast cleaned with clean, dry premium grade garnet to white metal. Floor Surfaces may be
cleaned with steel grit if a vacuum blast cleaning unit is used.
Garnet shall not be recycled for blast cleaning. Steel grit may be reused for floor surfaces when a vacuum blast
cleaning unit is used provided the grit is checked for oil contamination at least once per every 100 square meters
of floor surface and recyclable unit is available. If oil contamination is suspected, the grit shall be immediately
discarded, and 100 percent of the cleaned floor surface shall be checked for oil contamination using a black light.
Any contamination on the floor shall be completely removed.
Before initial blast inspection, the bulk of the spent abrasive shall be removed. Any substandard areas including
burrs, slivers, scabs and weld splatter shall be identified and repaired. All marking paint, chalk, etc. shall be
removed after repairs.
All Surfaces shall be thoroughly cleaned to remove all embedded materials from the surface. Industrial vacuum
cleaners fitted with non-metallic brushes shall be used to remove surface dust and embedded materials. Blowing
the dust with compressed air is not permitted.
Cleaning shall be carried out on all areas on which debris or dust can collect. This shall include bit is not limited
to scaffolding, underside of the lowered floating roofs, support columns, etc.
The steelworks for lining application shall be checked after the final cleaning process is finished in accordance
with applicable ISO.
During blast cleaning operations, the spent abrasive shall be periodically removed. Before the end of day, all
spent abrasive shall be removed, and floor surface shall be kept tidy.
General Requirements
Lining application shall not commence when the substrate temperature is higher than 50°C or as required by
Application Data where this is more stringent.
If specified as a part of the lining system, a prime coat or the first coat of the lining system shall be applied within
a maximum of four hours after the abrasive blast cleaning operation is completed or, before blasted surfaces start
to rust, whichever is sooner. Surfaces that change colour or rust bloom begins to form shall be re-blast and
cleaned to the specified degree of cleanliness.
All weld lanes, edges of support steel, steel plate laps, or other irregular surfaces, where spray application of
material may result in holidays or inadequate dry film thickness, shall have the first coat applied by brush.
Roller application of the lining is not allowed.
The applied lining shall not have any surface defects such as cracking, runs, sags, voids, drips, overspray, dry
spray, pinholes, blisters, craters, orange peel, fisheyes and other defects.
The bond strength between the substrate, the lining and between coats shall not be less than the requirements
stated in Section 26.6.Testing shall be in accordance with ISO 4624 after full cure and at the time of holiday
testing.
The dry film thickness of each coat shall be within the minimum and maximum limits stated in APPENDIX A12 or
as required by Application Data where this is more stringent.
Lining Systems
Surfaces shall be lined in accordance with the Lining Schedules within APPENDIX A11, the Lining Systems within
APPENDIX A12, and Tank Data Sheets. The systems are specified by generic type and approved by COMPANY.
Mixing of Materials
Mixing of materials shall be completed using power type mixers and always in the proportions and the order
specified in the Application Data. Mixing shall be completed at moderate speeds so that air bubbles and / or
moisture is not introduced into the lining materials. Any lining materials into which either air or moisture are
inducted shall be discarded.
Recoating
Drying times between coats shall be in accordance with the Application Data.
Unless otherwise approved by COMPANY, the minimum recoating time shall be at least 24 hours and the
maximum recoating time shall not exceed 75 percent of the longest recoating time stated in the Application Data.
Curing
The SUB-CONTRACTOR is solely responsible for full curing of the lining system including repaired areas.
The curing shall be in accordance with this specification.
The SUB-CONTRACTOR shall transfer custody and control of the vessels, piping, tanks or equipment to the
CONTRACTOR after full cure of the lining systems and linings are in the ready-to-use condition.
LINING IDENTIFICATION
All tanks, pressure vessels, and equipment that have been internally lined shall be marked as follows:
The Interior of This Equipment Is Lined with (Lining Brand Name and Catalogue Number).
Lining MANUFACTURER’s Address (City, Country).
Do Not Weld.
Date of Application.
The marking letters shall be at least 150 mm high and in contrasting colour. Marking shall be applied at all nozzles
and shall be in English and Arabic.
LINING REPAIR
The decision to repair lining defects shall be made on a case-by-case basis by the COMPANY.
Lining repairs shall be allowed, provided that the repair area is less than 5% of the total area. If repairs exceed
5% of the total area, the entire tank shall be relined. COMPANY shall make the final decision on repairs versus
total relining.
The repairs described in the following paragraphs are intended only as guidelines.
Surfaces adjacent to repair areas shall be protected from damage. Suitable protective cover shall be cardboard
or similar material.
Damaged surface lining shall be removed unless it is tightly bonded to the substrate metal. The surface shall be
wiped with a clean rag to remove all dust and loose materials. Oil, grease or other foreign matters present shall
be washed with a water based biodegradable cleaner followed by further rinsing with potable water to remove all
traces of the cleaner. The surface shall be dried.
Areas with spot rust, burnt residue, weld spatter and other solid adherent foreign material shall be cleaned using
portable vacuum blast cleaning unit. Other methods of surface conditioning may be acceptable with prior
agreement by the CONTRACTOR.
Surfaces with pinholes may be cleaned using pencil-head type grinding wheel. Pinholes shall be repaired as
follows:
Grind back to the steel substrate at the pinholes and feather the edges of the existing lining with clean
sandpaper back for a radius of 3 to 5 cm, ensuring that the steel substrate does not become polished.
All dust shall be removed with a vacuum cleaner equipped with a brush.
Brush full system (except primer) on to the prepared surface.
Allow the material to cure to a tack-free state and recoat as necessary to bring thickness to that specified.
Allow the material to cure and retest the repaired area for pinholes.
Primer material shall not be used as a repair material as it will affect the integrity of the lining system in the areas
where primer material overlaps the existing lining.
INSPECTION
General Inspection
Prior to commencement of internal lining activities, the SUB-CONTRACTOR shall submit an inspection procedure
indicating inspection and tests to be conducted during surface preparation and application of the lining system
for approval by COMPANY.
The SUB-CONTRACTOR is solely responsible for all the tasks of quality control and quality assurance including
maintaining the necessary documentation for a period of five years to verify compliance with this specification
regardless of partial, full, intermittent or continuous inspection by the CONTRACTOR.
The applied lining shall be free of runs, sags, voids, drips, overspray, pinholes, loss of adhesion, blistering, peeling,
inadequate cure, spot rust, localized rusting and any other defects.
All defects shall be repaired and re-inspected:
As a minimum, inspection hold points for Third Party Agency (TPA) shall be established as follows:
Prior to start of work.
Immediately following the surface preparation.
Immediately prior to the application of each coat.
Following the application of each coat.
Following the curing of the lining.
To witness holiday testing.
Prior to using compressed air, the quality of the air downstream of the separator shall be tested in accordance
with ASTM D4285. This test shall be performed at the beginning and end of each shift and at not less than four-
hour intervals. The test also shall be made after any interruption of the compressor operation or as required by
the CONTRACTOR.
The air shall be used only if the test indicates no visible contamination, oil, or moisture. If contaminants are evident,
the equipment deficiencies shall be corrected, and the air stream shall be retested. Separators shall be bled
Surface Preparation
NACE SP0178 shall be used for inspection of Surfaces before blast cleaning.
SSPC-VIS 1 Visual Standards shall be used to verify the degree of surface cleaning. They shall not be used to
compare surface profile depth. Profile depth shall be verified in accordance with NACE SP0287.
Tests indicating the extent of substrate contamination as a result of iron, chlorides and dust shall be performed
in accordance with ISO 8502-1, ISO 8502-2 and ISO 8502-3 respectively.
Abrasives for blast cleaning shall be sharp, angular, clean, dry and free of oil or contaminants. The particle size
shall be capable of producing the specified surface profile. The degree of cleanliness and depth of profile shall
be recorded.
Recirculated grit used for vacuum blast abrasive cleaning shall be tested for the presence of oil by immersing a
sample in water and checking for oil flotation. Tests shall be made at the start of blast cleaning, every four hours
thereafter, and at the end of blast cleaning. If oil is evident, the contaminated abrasive shall be cleaned or replaced.
All surfaces blasted since the last successful test shall be re-blasted using clean abrasive.
All surfaces shall be inspected immediately prior to the application of the first coat of lining material to ensure
compliance with the specified degree of cleanliness and limits set forth for water soluble salts on the surfaces to
be coated.
Verify welds are acceptable relating to roughness, continuity, porosity and sharp edges.
Grease-free chalk shall be used to mark local areas which do not meet the specified requirements and later
removed during repairs.
Application of Lining
The SUB-CONTRACTOR shall request the Lining MANUFACTURER to supply three reference panels with lining
material applied by the Lining MANUFACTURER at least fifteen days prior to the start of the work in accordance
with the Application Data and requirements stated in this specification. The reference panels, at least 300 mm by
300 mm, shall be used to compare the workmanship of the finished lining inside the tank. Each panel shall be of
step wise construction showing the degree of blast cleaning and all succeeding coats. SUB-CONTRACTOR shall
notify the CONTRACTOR when the panels will be prepared so that the CONTRACTOR may witness such
preparation. All reference panels shall be approved by the CONTRACTOR for compliance with this specification
before they can be used as inspection standards. One panel shall be used by the SUB-CONTRACTOR, one
panel by the CONTRACTOR and the third panel shall be kept by the CONTRACTOR as a reserve set.
The SUB-CONTRACTOR shall also prepare three reference panels (300 mm x 300 mm) under site conditions in
accordance with the approved lining procedure. These panels shall be compared with the panels supplied by the
Lining MANUFACTURER for workmanship. Subsequent to approval of workmanship, the adhesion of the primer
Lining Inspection
Verify that the lining material is stored in a pre-assigned area at the temperature range specified in the Application
Data.
Record batch numbers of the lining material.
Verify that the shelf life of the lining material has not been exceeded.
Verify that the mixing of the lining materials and amount and type of thinner is in accordance with the Application
Data.
Verify that substrate, ambient, and material temperatures are within the range specified in the Application Data.
Work shall not proceed unless humidity and dew point are within the specified limits.
Verify the lined surface is free of abrasives, contaminates, runs, and sags and other lining defects prior to the
application of successive coats.
Verify the method of application, time interval between coats, number of coats applied, and the minimum cure
time to put the lining into service, are in accordance with the Application Data.
The required dry film thickness of each coat shall be in accordance with the requirements stated in this
specification. Verify the gauges are properly calibrated and the readings obtained are recorded.
Five separate spot measurements (average of three individual readings) spaced evenly over each 9.3 square
meters shall be taken. The average of five spot measurements for each 9.3 square meters shall be within the
specified thickness. The DFT measurements shall be in accordance with SSPC-PA 2.
All lined steel shall be 100 percent inspected for holidays after full cure of the lining system and in accordance
with the requirements of NACE SP0188. Voltage settings shall be as recommended by the Lining
MANUFACTURER and approved by the CONTRACTOR and COMPANY.
Inspection Instruments
The following inspection instruments shall be supplied, calibrated and maintained by the SUB-CONTRACTOR
and available to the CONTRACTOR or their authorized representative:
100 power illuminated inspection microscope.
Binoculars (for visual inspection of high points).
Calibration standards for dry film thickness gauge.
Dry film thickness gauge with computer interface.
Elcometer adhesion tester Model 106/2.
Salt contamination Bresle Kit.
Testex Press-O-Film Kit.
NACE SP0178 surface finish weld replica.
INTRODUCTION
This section describes the minimum requirements for the internal coating of line pipe for non-corrosive sales gas
transmission.
The application of Internal flow coating systems promotes two primary functions:-
Reduced gas friction by provision of a very smooth surface profile.
The inhibiting of Black Powder* formation within the gas pipeline.
The term “Black Powder” is a colour descriptive term used to describe a blackish material (very small, jagged and
very hard particles) that can develop within the gas pipelines) due to a reaction of Fe with condensed moisture,
containing O2, H2S and CO2) which leads to erosion failures and damage to pipeline operational valves, lowers
efficiency of compressors and clogs instruments. This is a world-wide problem that affects most gas Pipeline
operators.
The coating may also offer short term corrosion protection during transport and storage, however additional
preservation measures may still be required.
It specifies the requirements for coating materials, coating application, inspection and testing and gives
procedures for the qualification of coating materials and SUB-CONTRACTORs.
General coating qualification is performed for the purpose of an overall qualification of coating system and SUB-
CONTRACTOR but is not necessarily related to a specific project.
With this process, a list of qualified coating systems and SUB-CONTRACTORs is developed, from which the
COMPANY may select a coating system and SUB-CONTRACTOR for a specific project. It saves time and avoids
re-qualification for similar projects. The general qualification is given independent of line pipe diameter and wall
thickness. When required for specific projects, additional testing should be performed on different line pipe
diameters and wall thicknesses.
General
The coating material shall typically be two-pack epoxy paint. It shall not contain any substances which will be
released from the paint film after it has cured and are proven to be detrimental to the operation of the pipeline
and the quality of the gas.
Unless otherwise agreed, the coating material shall be qualified in accordance with 28.3 and 28.4 and shall not
be changed after qualification.
The MANUFACTURER of the coating material shall provide on request infrared spectrograms of the base
component and the curing agent component (see 28.3.8).
In addition, the Coating MANUFACTURER shall provide a product data sheet (see 28.6), a health and safety
data sheet and a certificate stating the test results obtained in accordance with 28.3 and 28.4 respectively and, if
applicable, deviating test conditions.
28.3.1 General
The following clauses describe the laboratory test methods and requirements for qualification of the individual
coating components.
28.3.4 Viscosity
When determined by the method specified by the Coating MANUFACTURER, the viscosity of the ready-mixed
coating material shall comply with the value specified by the Coating MANUFACTURER in the qualification
certificate (Table 28.2).
The viscosity should preferably be measured in accordance with ISO 2431.
28.3.9 Appearance
The appearance and continuity of the coating shall be inspected visually without any magnification.
28.4.14 Appearance
The coating shall be free from blisters, visual holidays, scratches or any other irregularities and shall have a
uniform colour and gloss.
28.4.16 Porosity
The porosity of the coating shall be checked on glass panels by the method given in ISO 15741 (Annex E). The
coating shall show no pinholes.
Date of issue
Name of coating material
Name of coating material MANUFACTURER
Colour of coating material
Type of curing agent
Shelf life
Non-volatile matter by volume (a) Test Method used (See 28.3.3)
Density (b) Test Method used (See 28.3.5)
Pot life (a) (See 28.3.7)
Flash point (a) and (c)
Time to complete curing.
Recommended thinner.
Maximum allowed quantity of thinner, in %.
Recommended surface preparation grade.
Recommended method of application.
Recommended maximum/minimum dry film thickness of the applied coating.
Recommended cleaning solvent (for the application equipment).
Recommended application conditions (air and steel temperature and relative humidity).
Recommended minimum curing conditions.
Recommended maximum/minimum service temperature.
Recommended storage conditions.
Reference to instructions and warnings regarding health, safety and environmental protection.
Theoretical spreading rate (1/m2 or kg/m2 ) for a given dry film thickness.
(a) Only for the mixed coating material.
(b) Give separately for base component and curing agent component (if pigmented).
(c) Give separately for base component, curing agent component and mixed coating material.
Date of issue
Name of coating material
Name of coating material MANUFACTURER
Required surface profile
Overcoating intervals (if applicable)
Curing time
Date of issue
Authority for issue
Property Test Method Section
Non-volatile matter by mass (a) ISO 3251 See 28.3.2
Ash (b) ISO 15741 (Annex A) See 28.3.6
Viscosity (c) See 28.3.4
Adhesion ISO 2409 See 28.4.4
Buchholz hardness ISO 2815 See 28.4.5
Resistance to neutral salt spray ISO 9227 See 28.4.6
Resistance to artificial ageing See 28.4.7
Bend test (conical mandrel) ISO 6860 See 28.4.8
Resistance to gas pressure variations ISO 15741 (Annex C) See 28.4.9
Resistance to water immersion ISO 2812-2 See 28.4.10
Resistance to chemicals
Resistance to 95% by volume diethylene glycol solution in ISO 2812-1 See 28.4.11
water
Resistance to hexane
Resistance to methanol
Resistance to toluene
Resistance to lubricating oil (e.g. compressor seal oil)
Resistance to hydraulic blistering ISO 15741 (Annex D) See 28.4.12
a. Separately for base component, curing agent component and mixed coating material.
b. Separately for base component and curing agent component (if pigmented).
c. Only for the mixed coating material.
Batch number
Production date
The non-volatile matter by mass of the curing agent component shall not be used for any purposes other than
batch consistency checks.
As specified by the Coating MANUFACTURER.
If required.
If pigmented.
28.9.1 General
Before production application of a coating system may commence, the SUB-CONTRACTOR shall be qualified to
apply the coating system. The qualification shall be carried out according to the following procedures:
28.9.4 Qualification
With approval of the process and plant details 28.9.2 and 28.9.3 and before production starts, the SUB-
CONTRACTOR shall submit evidence that he has successfully applied the coating system before on pipes of the
specified material, and that the product complied with the requirements of this specification for the tests indicated
in Table 28.4.
The SUB-CONTRACTOR shall coat at least 5 pipes with the proposed coating system and shall subject samples
from these pipes to the tests given in Table 28.4. These tests may be carried out in the SUB-CONTRACTOR's
own laboratory, or by an independent laboratory. The COMPANY shall witness the application and the tests. The
results of the tests shall be reported to the COMPANY, signed by the head of the laboratory and the witness.
The tests described in the last column of Table 28.4 shall be performed on panels which have been attached
inside the sample pipes at both pipe ends. The test panels shall be prepared in accordance with 28.4.1.
The test panels shall be fixed on the inside of the pipes or on a temporary pipe extension specifically designed
for holding the test coupons using appropriate adhesive tape, at a distance of between 100 mm and 300 mm from
the pipe ends; the ground face of the glass panels shall face outwards. The adhesive tape shall overlap the long
ends of the test samples by approximately 12 mm.
Table 28.4 Requirements and Test Samples Required for Qualification of Coating System and the SUB-
CONTRACTOR
Requirement Coating System SUB-CONTRACTOR SUB-CONTRACTOR
Property and Test Qualification on Qualification on Qualification on
Method Panels Pipes Panels
Cleanliness of blast See 0 5 5 3
cleaned surface
Chloride and dust See 0 5 5 3
contamination
General
Table 29.1 Minimum Items to be Checked and Recorded During the Coating Process
Requirement and
Property Minimum Frequency
Test Method
Coating material At every change of shift
Name of product
Name of MANUFACTURER
Batch number
Environmental conditions during blasting
and coating
Ambient temperature See 30.1.2 Every 2 h
Steel temperature
Relative humidity
Dew point
Surface condition before surface preparation See 30.1.3 Every pipe
Surface condition after surface preparation Every pipe
Surface cleanliness See 30.1.4 Three pipes per shift evenly spaced.
Surface profile Tests performed on both ends
Surface contamination
Wet paint (mixed) Every time paint is mixed, and every
Viscosity and temperature See 29.3 time painting is interrupted
Testing coating on pipes Every pipe
Appearance
Dry film thickness See 28.4.14 10 pipes per shift, evenly spaced
Coating roughness See 28.4.3 Three pipes per shift, evenly spaced
Holiday detection (wet sponge) See 28.4.15 (a)
Testing coating on panels
Adhesion See Table 30.1 Three pipes per shift, evenly spaced
Buchholz hardness
Bend test
Curing test
Porosity (glass panels)
a. The wet-sponge test shall be carried out if the porosity tests on glass panels constitute a failure
Paint Preparation
Before removing each component from its container, stir or agitate it until it is homogeneous, using equipment
which is capable of homogenizing the entire contents of the container without excessively entraining air into the
material.
Mix the two components (base component and curing agent component) thoroughly and, if necessary, dilute in
accordance with the Coating MANUFACTURER's instructions. After the material has been homogenized; it shall
be continuously mixed at a slow speed. The mixed paint shall be free of any lumps and pieces of skin. Measure
the viscosity in accordance with the method recommended by the Coating MANUFACTURER and record. Check
whether it complies with the value specified by the Coating MANUFACTURER and keep it constant during the
application procedure.
The SUB-CONTRACTOR shall batch-test the materials for:
Density, in accordance with ISO 2811.
Non-volatile content (mass), in accordance with ISO 3251.
Paint Application
Check the surface to be coated to see whether it still complies with the specified surface preparation grade and
profile (see 0). Pipes showing any visible rust or stains shall be blasted again.
Apply the paint in a covered or enclosed space, shielded from wind, blowing dust and inclement weather, using
the application parameters recommended by the Coating MANUFACTURER and approved by the SUB-
CONTRACTOR.
Coating application shall not be performed when the relative humidity exceeds 85%, or when the substrate
temperature is less than 5°C, or less than 3°C above the determined atmospheric dew point. Substrate
temperature shall not exceed 50°C. In locations with consistent high humidity, the COMPANY may agree
atmospheric criteria based on ISO 8502-4; in which case, continued coating operations shall be subject to the
agreement of the Inspector.
Unless a specific accelerated curing schedule is defined in the Coating MANUFACTURER's data sheet and
qualified during laboratory testing, heating shall not be used to accelerate curing of the applied coating.
Spray the paint continuously and uniformly on to the whole surface to be coated. The coating shall be uniform,
and particular attention shall be given to achieving the specified dry film thickness. Unless otherwise specified or
agreed, maintain a cutback length of (20 ±5) mm.
30.1.1 General
During production application of the coating, the SUB-CONTRACTOR shall carry out all quality control activities
needed to ensure that the coating is being applied in accordance with the approved coating application
procedures and that the final product complies with the requirements of this specification.
The minimum quality control tests to be performed shall be as indicated in Table 29.1.
Records of all coating application and quality control test results shall be kept in accordance with Section 33.
30.2.1 General
Three test panels per shift, from the start, middle, and end, shall be prepared and evaluated. Each test shall be
performed at least twice.
Table 30.1 Required Frequency of, and Acceptance Criteria for, the Production-control Tests
Test Method Frequency Acceptance Criteria
Adhesion ISO 2409 Twice per shift Classification ≤ 1
Curing test ISO 15741 (Annex F) Twice per shift No softening, wrinkling or blistering
Porosity Test ISO 15741 (Annex E) Twice per shift More than five pinholes shall
constitute a failure.
DOCUMENTATION
Pre-Manufacturing Documentation
The CONTRACTOR’s contract-specific quality plan shall be submitted to the COMPANY for agreement within an
agreed time period.
The format and issue of the quality plan shall be consistent with the document control requirements of the
CONTRACTOR’s quality system.
The content of the quality plan should be based on ISO 10005 and shall include the following:
Identification of the product and contract to which the plan is to be applied.
Reference to ISO 15741 and this specification.
Location of coating application.
Identification of the individuals responsible for controlling the activities defined in the plan.
Identification of the individuals with the authority to interface directly with the COMPANY.
Identification of all SUB-CONTRACTORs.
The quality plans of all SUB-CONTRACTORs.
All sequenced activities for the contract, and references to the quality system procedures and work
instructions which will be applied to these activities.
Certification
The CONTRACTOR shall provide the COMPANY with a certificate of compliance with the order prior to shipment
of the pipe. If the COMPANY has deployed an Inspector, the certificate of compliance with the order shall be
issued after the inspection records have been reviewed and approved by the Inspector.
The certificate of compliance with the order shall be drawn up on the basis of specific inspection and testing on
the product supplied.
Submerged Structure - Equipment / Piping / Pipe Fittings / Structures CS -20°C ≤ T ≤ 100°C A-1
Atmospheric Zone for Offshore (above splash zone) CS -20°C ≤ T ≤ 100°C A-26
Atmospheric Zone for Offshore (above splash zone) SS -20°C ≤ T ≤ 100°C A-27
Carbon Steel Structural for Granular Sulphur Handling Services CS T ≤ 70°C A-12
Cyclic Service
CS A-17
-20°C ≤ T ≤ 200°C
Galvanized Components
HDG Gratings are generally excluded in new construction until GS -20°C ≤ T ≤ 100°C A-18
specifically recommended by COMPANY
COS Tanks Double Shell Annulus Area (Bottom Plates and Shell 2
CS T ≤ 100°C A-20
Metres High)
Single Wall Storage Tanks External - Shell External - Roof Top Side -
Wind Girders / Stair Tower / All CS Accessories / Structures at this
Level CS -20°C ≤ T ≤ 100°C A-14
Double Wall - Outer Tank Shell Internal / Inner Tank Internal Top 2
Metres
COS Tanks Double Shell Annulus Area - Bottom Plate / Both Shells
CS -20°C ≤ T ≤ 100°C A-18
Lower 2 Metres and All CS
New Construction: Conductor pipes shall be coated from Xmas tree top flange till sea bed.
Site Maintenance: Conductor pipes shall be coated from Xmas tree top flange till lowest water level on the
application day.
Primer is an optional and shall be applied to facilitate mechanical works during site maintenance campaign only.
Preferred method is to apply Epoxy directly on fully blasted surface on same day.
Holiday testing shall be carried out to new construction components and for buried components.
Total DFT of 750 microns Can be applied in a single coat application through wet on-wet technique, if required.
Splash Zone description for UZF / SATF / UADF up to underside of the 1st deck level.
Splash Zone description For USF / LZF / UL / NASR up to 5m above the MSL or underside of the 1st deck level.
Fully cured coating shall be 100% holiday tested according to NACE RP0274 and shall be free of holidays.
Coating shall be stripped and recoated when the number of holidays exceeded 10 in one conductor pipe.
Detail application procedure and project specific ITP shall be submitted for COMPANY’s approval prior to
commencement.
Coated pipes shall be protected by appropriate means during storage against UV for approximate one year.
Collar / sleeve passing test over the coated casings shall be carried to control the maximum 1100 µm DFT.
Fully cured coating shall be 100% holiday tested according to NACE RP0274 and shall be free of holidays.
Coating shall be stripped and recoated when the number of holidays exceeded 10 in one pipe.
Detail application procedure and project specific ITP shall be submitted for COMPANY’s approval prior to
commencement.
Coated well casings shall be protected by appropriate means during storage against ultraviolet rays for
approximately one year.
Collar / sleeve passing test over the coated Inner casings shall be carried to control the maximum 1100 µm DFT.
Outer conductor pipes shall be coated from Xmas tree top flange till sea bed.
When the coating has fully cured, all of the coated surface shall be tested for imperfections and defects (holidays)
to the NACE Standard SP-0188.
Total DFT of 400 microns Can be applied in a single coat application through wet on-wet technique, if required.
Apply Densopol 80 HT self-adhesive, bitumen based anti- corrosive tape that has a heavy duty PVC backing over
the coated section plus 1 meter at both protruding ends to act as a backfill protective coating. Overlap each turn
of wrapping tape by at least 1" (25 mm) or 55% to achieve double thickness. Ensure that entire surface is covered
with no gaps and air pockets.
Holiday testing as per NACE SP0188 shall be conducted for all of the Denso wrapped surface with a set voltage
recommended by Denso Tape MANUFACTURER.
Application shall note that some Coating MANUFACTURER’s recommend that the tie-coat or the anti-foulant coat
should be applied into the corrosion protection coat while tacky. Coating MANUFACTURER’s recommendation in
this regard shall be strictly observed.
Coating MANUFACTURER / SUB-CONTRACTOR shall ensure that the applied anti-skid coating system meets
the requirements of CAAP 071 and the friction values of 0.85 is achieved.
In case, the friction values are lower than the desired value of 0.85, then Coating MANUFACTURER / SUB-
CONTRACTOR shall repair the system to achieve the desired friction properties.
Only, GCAA approved organisation shall be allowed to conduct and certify the friction values.
Specific marking sketch to be submitted to COMPANY for review / approval prior to commencement of project.
Prior to the application of intermediate coat, the surface of inorganic zinc silicate primers shall be sealed by
application of a tie coat by mist coat / wet on wet method to seal off the surface of the zinc and to avoid solvent
entrapment and post application blistering.
The applied coating system shall be free of any defects and shall perform satisfactory during the entire
construction stage till commissioning at ambient temperature.
The applied coating system shall be free of any defects and shall perform satisfactory during the entire
construction stage till commissioning at ambient temperature.
Perform satisfactorily during non-operative phase in CX environment.
Unless specifically mentioned by COMPANY, HDG gratings are excluded from over coating in new constructions.
Coating shall only be applied in combination with effective cathodic protection and shall be consulted with
COMPANY prior to application.
4th Polyurethane 50 µm
Additional Notes for Coating System A-26.
Prior to the application of intermediate coat, the surface of inorganic zinc silicate primers shall be
sealed by application of a tie coat by mist coat / wet on wet method to seal off the surface of the zinc
and to avoid solvent entrapment and post application blistering.
Maximum DFT of inorganic zinc silicate shall be 90 µm to avoid any mud-cracking.
Appendix Table 3.3 Painting System A4 Epoxy Novolac Coating System Requirements
Parameter Test Method Minimum Required Value
Compressive Strength ASTM C109 > 12000 psig / 827.37 barg
Adhesion to Barge Steel ASTM D4541 > 2500 psig / 172.37 barg
Taber Abrasion Resistance Wear Cycles CS-17 Wheel, 1 k g ASTM D4060 ≤ 90 mg / 1000 cycles
Cathodic Disbondment
30 Days @ 23°C ASTM G8 < 5 mm
30 Days @ 95°C ASTM G42 <10 mm
Visual Inspection of the Casing Thread and Seal Area After Washing All 5 Pipes
Visual Inspection of the Finished Coating and Ensure Contamination All 5 Pipes
free from Pin End and Box End Threads
Visual Inspection of the Casing Thread and Seal Area After Coating All Pipes
Final Inspection of Thread and Seal Area and Installation of Thread All Pipes
Protector
Adhesion Test 1 test / joint. To be done in all PQT
pipes
DSC Test 1 test
Repair If required
Powder Coating
Powder coating is included as an alternative where approved by COMPANY, and shall be highly durable.
Powder Coating for an external setting shall be suitable for a CX environment and be a minimum of 100 µm DFT.
Powder Coating within an internal setting shall be MANUFACTURER's / SUPPLIER's standard, and approved by
COMPANY.
Appendix Table 6.5 Required Safety and Identification Colour Coding - Gas Processing
Description Colour Colour Number
Piping
Process and Utility Piping (other than services listed below) Light Grey RAL 7035
Instrument and Plant Air (plant air shall have a Pure White (RAL Light Blue RAL 5012
9010) band 150 mm long @ 30 M intervals)
Potable Water (potable water shall have a Gentian Blue (RAL May Green RAL 6017
5010) band 150 mm long @ 30 M intervals)
Fire Water Vermillion RAL 2002
Sea Water Pine Green RAL 6028
Acids and Alkalis Red Lilac RAL 4001
Control Valves (Actuator Only) and Relief Valves Golden Yellow RAL 1004
Gas Transmission Piping Pure White RAL 9010
Liquid Transmission Piping White Aluminium RAL 9006
Equipment - Furnaces
Furnace Casing and Attached Steel Work Light Grey RAL 7035
Steel Work Not Connected Tarpaulin Grey RAL 7010
Stacks and Flue Duct (Note 3) White Aluminium RAL 9006
Top of Stack (Note 3) Vermillion RAL 2002
Ladders and Walkways Tarpaulin Grey RAL 7010
Handrail Assemblies Golden Yellow RAL 1004
Low Pressure Steam Two Tomato Red Stripes RAL 3013 STL
Superheated Low-Pressure Five Tomato Red Stripes RAL 3013 SLH
Steam
High Pressure Steam Three Tomato Red RAL 3013 STH
Stripes
Superheated High-Pressure Four Tomato Red Stripes RAL 3013 STS
Steam
Ultramarine Blue RAL 5002
Steam Condensate SC
and Signal White and RAL 9003
Flow Direction
Flow direction shall be indicated by bands as described in Direction by Bands, below. Arrows can also be used
to indicate the flow direction as described in Directions by Arrows.
Direction by Bands
The coding shall be arranged as indicated in the example shown in Appendix Figure 6.1
← Flow Direction
Letter Code
First two letters of this example indicate contents (see Appendix Table 6.7). Last letter indicates phase:
L = Liquid phase
G = Gas phase
V = Vapour phase
For Dia > 4", A = Dia x 2, B = Dia x 1/2 and C = Dia x 1/2 up to maximum widths equivalent to 18".
For piping above 18 inches diameter width, shall be 18".
For Dia < 4", A = 100 mm, B = 50 mm and C = 25 mm.
Colour Band C is located on downstream side of Colour Band and indicates direction of flow.
In case of bi-directional flow, flow Band C will be located on each side of Band A.
Where two colours are used for quick identification (such as for steam, fuel gas, hydrogen, etc.) the following
procedure will be adopted:
Up to 4" Dia Piping, Band A shall be in alternating circumferential bands and Band C shall be the
predominant colour.
Directions by Arrows
Arrows shall be used to indicate the flow direction of commodities contained in piping.
The arrows shall be white or black in colour to contrast with the basic colour of the pipe. The following sizes are
recommended:
Pipe 2" to 6" NPS, arrow to fit in a 25 mm x 100 mm rectangle.
Pipe 8" NPS and larger, arrow to fit in a 50 mm x 150 mm rectangle.
Where flow of the commodity is possible in either direction, two arrows shall be indicated pointing in
opposite directions.
Arrows and band markings shall be made at the unit battery limits and at the COMPANY designated locations.
Colour
The code indications shall be painted either in white or in black in order to contrast clearly with the colour of paint
on the pipe or equipment. For insulated lines, the code indications shall be painted over the insulation jacket.
Labelling Requirements
For piping and equipment, full name or abbreviations of chemical and symbol of fluid flowing inside a pipeline
shall be indicated. The line number shall also be painted on the pipelines.
Line numbering labels shall be applied to all pipes every 30 m.
For equipment, the name, tag number and service are required to be painted.
For support columns, Code indication in the form of serial numbers shall be adopted for supporting columns of
concrete or structural steel. Numbers shall be provided by the CONTRACTOR.
Size
The size of lettering used for code indications on insulated and un-insulated piping is as follows. The following
are suggested sizes only and may be varied by the COMPANY.
Appendix Table 7.8 Required Safety and Identification Colour Coding - Refining
Description Colour Colour Number
Piping
Process and Utility Piping (other than services listed below) Light Grey RAL 7035
Instrument and Plant Air (plant air shall have a Pure White (RAL Light Blue RAL 5012
9010) band 150 mm long @ 30 M intervals)
Potable Water (potable water shall have a Gentian Blue (RAL May Green RAL 6017
5010) band 150 mm long @ 30 M intervals)
Fire Water Vermillion RAL 2002
Sea Water Pine Green RAL 6028
Acids and Alkalis Red Lilac RAL 4001
Control Valves (Actuator Only) and Relief Valves Golden Yellow RAL 1004
Gas Transmission Piping Pure White RAL 9010
Liquid Transmission Piping White Aluminium RAL 9006
Equipment - Furnaces
Furnace Casing and Attached Steel Work Light Grey RAL 7035
Steel Work Not Connected Tarpaulin Grey RAL 7010
Stacks and Flue Duct (Note 3) White Aluminium RAL 9006
Top of Stack (Note 3) Vermillion RAL 2002
Ruwais Refinery
1. Straight Strip Design: From top of the tank shell a 4.2 m wide grey stripe shall be applied followed
by a 1.65 m dark blue stripe. The rest of the storage tank shell shall be painted light blue.
Flow Direction
Flow direction shall be indicated by bands as described in Direction by Bands, below. Arrows can also be used
to indicate the flow direction as described in Directions by Arrows.
Direction by Bands
The coding shall be arranged as indicated in the example shown in Appendix Figure 7.2
← Flow Direction
Letter Code
First two letters of this example indicate contents (see Appendix Table 6.7). Last letter indicates phase:
L = Liquid phase
G = Gas phase
V = Vapour phase
For Dia > 4", A = Dia x 2, B = Dia x 1/2 and C = Dia x 1/2 up to maximum widths equivalent to 18".
For piping above 18 inches diameter width, shall be 18".
For Dia < 4", A = 100 mm, B = 50 mm and C = 25 mm.
Directions by Arrows
Arrows shall be used to indicate the flow direction of commodities contained in piping.
The arrows shall be white or black in colour to contrast with the basic colour of the pipe. The following sizes are
recommended:
Pipe 2" to 6" NPS, arrow to fit in a 25 mm x 100 mm rectangle.
Pipe 8" NPS and larger, arrow to fit in a 50 mm x 150 mm rectangle.
Where flow of the commodity is possible in either direction, two arrows shall be indicated pointing in
opposite directions.
Arrows and band markings shall be made at the unit battery limits and at the COMPANY designated locations.
Colour
The code indications shall be painted either in white or in black in order to contrast clearly with the colour of paint
on the pipe or equipment. For insulated lines, the code indications shall be painted over the insulation jacket.
Labelling Requirements
For piping and equipment, full name or abbreviations of chemical and symbol of fluid flowing inside a pipeline
shall be indicated. The line number shall also be painted on the pipelines.
Line numbering labels shall be applied to all pipes every 30 m.
For equipment, the name, tag number and service are required to be painted.
For support columns, Code indication in the form of serial numbers shall be adopted for supporting columns of
concrete or structural steel. Numbers shall be provided by the CONTRACTOR.
Size
The size of lettering used for code indications on insulated and un-insulated piping is as follows. The following
are suggested sizes only and may be varied by the COMPANY.
Colour Coding
Colour coding does only apply to aboveground installations. The colour coding requirements are based upon BS
1710.
Three methods of identification are included:
Basic identification colours only,
Basic identification colours and code indications,
Basic identification colours used in conjunction with an ADNOC Onshore colour coding scheme.
A8.2.1 General
All methods of identification shall be compatible with pipe and operating conditions.
This finish colour is the protective or decorative colour.
The basic identification shall be applied at all junctions, at both sides of every valve, entry into or from every piece
of equipment or vessel, bulkhead and wall penetration and any other place where identification is necessary.
In firefighting service all the piping, valves and flanges shall be painted Signal Red.
Methods of Application
Appendix Figure 8.3 Example of Application of Safety Colour and Coding - Onshore
Names, chemical symbols and flow arrows shall be in black or white in order to contrast clearly with the colour of
the pipe or with the basic identification colour.
They shall be placed directly on the pipe or on a label fixed to the pipe near the basic identification colour. Where
labels are to be used on an installation in conjunction with a safety colour the background colour of the label shall
be that of the safety colour.
A8.3.3
The base colour will be applied in two bands 150mm in length applied either side of the colour code indication.
The colour code indication will consist of one band 150mm in length or three bands of 50mm in length as shown
in Appendix Table 8.16
A8.4.1 General
This section details the minimum requirements for painting of tag numbers on main vessels and storage tanks
and painting of identification strings on pipelines.
Test Separators.
Production Separators.
Flow Suction Tanks.
Storage Tanks.
Degassing Tanks.
Knock-Out Vessels.
Equipment / Manifold Skids.
The minimum character heights for painting of tag numbers shall be as follows:
The piping shall also be identified at the 6 o’ clock position when installed on an overhead rack.
The minimum character heights for painting of identification strings shall be as follows:
Colour Coding for Umm Shaif / Lower Zakum / Nasr / Umm Lulu Offshore Structures
The colours specified in Appendix Table 9.17 shall be used as an overall finish of the external surfaces of the
relevant plant, pipework or structure offshore.
Appendix Table 9.17 Colour Coding for Umm Shaif / Lower Zakum / Nasr / Umm Lulu - Offshore
Application Colour to BS 4800 Colour Coding to
BS 4800
Complex Structures
Submerged zone and Splash zone up to 5 m above the MSL or Black 00 E 53
underside of the 1st deck level
Intermediate zone, cellar and lower deck areas (up to the next Poppy Red 04 E 53
deck level)
Top Zone Ivory 10 C 31
Piping, Fittings, Valves, Actuators and Supports Nimbus Grey 10 A 07
Vessels Exchangers, Tanks and Equipment Nimbus Grey 10 A 07
Handrails, Ladders and Stanchions (Atmospheric and Splash Golden Yellow 08 E 51
Zones)
Wellhead Towers Structures - USF / LZF / UL / Nasr
Submerged zone and Splash zone up to 5m above the MSL Black 00 E 53
Topside Zone - All surfaces above 5m above the MSL to the top Poppy Red 04 E 53
of the structure
Piping, Fittings, Valves, Vessels and Tanks Nimbus Grey 10 A 07
Handrails, Ladders and Stanchions (Atmospheric and Splash Golden Yellow 08 E 51
Zones)
Appendix Table 9.18 Colour Coding for Upper Zakum / SATF / UADF - Offshore
Application Colour to BS 4800 Colour Coding to
BS 4800
Central Complex Structures
Individual characteristics of different services within the common group are distinguished by a secondary colour.
Any pipework originally painted (background colour coded) along its entire length with one of the basic colours,
an aluminium contrast band shall be used as an additional outer most colour to distinguish between the decorative
colour and the basic colour identification of this particular pipework.
Materials
The application of the colour identification shall be employed using approved Polyurethane paint applied over a
contrasting high build undercoat matching British colour BS 4800. The former materials shall be chosen from
COMPANY Approved Paint products.
All plant equipment, piping and structure shall be coated the same colour, Goose Grey (BS 00 A 05) and shall be
known as the general site background colour.
All colours used for the basic identification colours and colour code indications used in conjunction with the
ADNOC particular colour coding scheme shall be BS 4800 Colour Reference in general in accordance with BS
1710.
Additional information such as Line Nos., Contents, or Equipment / Tag Numbers shall be stencilled in black or
white on the safety colour code or on yellow information panels.
Line Numbers
Line number shall be adopted to give assistance and clarity to the complex geometrical piping layout of the plant.
Line numbers (where adopted) shall be Black (BS 00 E 53) stencilling on Golden Yellow (BS 08 E 51) information
panels, these shall be shown immediately after inlet / outlet nozzles (where possible) of all equipment, vessels
and columns, and shall be repeated every 30 meters on straight line configuration of pipework, at change of
direction they shall be repeated immediately after bends and elbows, located below the centre line of the pipe
making it easily and clearly visible from ground level.
Tanks - Sea Water / Brackish Water / Utility Water / Treated Water CS T ≤ 80°C B-12
Only approved glass fibre laminate and tissue material shall be used:
CONTRACTOR shall submit detail application procedure for COMPANY review / approval prior to commence any
internal GFRE lining.
PQT with approved material shall be completed prior to commence any internal GFRE lining works.
Internal GFRE lining shall be carried out by COMPANY qualified SUB-CONTRACTORs only.
Primer shall be considered only in case of failure in dehumidification system for short period and shall be strictly
in the recommended DFT range.
GFRE lining shall be applied at shell height of 2.15m for DAS Island and 1.65 m for Zirku Island COS tanks.
The lining system shall be certified and suitable for drinking water and shall have local (Municipality / ADWEA)
statutory authority approval for potable / drinking water.
The lining system shall be resistant to chemicals, suitable for use in permanent contact with water and not affects
the quality of water. Lining MANUFACTURER shall provide the relevant certification that shall be submitted to
COMPANY for approval.
Sa 3 / SSPC-SP 5
B-16 CS 1st Solvent Two Hybridized Epoxy 400 µm
50 µm - 75 µm
Visual Aids
Offshore is committed to provide the required visual aids in all its helidecks, manned and unmanned, to satisfy
the regulatory requirements for offshore helidecks in the UAE as established in General Civil Aviation Authority’s
(GCAA) CAAP 71.
A13.2.1 Dimension
The touchdown / positioning marking is defined as a circle of 0.5 x D inner radius and a line width of at least 1 m.
Location
The touchdown / positioning marking circle should be ideally located in the centre of the Final Approach and
Take-off (FATO), except where the results of an aeronautical survey indicates that an offset marking may be
beneficial to the safety of helicopter operations and not detrimental to the safe movement of personnel.
In case of offset, the centre of the circle may be moved up 0.1 x D.
Appendix Figure 13.7 Location of Touchdown Markings - Centralised Touchdown Markings - Offshore
Appendix Figure 13.8 Location of Touchdown Markings - Fully Offset Touchdown Markings - Offshore
A13.4.1 Dimension
A helideck identification marking must be provided in the form of an “H” with:
Height of 4 m
Width not exceeding 3 m
Stroke width not exceeding 0.75 m
Appendix Figure 13.9 Dimensions of the Helideck Identification “H” Marking (Standard Size) - Offshore
A13.4.3 Characteristics
The “H” marking must be painted white.
A13.5.1 Location
A maximum allowable mass marking has to be arranged so as to be readable from the preferred final approach
direction. This is usually a direction lining up with the prevailing wind direction for the facility.
A13.5.2 Dimension
The size (height) of the characters must be at least 90 cm with decimal point of 18cm 2. The form and proportions
of numbers and letters must follow the following form and proportions.
A13.5.3 Characteristics
The maximum allowable mass marking has to be expressed with one decimal value followed by the units’
abbreviation (t). All existing helidecks must be painted with the t-value corresponding to its maximum bearing
capacity as established in the Helideck Landing Limitation (HLL).
The numbers and the letter of the marking and the decimal point must be painted in white and outlined with black
to improve colour contrasting with the background.
A13.6.1 Location
A Final Approach and Take-off / Touchdown and Lift-off (FATO / TLOF) perimeter marking denoting the extent of
the FATO / TLOF must be painted around the edge of the FATO / TLOF.
A13.6.2 Dimension
The FATO / TLOF perimeter marking must be painted using a continuous line having a thickness of at least 30
cm.
A13.6.3 Characteristics
The FATO / TLOF perimeter marking must be painted white.
A13.7.1 Location
D-value markings have to be displayed within the broken white FATO / TLOF perimeter line at three locations as
shown below, so that at least one marking is readable from the final approach direction.
A13.7.2 Dimension
The size of the characters must be at least 90 cm.
A13.7.3 Characteristics
A13.8.1 Location
The apex of chevron is located in the perimeter of the FATO / TLOF. Typical locations of the chevron include:
Nearby solar panels or other equipment installed in proximity to the FATO and outstanding the level of
the FATO
Upon vent booms installed below the FATO.
Strategically located to clear both obstacles above the FATO and below it
A13.8.2 Dimension
The origin of the obstacle-free sector must be marked on the helideck by a chevron, each leg forming the angle
of the obstacle-free sector and being:
79 cm long
10 cm wide
Where the OFS is swung then the chevron must be swung as well accordingly.
A13.8.3 Characteristics
The chevron must be painted in black.
A13.9.1 Location
The helideck name marking must be painted between the chevron and the touchdown / positioning marking circle.
A13.9.2 Dimension
The helideck name marking must have a height of 1.5 m.
Where the helideck name marking consists of more than one word it is recommended that the space between
words be approximately 50% of character height.
A13.9.3 Characteristics
The helideck name marking must be painted in white.
The helideck name marking must consist of the name or the alphanumeric designator of the helideck as used in
the radio (R/T) communications.
Providing a name that is unique and simple helps to keep to a minimum pilots’ concentration during final approach
and landing manoeuvre.
The character widths and stroke widths of nominal 1.2 m characters should be 80% of those prescribed by
International Civil Aviation Organisation (ICAO) Annex 14. Where the character height is 1.5 m, the character
widths and stroke widths should be in accordance with ICAO Annex 14.
Surface Marking
Surface background marking is provided to assist pilots to identify the location during an approach and to
emphasise the position of the markings.
A13.10.1 Characteristics
The helideck surface encapsulated by the white FATO / TLOF perimeter marking must be:
Dark green in steel surface helidecks.
Light grey in aluminium surface helidecks.
The conspicuity of white and yellow markings on light grey helideck surfaces should be outlined with a 10 cm
black line or by overlaying white or yellow markings on a painted black background.
A13.11.1 Location
The PLS must be located in a way that ensures that a helicopter cannot land towards an obstacle which is not
within the pilot’s field of view.
The PLS has to be located on the touchdown / positioning circle, opposite from the personnel access point.
A13.11.2 Dimension
The arc of coverage should be sufficient to ensure that the tail rotor system will be positioned clear of the
obstruction when hovering above, and touching down on, the yellow circle at any location beyond the PLS marking.
The minimum PLS marking should cover an arc of at least 30 degrees, extending by a minimum 10 to 15 degrees
either side of the edge of the obstacle.
A13.11.3 Characteristics
There is two different ways to define a PLS:
By a hatched marking overlaid on the portion of the yellow touchdown / positioning marking circle, and
extending out to the FATO / TLOF perimeter marking within the relevant headings
“No Nose” arc into a touchdown / positioning marking circle bordered in red with the words “No Nose”
clearly marked in red on a white background
Appendix Figure 13.18 Examples of an Alternative Prohibited Landing Sector (PLS) Marking – Offshore
General
This section covers COMPANY minimum requirements for abrasive blasting and lining of internal steel surface
of the tank bottom, a minimum of level as follows:
Appendix Table 14.33 Minimum Level of Internal Steel Surface of Tank Bottom
Location Bottom Height Upright Shell
ADNOC Offshore (Das Island) 100% 2.15 m
ADNOC Offshore (Zirku Island) 100% 1.65 m
ADNOC Offshore (SARB) 100% 1.15 m
ADNOC Onshore 100% 2.0 - 2.5 m
ADNOC Refining 100% 1m
The system described in this specification consists of 2 mats (450 g/m 2) plus one tissue (27-30 g/m2) embedded
in an epoxy resin with a final DFT of not less than 2800 microns.
Prior to commencement of any blasting work, all grease, oil, dirt and any other contamination shall be removed
in accordance with the requirements of SSPC-SP 1.
On completion of the degreasing / cleaning all surfaces shall be high pressure fresh water washed (3500 psig /
241.32 barg). All surfaces shall be allowed to dry.
Following washing down, Chloride levels shall be measured on the shell, underside of the roof and the tank floor
and recorded. Bresle method shall be used to determine soluble salt levels.
Prior to commencement of any GFRE work, all surface irregularities including weld spatters, weld fluxes, rough
capping, surface lamination and underlying mill scale shall be removed using mechanical tools.
Any surface irregularity which may become apparent after surface preparation shall be similarly treated.
Open Blasting
Blasting shall start on nozzles, pipes, shell, around the legs and the annular plate by means of open blasting.
Appropriately sized abrasives shall be used. Following the completion of the open blasting, spent abrasives shall
be removed and the roof underside blown down with compressed air to remove residual dust; this should be
followed by a complete vacuum cleaning of the tank floor using industrial vacuum cleaners.
Vacuum Blasting
Following the completion of all open blasting of the shell and associated components, the floor shall be blasted
using fully enclosed shot blasting machines (vacuum blasting - dust free blasting). In order to reduce the possibility
of contamination by using hydraulically powered machines electrically powered machines are to be used. A full
Risk Assessment covering the use of electrically powered blasting machines must be submitted by the
CONTRACTOR.
A mixture of a steel grit and shot shall be utilized to produce the desired angular surface profile. Vacuum blasting
shall only commence following the completion of the open blasting.
All abrasive material used for both open and vacuum blasting shall meet the requirements of this specification.
Appendix Figure 14.25 Appendix Interface Area Between the GFRE System and Barge Steel - Das Island COS
Tanks
The catalysed epoxy resin applied to the shell areas should not run or sag.
Catalysed epoxy resin shall be laid down to the primed steel surface by brush or roller.
The glass reinforcing mat (450 g/m 2) be embedded into the resin using a metal roller to remove entrapped
air, folds and wrinkles and ensure the complete wetting of the glass mat.
Additional resin should be applied and rolled as required to ensure that the glass mat is fully saturated,
and no entrapped air remains.
Each strip of reinforcement should overleap the adjoining strip to a minimum of 5 cm within the over-
coating internal otherwise 10 cm overlap shall be considered after adequate sanding down of the
overlapped strip.
The second (450 g/m 2) mat shall be laid as per explained and with a 50% overlap with the first layer
ensuring that the joints are staggered from all directions.
Immediately apply the glass reinforced tissue to the wet application, workout using metal roller.
The embedding of the surfacing tissue shall be staggered so as not to correspond with the joints of the
glass reinforcement mat.
The glass reinforced laminate system, when dry enough to walk on, shall be inspected at all stages by
both the CONTRACTOR and the COMPANY representative. Any defects shall be made good by the
CONTRACTOR in accordance with the approved repair procedure. Repair procedure shall be submitted
to COMPANY by the CONTRACTOR prior to the commencement of the work for approval.
The minimum laminate thickness prior to the gel coat application shall be 2,500 microns.
A14.11.1 General
All material shall be chemically pure, and free from foreign contaminates. The age of the primer, resin and catalyst
shall not exceed the recommended shelf life as specified by the Lining MANUFACTURER.
The primer and resin must be delivered to the site in unopened containers with batch number and date of
manufacture clearly marked thereon.
Primers, caulking / coving materials, laminating resin, and topcoats shall be supplied by one Lining
MANUFACTURER, unless otherwise approved by the owner.
A14.11.3 Resin
The resin shall be 100% pure epoxy resin. It should consist of resin and catalyst only. The resulting catalysed
mixture shall be transparent.
Approved Material:
Glass Fibre Laminate - Owens Corning M705
Tissue - Fiberill 1777
Inspection
Holiday Detection
The main laminate system shall be holiday tested using high voltage spark tester at 6 KV. However, the
completed laminate system shall be holiday detected at 10 KV.
Any spot which fail the high voltage spark test at the prescribed voltage shall be repaired and re-tested
at the same voltage.