Method Statement Cementitious Grouting
Method Statement Cementitious Grouting
Method Statement Cementitious Grouting
Successful Grouting
To assure successful grouting, be positively sure of four essential points:
I. The right selection of grout from the beginning (the right specification).
II. The right surface preparation.
III. The right application steps.
IV. The full curing.
Steel Substrates
All under faces of base plates and skids should be clean and rust free. Any oily or greasy
materials should be removed.
Cementitious Grouting
Formwork
Plywood sides should be strongly tight to avoid grout leakage during pouring and the
upper level to be approximately one inch chamfered edged.
Shuttering sides should be 2-4 mm higher than the bottom level of the base plate/skid.
Exposed outer surface of the grout should kept as minimum as possible, but not less than
gap width to assure ideal bearing angle (45°). Generally, it starts from 30 mm.
Good Surface Preparation means cutting halfway to successful grouting .
III. Application
In general, it is quite important to use well trained crews, who are specifically recruited for
grouting. Even for one crew, it is recommended to be divided into separate groups, one for
each activity, like mixing, pouring, surface finishing and curing.
Mixing
Use a clean suitable container (not less than 20 liter volume) for one bag mixing, using
high torque medium speed mixer and suitable pedal for about 90 seconds.
In case of more than one bag mixing, using drum mixer of 150 - 200 liter volume is
recommended but for 2 - 3 minutes. Please ask for CIC technical support to state the right
number of bags for each product first.
Always add grout to clean water (the right quantity of water is variable, depending on the
desired flowability state, and mentioned in each product’s TDS).
o
It is recommended to keep the mixed grout temperature in the range of 10 – 30 C, by using
cold water in hot weather and warm water in cold weather, while storing, mixing and
placing should be shaded all the time.
Placing
Mixed grout should be kept for 5 minutes in its container after mixing, to allow entrapped
air bubbles to come out.
Choose the pouring point that saves traveling distances of grout i.e. the center of the
longest side of a rectangle.
The pouring point is preferable to be at least 150 mm higher than grout level, to enlarge the
grouting pressure; the same action could be done by using pyramidal wooden duct with
the same height for pouring.
It is essential to pour a continuous current of grout to avoid loss of workability during
pouring, that’s why the required quantity of grout should be previously estimated and
prepared in advance. A small spatula or steel rod could be used by hand to help grout
spread underneath the base plat/skid during casting.
NEVER pour grout from opposite sides in a time, otherwise air will be entrapped under the
base plat/skid forming critical voids in the bearing area.
DON’T compact grout by any means even by hand tools, and in case surface smoothing is
required, wait for not less than 20 minutes after pouring to finish the surface by proper
spatula or steel float.
IV. Curing
The highest curing procedures should be applied to keep the hydration water of grout in
place.
That means early curing and multi stage curing together as follows:
x Just after finishing the surface (within 30 minutes after casting), spray any of
®
Cicocure products on the exposed area and then cover with PET sheet.
x After deshuttering, (normally in 24 hrs) all exposed areas should be wetted by
water, then covered with wet cloth and kept wet for minimum 3 days.
This is the best curing method, but in case of lack of water, another curing compound
spray should be applied over all exposed surfaces after deshuttering, and to be re covered
again with PET sheet for minimum 3 days.
Cementitious Grouting
Cicofloor®FS-50
Precautions
Health and Safety
®
Cicogrout products are non-hazardous. However, they should not be swallowed or
allowed to come into contact with skin or eyes. Suitable protective goggles should be
worn. Splashes on the skin should be removed with water. In case of contact with eyes,
rinse immediately with plenty of water and seek medical advice. If swallowed, seek medical
attention immediately. Do not induce vomiting.
Technical Support
CIC provides on-site assistance, as well as consulting services on projects when
requested. Technical data sheets on other CIC products and guidance on their use are
available on request.
Warranty
CIC products are guaranteed against defective materials and manufacture and sold subject to CIC's standard terms and conditions of sale.
Whilst CIC endeavors to ensure that any advice, information or recommendation given is correct, the company cannot accept any liability either
directly or indirectly arising from the use of its products, since the company has no control over the application of its products. Information
contained in this document is given on the best current knowledge. CIC's policy is one of continuous improvement and the company reserves
the right to change the company products without prior notice.
Head Office: Jeddah Towers Building, Sharafeyah – P.O Box 7232, Jeddah 21462
(+96612) 653-2152 – 6514414 – 6531622 Fax (+96612) 651-9230
Factories: Plant 1: AlKhomra - Jeddah Telefax (+96612) 6365190
Plant 2 Jubail (+966013) 3404771 – 3404772 Fax (+966013) 3404770
Aal Taher Group
Branches: Jeddah (+966012) 6055657 Riyadh (+966011) 493 7635 Khobar (+966013) 8651349
Madina (+966014) 8390424 Makkah (+966012) 5482280 Yanbu (+966014) 3907539 Tabuk (+966014) 4275680
www.cictg.com