Process
Process
17
Tasks
61
Enablers
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.13. : Determine Appropriate Project Methodology/Methods and Practices
Predictive
- A more traditional approach, with the bulk of planning occurring
upfront, then executing in a single pass a sequential process.
Hybrid
-It is not necessary to use a single approach for an entire Project. Projects often
combine elements of different life cycles in order to achieve certain goals
The business case lists the objectives and reasons for project initiation.
It helps measure the project success at the end of the project against the project objectives.
The business case is a project business document that is used throughout the project life cycle.
The business case may be used before the project initiation and may result in a go/no go decision
for the project.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.13. : Determine appropriate project methodology/methods and practices
Business Case and Business need Documents
Business Case
Business Needs
According to the PMBOK Guide 6th edition, product scope is the features and functions that characterize a
product, service or result.
For example, if the product is a bridge, the product scope might be its length,
width, load strength, etc.
If the product is a T.V , its product scope will be its screen size, Weight, Screen
dimension, receiver type, Resolution, etc.
Most of the time, determining the product scope is not a difficult task. If you get a project through a contract,
you get the product scope with the contract document.
However, if the project is initiated by your organization, you will have to define the product scope.
In this case, you meet with all the stakeholders to find their expectations and requirements regarding the final
product.
Once the requirement and expectations are finalized, you get them signed by stakeholders and then forward
them for approval
The project scope is the work required to create the product. It also defines what is in the scope and
whatnot, which helps you avoid scope creep.
According to the PMBOK Guide 6th edition, project scope is the work performed to deliver a product,
service, or result with the specified features and functions.
• Getting a weekly progress update from your contractor, and making monthly
payments could be your Senior management requirements.
Project scope Management Includes the process required to ensure that the project
includes all work required, and only the work required, to complete the project successfully.
Managing the Project scope is primarily concerned with defining and controlling what
is and what is not included in the Project
OR
Project Scope Product Scope
Planning M&Q
3 Define Scope
4 Create WBS
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.1.Plan Scope Management (Planning)
Plan scope Management is the process of Creating a scope management plan that
documents how the project and product scope will be defined,
The Key Benefit of this process : Provides guidance and direction on how scope will
be managed throughout the project.
T&T
1- Expert judgment
Expertise should be considered from individuals or groups with specialized knowledge or training in the following
topics:
• Previous similar projects,
• Information in the industry, discipline, and application area.
2-- DATA ANALYSIS
A data analysis technique that can be used for this process includes but is not limited to alternatives analysis. Various
ways of collecting requirements, elaborating the project and product scope, creating the product, validating the scope,
and controlling the scope are evaluated.
3 - Meeting
Meetings to develop the scope management plan Attendees may include the project manager, the project sponsor,
selected project team members, selected stakeholders, anyone with responsibility for any of the scope management
processes, and others as needed.
BY: MOHAMED GHANEM,PMP
5.1. PLAN SCOPE MANAGEMENT (PLANNING)
Outputs
The Key Benefit of this process : Provides the basis for defining the product scope
and project scope..
Data Gathering
Elicitation
Techniques
Brainstorming
Quaternaries
Benchmarking And Survey
Used to generate and collect multiple ideas related to project and product requirements
Bring together prequalified stakeholders and subject matter experts to learn about their expectations.
Written sets of questions designed to quickly accumulate information from a large number of respondents.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.2. COLLECT REQUIREMENTS (PLANNING)
Benchmarking involves comparing actual or planned practices, such as processes and operations, to those of comparable
organizations to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.
The organizations compared during benchmarking can be internal or external
Data Analysis
Document Analysis:
Such as agreements, business plans, current process flows, issue logs, policies, procedures, Specs.
Decision Making :
Plurality: The largest group even if no majority , When voting is for more than two options ( More
than 50% not support the decision )
Decision Making :
One individual takes responsibility for making the decision for the group
Uses a decision matrix to provide a systematic analytical approach for establishing criteria, such as
risk levels, uncertainty, and valuation, to evaluate and rank many ideas.
Data Representation :
Ideas created through individual brainstorming sessions are consolidated into a single map to reflect
commonality and differences in understanding and to generate new ideas
Allow large numbers of ideas to be classified into groups for review and analysis
Enhances brainstorming with a voting process used to rank the most useful ideas for further
brainstorming or for prioritization
- A direct way of viewing individuals in their environment and how they perform their jobs or tasks
and carry out processes.
- It is particularly helpful for detailed processes when the people who use the product have difficulty
or are reluctant to articulate their requirements
- Used to uncover hidden requirements
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.2. COLLECT REQUIREMENTS (PLANNING)
Interpersonal and team skills :
can be used to quickly define cross-functional requirements and reconcile stakeholder differences.
Well-facilitated sessions can build trust, foster relationships, and improve communication among the
participants.
Context Diagram :
Context diagrams visually depict the product scope by showing a business system
(process, equipment, computer system, etc.), and how people and other systems
(actors) interact with it.
Context diagrams show inputs to the business system, the actor(s) providing the input, the outputs from
the business system, and the actor(s) receiving the output.
Prototypes :
- Small-scale products
- Computer generated 2D and 3D models
- Mock-ups
Workshops bring subject matter expert and the development team together to discuss and improve on
the software development process.
Quality Functional Deployment (QFD)
Workshops are commonly used in the manufacturing field to determine new product development.
Storyboarding
A prototyping method that can use visuals or images to illustrate a process or represent a project
outcome.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.2. COLLECT REQUIREMENTS (PLANNING)
Storyboarding
Outputs
1- Requirements documentation
How individual requirements meet the business need for the project.
Before being base lined, requirements need to be unambiguous (measurable and testable), traceable, complete,
consistent, and acceptable to key stakeholders
Define Scope is the process of • Developing a detailed description of the project and
product.
The Key Benefit of this process : Describes the product, service, or result
boundaries and acceptance criteria
Boundary
▪ Alternatives analysis used to evaluate ways to meet the requirements and the objectives identified in
the charter.
Used in workshops and working sessions with key stakeholders who have a variety of expectations or fields of
expertise.
The goal is to reach a cross-functional and common understanding of the project deliverables and project
Outputs
• Acceptance criteria
• Project deliverables
• Project exclusions
• Project constraints
• Project assumptions
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.4.Create Work Breakdown Structure (Planning)
Create WBS is the process of • Subdividing project deliverables and project work
into smaller, more manageable components.
T&T
Is a technique used for dividing and subdividing the project scope and project deliverables into smaller,
more manageable parts.
The work package level is the lowest level in the WBS that the cost and the durations can be estimated and
managed.
Project Scope
Work Package
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
5.4.Create Work Breakdown Structure (Planning)
Outputs
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the
project team to accomplish the project objectives and create the required deliverables.
WBS Dictionary The WBS dictionary is a document that provides detailed deliverable,
activity, and scheduling information about each component in the WBS
Story 5
Product Backlog
Story 1
Story 6
Story 3
Story 2
Story 4
The Key Benefit of this process : Increases the probability of final product,
service, or result acceptance by validating each deliverable.
Inputs
Verified deliverables
Verified deliverables are project deliverables that are completed and checked for correctness through
the Control Quality process by Project team
Inspection
Includes activities such as measuring and testing to determine whether deliverables meet
requirements and product acceptance criteria
Outputs
Accepted Deliverables
Deliverables that meet the acceptance criteria are formally signed off and approved by the
customer or sponsor.
It includes information about progress, such as which deliverables have started, their progress,
which deliverables have finished, or accepted.
Control Scope is the process of • Monitoring the status of the project and
product scope and managing changes to the scope baseline
• You should give the customer what they asked for, no more and no less.
Giving any extras is a waste of time and adds no benefit to the project!
T&T
Variance Analysis
Used to compare the baseline to the actual results and determine if the variance is within the
threshold amount or if corrective or preventive action is appropriate.
Trend analysis
Planning M&Q
Expertise should be considered from individuals or groups with specialized knowledge or training in previous, similar projects:
• Schedule development, management, and control;
• Scheduling methodologies (e.g., predictive or adaptive life cycle);
• Scheduling software The specific industry for which the project is developed.
2- DATA ANALYSIS
Alternatives analysis
Can include determining which schedule methodology to use, or It can also include determining how detailed the schedule
needs to be, the duration of waves for rolling wave planning, and how often it should be reviewed and updated.
3- MEETINGS
Project teams may hold planning meetings to develop the schedule management plan. Participants at these meetings
may include the project manager, the project sponsor, selected project team members, selected stakeholders, anyone
with responsibility for schedule planning or execution, and others as needed. BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
Outputs
6..1Plan Schedule Management (Planning)
✓ Level of accuracy (acceptable range used in determining realistic activity duration estimates)
✓ Units of measure (such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers,
or cubic yards for quantity measures)
✓ Reporting formats.
Release and iteration length ( The time boxed periods per iterations )
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.2.Define Activities (Planning)
Plan scoPlan scope Management is the process of pe
Define Activities is theis process
Management the processof
of
• Identifying and documenting the specific actions to be performed to produce the
project deliverables
❑Decomposition
Each work package within the WBS is decomposed into
the activities required to produce the work package
deliverables.
Water
Drainage Work Packages
supply
Work Work
T&T
Outputs
❑ Activity List
• Includes the schedule activities required on the project.
• Includes an activity identifier and a scope of work description for each activity in sufficient detail
to ensure that project team members understand what work is required to be completed.
•Activity name
•Activity description
•Predecessor and successor activities
•Logical relationships
•Leads and lags
•Imposed dates
•Constraints
•Assumptions
•Resource requirements and skill levels
•Location of performance BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.2.Define Activities (Planning)
Outputs
❑ Milestone List
• Is a significant point or event in a project.
• Milestones have zero duration because they represent a significant point or event.
• External Dependency
– Example outsource activity
- External dependencies involve a relationship between project
activities and non project activities for example government
permissions
• Internal Dependency
BY: MOHAMED GHANEM,PMP
– Project Dependency within the project PROFFISIONALS COACH
Lecture 03 : Project Schedule Management
6.3. Sequence Activities
.3Sequence Activities (Planning)(Planning)
Lead: Is the amount of time a successor activity can be advanced with respect to a predecessor activity.
)Starting the activity before completing its predecessor)
Lag: Is the amount of time a successor activity will be delayed with respect to a predecessor activity.
(Waiting time between activities)
Activity
B
Lead:
"Amount of time whereby a successor activity can be advanced with respect to a predecessor activity''
Example: Begin developing prototype one day before design complete
Figure 6-11. Example of Lead
Activity A
Activity B
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.3. Sequence Activities (Planning)
Outputs ❑Project Schedule Network Diagram
AON
• Estimating the number of work periods needed to complete individual activities with
estimated resources.
✓It provides the amount of time each activity will take to complete.
Used to calculate cost or duration based on historical data and project parameters. (e.g.,
square footage in construction) to calculate an estimate for activity parameters, such as
cost, budget, and duration.
Triangular Distribution
E = (O + M + P) / 3
✓ A method of estimating project duration or cost by aggregating the estimates of the lower level components
of the WBS.
✓When an activity’s duration cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail. The detail durations are estimated. These estimates are then
aggregated into a total quantity for each of the activity’s durations.
Contingency
Reserve
VS Management
Reserve
✓ One variation of the voting method that is often used in agile-based projects is called the fist of five.
✓ The project manager asks the team to show their level of support for a decision by holding up a closed
fist (indicating no support) up to five fingers (indicating full support.)
✓ If a team member holds up fewer than three fingers, the team member is given the opportunity to discuss
any objections with the team.
✓ The project manager continues the fist-of-five process until the team achieves consensus (everyone
holds up three or more fingers) or agrees to move on to the next decision.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS
BY: E L- Sayed Mohsen , PMP®, COACH
MI- RMP®, PMI-SP
P
2.6. : Plan and Manage Schedule
Cycle Time
Story Points
Team Velocity = (15+20+13+24)/4 = 18
Iteration
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.4. Estimate Activities Durations (Planning)
Outputs ❑ Duration Estimates
✓ Duration estimates are quantitative assessments of the likely number of time periods that are required to
❑ BASIS OF ESTAMITS
✓The amount and type of additional details supporting the duration estimate vary by application area
✓ Documentation of the basis of the estimate (i.e., how it was developed,)
✓ Documentation of all assumptions made ,
✓ Documentation of any known constraints,
✓ Indication of the range of possible estimates (e.g., ±10%) to indicate that the duration is estimated
between a range of values,)
✓ Documentation of individual project risks influencing this estimate.
• Analyzing activity sequences, durations, resource requirements, and sche dule constraints to create a
schedule model for project execution and monitoring and controlling.
.ن تمزن لودج الجذوم ءالش إل تنتملزي لودالج لىع دو اقبو در وم ت ط هت قرموالعوشم ذالف
مكحتالوال ي
ابلهيفال ا •ةيلمع
ا
✓ Generates a schedule model with planned dates for completing project activity
.ل عوشم الةطش يل امك سال ةططخمتخ راو نأتمز لوالدج جذ
تي ل
ES D EF
Activity Name
LS TF LF
B 4 Start
C 3 Start 0 5 5 5 3 8 8 9 17
A D G
D 3 A
E 6 A, B
F 4 C
0 18
G 9 D 0 4 4 5 6 11 11 7 18
H 7 D, E
Start B E H End
5
Consider all relationships are FS=0 0 18
Example for Activity
Form 0 3 3 3 4 7
ES D EF C F
Activity Name
LS TF LF
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.5. Develop Schedule (Planning)
D
Activity )Days) Dependency Critical Path Method (Example)
A 5 Start
B 4 Start
C 3 Start 0 5 5 5 3 8 8 9 17
A D G
D 3 A
E 6 A, B
F 4 C
0 18
G 9 D 0 4 4 5 6 11 11 7 18
H 7 D, E
Start B E H End
5
Consider all relationships are FS=0
0 18
Example for Activity
Form 0 3 3 3 4 7
ES D EF C F
Activity Name
LS TF LF
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.5. Develop Schedule (Planning)
D
Activity )Days) Dependency Critical Path Method (Example)
A 5 Start
B 4 Start
C 3 Start 0 5 5 5 3 8 8 9 17
A D G
D 3 A
0 0 5 6 1 9 9 1 18
E 6 A, B
F 4 C
0 18
G 9 D 0 4 4 5 6 11 11 7 18
H 7 D, E
Start B E H End
1 1 5 5 0 11 11 0 18
Consider all relationships are FS=0 0 18
Example for Activity
Form 0 3 3 3 4 7
ES D EF C F
11 11 14 14 11 18
Activity Name
LS TF LF • Critical Path is : A – E – H
• FF.B = 1 BY: MOHAMED GHANEM,PMP
• TF.H = 0 PROFFISIONALS COACH
6.5. Develop Schedule (Planning)
Critical Path Method
ES : Early Start EF: Early Finish
LS : Late Start LF : Late Finish
Total Float: amount of time that a schedule activity can be delayed without delaying the project finish date.
TF= ( LF – EF ) = ( LS – ES)
Free Float: amount of time that a schedule activity can be delayed without delaying the early start date of any successor.
FF = ESE - EFB
ES D EF 0 4 4 5 6 11
Activity Name B E
1 1 5 5 0 11
LS TF LF
BY: MOHAMED GHANEM,PMP
PROFFISIONALS
BY: E L- Sayed Mohsen , PMP®, MICOACH
- RMP®, PMI-SP
6.5. Develop Schedule (Planning)
T&T Schedule Network Analysis
Float
Defines how long non-crltlcal activities can be delayed without delaying project
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
6.5. Develop Schedule (Planning)
T&T ❑Resource optimization
Resource Optimization
Resource Leveling
Resource Smoothing
Activities may only be delayed within their free and total float
45hrs
Resourœ
Leveling
Wl W7 W9
Wl W7
Week. Week.
s s
45hrs
38hrs
::!
!.'
Resourœ
,:
0 Smoothing
::I:
w1 Week. W7 W9
s
Is the approved version of a schedule model that can be changed only through formal
change control procedures.
Bar charts
• Also known as Gantt charts, bar charts
Milestone charts
• Only identify the scheduled start or completion of major deliverables and key external interfaces
• Monitoring the status of the project to update the project schedule and managing changes to the
schedule baseline.
Performance Reviews
Measure, compare, and analyze schedule performance against the schedule baseline
such as actual start and finish dates, percent complete, and remaining duration for work
in progress.
Trend Analysis
Planning M&Q
4 Control Costs
2 Estimate Costs
3 Determine Budget
• Defining how the project costs will be estimated, budgeted, managed, Monitored, and controlled.
تعو,•يالكت ريدقت ةيفيك ديدحت ةيلمع ه المكح و ه ق ر م و هتيرناد او إه ت ايم ع اضوتو ا
.الشم بف ا
ب ا
✓ provides guidance and direction on how the project costs will be manag
ed throughout the project.
.دم لىع عوشم ف ا كال ةر د ة
تو يشمال ر ال
يفيك نأشب هيجوتالو داشرإلا رفوت إ ا ع
✓
❖ Triangular distribution. E = (O + M + P) / 3
❖ Beta distribution. E = (O + 4M + P) / 6
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
7.2. Estimate Cost (Planning)
Outputs ❑ COST ESTIMATES
Costs are estimated for all resources that are applied to the cost estimate includes:
Direct Cost (Labor, materials, equipment and services).
Inflation allowance, exchange rates
Cost contingency reserve
Indirect costs
✓ Determines the cost baseline against which project performance can be monitored and
controlled.
Cost Baseline
Cost Budget
• Contingency Reserve.
• Management Reserve : Cost estimates
• For unforeseen work that is within scope of the project.
• Address the unknown unknowns that can affect a project.
• Is not included in the cost baseline but is part of the overall project budget.
• When an amount of management reserves is used to fund unforeseen work, the amount of management reserve
used is added to the cost baseline, thus requiring an approved change t o the cost baseline.
• Monitoring the status of the project to update the project costs and managing
changes to the cost baseline.
- It is the authorized budget planned for the work to be accomplished for an activity.
( SPI = EV / PV )
Example :
Cost/Unit Quantity
Budget 2180 000
Actual 24160 00
PV =2000x180 = 360,000.00
EV =2000x160 = 320,000.00
AC =2400*160 = 384,000.00
Variance :
SV = EV - PV = 320'000 - 360'000 = -40'000 (Behind Schedule)
CV = EV - AC = 320'000 - 384'000 = -64'000 (Over Budget)
Performance Index
SPI = EV / PV = 320'000 / 360'000 = 0.88 (Behind Schedule)
CVI = EV / AC = 320'000 / 384'000 = 0.833 (Over Budget)
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
7.4. Control Cost (M&C)
SV > 0 Ahead of Schedule CV > 0 Under Budget
SV = 0 On Schedule CV = 0 On Budget
SV < 0 Behind Schedule CV < 0 Over Budget
• is a measure of the cost performance that is required to be achieved with the remaining resources in order
to meet a specified management goal.
Planning M&Q
2 Manage Quality
VS
Quality
Grade
• Identifying quality requirements and/or standards for the project and its deliverables, and documenting
how the project will demonstrate compliance with quality requirements and/or standards.
✓ Provides guidance and direction on how quality will be managed and verified throughout the
project.
• Help the project manager determine if the planned quality activities are cost effective.
• Examples of benefits: less rework, higher productivity, lower costs, increased stakeholder
satisfaction, and increased profitability.
Cost of quality:
• A component of the project management plan that describes how applicable policies, procedures, and guidelines will
be implemented to achieve the quality objectives.
The quality management plan may include:
• Quality standards that will be used by the project.
• Quality objectives of the project.
• Quality roles and responsibilities.
• Project deliverables and processes subject to quality review.
• Quality control and quality management activities planned for the project.
• Major procedures relevant for the project, such as dealing with nonconformance, corrective actions procedures, and
O Quality Metrics : سايق
continuous improvement ةدوجال ات
procedures.
• Specify project or product attributes, how will be measured, and tolerance.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
Lecture 05 : Project Quality Management
8.1. Plane Quality Management (Planning)
.01Plan Quality Management (Planning)
Describes a project or product attribute and how the Control Quality process will verify compliance to it.
• Failure rate
• Number of defects identified per day.
• Translating the quality management plan into executable quality activities that incorporate the
organization’s quality policies into the project.
➢ Audit is a structured, independent process used to determine if project activities comply with
organizational and project policies, processes, and procedures.
❑ Data Representation
❑ Cause-and-effect diagrams
➢ Also known as fishbone diagrams, why-why diagrams and Ishikawa diagrams
➢ Helping to identify the main or root cause of the problem.
• Monitoring and recording results of executing the quality management activities in order to assess
performance and ensure the project outputs are complete, correct, and meet customer expectations.
✓ verifying that project deliverables and work meet the requirements specified by key stakeholders
Control Pareto
Charts Chart
Statistical
Inspection
Sampling
Measurements that above the UCL or below the LCL result from an unstable process.
Used to determine
characteristics of an entire
population based on actual
measurement of it’s
representative sample.
Outputs
VERIFIED DELIVERABLES
➢ The results of performing the Control Quality process are verified deliverables that become an input to
the Validate Scope process for formalized acceptance.
Vou try to find defects and correct them while making the Vou plan to avoid the defect in the planning phase.
product.
ls a Reactive process ls a Proactive process.
Are used to verify the quality of the product. lnvolves processes managing quality
Dealing with the deliverables to confirm if it is matching with Dealing with the processes during the execution to confirm if it
the is matching with organizational and project policies,
requirements and if it is approved will take it to validate scope processes , and procedures.
Process for Formai Acceptance by the customer.
Inspection are example of the quality contrai process. Quality audit is an example of Manage Quality Process
Summary
Control Quality = Product
Manage Quality = Process
Validate scope = Formal acceptance = accepted deliverables by customer
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
دقائق ان شاء هللا10 نبدأ بعد
Official to work
Un- •Horizontal: with peers
official
Written & oral: social media and websites, media
releases
BY: MOHAMED GHANEM,PMP
6
PROFFISIONALS COACH
Project
Communications
Gov Team Management
Sponsor
CRITICALLINKS
between
people, ideas and
Department information -> Success!
Top
Management 90% of PM time is
spent communicating.
•
•
Media
PM
In most situations there will be no feedback, thus providing an implicit acceptance of the
message by the recipient.
✓ Power/influence grid: grouping the stakeholders based on their level of authority (“power”)
and their active involvement (“influence”) in the project.
✓ Influence/impact grid: grouping the stakeholders based on their active involvement (“influence”)
in the project and their ability to effect changes to the project’s planning or execution )“impact”).
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
13.1. Identify Stakeholders (Initiation)
❑Power/interest grid
Sellers : who will provide components or services to the project under a contract.
Organization Groups : that are internal stakeholders affected by the activities of the project team
such as legal, finance, operations, sales, and customer services.
Functional Managers : who mange organizational departments such as human resources, finance,
procurement, or accounting and who need to support the project activities.
Other Stakeholders : that contribute to or have an interest in the deliverables such as government
regulators, consultants, and financial BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.4. : Engage Stakeholders
Stakeholders Engagement Strategy
Leading Resistant
Neutral
Supportive
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
13.2. Plan Stakeholder Engagement (Planning)
T&T ❑Data representation
➢Stakeholder engagement assessment matrix
Supports comparison between the current engagement levels of stakeholders and the desired engagement
levels required for successful project delivery.
❖The engagement level of stakeholders can be classified as follows:
✓ Unaware: Unaware of the project and potential impacts.
✓ Resistant: Aware of the project and potential impacts but resistant to any changes
✓ Neutral: Aware of the project, but neither supportive nor unsupportive.
✓ Supportive: Aware of the project and potential impacts and supportive of the work and its outcomes.
✓ Leading: Aware of the project and potential impacts and actively engaged in ensuring that the project is a success.
BY: MOHAMED GHANEM,PMP
13.2. Plan Stakeholder Engagement (Planning)
➢Stakeholder engagement assessment matrix
C: Represents the current engagement level of each stakeholder.
D: Indicates the level that the project team has assessed as essential to ensure project success (Desired).
✓ Identifies the strategies and actions required to promote productive involvement of stakeholders in decision
making and execution.
Planning Executing
Plan Risk Management is the process of Defining how to conduct risk management activities
for a project.
The Key Benefit of this process : ensures that the degree, type, and visibility of risk
management are proportionate to both risks and the importance of the project to the
organization and other stakeholders.
Outputs
Risk strategy: Describes the general approach to managing risk on this project
Methodology: Approaches, tools, and data sources that will be used.
Roles & responsibilities: Who will do what.
Funding: Identifies the funds needed to perform activities related to Project Risk Management
Timing: When and how often risk management processes will be done.
Risk categories : ( Risk Breakdown Structure) (RBS)
Definitions of risk probability and impact levels are specific to the project context and reflect the risk appetite and
thresholds of the organization and key stakeholders.
Identify the risk thresholds of the organization(s) and key stakeholders on the project with regard to each objective
Reporting Formats:
How risk management output will be analyzed and documented.
Tracking:
Identify Risks is the process of • Identifying individual project risks as well as sources of
overall project risk, and documenting their characteristics
The Key Benefit of this process : The documentation of existing individual project
risks and the sources of overall project risk.
Brainstorming
Obtain a comprehensive list of individual project risks and sources of overall project risk
Checklists:
Risk checklists are developed based on historical information and knowledge that has been accumulated
from similar projects.
Interviews.
• Used to discover the underlying causes that lead to a problem, and develop preventive action.
SWOT Analysis:
S= Strength W= Weakness
O= Opportunities T= Threats
Identify opportunities that are result of organization strength as well as threats that are result of
organization weakness
BY: MOHAMED GHANEM,PMP
10.2.Identify Risks (Planning)
Document analysis
Prompt List
The risk categories in the lowest level of the risk breakdown structure can be used as a prompt list for
individual project risks.
Outputs
Risk Register:
Outputs
Risk Report:
Information in the risk report may include but is not limited to:
✓ Sources of overall project risk, indicating which are the most important drivers of overall project risk exposure.
✓ Summary information on identified individual project risks, such as number of identified threats and
opportunities, distribution of risks across risk categories, metrics and trends
• Assumption log
• Issue log
• Lessons learned register BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.3. : Assess and Manage Risks
Risk Management Approach
T&T
Risk Data Quality Assessment : Evaluates the degree to which the data about individual project risks is
accurate and reliable.
T&T
Grouping risks into categories can lead to the development of more effective risk responses by
focusing attention and effort on the areas of highest risk exposure.
This helps finding risks need immediate response, risks need additional analysis, and risks need to be put on
the watch list.
Perform Quantitative Risk Analysis is the process of : Numerically analyzing the combined
effect of identified individual project risks and other sources of uncertainty on overall project
objectives.
The Key Benefit of this process : Quantifies overall project risk exposure, and
it can also provide additional quantitative risk information to support
risk response planning.
This process is not required for every project, but where it is used, it is performed throughout the
project.
T&T
Sensitivity analysis
Helps to determine which individual project risks or other sources of uncertainty have the most potential
impact on project outcomes.
Tornado diagram is a typical display of sensitivity analysis
T&T
T&T
Sensitivity analysis
Helps to determine which individual project risks or other sources of uncertainty have the most potential
impact on project outcomes.
Tornado diagram is a typical display of
sensitivity analysis
T&T
Plan Risk Responses is the process of • Developing options, selecting strategies, and
agreeing on actions to address overall project risk exposure, as well as to treat
individual project risks.
The Key Benefit of this process : Identifies appropriate ways to address overall project
risk and individual project risks.
Active acceptance
VS
Passive acceptance
➢ Escalation
T&T
EXPERT JUDGMENT
Expertise should be considered from individuals or groups with specialized knowledge to validate
or modify risk responses if necessary, and decide how to implement them in the most efficient
and effective manner.
Project management information systems can include schedule, resource, and cost software to
ensure that agreed-upon risk response plans and their associated activities are integrated into
the project alongside other project activities
Outputs
CHANGE REQUESTS
Implementation of risk responses may result in a change request to the cost and schedule
baselines or other components of the project management plan
The Key Benefit of this process : enables project decisions to be based on current
information about overall project risk exposure and individual project risks.
Reserve analysis
Compares the amount of the contingency reserves remaining to the amount of risk remaining at
any time in the project in order to determine if the remaining reserve is adequate.
AUDITS
✓ The project manager is responsible for ensuring that risk audits are performed at an
appropriate frequency, as defined in the project’s risk management plan.
Risk Reviews
✓ Examine and document the effectiveness of risk responses in dealing with overall project risk
and with identified individual project risks.
When any unidentified risk occurs, you will discuss it with your team members and come up
with a strategy to contain the incident.
Which reserve will you use for workarounds❓ BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.11. : Plan and Manage Procurement
Task 11 : Plan and manage procurement
2.11.1- Define resource requirements and
needs
2.11.2- Communicate resource requirements
2.11.3- Manage suppliers/contracts
2.11.4- Plan and manage procurement strategy
2.11.5- Develop a delivery solution
تخطٌط المشترٌات وإدارتها:11 مهمة
تحدٌد متطلبات الموارد واحتٌاجاتها
التواصل بشأن متطلبات الموارد
العقود/ إدارة الموردٌن
تخطٌط استراتٌجٌة المشترٌات وإدارتها
- تطوٌر حل للتسلٌم
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.11. : Plan and Manage Procurement
Procurement Strategy
✓ Ex: for every month early, $15,000 will be paid to the seller. BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.11. : Plan and Manage Procurement
Contract Types
✓ Used whenever the seller’s performance period spans a considerable period of years.
✓ Special provision allowing for predefined final adjustments to the contract price due to changed conditions,
such as inflation changes or cost increases (or decreases) for specific commodities.
✓ Receives a fixed-fee payment calculated as a percentage of the initial estimated project costs.
✓ If the final costs are less or greater than the original estimated costs, then both the buyer and seller share costs
based upon aprenegotiated cost-sharing formula.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.11. : Plan and Manage Procurement
Contract Types
2- Cost-reimbursable contracts
2.3Cost plus award fee (CPAF.)
✓ The seller is reimbursed for all legitimate costs, but the majority of the fee is earned based on the satisfaction
of certain broad subjective performance criteria that are defined and incorporated into the contract.
✓ The determination of fee is based solely on the subjective determination of seller performance by the buyer.
✓ a hybrid type of contractual arrangement with aspects of both cost-reimbursable and fixed-price
contracts.
✓ are often used for staff augmentation, acquisition of experts, and any outside support when a precise
statement of work cannot be quickly prescribed.
Buyer Seller
✓ Ensures that both the seller’s and buyer’s performance meet the project’s requirements according to
the terms of the legal agreement.
Defining, preparing, and coordinating all plan components and consolidating them into an integrated project
management plan.
✓ Production of a comprehensive document that defines the basis of all project work and how the
work will be performed.
✓ Is the document that describes how the project will be executed, monitored and controlled, and
closed.
✓ It integrates and consolidates all of the subsidiary management plans and baselines, and other
information necessary to manage the project.
Microsoft Project
4.2. Develop Project Management Plan (Planning)
Outputs ❑ project management plan
✓ Change management plan. Describes how the change requests throughout the project will be
formally authorized and incorporated.
✓ Configuration management plan. Describes how the information about the items of the project
(and which items) will be recorded and updated so that the product, service, or result of the
project remains consistent and operative.
✓
Performance measurement baseline. An integrated scope-schedule-cost plan for the project
work against which project execution is compared to measure and manage performance.
✓ Project life cycle. Describes the series of phases that a project passes through from its
initiation to its closure.
BY: MOHAMED GHANEM,PMP
PROFFISIONALS COACH
2.9 : Integrate Project Planning Activities
Configuration Management Plan
Is a component of the project management Plan that describes how to identify and account for
project artifacts under configuration control, and how to record and report changes to them
2.9 : Integrate Project Planning Activities
Guidelines to Develop a Project Management Plan
Daily or 3 Times
per week
• Leading and performing the work defined in the project management plan.
• Implementing approved changes to achieve the project’s objectives.
Product Roadmaps
Incremental Delivery
Minimum Viable
Product
The team works in iterations (Time boxes of equal duration) to deliver completed
features.
The team works on the most important feature, collaborating as a team to finish it.
Then the team works on the next most important feature and finishes it. The team may
decide to work on a few features at a time, but the team does not address all of the
work for the iteration at once (i.e., does not address all of the requirements, followed
by all of the analyses, etc.).
▪ Reviewing all change requests; approving changes and managing changes to deliverables, project
documents, and the project management plan; and communicating the decisions.
✓ Allows for documented changes within the project to be considered in an integrated manner while
addressing overall project risk, which often arises from changes made without consideration of the
overall project objectives or plans.
Inaccurate initial
Specification Changes
estimates
Forms
Tracking Methods
Processes
Approval levels required for authorizing or rejecting
requested change.
❖Customer or sponsor approval may be required for certain change requests after CCB
approval, unless they are part of the CCB.
BY: MOHAMED GHANEM,PMP
2.10 : : Manage Project Changes
Change Control Strategy
1- Change Identification
4- Course of Action
2- Change
Documentation
5- Updating Related Plans
If Rejected
7 Project
Management Impacted
Update project management plan,
Plan baseline
Baselines and documents.
Change Management
Process Flowchart
Risks VS Issues
Explicit
VS
Tacit
knowledge knowledge
❑ The lessons learned register is created as an output of this process early in the project. Thereafter
it is used as an input and updated as an output in many processes throughout the project.
❑ The persons or teams involved in the work are also involved in capturing the lessons learned.
❑ At the end of a project or phase, the information is transferred to an organizational process asset
Political Awareness to keep the project manager aware of the organization’s political
environment.
Networking.
Meetings, Seminars, encourage people to interact and exchange ideas and knowledge.