XN-L E Chap07 Installation

Download as pdf or txt
Download as pdf or txt
You are on page 1of 46

Edition: 55

CHAPTER 7 INSTALLATION

7.1 XN-XX instrument installation ..................................................................................................... 1


7.1.1 XN-530/550 ..................................................................................................................... 1
7.1.2 XN-430/450 ..................................................................................................................... 6
7.1.3 XN-330/350 ..................................................................................................................... 8

7.2 Tube/cable/reagent connections............................................................................................... 10


7.2.1 Tube/reagent connections............................................................................................. 10
7.2.2 Cable connections......................................................................................................... 12
7.2.3 Monitor cable connections (XN-530/550) ...................................................................... 13

7.3 Starting the instrument [BA] ...................................................................................................... 14

7.4 Setting....................................................................................................................................... 23
7.4.1 Software settings........................................................................................................... 23
7.4.1.1 System configuration settings (System Configurator) ........................................... 23
7.4.1.2 Common procedure for using Windows to perform tasks...................................... 24
7.4.1.3 Keyboard setting.................................................................................................... 27
7.4.1.4 Touch panel settings [AJ] .................................................................................... 28
7.4.1.5 GP printer settings................................................................................................. 31
7.4.1.6 Installation procedure for online manual................................................................ 31
7.4.1.7 Default rules (not supported) ................................................................................. 32
7.4.1.8 Locale setting [AJ] [BM] [BN]................................................................................. 32

7.5 Prime reagent [BM] ................................................................................................................... 38

7.6 Reagent Registration ................................................................................................................ 40

7.7 Blank check............................................................................................................................... 43

7.8 Various adjustments ................................................................................................................. 43

7.9 Final Operation Check .............................................................................................................. 43

7.10 Connecting with RU-20 [AJ]...................................................................................................... 44

2015011

XN-L S/M April 2018


CHAPTER 7 INSTALLATION

NOTE: USB keyboard and USB mouse are needed for installation work.

[AJ]

7.1 XN-XX instrument installation

7.1.1 XN-530/550
(1) Remove tape from the front of the instrument.

(2) Remove tape from the reagent holder.

[AJ] 2015056

XN-L S/M 7-1 April 2018


XN-L S/M 7-2 April 2018
(3) Remove the cover as shown in Fig.

(4) Remove tape from the sample holder open/close unit.

XN-L S/M 7-3 April 2018


(5) Remove tape from the hand unit.

(6) Remove the machine screws with captive washers (for thin plate t0.8) M3 x 16 SUS: x2 that fasten
fixture NO. 1657.

XN-L S/M 7-4 April 2018


(7) Remove the machine screws with captive washers (for thin plate t0.5) M3x8 SUS: x2, and then
remove Fixture NO.1657.

(8) Replace the cover.

XN-L S/M 7-5 April 2018


(9) Remove the indicated binder clip NO. 105 and CV-250 bundled wire shipping stopper.

(10) Two plates (INTERRUPTER PLATE NO.395) are installed on the bottom of the two sampler
adapters (ADAPTER NO.328) respectively, then set the adapters to the sampler, the installation
positions shown as below for the plate are used for setting the testing tube.[AH]
*The following picture shows the normal tube position is installed by the plate (INTERRUPTER
PLATE NO.395).

7.1.2 XN-430/450
(1) Remove tape from the sample holder.

[AH]2015165

XN-L S/M 7-6 April 2018


(2) Remove tape from the reagent holder.

(3) Remove the indicated binder clip NO. 105 and CV-250 bundled wire shipping stopper.

XN-L S/M 7-7 April 2018


7.1.3 XN-330/350
(1) Remove tape from the reagent holder.

(2) Remove tape from Protective Cover No.174.[AN]


Note: Please do not remove the Protective Cover No.174.

[AN]2016144

XN-L S/M 7-8 April 2018


(3) Remove the indicated binder clip NO. 105 and CV-250 bundled wire shipping stopper.

XN-L S/M 7-9 April 2018


7.2 Tube/cable/reagent connections

7.2.1 Tube/reagent connections


(1) Connect each dispensing set and reagent (Cellpack DCL, Sulfolyser, Lysercell WDF, and Cellpack
DFL) to the back of the instrument.
Parts used: Intake Tube_ASSY NO.58
Intake Tube_ASSY NO.60
Intake Tube_ASSY NO.61
Intake Tube_ASSY NO.62

Caution: [BM]
Be sure to connect the instrument waste fluid to a waste container in the facility (a
container that has an insertion nipple for the waste tube or other means of fixing the
waste tube so that there is no risk of waste fluid splattering) or an optional waste
tank.
When connected to a waste container in the facility, periodically verify that the
waste tube is securely connected and there is no risk of waste fluid splattering.

[BM] 2017117

XN-L S/M 7-10 April 2018


(2) Install Fluorocell WDF and Fluorocell RET stains on ASP_ASSY NO. 62 in the instrument (left side).
(3) After installation, a "beep" will sound. Make sure that the error message disappears.

XN-L S/M 7-11 April 2018


7.2.2 Cable connections
(1) Connect power cable TA-6P(A)+TA-5(A) H05VV-F to the instrument (back).
(2) Connect the keyboard, mouse, and hand-held barcode reader to the USB ports on the instrument
(top of back side).BARCODE READER_ASSY NO. 29 ((USB))

(3) Adding Connector


When RU-20 or waster sensor is not used, static protection connector (provided in supply parts)
must be connected as shown.

04315817 96308015
WIRING CORD NO.3497 WIRING CORD NO.2188

XN-L S/M 7-12 April 2018


7.2.3 Monitor cable connections (XN-530/550)
[550 only] Connect the Touch Panel Monitor TM104-SYX01 and cables to the instrument.

XN-L S/M 7-13 April 2018


7.3 Starting the instrument [BA]

(1) Switch the power on the back of the instrument to "ON".

<Switch button description>

[BA] 2017060

XN-L S/M 7-14 April 2018


(2) Press the button on the left side of the front to start the IPU.
Caution: Do not touch the screen to log on with Hotstart. If you touch the splash screen before the
Initial setup Wizard appears and Initial setup Wizard is not displayed, press [Alt+TAB] so that Initial
setup Wizard can be brought to the front. Then, proceed to the step (3).
If you turn off the analyzer when Initial setup Wizard is not displayed after touching the splash
screen before the Initial setup Wizard appears, the IPU will start up with Japanese. In this case,
you need to initialize the database and set up the configuration. For procedure, refer to “XN-L
series IPU Recovery Procedure When IPU starts up in Japanese on Installation.”

(3) The screen below appears. Set the destination and units, and press the "OK" button.
- Destination : Select EU, JP, AM, or CN.
- Units : Set "Use" or "Do not use" SI units.

Caution:
Set the destination and units settings with care.
If any changes become necessary, initialization of the settings will be required.

XN-L S/M 7-15 April 2018


(4) The dialog box below appears. Press the [Yes] button.

(5) Make sure that you have set the configuration as intended, and press the [Close] button.

(6) Splash screen will appear again, then touch the screen after confirming [Start up] and green dots
are shown in the right bottom of the screen.

(7) After beeps, confirm [Service Mode On] shown in the right bottom of the screen.

(8) Touch "Manual". The keyboard screen appears.

XN-L S/M 7-16 April 2018


(9) Enter the service mode logon name and password, and press "OK".

2015057

(10) Press [Logon].

(11) When the screen appears, select as indicated below.


▪ Error "Not ignore"
▪ Sequence "Skip all initial sequence"
▪ Heater "ON"
▪ Auto validation/output "OFF"

(12) Close the screen with "OK".


The air pump starts, and startup operation takes place.

(13) Wait until the green part of the display in the lower left corner of the screen changes from blinking
to solidly lit, and "Starting up..." changes to "Enter a sample number".

XN-L S/M 7-17 April 2018


(14) Touch “Version”.

(15) When following screen appears, touch “Upgrade”.

XN-L S/M 7-18 April 2018


(16) When following screen appears, enter license code and touch “verify”.[AJ]

[AJ] 2015056

(17) Touch “Turn off”. Instrument will be turned off automatically.

XN-L S/M 7-19 April 2018


(18) Press start button on the front panel to startup the instrument.

(19) Touch the screen when beep sounds once and hold the touching the screen until beep sounds
twice.
(20) Touch “Power” icon at lower left in logon screen.

XN-L S/M 7-20 April 2018


(21) Touch “Config” button in screen.

Check

Do you really want to exit?

Yes No

(22) The screen below appears. Enter “sysmex” in the [Login Name] field and enter “c9.0” in the
[Password] field, and press the [login] button.

(23) The dialog box below appears. Press the [Start] button.

XN-L S/M 7-21 April 2018


(24) Wait while the instrument restarts.
XN-L series IPU Recovery Procedure When IPU starts up in Japanese upon Installation

Note:
1) This procedure can be used when the analyzer is started up in Japanese, after turning
the analyzer OFF and back ON when Initial setup wizard stays on the back of splash
screen with a destination setting “JP”.
2) This procedure describes initialization process of region settings and stored data by
executing “XNL_Data Initialize.exe.” The program “XNL_Data Initialize.exe” will
initialize only the region setting and stored data. It does not initialize NVRAM file.

(1) Turn the analyzer power ON.


(2) When the system displays the splash screen and then a blip sounds one time, keep touching the
screen until two blips sound (Hotstart).
(3) Press the power button on IPU logon screen.
(4) Press [Config] button on the screen.
(5) When “SysmexCustomShell” appears, login with the login name and password shown below.
Login name: “sysmex”
Password: “c9.0”
(6) Press [Start] button in the “SysmexCustomShell” screen to start the Windows Mode.
(7) Wait until the analyzer automatically shuts down and reboots.
(8) After the analyzer reboots, login with the login name and password shown below,
after“SysmexCustomShell” appears.
Login name: “sysmex”
Password: “c9.0”
(9) Press [Start IPU] button.
(10) When the splash screen appears and a blip sounds one time, keep touching the screen until two
blips sound (Hotstart).
(11) Press the power button on IPU logon screen.
(12) Press [Config] button on the screen.
(13) The Windows desktop appears and you can open the windows explorer.
(14) Initialize the analyzer settings by executing “XNL_Data Initialize.exe” in D:\Sysmex\Tools.
*The program “XNL_Data Initialize.exe” will initialize only the region setting and stored data. It does
not initialize NVRAM file.
(15) Press [Finish] to exit the Windows mode.
(16) Upon next startup of the analyzer, do not touch the screen to avoid starting the analyzer with
Hotstart.
Then, the regional settings screen will be displayed. Select appropriate destination and press
“Complete.” When the settings are successfully complete, the analyzer starts up in the appropriate
language.

XN-L S/M 7-22 April 2018


7.4 Setting

7.4.1 Software settings

Caution: [BP]
Software and Windows settings should not be changed except for certain items
described in this chapter. If changed, it may cause the device to malfunction.
Example: If changing the following item, it was confirmed that the IPU browser
screen program will not work properly.
(Control Panel -> Personalization -> Change the theme)

7.4.1.1 System configuration settings (System Configurator)


(1) The dialog box below appears. Press [Yes]. If the system configuration has not been set, Sys-
tem Configurator automatically starts when the instrument power is turned on.
* If the system configuration is already set, System Configurator does not automatically start.
If you need to change the system configuration settings, Run "D:\Sysmex\IPU\IPUSystem-
Config.exe".Press [Change Setting] in the screen of (3).

(2) The screen below appears. Set the destination and units, and press the "OK" button.
- Destination : Select EU, JP, AM, or CN.
- Units : Set "Use" or "Do not use" SI units.

Caution:
Set the destination and units settings with care.
If any changes become necessary, initialization of the settings will be required.

[BP] 2018024

XN-L S/M 7-23 April 2018


(3) The dialog box below appears. Press the [Yes] button.

(4) Make sure that you have set the configuration as intended, and press the [Close] button.

7.4.1.2 Common procedure for using Windows to perform tasks


(1) The screen below appears. Enter “sysmex” in the [Login Name] field and enter “c9.0” the
[Password] field, and then press the [Login] button.

XN-L S/M 7-24 April 2018


(2) The dialog box below appears. Press the [Start] button.

(3) Wait while the instrument restarts.

(4) Perform the necessary tasks in Windows.


(5) When finished, enter sysmex for the login name in the screen below, and press the [Login] button.

(6) Press the [Finish] button below.

(7) The instrument automatically restarts and the screen below appears ("Finish" and "Shutdown"
are disabled).
Wait while the instrument automatically shuts down.

XN-L S/M 7-25 April 2018


(8) When the screen disappears, turn off the instrument power.

XN-L S/M 7-26 April 2018


7.4.1.3 Keyboard setting
* A mouse and keyboard must be connected to perform this task.

(1) Select "Control Panel" - "Regional and Language Options".


(2) Click the [Change keyboards] button.

(3) Click the [Add] button in the "Text Services and Input Languages" screen.

* Adding an English keyboard


In the "Add Input Language" screen, select [English (United States)] - [Keyboard] - [US], and
click the [OK] button.
(To set a different language, follow the same procedure.)

XN-L S/M 7-27 April 2018


7.4.1.4 Touch panel settings [AJ]
(1) Press the power button.

(2) Press "Config" in the confirmation dialog box to close the IPU.

(3) The Windows screen appears.

[AJ] 2015056

XN-L S/M 7-28 April 2018


(4) Double-click the “Calwin.exe - shortcut”.

(5) When the "Touch Panel Settings" screen opens, select the "Calibration" tab.

XN-L S/M 7-29 April 2018


1. Select the "20 Points (5 x 4)" checkbox in "Number of correction points (R)".
2. Press "Apply".
3. Press "Execute Correction (N)" in "Correction Program (C)".

(6) The screen changes to the screen at right.


Touch the " + " marks that appear on the screen in the order that they appear.

Touch a total of 20 marks

XN-L S/M 7-30 April 2018


(7) When you have finished touching the 20 marks, the "Calibration" screen will appear.
Press "Update".

(8) Close all dialog boxes that are open.

7.4.1.5 GP printer settings


* Perform this task after you have installed the printer driver.
* A mouse and keyboard must be connected to perform this task.
(1) Select "Control Panel" - "Hardware and Sound" - "Devices and Printers".
(2) Right-click the icon of the printer to be used, and select "Properties".
(3) On the General tab, enter "GP PRINTER" for the printer name.

7.4.1.6 Installation procedure for online manual


* A mouse and keyboard must be connected to perform this task.
* Connect a media, which is including online IFU manual.
(1) Open D:\SYSMEX\MANUAL.
(2) Create a new folder as follows.

Destination Folder name


Europe EU
America AM
China CH
(3) Copy online IFU manual stored in the connected media to the folder created above step.

XN-L S/M 7-31 April 2018


(4) Start IPU program.
(5) When approval screen for Adobe Reader appears, touch “Accept”.
(6) Logon to IPU with “sysmex” user.
(7) Confirm that the IFU manual apprear when “Instruction for Use” icon in the “Menu” is touched.

7.4.1.7 Default rules (not supported)

7.4.1.8 Locale setting [AJ] [BM] [BN]


* A mouse and keyboard must be connected to perform this task.
(1) Select "Control Panel" - "Clock, Language, and Region" - "Date and Time Options”.

(2) Click "Change time zone..."

[AJ] 2015056 [BM] 2017117 [BN] 2017187

XN-L S/M 7-32 April 2018


(3) When the setting is different from your time zone, select appropriate one.
(4) Click "Change date and time...”

(5) Set the date and time to the current date and time and click OK.

XN-L S/M 7-33 April 2018


(6) Click OK to close the "Date and Time" dialog.

(7) Select "Control Panel" - "Clock, Language, and Region" - "Regional and Language Options".

XN-L S/M 7-34 April 2018


(8) Select the [Administrative] tab, and click the [Change system locale] button.

(9) Select the system locale of the installation location, and click the [OK] button.

(10) A restart message appears. Execute restart.

XN-L S/M 7-35 April 2018


(11) Right-click "McAfee Solidifier Command Line" on the desktop, and select "Run as administra-
tor" to run.

(12) The McAfee Solidifier command line (DOS prompt) screen opens.

(13) Input “sadmin eu” from the keyboard, then press the [Enter] key. Text to input:sadmin eu

(14) Enter the password that you set (red part), and hit the return key.
Password: McAfee password(e.g. c9.0) [BG]

[BG] 2018022

XN-L S/M 7-36 April 2018


(15) Click in the top right corner of the McAfee Solidifier command line (DOS prompt) screen to
close the window.
(16) The screen below appears. Enter “sysmex” in the [Login Name] field and Enter “c9.0” in the
[Password] field, and then press the [login] button.

(17) Press the [Finish] button below.

(18) The instrument automatically restarts. Wait while the instrument automatically shuts down.
[AJ] 2015056 [BM] 2017117

XN-L S/M 7-37 April 2018


7.5 Prime reagent [BM]
(1) Execute the water adding sequence (about 30 minutes).
(2) In the menu screen, press "Service"
→ "Service/Factory Tools"
→ "Setup/Shipping"
→ "Setting Sequence".

(3) Dispense 2 mL of ethanol into the RBC chamber.

[BM] 2017117

XN-L S/M 7-38 April 2018


(4) Press "Execute" in the Setting Sequence screen.

XN-L S/M 7-39 April 2018


7.6 Reagent Registration
Registering the diluents and hemolyzing agents
(1) Press the button on the left side of the front to start the IPU.

(2) Press [Manual]. The keyboard screen appears.

(3) Enter “sysmex” in the [Logon Name] field and enter service login password in [Password] field,
then press [OK]. [BG]

[A] 2015011 [BG] 2018022

XN-L S/M 7-40 April 2018


(4) Press [Logon].

(5) When the screen appears, select as indicated below.


▪ Error "Not ignore"
▪ Sequence "Skip all initial sequence"
▪ Heater "ON"
▪ Auto validation/output "OFF"

(6) Close the screen with "OK".


The air pump starts, and startup operation takes place.

(7) Wait until the green part of the display in the lower left corner of the screen changes from blinking
to solidly lit, and "Starting up..." changes to "Enter a sample number".

(8) Press the "Replace Reagent" icon in the


bottom left corner of the screen.
(9) The reagent replacement screen appears.
<Procedure>
▪ Read in the reagent code of the reagent
with the hand-held barcode reader.
▪ The reagent shows "Accepted".

▪ Repeat this procedure to read in all the remaining diluents and hemolytic agents.

XN-L S/M 7-41 April 2018


▪ Make sure that all diluents and hemolytic
agents show " " and press "Execute".

▪ All diluents and hemolytic agents are filled.


(After all are filled, the reagent replacement
screen closes.)

XN-L S/M 7-42 April 2018


7.7 Blank check
Run automatic washing, and perform blank check.

<Allowable blank values>


WBC-C: 1.0×10 ^ 2/μL or less
WBC-D: 1.0×10 ^ 2/μL or less
RBC: 2×10^4/μL or less
HGB: 0.1g/dL or less
PLT-I: 1.0×10 ^ 4/μL or less
PLT-O: 1.0×10 ^ 4/μL or less

7.8 Various adjustments


When installing the instrument, perform the adjustments below. For details, refer to the "Adjustment"
chapter.

▪ Piercer/pipette position check


▪ Sampler position check
▪ Optical axis check
▪ Sensitivity check
▪ Calibration check

7.9 Final Operation Check


Run the instrumen and check that no error are displayed.

XN-L S/M 7-43 April 2018


7.10 Connecting with RU-20 [AJ]
(1) Remove Wiring Cord No. 3497.

04315817
WIRING CORD NO.3497

(2) Connect Main connector on RU-20 rear panel (item 11 in figure below) and RU Supply Tank
connector on XN-L rear panel (item 13 in figure below) with Wiring Cord 8471.
Use either of following cord according to the installation situation.
AA050180 WIRING CORD_ASSY NO. 8471 (13m)
BN528860 WIRING CORD_ASSY NO. 8471 (5m)

WIRING CORD NO.8471

RU‐20 Rear Panel

XN‐L rear Panel

[AJ] 2015056

XN-L S/M 7-44 April 2018


(3) Connect supply tank nipple on supply tank rear panel (item 1 in figure below) and DCL nipple on
XN-L rear panel (item 8 in figure below) with polyurethane tube 6X4.

Polyurethane tube
6X4 (1500)
XN‐L rear Panel

Supply Tank Rear Panel

(4) Select Version - Upgrade - RU connection on XN-L main screen.

XN-L S/M 7-45 April 2018