Detection of Incipient Faults in Power T
Detection of Incipient Faults in Power T
(1)
Faculty of Engineering, Cairo University
(2)
Egyptian Electricity Transmission Company (EETC)
(3)
Cairo Electricity Production Company (CEPC)
Egypt
* [email protected]
1. INTRODUCTION A protection technique was proposed to detect the
incipient faults in the transformer, based on
The worldwide international changes in the analysis of the differential current of the simulated
electricity market put the electric utilities under faulty transformer by the developed WPT
severe stress to reduce the running (operating) algorithm.
cost, enhance the availability of the power system
and prevent forced outage while work with the
existing equipment harder and longer. Power 2. COMPUTER MODELING PRINCIPLES
transformers are considered as the most expensive
infrastructure in the substations, and hence the The basic model used in this work is the one
outage and/or damage of such critical equipment supplied by the BCTRAN routine of the ATP
is costly to any electric utility. software (Alternative Transient Program). The
transformer is handled as mutually coupled R, L
A high voltage transformer connected to an branches as shown in figure (1). Based on data of
overhead transmission system is very likely to be excitation and short circuit tests, this routine
subjected to steep fronted impulse voltages. A line computes two matrices [R] and [L] modeling the
surge, which may be of several times the rated transformer. In the case of a three-phase
system voltage, will concentrate on the end turns transformer with two windings, these matrices are
of the winding because of the high equivalent of order 6 as in equations (1-a) and (1b), where Ri
frequency of the surge front. The interturn and Li are the resistance and the self inductance of
insulation of the end turns is reinforced, but coil i, and Mij is the mutual inductance between
cannot be increased in proportion to the insulation the coils i and j [3, 4] .
to earth, which is relatively great. The risk of a
partial winding flashover compared with that of a The principle used to model a fault between a coil
breakdown to earth is therefore comparatively turn and the earth or between any two turns is to
high. A study of the records of modern divide the faulty coil into sub coils. In case of
transformer breakdowns, which have occurred turn-to-earth fault, the faulty coil will be divided
over a period of years, shows very conclusively into two coils (a, b), then, the transformer can be
that between 70 and 80% of the number of failures described with two 7x7 matrices [R], [L]. In case
are finally traced to short-circuit between turns of turn-to-turn fault, the faulty coil will be divided
[1]. The subsequent progress of the fault, if not into three coils (a, b, c), consequently, the
detected in the earliest stage, may well destroy the transformer is divided into two 8x8 matrices are
evidence of the true cause. A short circuit of a few required. This principle is used such that the
turns of the winding will give rise to a heavy fault number and location of the shorted turns can be
current in the short-circuited loop, but the terminal variable. The divided coil, no. 3, for the two faulty
currents will be very small, because of the high cases is shown in Figures 2(a, b). In the following
ratio of transformation between the whole two sections, the analysis will be described in
winding and the short-circuited turns [2]. details [5, 6].
1. Consistency :
M3i = Mai + Mbi (10)
2. Proportionality :
[R]= M ai / M bi = na / nb = k (11)
(2-a)
Let the original signal contains 2N sampling This will provide sharper cut-off frequency to the
points. The wavelet coefficients at the level (j) and selected mother wavelet and
node (i) is (dij).The maximum resolution level can reduces the amount of leakage energy to the
be achieved is N. adjacent resolution levels [12, 13]
Where
i = 0 ,1 , 2 , 3,……… 2 j -1 ,
Capture Signal
j = 1 , 2 , 3 , 4,……….N
Samples
Figure (4) shows a flow chart for the proposed
algorithm.
Apply Wavelet
Packet Analysis
From the previous analysis, it's clear by choosing
the appropriate sampling frequency and the WPT
resolution level; we can allocate the required Get the Wavelet
harmonics in different frequency bands (nodes). Coefficients
I = ∑ (d
Get the RMS Values of the
i 1 i 2 Harmonics
) (16)
k =0
j
2N j
(17)
and so on for the other harmonics.
4. SIMULATION WORK
Figure (5): The circuit of the system under the study Figure (7): Secondary Currents of the
in the ATP program environment three simulated Incipient Fault cases
Figure (8): Differential currents of the
three simulated incipient fault cases
4.3 Harmonic Analysis of the Differential Figure (9): The harmonic analysis results of the
Currents of the Simulated Incipient Fault differential currents of the simulated incipient faults
Cases
In the previous section, harmonic analysis was Figure (10): The harmonic analysis results of the
done for the differential current in cases of differential currents in case of switching 25% load
transformer incipient faults and it was found that
the change in the harmonics value has some
characteristics, which could be used to detect the
incipient faults. To make sure from these results
we need to make analysis of other transient
conditions, which may occur to the transformer,
from these transient conditions is load switching.
From this summery it can be shown that the If T1 equals one cycle time and T2 equal zero, a
incipient internal faults can be detected and load switching condition is detected. If T1 equals
discriminated by observing and monitoring the one cycle time, T2 does not equal zero and the
characteristics of the harmonics content and its primary current in time T1 changed with no
change behavior. change in the secondary current, an incipient
internal fault is detected.
Figure (12) shows a flow chart for the designed As initial inter-turn insulation failure does not
technique. The results shown in table (I) were draw sufficient current from the line, traditional
used to make this technique. The differential differential relays are unable to detect such faults
currents of the three phases are computed as a result the transformer will only be
continuously. Harmonic analysis is done by the disconnected from the line when the fault has
WPT algorithm, the DC component, 2nd and 3rd extended to such a degree to embrace considerable
harmonics are portion of the affected winding.
Table (I)
Comment - The Transient Change in the Harmonic values starts and ends
in one cycle.
- The Max value remains for less than 1/2 cycle
- The primary current increase with no change in the secondary
current.
Load Switching
Max <<60 Max <<60 Max << 60
Comment - The Transient Change in the Harmonic values starts and ends
in one cycle.
- The Transient Change is accompanied by a large change in
the secondary current.
Start
T1=0, T2=0
NO | Idc(k) - Idc(k-2) | ≥ 3%
and | I2nd (k) -I2nd(k-2) | ≥ 3%
and | I3rd (k) -I3rd (k-2) | ≥
YES
T1 =0
YES
NO
The End of the Transient Period Transient Change Detected
Transient Period = T1 Compute the Transient Period
T1=T1 + sample time
NO
T1 =1 Cycle?
Idc(k) > 60% NO
YES Or I2nd (k) > 60%
Or I3rd (k) > 60%
T2=zero?
YES
NO YES
Compute the Transient Peak Period
NO T2=T2 + sample time
In T1 the Prim Current
changed with no
change in the Sec
YES
Detect an Incipient Fault Detect a Load Switching
Condition Condition