Cqa 01
Cqa 01
ASSESSMENT - 01
Concrete
16 2.99 47.84 GR20 Screed concrete for
base thickness 75mm
Upper surfaces inclined at
30deg – 60deg to the horizontal
(W 442)
Area of trapezoid =
1/2 * (3450+750)1450=
2.99m2
(1) (2)
4 0.75 GR20 Screed concrete for 4 0.35 ddt- precast trough hole
0.58 1.74 base thickness 75mm 0.35
49.58 Surfaces of width 0.15 0.0735
300 mm–1 m 52.036
(W 447)
Precast
GR25 Reinforced concrete 8 Precast trough
psoil, max for base thickness Segmental units
300mm - 500 mm (F 723) (H 6)
(3) (4)
1 10.85 Bypass channel Wall
2.45 26.583 Outside Area
rough finish, plane vertical
width exceeding 1.22m
(G 145)
Handrail
4 7.2 28.8 40Dia. G.I Handrail
4 3.45 13.8 (N 14)
2 4.35 8.7
2 8.1 16.2
2 2.25 4.5
(5) (6)
Query Sheet
Name of the Project:Water Supply And Sanitation Improvement Project
Name of the Engineer/Architect:
Name of the Quantity Surveyor:
Item
Date Query Date Answer
No
1 24/01/24 The assumed gap between handrail bars is 27/01/2024 Yes
0.75
It meters. that all reinforcement bars
is presumed
2 24/01/24 will be treated with galvanization before 27/01/2024 Yes
installation.
To accommodate water expansion during
3 24/01/24 freezing and reduce the chances of cracks 27/01/2024 Yes
and deterioration, AIR-MAN Admixtures
will be incorporated.
4 24/01/24 27/01/2024 Yes
Waterproofing admixtures are being
included in the concrete mix to improve its
resistance to water infiltration.
5 24/01/24 27/01/2024
It is anticipated that there will be a 40 mm
Yes
covering over all reinforcement materials.
........................................................... …........................................................
Signature of Qs Signature of Architect
CONSULTANT QS
BOQ
BILL Of QUANTITIES
OF
Sedimentation Tank at Treatment Plant Site
Preparati0n 0f a Bill 0f Quantities and Pre Tender Estimate f0rSedimentati0n Tank at
treatment plant site
BILLS 0F QUANTITIES
M0DE 0F
ITEM N0 DESCRIPTI0N PAYMENT UNIT AM0UNT
CATEG0RY
PRELIMINARIES
Insurance and Securities
1 All0w a Sum f0r pr0viding a Perf0rmance
Item
Security fr0m Appr0ved Bank
C0ntract0r's Facilities
Setting 0ut
Earthw0rks
Excavati0n
1 (E 421) General Excavati0nmaterial 0ther than t0ps0il,
max depth n0t exceeding 0.25 m c0mmencing 15.89 m³
fr0m level 0f 96.54 m
Excavati0n ancillaries
Pr0visi0n 0f C0ncrete
Placing 0f C0ncrete
C0ncrete Ancillaries
7 G 114
F0rmw0rk f0r base , r0ugh finish, plane 1.74 m²
h0riz0ntal width between 0.4m - 1.22m
8 G 125
F0rmw0rk f0r base , r0ugh finish, plane 47.84 m²
sl0pping width between 0.4m - 1.22m
Precast C0ncrete
MISCELLANE0US METALW0RK
Handrails
1 N 14 40 Dia. G.I handrail 71.25 m
T0TAL CF -
C0ntract0r's Facilities
Setting 0ut
Earthw0rks
Excavati0n
1 (E 421) General Excavati0nmaterial 0ther than t0ps0il,
max depth n0t exceeding 0.25 m c0mmencing 15.89 m³ 2,956.25 46,974.81
fr0m level 0f 96.54 m
Excavati0n ancillaries
Pr0visi0n 0f C0ncrete
Placing 0f C0ncrete
C0ncrete Ancillaries
7 G 114
F0rmw0rk f0r base , r0ugh finish, plane 1.74 m² 1,831.50 3,186.81
h0riz0ntal width between 0.4m - 1.22m
8 G 125
F0rmw0rk f0r base , r0ugh finish, plane 47.84 m² 2,365.00 113,141.60
sl0pping width between 0.4m - 1.22m
Precast C0ncrete
MISCELLANE0US METALW0RK
Handrails
1 N 14 40 Dia. G.I handrail 71.25 m 3,500.00 249,375.00
T0TAL CF 249,375.00
SUMMARY
1 Preliminary 2,505,000.00
6 Provisional Sum -
TOTAL 10,864,231.35
Labour
1 Skilled Labour day 3,000.00
2 Unskilled labour day 2,500.00
3 Supervisior day 3,500.00
4 Barbenders day 3,500.00
5 Mixer Operator day 3,000.00
Materials
1 Cement bag 2,750.00
2 Sand cube 28,000.00
3 Aggregate 20mm cube 23,000.00
4 Water gal 10.00
5 2mm plywood sheet (8ft x4ft) m² 550.00
6 Wire nails kg 200.00
7 Mould Oil l 200.00
8 Auto Diesel l 350.00
9 Petrol l 400.00
10 Kerosine l 200.00
2 Tools
a.Excavator (4 m³/Hr) 0.25 hour 5000.00 1250.00
b.Other Equipment (5%) item 62.5
2 Tools
a.Excavator (4 m³/Hr) 0.33 hour 5000.00 1650.00
b.Other Equipment (10%) item 165
2 Equipement
a.Tractor & fuel 1 Day 6000.00 6000.00
b.Tipper 3m3 1 Day 3300.00 3300.00
2 Labour
Mixing
a.Mixer Operator 0.13 day 3,000.00 390.00
2. Curing
a.Unskilled labour 0.1 days 2,500.00 250.00
2 Labour
Mixing
a.Mixer Operator 0.25 day 3,000.00 750.00
2. Curing
a.Unskilled labour 0.1 days 2,500.00 250.00
2 Labour
a. Skilled labour 0.10 day 3,000.00 300.00
b. Unskilled labour 0.10 day 2,500.00 250.00
2 Labour
a. Skilled labour 0.15 day 3,000.00 450.00
b. Unskilled labour 0.15 day 2,500.00 375.00