Method Statement
Method Statement
Project:
Activity: Roof Work
Description: Carrying out roof work including installation and repair of roof coverings
Start Date: TBC Duration: TBC
Assessor: Harry Isaac Hours of Work: TBC
Responsibilities
Hazards
TRAINING
Only qualified, certified or otherwise competent personnel will be permitted to undertake the work.
All operatives are to receive training on manual handling techniques, asbestos awareness and work at height.
All workers to undertake site induction prior to commencing work.
Toolbox talks will be carried out at weekly intervals during the works to raise awareness of relevant H&S issues.
ACCESS
Fixed scaffolding to be provided to access roof level and to provide a safe working platform for operatives. Full edge
protection to be in place and fall restraint systems or crash deck to prevent falls through roof structure during
construction.
Ladders are only to be used for access and short duration work, and only when there is no suitable alternative.
Preferred access equipment includes full access scaffolding, tower scaffold or MEWP. Scaffolding to be erected by
others.
Access equipment will be securely stored at the end of each shift to prevent unauthorised use. Exclusion zones will be
established in the area below any overhead works, using suitable barriers and signage, to protect people below from risk
of any falling tools or materials.
PREPARATION
Perimeter scaffolding to be provided for full edge protection, working platform and safe access/egress. Alternatively,
full edge protection at eaves level must be erected by a qualified or competent person. The edge protection must be
strong enough to withhold a person leaning against it.
Safety decking system to be erected or other effective fall prevention system and working
platforms.
All trusses and other building materials to be inspected prior to lifting to ensure free from defects.
Any defective materials reported to site management.
All wall plates to be level and secured to load-bearing walls. No trusses to be placed on wall plates if they appear to be
in an unsafe condition.
ROOF WORK
Roof materials will be safely lifted to the roof area. Materials lifted under the control of a lifting plan for the
lifting operations.
Fall protection to be provided throughout the roofing works, either via permanent edge protection, full
access scaffold providing edge protection or for minor repair works, fall prevention will be via harness and
lanyard connected to suitable anchor device.
Where existing materials are removed from the roof, they will be discarded into skips positioned at ground
level via a debris chute with a hopper. The skip will be fenced off and suitably screened to prevent debris
from falling outside the controlled area.
All materials temporarily stored on the roof will be evenly distributed and away from roof edges.
Lightweight materials (e.g. insulation) will be weighed down to prevent it being blown from the roof.
All equipment and services checked to ensure they are sufficiently secured to roof. Redundant aerials, cables
etc will be removed as instructed and carefully lowered for disposal.
Check roof materials for gaps, missing or slipped tiles and leaks.
Carefully removed damaged or cracked tiles and lower to ground level via a pulley, chute or carried.
The roof tile underfelt is to be reinforced bituminous felt, replace as necessary to ensure full coverage.
Assess, treat and replace battens as necessary due to damage, rot or infestation. Battens to be fixed
with staggered joints and square butt joint.
Nails for battens shall be sized to give a secure fixing without splitting the batten.
Roof tiling to be laid in even courses to suit existing gauging and laps and be secured with the appropriate
patent clips and or nails. Tiles shall be head nailed with two nails in every tile.
Eaves shall be formed with a double course of tiles.
Do not place materials to be cut directly onto scaffold boards.
Where roof tiles cut by powered saw, ensure that the equipment is in good order. Only to be used by
experienced and trained operatives.
Additional PPE to be worn during cutting operations including wear eye protection, ear protection and a
respiratory protection.
EXTERNAL WORK
External work prohibited during extreme weather such as rain, strong winds or snow. External work at height also
prohibited in icy conditions.
Operatives to be warned of the dangers of skin damage prior to external work. Operatives must wear appropriate clothing
to protect skin and must apply sufficient sun protection when exposed to UV rays.
Work area to be segregated from any pedestrians or traffic and signs erected to prevent
members of the public or vehicles coming into contact with operatives or access equipment.
HOUSEKEEPING
All good practice guidelines regarding housekeeping in the workplace will be observed. All spillages will be
immediately cleaned up so as to prevent any slip hazards.
All work equipment, chemicals and substances will be properly secured when they are not in use, so as to prevent any
unauthorised usage or accidental contact. During the works, the area will, so far as is reasonably practicable, be kept
clean and tidy with clear walkways as appropriate.
LIFTING OPERATIONS
Crane lifting plan/lifting plan to be completed for all lifting operations involved with the task. Lifting equipment will
be of sufficient capacity, will have a current test and thorough examination certificates and will be inspected weekly.
All lifting gear to be clearly identifiable and colour coded for the currency of examinations. All lifting gear is subject to
thorough examinations which are to be carried out by a competent person and recorded at least at six monthly intervals.
Damaged equipment is to be taken out of use immediately.
Equipment is to be of the correct length(s) and have sufficient safe working load capacity for the task.
All persons involved in any lifting operations to be competent for the task they are to carry out. Communication between
the crane operative and banks man is to be by two-way radios or hand signals if there is a good line of vision. Access to
the area below lifting operations prohibited and to be prevented at all times, with suitable barriers and signage.
Heavy loads are to be lifted into position by mechanical aids to minimise manual handling. Where manual handling is
required this will be supported by lifting gear and sufficient personnel must be allocated to the work, from a safe
working platform.
MANUAL HANDLING
All manual handling will be minimised through the provision of mechanical aids where practicable.
Where possible materials will be supplied in loads under 25kg. Operatives are not expected to handle loads any items
weighing more than 25 kg on the site without assistance.
If items above 25kg are to be lifted, or unusual, unstable or hazardous items, the supervisor/site manager will determine
a safe method of handling through completing a risk assessment and specifically instruct nominated individuals.
Any items or loads above 25kg to be handled through mechanical aids or team lifting. Deliveries and materials
handling will be planned to minimise the extent of manual handling of materials.
Routes by which materials have to be carried by hand will be checked for and kept free of, obstructions.
Appropriate PPE will be worn to make sure that materials can be handled safely, e.g. gloves and safety footwear.
Two or more operatives will carry larger or heavier items.
LEAD
Lead working will always be carried out outside with natural ventilation.
Additional PPE including gloves and respiratory protective equipment shall be used. The PPE will not be taken
home and will be disposed of when used.
Food and drink must not be consumed until operatives have thoroughly washed their hands after working with lead.
All employees that are exposed to lead will be subject to health surveillance.
FIRE PREVENTION
All current legislation and codes of practice regarding fire prevention will be complied with. Where possible any
flammable substances will be substituted for alternative non-flammable substances.
All hot works will be controlled through the use of a permit to work system.
Prior to the commencement of any works that may involve the use of a naked flame, all combustible material /
pressurised containers will be removed from the immediate vicinity. Prior to the commencement of any works that
could create a fire, suitable portable firefighting equipment will be positioned accordingly. During any work which
involves the use of a flammable article or substance, all appropriate measures will be taken so as to keep sources of
ignition (naked flames, cigarettes etc) away from said flammable articles or substances. Skips and storage of flammable
materials will be positioned away from any potential sources of ignition and protected from any foreseeable risk of
arson.
Upon completion of any works which may have given rise to the risk of fire/explosion, the area will be checked and left
in a clean condition. A 1-hour fire check will be in place for all hot works.
HARMFUL SUBSTANCES
All current legislation and codes of practice regarding chemical and substance usage will be complied with.
Where possible any hazardous substances will be substituted for alternative non-hazardous substances.
COSHH assessments will be carried prior to use of hazardous substances.
Only those persons who are fully conversant with a chemical or substance will be permitted to use the chemical or
substance. Adequate ventilation will be maintained at all times where hazardous chemicals or substances are used.
When not required for immediate use, chemicals and substances will be kept in suitable closed containers and in a
secure location, so as to prevent their unauthorised use.
WORK EQUIPMENT
All current legislation and codes of practice regarding work equipment usage will be complied with.
Only those persons who have received suitable and sufficient instruction and training will be permitted to use work
equipment.
All work equipment to operate on 110v.
Any mains powered 240v work equipment will operate, via a transformer or other power- reducing device, at a reduced
voltage of no more than 110v.
Prior to using any item of work equipment, it will be inspected to ensure that it is in good condition and unlikely to cause
injury or harm to any person as a result of its correct usage. Equipment guards to be correctly fitted before use.
All personnel are advised to check tools before each use and to take unsafe equipment out of service immediately, for
repair or replacement.
Periodic testing and maintenance of all equipment carried out in accordance with regulations and manufacturer’s
instructions.
When not required for immediate use, all items of work equipment will be securely stored so as to prevent any
unauthorised use or accidental contact with any sharp or rotating blades.
WORK AT HEIGHT
For potential falls through unfinished roofs where there are openings then these should be adequately protected by using a
solid platform to eliminate the fall potential or by using a soft landing system and fall restraint system to minimise injury.
All current legislation and codes of practice regarding working at height will be complied with. Suitable access
equipment will be selected to provide a safe working platform (taking into account the task, the duration of the platform
use and the location in which the platform is to be used) shall be employed whilst undertaking any work at height
and will be subject to inspection before and during its use.
Suitable access shall be provided to the working platform and will be subject to inspection before and during its use.
Suitable barrier edge protection shall be employed where necessary.
Suitable warning signage and barriers (as appropriate) shall be positioned around the work platform base and danger area,
so as to prevent unauthorised access.
Only those persons who have received suitable instruction shall be permitted to undertake work at height.
WASTE DISPOSAL
All current legislation regarding the prevention of environmental contamination (including waste disposal) will be
complied with. Any contaminated or hazardous waste created as a result of works carried out will be properly
contained and disposed of by a specialist company. Waste must be transferred using a waste transfer note.
CLEANING
After completion of the work, the area shall be left in a clean, tidy condition and all associated waste shall be removed
and properly disposed of.
PPE Requirements
Other PPE:
Additional PPE is required for certain activities as indicated by specific risk assessments.
Management Arrangements
Monitoring Arrangements:
Monitoring of this activity will be carried out using a variety of different means such as: inspections, checklists, meetings, aud
Welfare Provision:
Welfare facilities will be provided within close proximity to the work area.
Personnel must not eat, drink or smoke in the work area. Welfare facilities, including rest areas and toilet facilities, will be lef
Emergency Procedures:
In the event of an accident notify the first aider immediately, for a major injury call 999 or if in doubt call 111.
In the event of a fire sound the alarm and exit the site by the nearest exit, to not attempt to tackle the fire unless yo
In the event of discovering a material that you suspect could be asbestos containing, stop work immediately and n
Completed By
Name: Tracey Pilkington
Signature:
Date: 04/01/2020
Acknowledgement
Name Signature Date