Bill of Quantity For The Work Dismantling and Shifting of Existing View Tower at New Birsa Outsourcing Mines Through Birsa Project. Remarks Sor-2014

1) The document provides a bill of quantities for dismantling and shifting an existing view tower at an outsourcing mines site, including 21 line items describing the work, quantities, unit rates, and total costs. 2) The work includes dismantling steel structures, roofing, and tile flooring; excavation; masonry work; plastering and painting; and the installation of precast concrete pavers and reinforcement. 3) The total cost for the project is Rs. 164,983.18 including an 18% GST on the subtotal of Rs. 139,816.25.

Uploaded by

Tricolor C A
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views3 pages

Bill of Quantity For The Work Dismantling and Shifting of Existing View Tower at New Birsa Outsourcing Mines Through Birsa Project. Remarks Sor-2014

1) The document provides a bill of quantities for dismantling and shifting an existing view tower at an outsourcing mines site, including 21 line items describing the work, quantities, unit rates, and total costs. 2) The work includes dismantling steel structures, roofing, and tile flooring; excavation; masonry work; plastering and painting; and the installation of precast concrete pavers and reinforcement. 3) The total cost for the project is Rs. 164,983.18 including an 18% GST on the subtotal of Rs. 139,816.25.

Uploaded by

Tricolor C A
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Bill of quantity for the work Dismantling and shifting of existing view tower at New Birsa

Outsourcing Mines through Birsa Project.

Remarks
Sl. updated
Description of work Qnty. Unit Amount SOR-
No. rate
2014
1 Dismantling steel work in built up sections in 1338.24 kg 2.95 3947.81 15.18
angles, tees, flats and channels including all
gusset plates, bolts, nuts, cutting rivets, welding
etc. including dismembering and stacking
within 50m lead.
2 Structural Steel work in single section fixed 1338.24 kg 14.85 19872.86 10.1 AR
with or without connecting plate including
cutting, hoisting, fixing in position and applying
a priming coat of approved steel primer all
complete.
3 Dismantling roofings including ridges, hips, 50.23 sqm 85.97 4318.27 15.28.1
valleys and gutters etc. including stacking of
materials within 50 metres lead of GS Sheet.
4 labour for fitting and fixing GCI or CA sheet 50.23 sqm 204.85 10289.62 JH-15
roofing in proper slope including the castoff J 5.9.10
or L hooks limpet and bitumen washers,
carriage of sheets to work site and taxes all
complete as per building specification and
direction of EIC.
5 Fixing old wind ties with new fittings including 32.00 metre 80.17 2565.44 14.20
painting two or more coats with anti-corrosive
bitumastic paint of approved brand and
manufacture over and including priming coat of
ready mixed zinc chromate yellow primer of
approved brand.
6 Earth work in excavation by mechanical means 7.79 cum 201.56 1570.15 2.8.1
(Hydraulic excavator) / manual means
foundation trenches, drain not exceeding 1.5 m
in width as well as 10 sqm on plan including
dressing of sides and ramming of bottom, lift up
to 1.5 m including getting out the excavated
soil and disposal of surplus excavated soil as
directed within a lead of 50 m. (All kinds of
soils).
7 Demolishing brick work manually / by 4.625 cum 977.04 4518.81 15.7.4
mechanical means including stacking of
serviceable materials and disposal of
unserviceable materials within 50 metre lead as
per direction of Engineer-in-charge. In cement
mortar.
8 Structural Steel work in single section fixed 113.92 kg 58.48 6662.04 10.10
with or without connecting plate including
cutting, hoisting, fixing in position and applying
a priming coat of approved steel primer all
complete.
9 Providing and fixing precoated galvanised iron 12.20 sqm 605.54 7387.59 12.50
profile sheets (size, shape and pitch of
corrugation as approved by Engineer-in-charge)
0.50mm +/- 5% total coated thickness (TCT)
Zinc coating 120gsm as per IS:277 in 240mpa
steel grade, 5-7 microns epoxy primer on both
side of the sheet and polyester top coat 15-18
microns. Sheet should have protected guard
film of 25 microns minimum to avoid scratches
while transportation and should be supplied in
single length up to 12 metre or as desired by
Engineer-in-charge. The sheet shall be fixed
using self drilling / self tapping screws of size
(5.5x55mm) with EPDM seal or with polymer
coated J or L hooks, bolts and nuts 8mm
diameter with bitumen and GI limpet washers
or with GI limpet washers filled with white lead
complete upto any pitch in horizontal / vertical
or curved surfaces excluding the cost of purlins,
rafters and trusses and including cutting to size
and shape wherever required.
10 Brick work with FPS bricks of class designation 5.00 cum 5700.02 28500.10 6.1.2 DR
5.0 in foundation in plinth in cement mortar 1:6
(1cement : 6coarse sand).
11 Providing and laying cement concrete of 1.69 cum 5326.57 9001.90 4.1.3
specified grade excluding the cost of centering
and shuttering in all works up to plinth level :
1:2:4 (1cement : 2coarse sand : 4graded stone
aggregates 20 mm nominal size).
12 Half brick masonry with common burnt clay 8.85 sqm 820.83 7264.35
FPS (non-modular) bricks of class designation
5.0 in superstructure above plinth level in
Cement mortar 1:4 (1 cement : 4 coarse sand).
13 Brick work with common burnt clay FPS (non- 0.25 cum 6686.02 1671.51 6.13.2
modular) bricks of class designation 5.0 in DR
super structure above plinth level up to floor V
level in all shape and size in cement mortar 1:6
(1cement : 6coarse sand).
14 12mm cement plaster finished with a floating 25.78 sqm 252.37 6506.10 13.7.2
coat of neat cement of mix: 1:4 (1cement : 4fine
sand).
15 12mm cement plaster of mix: 1:6 (1cement : 21.70 sqm 190.40 4131.68 13.1.2
6fine sand).
16 White washing with lime to give an even shade: 21.70 sqm 20.08 435.74 13.37.1
New work (three or more coats).
17 Painting with synthetic enamel paint of 25.78 sqm 85.38 2201.10 13.61.1
approved brand and manufacture to give an
even shade: Two or more coats on new work.
18 Dismantling tile work in floors and roofs laid in 84.83 sqm 62.70 5318.84 15.23.2
cement mortar including stacking of materials
within 50m lead: For thickness of tiles above
25mm and up to 40mm.
19 Providing and laying factory made chamfered 60.00 sqm 205.86 12351.60 AR 16.94
edge Cement Concrete paver blocks of required
strength, thickness & size/shape, made by table
vibratory method, to attain superior smooth
finish using PU or equivalent moulds, laid in
required Grey colour & pattern over 50mm
thick compacted bed of coarse sand,
compacting and proper embedding / laying of
inter locking paver blocks into the sand bedding
layer through vibratory compaction by using
plate vibrator, filling the joints with jamuna
sand and cutting of paver blocks as per required
size and pattern, finishing and sweeping extra
sand in footpath, parks, lawns, drive ways or
light traffic parking etc. all complete as per
manufacturer’s specifications & direction of
Engineer -in-Charge: (a) 80 mm thick c.c. paver
block of M-30 grade with approved color
design and pattern.
20 Providing hoisting and fixing up to floor five 0.11 cum 6937.44 763.12 5.12
level pre-cast reinforced cement concrete work
in string courses, bands, copings, bed plates,
anchor blocks, plain window sills and the likes
including the cost of required centering and
shuttering finishing smooth with 6mm thick
cement plaster 1:3 (1cement: 3fine sand) on
exposed surfaces but excluding the cost of
reinforcement with 1:2:4 (1cement : 2coarse
sand : 4graded stone aggregates 20mm nominal
size).
21 Reinforcement for RCC work including 6.60 kg 81.46 537.64 5.22.6
straightening, cutting, bending, binding and
placing in position complete: Thermo
Mechanically Treated bars.
Total Rs. 139816.25
Add GST @18% 25166.93
Total Cost including GST Rs. 164983.18