Load Classfication
Load Classfication
Demand - “The demand of an installation or system is the load at the receiving terminals
averaged over a specified interval of time” . Here, the load may be given in kilowatts,
kilovars, kilovoltamperes, kiloamperes, or amperes.
- The average value of power or a related quantity over a specified interval of time.
Demand is expressed in kilowatts, kilovolt-amperes, kilovars, or other suitable units.
Demand interval - It is the period over which the load is averaged. This selected ∆t period
may be 15 min, 30 min, 1 h, or even longer. Of course, there may be situations where the 15
and 30 min demands are identical.
End-User. - Any person or entity requiring the supply and delivery of electricity for its own
use.
Meter- A device, which measures and records the consumption or production of electricity.
Load Data
Time Load in kW
0:00-1:00 200
1:00-2:00 200
2:00-3:00 200
3:00-4:00 300
4:00-5:00 400
5:00-6:00 500
6:00-7:00 600
7:00-8:00 600
8:00-9:00 800
9:00-10:00 1000
10:00-11:00 1000
11:00-12:00 900
12:00-13:00 800
13:00-14:00 1000
14:00-15:00 1000
15:00-16:00 1200
Time Load in kW
16:00-17:00 1300
17:00-18:00 1500
18:00-19:00 1700
19:00-20:00 1800
20:00-21:00 1800
21:00-22:00 1600
22:00-23:00 800
23:00-24:00 400
Daily Load Curve
2000
1800
1600
1400
1200
1000
800
600
400
200
0
Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Load Duration Data
Duration(hrs.) Load in kW
2 1800
3 1700
4 1600
5 1500
6 1300
7 1200
11 1000
12 900
15 800
17 600
18 500
20 400
21 300
24 200
Load Duration Curve
2000
1800
1600
1400
1200
1000
800
600
400
200
0
Time
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
-Load curve decides the installed capacity of the power station and the economical sizes of
the various generating units.
-The load curves allow also to estimate the generating cost, and to decide the operating
schedule of the power stations.
-To evaluate the reliability of the generating units, the load demand that persists for
particular duration should be known. For that we need the load duration curve.
Diversified demand (or coincident demand)- It is the demand of the composite group, as a
whole, of somewhat unrelated loads over a specified period of time. The maximum
diversified demand has an importance. It is the maximum sum of the contributions of the
individual demands to the diversified demand over a specific time interval.
Demand Factor- ratio of the sum of the maximum demand of a system to the total connected
load
Utilization factor-It is “the ratio of the maximum demand of a system to the rated capacity of
the system” . Therefore, the utilization factor (Fu) is
Plant factor- It is the ratio of the total actual energy produced or served over a designated
period of time to the energy that would have been produced or served if the plant (or unit)
had operated continuously at maximum rating. It is also known as the Plant capacity factor
or the Plant utilization factor.
Load factor- It is “the ratio of the average load over a designated period of time to the peak
load occurring on that period”. Therefore, the load factor FLD is average load:
Diversity factor- It is “the ratio of the sum of the individual maximum demands of the
various subdivisions of a system to the maximum demand of the whole system” . Therefore,
the diversity factor (FD) is
Coincidence factor- It is “the ratio of the maximum coincident total demand of a group of
consumers to the sum of the maximum power demands of individual consumers comprising
the group both taken at the same point of supply for the same time”. Therefore, the
coincidence factor (Fc) is
Load diversity- It is “the difference between the sum of the peaks of two or more individual
loads and the peak of the combined load” . Therefore, the load diversity (LD) is
Contribution factor- defines ci as “the contribution factor of the ith load to the group
maximum demand.” It is given in per unit of the individual maximum demand of the ith load.
Therefore,
Loss factor- It is “the ratio of the average power loss to the peak-load power loss during a
specified period of time” .Therefore, the loss factor (FLS) is
EXAMPLES
Typical Daily Load in kW
Time Street Lighting Residential Commercial
0:00 AM-1:00 AM 100 200 200
1-2 100 200 200
2-3 100 200 200
3-4 100 200 200
4-5 100 200 200
5-6 100 200 200
6-7 100 200 200
7-8 100 300 200
8-9 400 300
9-10 500 500
10-11 500 500
11-12 500 1000
12 Noon-1 500 1000
Time Street Lighting Residential Commercial
1-2 500 1200
2-3 500 1200
3-4 500 1200
4-5 500 1200
5-6 600 800
6-7 100 700 400
7-8 100 1000 400
8-9 100 1000 200
9-10 100 1000 200
10-11 100 600 200
11-12 100 600 200
12 PM- 100 600 200
An oversized motor-15kW-drives a constant 12 kW load whenever it is on. However the
motor is only used for 8hrs./day, 50 weeks/year. Determine the Utilization Factor or Use
Factor.
Using a large commercial building that electrical bill indicates that it has a peak demand of
436 kW and the energy used is 57200 kWh in the span of 30 days. Determine its load factor.
Calculate the size of a main feeder from substation switchgear that is supplying five feeders
with connected loads of 400,350,300,250 & 200 kilovolt-ampere (kVA) with demand factor
of 95, 90, 85, 80 & 75 percent respectively. Use a diversity factor of 1.5.
A 5 stories apartment building with 25 consumers each having 6 kVA of installed loads is
shown in this figure. Given the diversity factor table, determine the apparent-power supply
required for the building. If the feeders are 3-phase 400 V line voltage, determine the
magnitude of currents in different sections of the common main feeder supplying each
floors.
𝑃 𝐿 𝑆 𝑎𝑣
The Loss Factor can be determined by FLS = . ,
𝑃 𝐿𝑆 𝑚𝑎𝑥
,
Wherein FLs = Loss Factor, PLSav = Average Power Power Loss, PLSmax = Maximum Power
Loss