QA QC Civil Site Engineer Interview Notes
QA QC Civil Site Engineer Interview Notes
PQP is also called Quality management plan/ Quality 2. Project completion in time
Assurance plan. 3. Project should be complete within Budget.
As per Schedule Q requirements, PQP document is Quality Documents
submitted by contractor to consultant/ client , 30 days 1. PQP Project Quality Plan
prior executing to project. 2. ITP Inspection and test plan
PQP is comprehensive document that outlines the 3. Inspection Checklist
strategies, processes and activities required to ensure that 4. WIR Work Inspection Request
a project delivers that expected level of Quality. 5. Material Inspection Request
In other words, we can say, It is the plan of project that 6. Daily Look ahead
everything we need to know about the project is describe 7. Two weeks look ahead
in PQP. 8 . Weekly Quality Report
PQP covers procurement Inspection, testing, construction 9. Monthly Quality report
completion, handing over and commissioning as per 10. Project Quality index
tender document provided by contractor. 11. Key performance Indicator
It typically includes the following sections. 12. SOR
1. Introduction Site observation Report
Quality policies 13. NCR Non Conformance Report
Abbreviations Supportive documents for quality
Definition 1. Drawings
There are many types of drawings, using for projects, like
Client
Contract Drawing, shop drawing , IFC Drawing. IFC stand
Consultant for issued for construction.
Contractor 2. Material Submittal
3. PQD Pre-qualification Document
2. Quality plan 4. Method statement
References: This project refers to the following What is material submittal in civil construction field?
documents. Material submittal is a combination of documents in which
ISO 9001-2015- Quality management system requirements included full details of supplier , manufacturer and
ISO- 1005- 2018- Quality management system Guidelines material, which contractor need to approved material and
for Quality plan supplier/ manufacturer from consultant.
3. Scope of work Before start activity at site of using that material ,
4. Responsibilities and role of contractor staff in project contractor need approval of that material for using at site
like Pm, CM, Quality managers, Quality Engineers and in the form of submission material submittal to consultant.
Quality inspectors. Contractor purchase department contact with supplier for
5. Quality documents getting material submittal and provide project
Submittal forms specifications for compliance statement and technical data
WIR form sheet.
MIR form Then supplier handover material submittal to contractor
Method statements Materials or QC engineer.
ITP form In that submittal there will be details in osy page which is
Non Conformance Report called table of contents such as below.
INCR 1. Company Profile
Calibration Record 2. Catalogue
Weakly Quality Report 3.Compliance statement
Monthly Quality report 4.commercial / trade / industrial licence
Internal audits 5. ISO certificates
External audits 9001 for quality purpose
Etc. 14001 for environmental
6. Resources 45001 for safety
Organization chart Note : 9001 is must for every materials submittal.
Contractor employees chart But 14001 and 45001 only required which materials has
7. Procurement environmental and safety effects.
8. Quality checklist 6. Previous approvals
9. Records and Registers 7. Material test reports
What is quality? 8. Warranty certificate
There are three parameters of Quality 9.country of origin
Such as ( if material from foreign country )
1. QUALITY Requirements 10. Technical or material data sheet
Like inspection and testing of site activities as per client 11. Safety data sheet
contract documents such as (A) specifications, (B ) Drawing When contractor receive above material submittal from
and (C) BOQ supplier which has 11 numbers of contents.