Impacted As-Planned Analysis Topic 6
Impacted As-Planned Analysis Topic 6
Impacted As-Planned Analysis Topic 6
Steps .
1. The contractor has to establish that the baseline schedule has been
achievable. When that is not true then the calculated delay may not be
right, since some or all of the calculated delay is inevitable.
2. The contractor must ensure that the program is appropriate for dynamic
simulation. This means that it will involve the calculation of the schedule
by simulation using computers and software. If the schedule is not capable
of dynamic simulation, the contractor must make adjustments to the logic
of the schedule and, in particular, replace the constraints applied in order
for the activities to react appropriately during the analysis.
3. The contractor must determine the nature, extent, and relationship of the
delay event to be established so that it can be properly linked to the
schedule.
How to Perform the Impacted As Planned
Delay Analysis in (Primavera P6)