Contract Costing
Contract Costing
CONTRACT COSTING
Carriage ₹ 6000, Sundry expenses ₹ 3000. On 30th June, 2006, the work was
completed and the balance of contract price was received in cash.
Prepare the contract account and the contractee’s account for three years.
Amount ₹
Materials sent to site 7,74,300
Labour paid 10,79,000
Labour outstanding as on 31.3.2012 1,02,500
Salary to engineer 20,500 per month
Cost of plant sent to site (1.7.2011) 7,71,000
Salary to supervisor 9,000 per month
(3/4 time devoted to contract)
Administration & other expenses 4,60,600
prepaid administration expenses 10,000
Materials in hand at site as on 31.3.2012 75,800
CMA PRIYADHARSHINI Contact no: 9840876583
Plant used for the contract has an estimated life of 7 years with
residual value at the end of life ₹ 50,000. Some of the materials
costing ₹ 13,500 found unsuitable and sold out for ₹ 10,000.
Contract price was ₹ 45,00,000. On 31.3.2012 two third of the
contract was completed.
The architect issued certificate covering 50% of the contract price
and contractor has been paid ₹ 20,00,000 on account. Depreciation
on plant is charged on straight line basis. Prepare contract account.
4) Asita Ltd. undertook a contract for ₹ 2,50,000 on 1st July, 2009. On 30th
June, 2010 when the accounted were closed, the following details about
the contract were gathered:
₹
Materials purchased 50,000
Wages paid 22,500
General expenses 5,000
Plant purchased 25,000
Material in hand 30th June, 2010 12,500
Accrued wages 30th June, 2010 2,500
Work certified 1,00,000
Cash received 75,000
Work uncertified 7,500
Depreciation on Plant 2,500
case”.
It was found that since the date of signing the agreement, the prices
of materials and wages rates increased by 25%. The value of work
certified does not take into account the effect of the above clause.