Resource Sheet - Rev
Resource Sheet - Rev
ID B C D=B/C
D1.1.1.1 Excavation & Backfill $30,000 15 $2,000
D1.1.2.1 Strip Foundation $4,400 10 $440
D1.1.2.2 Individual Foundation $238 10 $24
D1.1.2.3 Wall foundation $884 8 $111
D1.1.2.4 Wall insulation $2,860 3 $953
D1.1.2.5 Concrete floor $10,925 5 $2,185
D1.1.2.6 Floor insulation $19,800 3 $6,600
D1.2.1.1.1 Framework $50,740 10 $5,074
D1.2.1.1.2 Sub-Floor $76,570 18 $4,254
D1.2.1.1.3 Roofing $65,416 10 $6,542
D1.2.1.2.1 Insulation $21,648 3 $7,216
D1.2.1.2.2 Waterproofing $1,617 3 $539
D1.2.1.3.1 Break Veneer $73,950 12 $6,163
D1.2.1.3.2 Drywall $35,424 10 $3,542
D1.2.1.3.3 Windows $10,360 3 $3,453
D1.2.1.3.4 Doors $2,500 3 $833
D1.2.1.3.5 Roofing Work $50,388 10 $5,039
D1.2.1.3.6 Paint $43,296 5 $8,659
D1.2.1.3.7 Flooring finish $96,193 5 $19,239
D1.3.4.4 Lighting $22,950 15 $1,530
D1.3.4.5 Power outlet $4,050 3 $1,350
D1.3.4.6 Fire Alarm $1,700 10 $170
D1.3.5.3 HVAC $47,000 15 $3,133
D1.3.5.4 Plumbing $11,000 15 $733
D1.4.1 Rain water Drainage $4,400 5 $880
D1.4.2 Parking Lot / Landscape $170,000 5 $34,000
D1.5.1 Construction Project Manager $82,880 148 $560
D1.5.2 Superintedant $59,200 148 $400
D1.5.3 Project Coordinator $71,040 148 $480
D1.5.4 Scheduler $41,440 148 $280
D1.5.5 Estimator $41,440 148 $280
D1.5.7 Project Engineer $47,360 148 $320
D1.5.8 Field Engineer $41,440 148 $280
SUM $1,243,109
Duration Completed PV=BCWS Budget Cost of Work Percentage completed EV BCWP AC Actual Cost of
at reported date Scheduled at reported date = at reported date : From BAC x Works Performed
Planned Daily cost x Duration
from the site completed at reported date site % % to be given
from the site
E F= D*E G H= B*G I
15 $30,000 100% $30,000 $31,500
10 $4,400 100% $4,400 $4,620
10 $238 100% $238 $250
8 $884 100% $884 $928
3 $2,860 100% $2,860 $3,003
5 $10,925 100% $10,925 $11,471
3 $19,800 100% $19,800 $20,790
19 $96,406 90% $45,666 $53,277
19 $80,824 90% $68,913 $80,399
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
0 $0 0% $0 $0
18 $27,540 90% $20,655 $24,098
0 $0 0% $0 $0
0 $0 0% $0 $0
5 $15,667 20% $9,400 $15,299
5 $3,667 20% $2,200 $3,581
0 $0 0% $0 $0
0 $0 0% $0 $0
77 $43,098 52% $43,098 $43,098
77 $30,784 52% $30,784 $30,784
77 $36,941 52% $36,941 $36,941
77 $21,549 52% $21,549 $21,549
77 $21,549 52% $21,549 $21,549
77 $24,627 52% $24,627 $24,627
77 $21,549 52% $21,549 $21,549
$493,306 $416,037 $449,310
SV CV SPI CPI EAC ETC VAC Variance at
EV-PV EV-AC EV/PV EV/AC Estimate at Estimate to Completion
Completion Complete VAC=BAC-EAC
( AC/EV)*BAC EAC - AC
C
C I
C
R I
R C
R C
A R I
A R
A R
A R C
R
A C R
A C R
I R I