PRODUCTION TEMPLATE Lanbin 16-2

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

DAY: 5 OF 213

LANBIN PRODUCTION MINUTE DATE: 2/16/2020


OF: MO192017

PROJECT: CONSTRUCTION OF 2 MOLTEN SALT TANKS


CLIENT: SHANGHAI ELECTRIC
PROJECT REPORT
PERSONNEL MACHINERY TIMING
POSITION UD HH EQUIPMENT UD H
CONSTRUCTION MANAGER 1 38.0 Crane 1 38.0
QAQC MANAGER 0.0 Crane 1 9.5
HSE MANAGER 1 38.0 Crane 0 0.0
QAQC EMYPRO SUPERVISOR 1 38.0 Manlift 0 0.0
QAQC ASSISTANT 0.0 Trailer 0 0.0
QAQC LANBIN MANAGER 0.0 Generator 1 38.0
QAQC LANBIN SUPERVISOR 1 38.0 Generator 1 38.0
HSE EMYPRO SUPERVISOR 1 38.0 Welding Machine 15 570.0
HSE LANBIN SUPERVISOR 1 38.0 Grinding Machines 12 456.0
CONSTRUCTION LEADER 1 38.0 Hydraulic Jacks 0 0.0
FITTERS 9 342.0 Quiver 8 304.0
WELDERS 10 380.0
MECHANIC 28.5
ELECTRICIAN 1 38.0
DRIVERS 1 38.0
HSE ASSISTANT 0.0
CRANE OPERATOR 2 19.0
0.0
0.0

TOTAL 30 1112 TOTAL 39 1454 TOTAL 0 0 TOTAL 0 0


WELDING PROCESS DAILY ACCUM GRAPHIC ERECTION PROCESS DAILY ACCUM GRAPHIC
nº WELDERS 10 nº FITTERS 9
WELDING PROGRESS ERECTION PROGRESS
THEORIC PROGRESS (kg) 94.9 474.3 THEORIC PROGRESS (kg) 5300.7 26503.5
474.3 350000.0
REAL PROGRES (kg) 0.0 0.0 500.0 REAL PROGRES (kg) 0.0 337140.6
450.0 300000.0
DEVIATION (kg) -94.9 -474.3 DEVIATION (kg) -5300.7 310637.2
400.0
250000.0
DEVIATION (%) -100% -100% 350.0 DEVIATION (%) -100% 1172%
300.0 200000.0
ACUM TOTAL ACUM TOTAL
250.0 150000.0
TOTAL WELDING (kg) - 17,265 TOTAL ERECTED (kg) 337,141 17,265
200.0
0.0% 150.0 20 100000.0
TOTAL WELDING (%) 94.9 TOTAL ERECTED(%)
100.0 50000.0
DAILY PROGRESS HOT TK - - DAILY PROGRESS HOT TK - 168,321
50.0 0.0 0.0
0.0
ACCUMALATED PROGRESS 0.0% 9,594.1 0.0 ACCUMALATED PROGRESS 0 1,129,048
THEORIC PROGRESS (kg) REAL PROGRES (kg)
THEORIC PROGRESS REAL PROGRES (kg)
DAILY PROGRESS COLD TK 0 0 (kg)
DAILY PROGRESS COLD TK - 168,820
DAILY ACCUM
ACCUMALATED PROGRESS 0.0% 7,671 DAILY ACCUM ACCUMALATED PROGRESS 0 1,028,147

TODAY ACTIVITY
Annular Ring 1 Root pass welding started at Cold tank.
Annular Ring 1 Fit up is ongoing at Hot Tank
Stiffner preparation is ongoing at Hot tank for the welding support for Annular ring 1

FOTOS

LOST TIME

Due to the Fog in the morning, work delayed little bit.


DAY: 5 OF 213
LANBIN PRODUCTION MINUTE DATE: 2/16/2020
OF: MO192017

COMMENTS AND REMARKS

Placed the Wedge support at the Annular Ring 1 joints during the welding, of root pass. Already convey the chance of joint distortion after the welding due to the wedge support.

ISSUES

ACTIVITY FOR THE NEXT DAY


DPT of Root pass on Annular Ring 1 joints of Cold Tanks.
Fit up activity of Annular ring 1 joints of Hot tank and Installation of Stiffner supports.

PREPARED BY: APROVED BY:

SIGNATURE SIGNATURE

NAME Mymoonson NAME ENRIQUE ROCA