Block Sim Features
Block Sim Features
https://www.weibull.com/hotwire/issue174/hottopics174.htm
Example-1: Maintenance-induced Failures during the Scheduled Maintenance of a Component
Using Reliability Block Diagrams (RBDs)
Scenario-1: When motor or pump return from workshop after servicing – it is noticed that either
bearing temp. Has increased or vibration is increased in either unit:
Either this is due to fitment error, poor part or poor workmanship.
We use the PM Timer block: to keep track of when the lift is down for scheduled maintenance.
We use the PM Failure block: to model the chance of a maintenance-induced failure during
scheduled maintenance of the lift.
Result:
1st Scenario 2nd Scenario
Availability .98 .98
Downtime 692.61 Hrs 776 Hrs
Crew Cost 20500 KWD 24000 KWD
Part Cost 20600 KWD 25000 KWD
Using BlockSim 6 for Planning Just-In-Time Ordering of Spare Parts (weibull.com)
Example-2: Planning Just-In-Time Ordering of Spare Parts
In order to evaluate an inventory strategy, we need to consider the costs of maintaining spare parts
in the inventory.
1st- Through BlockSim calculate the nos. of expected failure for each equipment, which give nos. of
required spares in general scenario.
Spares we have option of Limited & Unlimited spares: select limited to design spare policy
Inventory Strategy-1: Schedule restock – i.e. restock every 100 hrs
Inventory Strategy-2: Restock as needed – i.e. restock when stock drop down to zero
Inventory Strategy-3: Emergency spare provision – i.e. restock when equipment has failed.
Result: System
Strategy Inventory Carrying Cost System Availability
S-1 200 kwd 99.96
S-2 100 kwd 99.96
S-3 500 kwd 98.56
Like for Oil Well ESP pumps & its Generator system, we can fit above scenarios.
Result:
Total
Total Number of Total System
Total Number of Corrective /
Maintenance Total Parts Corrective Corrective
Preventive Preventive Total Cost
Failures Replacement Replacement
Strategy Replacements Replacement
Trips Downtime
Trips
Strategy 1 $13,009.33 48.28 338.54 62.33 hr 386.82 $198,900.66
Strategy 2 $10,012.47 71.72 41.67 61.70 hr 71.72 $69,546.75
Strategy 3 $9,645.53 87.63 31.53 63.12 hr 87.63 $76,255.71
Other methods:
1- Analysing Excess System Downtime through System Modelling:
We can calculate that what is the Probability that entire Crude Export Pump downtime will
exceed permissible threshold downtime i.e. beyond that point GC’s production will be
affected. (Says 4 Hrs).
Step-1: RBD for Export Pump, after simulation – in simulation result we have RELEVANT
SUMMARIES and in it we have SYSTEM FAILURE EVENT (time to failure & repair distribution)
Step-2: Copy paste data in Weibull folio – Calculate & in QCP select PROBABILITY OF FAILURE
with mission end time as threshold decided.
For component A, RS FCI = 75.03%. This implies that 75.03% of the times that the system
failed, a component A failure was responsible. Note that the combined RS FCI of A and I is
81.41%. In other words, A and I contributed to about 80% of the system's total downing
failures.
FRED Report
FRED stands for Failure Reporting, Evaluation and Display. This report provides a graphical
demonstration of the maintainability/availability characteristics of the
components/subsystems in a system and helps to identify areas for improvement (i.e.,
better reliability and/or better maintainability).
For the repairable system example, the FRED report is shown next.
The FRED report shows the average availability, the MTBF, the MTTR (mean time to repair) and the
RS FCI values for each component in the system.
https://www.weibull.com/hotwire/issue139/hottopics139.htm
4- Using Cost Optimization Reliability Allocation Analysis to Set Component Specifications
Can be done in Analytical RBD not in Simulation RBD.
Achieving equipment targeted reliability requirement, by improving/allocating the reliability
at component level.
https://www.reliasoft.com/products/blocksim-system-reliability-availability-maintainability-ram-
analysis-software/treating-common-cause-failures-in-fault-trees
5- Effect of Common cause failure on system reliability and treating same with fault tree
analysis
Consider the following example in which Event A could cause both an X Failure (if it happens
along with a B event) and a Y Failure (if it happens along with a C event).
The above example describes a simple common cause failure problem. In this example, the A
event is the common cause. A failure distribution needs to be specified for the A, B and C
events. The events' failure distributions are listed next.
You can use mirrored blocks to indicate that the two A events are actually the same
event and to specify that if event A occurs then Failures X and Y could occur.
The probability of a system level failure occurrence can be found using the Quick
Calculation Pad as follows.
If the two events A in this fault tree example were not mirrored, the results would have
differed, as the following figure shows.