Method Statement - Relocate Street Lighting

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 1 OF 6

Document description:
M&E Method Statement

Document title :
Relocate existing DB and lay new cable for water pump

PREPARED BY REVIEWED BY APPROVED BY

Signature : Signature : Signature :

Name : Name : Name :

Designation: : Designation: Designation:

Date: Date: Date:

STATUS APPROVAL
A B C
COMPANY

NAME

DESIGNATION

SIGNATURE
DATE

CONTENTS :

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval


lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 2 OF 6

1.0 PURPOSE

2.0 REFERENCES

3.0 SCOPE OF WORKS

4.0 TOOLS AND TESTING EQUIPMENTS

5.0 IMPLEMENTATION / METHODOLOGY PROCEDURES

5.1 Open Cut Premix Area

5.2 Installation 1 x2c 10mm2 pvc/swa/pvc cable

6.0 TESTING PROCEDURES

7.0 SAFETY FEATURES

1.0 PURPOSE

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval


lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 3 OF 6

This method statement provides information concerning the equipment, material and
method of construction to ensure compliance with contract requirements, drawings,
technical specification and quality control

2.0 REFERENCES

a. Site marked location.


b. Propose layout

3.0 SCOPE OF WORKS

The scope of these electrical services –lay new cable for street lighting

4.0 TOOLS & TESTING EQUIPMENTS

The tools and testing equipment in provision as required and if necessary:-

a. Transportation i.e. van, pickup truck, ladder, back hoe etc.


b. Extension rope etc.
c. Cable Rollers
d. Cable Jack
e. Sheath Cutter
f. Gas Burner
g. 500V and 1000V Megger Tester
h. Circuit Tester
i. Cable stocking / Pulling eye.
j. straight-through joints and accessories.
k. compactor machine
l. diamond cutter

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval


lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 4 OF 6

5.0 IMPLEMENTATION / METHODOLOGY PROCEDURES

5.1 Open Cut Premix Area

5.1.1 Outline of works

The work shall apply to the excavation the premix, common base rock excavation,
gravel and crushed limestone base using heavy equipment such as JCB excavator,
diamond cutter and basic hand tools and laying of cable.

a. Secure all necessary working drawing layout and establish the actual
location/position and route taking account of other services. Establish the
necessary line position for the excavation of ground trenches. In establishing the
lines and position, this area shall be installed using diamond cutter

b. The work shall apply to excavate crusher run (road base), then excavation the
sand area (sub base) and finally laying the cable based on cable depth
requirement

c. Laying the g.i pipe 50mm for road crossing

d. The finished surface shall be left for premix area using cold premix

e. The finish layer of the working area shall be making good to its original condition.

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval


lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 5 OF 6

5.2 1 x 2c 10mm sq pvc/swa/pvc cable

5.2.1 Outline of works

The work shall apply to install and laying of cable using manpower, cable rollers.

5.2.2 Commence relocation work methodology

a. Secure all necessary working drawing layout and establish the actual location/
position and route taking account of other services. In establishing the lines and
position, this area shall be installed using diamond cutter.

b. After establishing the necessary lines and position based on the working drawing
layout, proceed with mobilization of required work force, tools and equipments.

c. Transport the cable drums of by truck or lorry from the storage area to the
located site where the positioning point to commence cabling.

d. Lay the 1 x2c 10mm sq pvc/swa/pvc cable from the feeder pillar to street lighting
pole

6.0 TESTING PROCEDURES

a. The cable installation shall be tested according to certified condition which is


the tests on electric cables.

b. The continuity test and insulation test on the cable shall be carried out to
make sure that the cable are in good condition and no faulty or leakage
current along the line.

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval


lay new cable for street lighting

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C7 Rev. No: 01


Date Issued: 23 / 08 / 2013 Page 6 OF 6

7.0 SAFETY FEATURES

All operation during this work will be done in an efficient and safe manner and in
accordance to the Safety Procedures.

However there are issues concerning safety for this work that are to be observed
base on the results of the audit, relevant safety measures shall be proposed and
implemented as follows:-

a. Carry out a Hazard Identification Audit (HIA) before start of work each day
and before the start of a new task.

b. The material shall be in good condition, clean and free from defect and crack
during the installation.

c. All materials shall be transported by lorry to the site. Upon arrival, the
materials shall be unloaded at identified storage yard, either manually or by
machinery. All material shall be checked and inspected by the supervisor and
consultant. It must be stacked on timber and cover with non-staining plastic
sheet.

Sub. No. : DY/SP/ME/MS/EL/04 1st. Issue For Review & Approval

You might also like