Method Statement - Relocate Street Lighting
Method Statement - Relocate Street Lighting
Method Statement - Relocate Street Lighting
Document description:
M&E Method Statement
Document title :
Relocate existing DB and lay new cable for water pump
STATUS APPROVAL
A B C
COMPANY
NAME
DESIGNATION
SIGNATURE
DATE
CONTENTS :
1.0 PURPOSE
2.0 REFERENCES
1.0 PURPOSE
This method statement provides information concerning the equipment, material and
method of construction to ensure compliance with contract requirements, drawings,
technical specification and quality control
2.0 REFERENCES
The scope of these electrical services –lay new cable for street lighting
The work shall apply to the excavation the premix, common base rock excavation,
gravel and crushed limestone base using heavy equipment such as JCB excavator,
diamond cutter and basic hand tools and laying of cable.
a. Secure all necessary working drawing layout and establish the actual
location/position and route taking account of other services. Establish the
necessary line position for the excavation of ground trenches. In establishing the
lines and position, this area shall be installed using diamond cutter
b. The work shall apply to excavate crusher run (road base), then excavation the
sand area (sub base) and finally laying the cable based on cable depth
requirement
d. The finished surface shall be left for premix area using cold premix
e. The finish layer of the working area shall be making good to its original condition.
The work shall apply to install and laying of cable using manpower, cable rollers.
a. Secure all necessary working drawing layout and establish the actual location/
position and route taking account of other services. In establishing the lines and
position, this area shall be installed using diamond cutter.
b. After establishing the necessary lines and position based on the working drawing
layout, proceed with mobilization of required work force, tools and equipments.
c. Transport the cable drums of by truck or lorry from the storage area to the
located site where the positioning point to commence cabling.
d. Lay the 1 x2c 10mm sq pvc/swa/pvc cable from the feeder pillar to street lighting
pole
b. The continuity test and insulation test on the cable shall be carried out to
make sure that the cable are in good condition and no faulty or leakage
current along the line.
All operation during this work will be done in an efficient and safe manner and in
accordance to the Safety Procedures.
However there are issues concerning safety for this work that are to be observed
base on the results of the audit, relevant safety measures shall be proposed and
implemented as follows:-
a. Carry out a Hazard Identification Audit (HIA) before start of work each day
and before the start of a new task.
b. The material shall be in good condition, clean and free from defect and crack
during the installation.
c. All materials shall be transported by lorry to the site. Upon arrival, the
materials shall be unloaded at identified storage yard, either manually or by
machinery. All material shall be checked and inspected by the supervisor and
consultant. It must be stacked on timber and cover with non-staining plastic
sheet.