1 - Knowledge of hazardous - Before performing any work at the planning stage, it is necessary to walk around
factors of TCO production the workplace, determine potential hazards, isolation points, whether existing
depending on the facility and equipment affects other systems (coordinate with another service), determine the
possession of the necessary necessary tools and equipment, work should be divided into stages.
knowledge by the type of work When identifying hazards and identifying existing types of energy, you should use
performed (for example, the special tool "Energy Wheel"
installation of scaffolding, - Attraction, Movement, Mechanical energy, Electric current
electrical work, earthwork, hot - Pressure, Temperature, Chemical energy, Biological
work, gas hazardous work, etc.). -Radiation, Sound
- Demonstrates knowledge of one should ask the question: “what can go wrong and what types of energy can be
environmental protection released, and what are the associated hazards at each stage of work?”
requirements The WRP should be appointed from experienced and qualified specialists at the
level of a foreman or an employee holding a similar position, have a complete
understanding of the work ahead, know the equipment and qualifications of each
member of the team. Have with you and check with each member of the brigade
certificates and certificates
- As the work progresses, as well as at the end, clean the workplace. Waste should
be strictly separated by type of material and disposed of in appropriate containers
2 Knowledge of actions in case of Gas alarm -→ --→ --→
an emergency and the layout of Fire alarm ---- ----- ------
objects, collection points Local signaling ------------------------
You need to be able to distinguish by sound which alarm went off
The evacuation plan, a map of the location of collection points (you need to know
all the nearest collection points, eyewash stations, emergency exits), a memo on
the notification procedure in case of an emergency with the phone numbers of
responsible persons
1. Applied
2. Left
3. Called for help (Channel 2 or 147)
When an alarm is triggered, immediately stop work, notify colleagues, put on a
minifilter, move perpendicularly, then against the direction of the wind to the
nearest collection point. Upon arrival at the Collection Point, follow the
instructions of the Head of the Collection Point
3 Knowledge of the process of Signatures - PIC, WRP, Facility Owner, AC, and Facility Owner may vary in the
obtaining permits and the role of order in which signatures are collected. 7 days old PTW.
the PTW in it (work permit Signatures - New outfits - WRP, PIC, Allowing, Approving - 30 days. The
special permits) category is put by AC (Approver)
New outfit
- Form Outfit - Permits + hot work + work in a confined space + work at height +
lifting work + earthwork
- List of work performers and list of change of responsible persons
- Hazard analysis of work - is developed at the stage of work planning, describes
the entire work in stages and indicates the hazards and protective measures.
Risk Assessment Matrix - for old outfits
Evacuation plan, location of muster points
Checklists, reminders - 8 types of work - Electrical work with voltage relief,
electrical work without voltage relief, work at height, lifting and rigging work,
earthwork, work with an open source of fire, work in a confined space, isolation of
sources of hazardous energy, removal of isolation of dangerous energy sources
Inf. for rescue when working at height
Orders (ELEC-838), 388, 404
Single Line Diagram, Location (if required) JSA
It is forbidden to work in the absence of at least one signature
Special permits - electrical work, cold tapping, radiographic work, gas hazardous
work - separate form
Category 1 - complex work with a limited number of control measures.
Category 2 - work with a high probability of injury or accident. 1 and 2 categories
- signatures of responsible persons according to the order
Category 3 - work with a low probability of injury or incident, where the main
hazards are identified. It is allowed to combine the Approver and the Permit or the
Permit and the PIC - both lines are signed. Renewal of the PIC is optional
Category 4 - simple routine work.
4 Understanding the content and PPHA is developed at the stage of work planning, should include: a description of
approval process of a job hazard the scope of work, the order number, the date of completion, the duration of the
analysis (PPHA) work, the place of work and the equipment on which the work will be carried out.
PPE and protective measures, equipment and tools, safety instruction and
procedures, marks of permits and plans are indicated. The work is divided into
tasks at each stage of which hazards are indicated when performing a certain stage
and means of protection against it
5 Ability to conduct JSA before 1. Looking at employees to determine their external state to work.
the execution of the work task 2. Tell employees about actions in case of an emergency (Gas, Fire, Trauma, etc.)
with the participation of team 3. Divide the scope of work into task stages, identify hazards and control
members, while recognizing measures with employees.
hazards and developing effective 4. Remind workers of concurrent work.
remedies 5. Before starting work, check and complete all checklists.
6. At the end of the work, discuss with the employees the errors identified during
the work and their improvement. Thank the workers.
7. Clean up the work area
6 Ability to effectively conduct The same as in the previous paragraph.
daily briefings at the workplace Number of types of briefings -
to familiarize the work crew Introductory - Introductory briefing in the organization is carried out by the safety
with the scope of work, potential and labor protection service or by the person who is assigned these duties by order
hazards and control measures of the organization
Primary - Primary briefing at the workplace is carried out by the immediate
supervisor of work (foreman, shop manager) with each employee with a practical
demonstration of safe working methods.
Repeated - employees pass, regardless of qualifications, education, length of
service, nature of the work performed, at least once every six months.
This briefing is carried out by the immediate supervisor of the work individually
or with a group of workers serving the same type of equipment and within a
common workplace.
Unscheduled - carried out in the following cases:
introduction of new or revised standards, rules, instructions, on safety and labor
protection, as well as changes to them;
changes in the technological process, replacement or modernization of equipment,
fixtures and tools, raw materials, materials and other factors affecting labor safety;
violations by employees of labor safety requirements that can lead or have led to
injury, accident, explosion or fire, poisoning;
Target - instructions for the safe performance of specific work in an electrical
installation, covering the category of persons defined by an order or order, from
the person who issued the order, gave the order to a team member or performer
7 Ability to control the At the end of the work, it is necessary to discuss with the employees all aspects of
implementation of the final the work, which stages raised questions about safe performance, at which points it
stages of work (discussion of was possible that wrong decisions could be made, but by discussing the situation
lessons learned, closing work corrected. If any of the employees have doubts about the safety of the work, they
permits, etc.) need to be voiced and discussed. Before closing the work permit and removal
teams from the workplace, the workplace must be removed from debris, close
cabinets and distribution boxes, etc. If the work will be continued the next day, it
is necessary to inform the operator of the installation / on duty what equipment is
turned off / on, places of isolation, etc. The operator / duty officer must take the
workplace upon completion of work
8 Complete understanding of the Application of SWA in case of detection of unsafe actions or conditions. SWA can
SWA process and the ability to be applied by any employee of TCO and business partners. Card "Save life" - talk
recognize conditions that require about it.
the application of SWA
9 Demonstration of knowledge Interaction and execution of two or more operations simultaneously and in close
about the requirements of the proximity to each other.
process of simultaneously The radius of simultaneous work is 10 meters. It is necessary to constantly keep in
SIMOPS carried out works and touch with the WRP of another service, to inform people. Consider alternative
the actions of the WRP during work methods
the pilot work
10 Ability to identify SSEs within SSEs needs to undergo primary briefing at the workplace
the team, as well as Carry TCO's SSEs approval form with you.
demonstrating knowledge of the Crew: 1 person – 0 people SSEs; 2-4 people – 1 SSEs; > 5 people – no more than
requirements of the SSE process 20% SSEs
Visual distinction of the SSEs from the rest of the personnel (green helmet or
green stickers).
The mentor should always be at the facility near the SSEs.
Independent admission of the SSEs to the performance of work is NOT allowed.
11 Understanding the WRP of what A qualified and experienced specialist at the level of foreman with experience in
is expected of him/her as a HSE people management should be appointed as the WRP. The WRP must maintain a
leader and demonstrating a high culture of safe behaviour.
culture of safe behavior in Be able to consider the scope of the planned work and determine the most
carrying out duties related to appropriate and safe way to carry it out.
responsibility for the safe
performance of work and the
work team
Basic principles
1 Do the job safely or don't do it at all
2 There is always time to get the job done right
Commandments of production
Always:
1 Operate equipment within design and environmental limits
2 Work in a safe and controlled environment
3 Make sure security equipment is in place and working
4 Use safe practices and instructions for safe work
5 Meet or exceed customer requirements
6 Maintain the integrity of specialized systems
7 Operate in accordance with all applicable rules and regulations
8 Eliminate abnormal conditions
9 Follow written instructions for high-risk work and unusual situations
10 Involve knowledgeable people when making decisions that affect instructions and equipment
Mechanical rotating equipment, compressed springs, drive belts, conveyors and motors
Electrical power lines, transformers, static charges, lightning, live equipment, wiring and
batteries
Pressure pressure pipelines, compressed gas cylinders, instrumentation lines, vessels,
tanks, hoses, pneumatic and hydraulic equipment
Temperature open flame; ignition sources; hot or cold surfaces, liquids or gases; steam;
friction, as well as general weather and climate conditions
Chemical combustible vapors; hazardous chemical reactions; carcinogens or other toxic
substances; corrosive, pyrophoric and combustible substances; oxygen
deficient atmosphere, welding fumes and dust
Biological animals, bacteria, viruses, insects, blood pathogens, spoiled food and
contaminated water
Radiation lighting problems, welding arc, sunlight, microwaves, lasers, x-rays and
NORM scale
Sound equipment noise, impact noise, high pressure release and the impact of noise
on communication
Attraction falling objects, collapsing roof, stumbling or falling body, falling
Movement movement of vehicles, vessels or equipment; flowing water; wind; body
position: lifting weights or bending