0% found this document useful (0 votes)
34 views1 page

Ass3-Network Diagram and Critical Path

The document provides a project schedule with activities and their durations listed along with any predecessor activities; the critical path and duration of the project in days must be determined by drawing the network diagram.

Uploaded by

gabboudeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views1 page

Ass3-Network Diagram and Critical Path

The document provides a project schedule with activities and their durations listed along with any predecessor activities; the critical path and duration of the project in days must be determined by drawing the network diagram.

Uploaded by

gabboudeh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Network Diagram and Critical path

Draw the Network Diagram and determine the Critical Path and duration of the project
(in days).

Activity Duration (days) Predecessor(s)


A 2 -
B 3 -
C 4 A,B
D 5 C
E 2 D
F 3 D
G 4 E
H 2 F
I 2 G,H