Rate-Analysis Hume-Pipes - NP2 & NP3 (200mm To 500mm) - 30.01.2024

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 10

Rate Analysis for Hume Pipes

Sl. No. Item Unit Rate


1 Providing & laying NP2 Class 200mm Hume
pipes ( 2 M length Type ).
2 a) Cost of Pipe Rmt 600.00
3 c) Sand filling around pipes Rmt 200.00
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
5 e) Labour charges for sand filling Rmt 133.33
6 Sub Total 1030.83
7 Cost of Socket Joining by Hemp & cemnent mortar) 200.00
8 Sub Total 1230.83
9 i) Add 15% for Overheads & Profit 184.62
Grand Total Says for 1 Meter Rs. 1415.46
Rate Analysis for Hume Pipes
Sl. No. Item Unit Rate
1 Providing & laying NP2 Class 250mm Hume
pipes ( 2 M length Type ).
2 a) Cost of Pipe Rmt 700.00
3 c) Sand filling around pipes Rmt 200.00
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
5 e) Labour charges for sand filling Rmt 133.33
6 Sub Total 1130.83
7 Cost of Socket Joining by Hemp & cemnent mortar. 250.00
8 Sub Total 1380.83
9 i) Add 15% for Overheads & Profit 207.12
Grand Total Says for 1 Meter Rs. 1587.96
Rate Analysis for Hume Pipes
Sl. No. Item Unit Rate
1 Providing & laying NP2 Class 300mm Hume
pipes ( 2.5 M length Type ).
2 a) Cost of Pipe Rmt 1150.00
3 c) Sand filling around pipes Rmt 200.00
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
5 e) Labour charges for sand filling Rmt 133.33
6 Sub Total 1580.83
7 Cost of Socket Joining by Hemp & cemnent mortar. 300.00
8 Sub Total 1880.83
9 i) Add 15% for Overheads & Profit 282.13
Grand Total Says for 1 Meter Rs. 2162.96
Rate Analysis for Hume Pipes
Sl. No. Item Unit
1 Providing & laying NP3 Class 350mm Hume
pipes ( 2.5 M length Type ).
2 a) Cost of Pipe Rmt
3 c) Sand filling around pipes Rmt
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt
5 e) Labour charges for sand filling Rmt
6 Sub Total
7 Cost of Socket Joining by Hemp & cemnent mortar.
8 Sub Total
9 i) Add 15% for Overheads & Profit
Grand Total Says for 1 Meter Rs.
es
Rate

2050.00
200.00

97.50
133.33
2480.83
350.00
2830.83
424.63
3255.46
Rate Analysis for Hume Pipes
Sl. No. Item Unit Rate
1 Providing & laying NP3 Class 400mm Hume
pipes ( 2.5 M length Type ).
2 a) Cost of Pipe Rmt 2100.00
3 c) Sand filling around pipes Rmt 200.00
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt 97.50
5 e) Labour charges for sand filling Rmt 133.33
6 Sub Total 2530.83
7 Cost of Socket Joining by Hemp & cemnent mortar. 350.00
8 Sub Total 2880.83
9 i) Add 15% for Overheads & Profit 432.13
Grand Total Says for 1 Meter Rs. 3312.96
Rate Analysis for Hume Pipes
Sl. No. Item Unit
1 Providing & laying NP3 Class 450mm Hume
pipes ( 2.5 M length Type ).
2 a) Cost of Pipe Rmt
3 c) Sand filling around pipes Rmt
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt
5 e) Labour charges for sand filling Rmt
6 Sub Total
7 Cost of Socket Joining by Hemp & cemnent mortar.
8 Sub Total
9 i) Add 15% for Overheads & Profit
Grand Total Says for 1 Meter Rs.
es
Rate

2200.00
200.00

97.50
133.33
2630.83
400.00
3030.83
454.63
3485.46
Rate Analysis for Hume Pipes
Sl. No. Item Unit
1 Providing & laying NP3 Class 500mm Hume
pipes ( 2.5 M length Type ).
2 a) Cost of Pipe Rmt
3 c) Sand filling around pipes Rmt
4 d) Labour charges for laying & jointing pipes
including cost of jointing material. Rmt
5 e) Labour charges for sand filling Rmt
6 Sub Total
7 Cost of Socket Joining by Hemp & cemnent mortar.
8 Sub Total
9 i) Add 15% for Overheads & Profit
Grand Total Says for 1 Meter Rs.
es
Rate

2500.00
200.00

97.50
133.33
2930.83
450.00
3380.83
507.13
3887.96