BOQ - External Development Works
BOQ - External Development Works
BOQ - External Development Works
Preamble
The rates quoted shall include:
Surface cleaning & grubbing of the ground including removing vegetation grass, brush wood,
trees and saplings of girth not exceeding 100 cm deep and disposal of rubbish within site
premises.
Pumping out surface runoff water collected from any source for keeping the surface dry as per
the requirement of site. Contractor should dispose water accumulated at excavated pit due to
rain.
The contractor shall take all precautions and measures to ensure safety of works and workman
during the execution of works.
Working Area shall be securely barricaded and provided with proper caution signs,
conspicuously displayed during the day and properly illuminated with red lights and/or written
using fluorescent reflective paint as directed by Project Manager during the day/ night to avoid
accident.
Adequate protective measures shall be taken by the Contractor to see that the excavation
operations do not damage the adjoining structures or dislocate the services, so that the
services remain functional. However, if any service is damaged during excavation shall be
restored in reasonable time.
Any damages done by the contractor to any existing work or third party properties shall be
made good by him at his own cost & nothing shall be paid extra.
Carrying out excavation in all types of soil is required profile and depth, including dressing of
sides, ramming of bottom, using mechanical excavator or manually wherever required. and
carting away and disposing the same within the site. Contour level to be taken jointly with the
Project Manager and prior written approval be taken before starting any excavation/ filling at
every grids for arriving at the actual quantity.
Nothing Extra will be paid for planking, strutting & timbering if required for excavation/back
filling done by Contractor.
Scope also includes carting away and disposing the same at dumping ground after obtaining
approval from the regulatory authorities. Obtaining royalty permission and maintaining all the
related records, covering the vehicle with plastic / tarpoline so as to prevent fall of any
excavated material on road, cleaning vehicle tyres before moving out of site, carting &
disposing of soil to approved destination, liaising etc. complete.
Contractor Must obtain approvals for all the materials intended to be used for the project
works. Inspections and Testing plan of materials shall be submitted in compliance with relevant
IS Codes.
Note:- Quantities mentioned in this subhead may vary to any extent. Rate shall hold good
irrespective of variation in quantities to any extent.
Supplying of good earth free from vegetation and unuseful material and filling with
mechanical/manual the same at site or within 3 Kms of site in road area , mounds , trenches,
plinth, sides of foundations, general area filling for landscape, or for maintain levels, spreading
the remaining soil for other locations as directed by Engineer-in-Charge, filling earth in layers
not exceeding 300mm in depth including breaking clods, watering, ramming, compacting,
consolidating in deposited layer to achieve 95% proctor density & rolling each layer with roller
2 and rolling every 3rd and top most layer with power roller of 8 tons-10 tons including re- Cum R/O
excavation, loading, unloading, transportation of soil, all labour, materials, machinery, tools &
tackles etc. for all depth, levels, lead & lift complete in all respect as per drawing, specifications
and as per the instruction/satisfaction of Project-in-Charge. Filling levels to be cross checked
with the Drawings.
Note : Cost of the field density test for every layer at 100 sqm shall be included in the rates.
Item same as above item no 2, but Earth shall be supplied by owner free of cost, however
2.1 dressing, compaction all complete shall be in Contractor scope. Cum 12168 240 2,920,320.00
SUB GRADE
Preparation and Consolidation of subgrade with power road roller of 8 to 12 tonne capacity
3 including after excavation/backfilling earth to an average of 22.5 cm depth, dressing to camber Sqm 6252 30 187,560.00
and consolidating with road roller including making good the undulations etc. and rerolling the
sub grade and disposal of surplus earth lead up to 50 m.
Precast Pavers :
Providing and fixing minimum 60mm thick of approved (colour/shade/type) precast cement
concrete pavers of M-35 grade of required size as per design & patterns laid over 50mm
thickness of sand bed. After laying pavers, sand shall be spread over the surface and joints shall
6 be filled with sand. paver at edges to be fixed with 20mm thick cement mortar (of ratio 1 Sqm 732 925 677,100.00
cement :5 coarse sand) bed, all complete as per the direction of Project Manager. The rate
includes cost of sand, all lead, shifting and handling to work as per engineer in charge etc.
Base rate of Paver- 55/per Sqft.
SAUCER DRAIN
Providing and laying precast concrete saucer drain of size 300L X 300 wide X 75 mm thick or as
approved of M-35 grade including preparation of subgrade by cutting and filling of earth
8 wherever required and consolidation of earth by earth rammer, including Providing & Laying Rmt 600 465 279,000.00
50mm thick PCC of 1 : 3 : 6 mix over prepared subgrade and fixing of saucer drain over PCC and
joints with cement mortar 1:3, all in proper line and level as per instruction of project manager.
Base rate- 220/- per Rmt.
Providing and applying two or more coat of synthetic enamel paint (Black & yellow
combination) on kerb stone including surface preparation, cleaning for all lead, shifting ,
9 handling and lift etc, cost of labour and material complete to the satisfaction of the Project Rmt 2400 25 60,000.00
Manager.
Providing necessary arrangements for packing of existing 600mm dia road Crossing's opening
with the seal pack arrangements by using plaster finish (15mm thick), 460mm thick Brickwork
11 all around with the usage cement mortar of 1:6, Work is including the cost of all providing base Nos. 2 - as per drawing
100mm thick PCC and their side shuttering etc.
EARTH WORKS
Preamble
The rates quoted shall include:
Surface dressing of the ground including removing vegetation grass, brush wood, trees and
saplings of girth not exceeding 100 cm deep and disposal of rubbish within site premises.
Pumping out surface runoff water collected from any source for keeping the surface dry as per
the requirement of site. Contractor should dispose water accumulated at excavated pit due to
rain.
The contractor shall take all precautions and measures to ensure safety of works and workman
during the execution of works.
Site shall be securely barricaded and provided with proper caution signs, conspicuously
displayed during the day and properly illuminated with red lights and/or written using
fluorescent reflective paint as directed by Project Manager during the day/ night to avoid
accident.
Adequate protective measures shall be taken by the Contractor to see that the excavation
operations do not damage the adjoining structures or dislocate the services, so that the
services remain functional. However, if any service is damaged during excavation shall be
restored in reasonable time.
Any damages done by the contractor to any existing work or third party properties shall be
made good by him at his own cost & nothing shall be paid extra.
Carrying out excavation in all types of soil is required profile and depth, including dressing of
sides, ramming of bottom, using mechanical excavator or manually wherever required. and
carting away and disposing the same within the site. Contour level to be taken jointly with the
Project Manager and prior written approval be taken before starting any excavation/ filling at
every grids for arriving at the actual quantity.
Nothing Extra will be paid for planking, strutting & timbering if required for excavation done by
Contractor.
S.No. ITEMS DESCRIPTION UNIT QUANTITY RATE AMOUNT REMARKS
Scope also includes carting away and disposing the same at dumping ground after obtaining
approval from the regulatory authorities. Obtaining royalty permission and maintaining all the
related records, covering the vehicle with plastic / tarpoline so as to prevent fall of any
excavated material on road, cleaning vehicle tyres before moving out of site, carting &
disposing of soil to approved destination, liaising etc. complete.
Contractor Must obtain approvals for all the materials intended to be used for the project
works. Inspections and Testing plan of materials shall be submitted in compliance with relevant
IS Codes.
Note:- Quantities mentioned in this subhead may vary to any extent. Rate shall hold good
irrespective of variation in quantities to any extent.
12 EXCAVATION
Earthwork in excavation by mechanical or manual as required over areas in all kind of soils for
all leads & lift including dense soil etc. in raft, footing, pedestal, foundation pits, trenches,
drains, lift pit, sumps etc. including all lead, lift, providing shoring, strutting, to the sides if
required, trimming and dressing the sides of the pits including carting away the excavated earth
within site or within 3 kms of site at Owner's designated place. Excavation shall be payable only
12.1 for vertical cut up to the outer edge of foundation lean concrete as indicated in Drawings for all
depths. Cost for extra excavation required for working space, supporting side shuttering of
foundations, retaining walls and that required for making slopes for stability of excavation shall
be deemed to be included in the rate quoted. The line & levels in drawings shall be strictly
followed and over excavation if any shall be made good by Principal contractor free of cost as
per drawing, specifications and as per the satisfaction of Engineer-in-Charge.
a Stacking the excavated materials within the Site area. Cum 134 120 16,080.00
EARTH FILLING
Filling with selected suitable excavated earth already available at site or within 3 Kms of site in
foundation, trenches, plinth, sides of foundations, behind retaining wall, general area filling for
landscape, or for maintain levels, spreading the remaining soil for other locations as directed by
Engineer-in-Charge, filling earth in layers not exceeding 300mm in depth including breaking
clods, watering, ramming, compacting, consolidating in deposited layer to achieve 95% proctor
13 density & rolling each layer with roller and rolling every 3rd and top most layer with power
roller of 8 tons including re-excavation, loading, unloading, transportation of soil, all labour,
materials, machinery, tools & tackles etc. for all depth, levels, lead & lift complete in all respect
as per drawing, specifications and as per the satisfaction of Project-in-Charge. Filling levels to
be cross checked with the architectural Drawings.
Note : Cost of the field density test for every layer at 100 sqm shall be included in the rates.
same as above item but with excavated stacked earth available within the site or within 3 kms
a from the site as per the direction of Engineer-in-Charge. Cum 85 240 20,400.00
iv) Working up or hacking of concrete surface & cleaning the surface from loose dust & dirt for
providing keys for further concrete work including applying thick cement slurry or mortar as
directed.
v) Use of cement slurry over shuttering before commencing concreting if required.
vi) Work in narrow widths, small quantities and curved alignment.
vii)Cleaning of slush, mud & debris etc. if any from laid reinforcement of sub structure work
before laying of concrete.
viii)Testing of overhead / underground water tanks, roof slabs, sunken slabs etc. by filling the
water to full depth keeping the same for a minimum period of 4 days. Contractor shall ensure
that the bottom & all sides are dry and their should not be any leakages.
ix)Work either straight or curved, plain or circular or any shape, work in inclined or sloping
surfaces.
x) Shuttering shall be placed adequately to receive the discharge from Pump concrete for ready
mix concrete use.
xi) Nothing extra shall be paid for working space required for supporting the shuttering in
foundations.
xii) Necessary curing & Protection, cost also includes the Curing Compound with prior approval
by Client's QC/Technical Head.
xiii) All the Sample collection, laboratory and testing cost shall be included.
xiv) All lead lift, loading, unloading, cartage, handling and storage.
xv) Cement & Reinforcement steel shall be supplied by Owner free of cost at one point within
the site. However, contractor shall coordinate with supplier by giving prior notice and shall
make necessary arrangement and to unload the material at the decided location.
xvi) Contractor to provide dowels as per drawings for all structural elements, if Contractor fails
to do so, the cost of rebaring shall be borne by the Contractor.
xvii) if contractor missed out to provide the dowels at location which is required on any
structural member, then the Contractor to do the rebaring at its own cost.
xvii) if contractor missed out to provide the dowels at location which is required on any
structural member, then the Contractor to do the Chemical rebaring at its own cost.
xix) RCC for drop panel & column flare shall be measured in slab at the respective level. All
measurement shall be done as per SP27 but the grade of concrete shall also confirm to the
respective structural member, which shall deem to be measured under same category as per IS
code. Else, the same shall be paid under the respective item, which shall confirm to the grade
of concrete.
S.No. ITEMS DESCRIPTION UNIT QUANTITY RATE AMOUNT REMARKS
xx) Cleaning of debris, removing of loose concrete from existing structure, removing broken
plywood/shuttering, RCC chipping, straitening of bars, cleaning joints, removing all inserted
unserviceable materials from existing structure, co-ordination for activities, including stacking &
disposal of debris at the required location as per complete instruction of Project Manager in all
respect.
Ready Mix Concrete(Produce at site batching plant or source from outside)
xxi) The Contractor shall use curing compound on all vertical surfaces of concrete, cost of
approved Curing compound shall include in quoted rates.
xxii) Hacking the exposed concrete to receive plaster and forming all necessary construction
joints, expansion joints, dummy joints etc. wherever directed and as per IS Codes.
xxiii) Trial Mix of Concrete and preparation of Design Mix report with all calculations will be in
contractor scope. The Concrete used for cube casting shall not be considered for payment.
Design mix shall be approved 15 days in advance prior to anticipated date of execution.
xxiv) The uneven concrete surfaces to be made even and smooth by chiselling and rendering
the concrete surfaces with non shrinkable material where ever applicable. Rendering and
chiselling shall not be paid extra.
xxv) In case of break down of batching plant Contractor is required to procure RMC from any
approved vendors at it's own cost. (Cement shall be supplied by the Owner)
Providing and laying batching plant machine mixed/ RMC Plain Cement Concrete (PCC) of
specific grade as bed concrete under foundation, bases of rafts underground water tank,
building machine equipment's, column footing, under floor landings, below road and pathways,
sill, coping, screeding at roof to required slope, in protection screed and other locations as
14.1 called for laid, consolidated and cured etc. all complete including finishing the top surface to
receive the next course / layer, cantering, shuttering/supports, curing, ramming, consolidating,
levelling and curing etc. as per technical specifications, drawing and as per satisfaction of
Engineer-in-Charge. (Cement shall be supplied by Owner free of cost at point within the site)
a 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm and down gauge) Cum 8 4200 33,600.00
b 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 20 mm and down gauge) Cum 10 4320 43,200.00
Providing and laying cast-in-place batching plant machine mixed & machine vibrated, design
mix reinforced cement concrete of specified grade using concrete pump with 20mm down
gauge coarse aggregate excluding cost of cantering, shuttering and steel reinforcement but
including cost of making shear keys, shrinkage strips, expansion joints and provision of
construction / control joints in various locations, laid, consolidated of any shape and size etc.
with specified compressive strength of 28 days at all depths, lead, levels, floors and lifts as
mentioned including curing, etc all complete in structural elements as per detail, drawings,
specifications and as directed by Engineer-in-Charge. The rates of RCC to include the cost of
admixtures/plasticizers/superplasticiser/ bonding agent to achieve specified requirements and
to facilitate pumpable concrete etc complete. Grade of concrete shall be as per approved
structural drawings.
(Note :- Max. Permissible Limit of Fly Ash is 25% of Cementitious Content) Fly ash conforming
to grade I of IS 3812 (Part-1) only be used as part replacement of OPC as per IS 456. Uniform
blending with cement to be ensured in accordance with clauses 5.2 and 5.2.1 of IS:456 -2000.
Principal Contractor shall take utmost care for water curing of RCC elements and in the absence
of proper curing, Engineer-in-Charge may direct Principal Contractor to provide & apply water
based/polymer based (as directed by Engineer in Charge) film forming curing compound at no
additional cost to the Owner.
15 FORM WORKS
Ply Board Shuttering
All Cost for Providing, cutting, bending, laying, fixing in position steel reinforcement ( TMT as
per IS 1786 ) for RCC works including straightening transporting, removal of loose rust by wire
brush, coating with cement slurry, protection and placing for all profile and for all lead and
specified levels and binding with 18 gauge GI annealed wire to the entire satisfaction of Project
manager . Payment of steel shall be made as per drawing and approved bar bending schedule
with permissible laps and paid on the basis of the sectional weights of bar as per relevant I.S.
Code. The rate shall include cost of binding wire, PVC cover blocks, which will not be measured
separately for payment. Approved chairs, spacers, pins shall be measured for reconciliation as
well as for payment. The quoted rate shall include sampling of materials. (TMT / High Yield
Strength deformed bars as specified)
Tenderers to quote the prices inclusive of materials, manpower, spares, consumables, tools, tackles, safety appliances, equipments, overhead, profits, cesses,
NOTE mobilization, de-mobilization, freight, transportation, loading & unloading, storing, handling, packaging, insaurances, scaffolding, safety arrangements, barricading etc.. all
complete; as applicable.GST shall be paid extra, as applicable.