Day 44 Time & Work
Day 44 Time & Work
QUANTITATIVE
APTITUDE
BASIC CIRCLE
DAY - 43
www.verandarace.com www.bankersdaily.in
BASIC CIRCLE BANKING
1) Aravindh and Biju can complete a work 4) A, B and C can complete a work in 10
and Biju started the work together. After 2 started the work. B joined after two days
days, Biju left, and the remaining work was and C joins them on every third day. In how
done by Aravindh. In how many days the many days the work will be completed?
4 1
remaining work gets completed? a) 6 days b) 8 days
5 5
days, 24 days and 60 days respectively. P and 40 days respectively. Vishnu and
started the work. Q and R joined after two Kishore started the work together.
days and four days respectively. After After 2 days Arjun joined them.
another two days P left. In how many days Kishore and Arjun left four days and
1
c) 9 days
6
d) 14 days the work is completed?
7 7
1 a) 8 days b) 12 days
e) 11 days
7
c) 9(1/13) days d) 7 days
7) A, B and C can complete a work in 20 and C will complete the entire work?
entire work is completed in 10 days, then 11) A is 33.33 % more efficient than B.
after how many days B joined? Together they can complete a work in 30
a) 7/3 days b) 5/3 days days. Then B alone will complete in how
e) 5/4 days a) 70 b) 40
started the work and A worked for last 5 12) B is 20% more efficient than C. A takes
days. After some days, B joined him. If the 25% less time than C. If A alone can
entire work is completed in 10 days, then complete the work in 20 days, then in how
after how many days B joined? many days A, B and C can complete it?
the time of C. If B alone takes 30 days to takes one fourth the time of A. If A and C
complete the work, in how many days C will work together they will complete the work
complete the entire work? in 22 days. In how many days B alone will
the time of C. If B alone takes 20 days to 14) A and B can complete a work in 12 days
B left, and the remaining work was 42 men and 72 women can complete the
15) A and B can complete a work in 35 complete a project work in 20 days working
days they started to work together. 4 hours per day. In how many days
After 14 days B left, and the remaining (approximately) 19 women and 21 children
work was completed in 24 days. In can complete the same project working 13
how many days B alone will complete hours per day if the efficiency of a women
e) 48 days e) 10 days
16) 20 men can complete a piece of work 20) X number of persons working 12 hours
in 15 days. In how many days can 40 men per day can build a 600 m wall in 16 days.
can complete the same piece of work? If 6 more persons join them by working 12
a) 15 days b) 20 days hours per day, they can build a 900 m wall
a) 2.33 days b) 10(5/39) days 21) There is enough food for 150 soldiers
c) 2.5 days d) 2(22/39) days for 20 days. After 10 days 90 soldiers left
e) 10/3 days the camp. For how many days will the rest
18) 7 men and 12 women can complete a of the food lasts for rest of the soldiers?
for 40 days and each person eats 900 gms 25) A contractor undertakes to build a
food every day. After 20 days 80 soldiers water tank in 30 days. So, he employs 120
left the camp. Now for how many days will men for this purpose, and they work for 6
the rest of the food lasts for the rest of the hours per day. After 15 days he finds that
soldiers if each soldier eats 700 gms food only 2/5th of the work is completed. Then
e) 20 days a) 35 b) 60
boys were employed for the work, due to 26) A can complete a work in 25 days. B
which the work is completed five day can complete 40% of the work in 16 days
earlier. How many days would it have been and C can complete of work in 30 days.
delayed if 20 more boys were not Then all the three can complete the work in
e) 60 days e) 7(10/59)
24) 39 men can complete a piece of work 27) A can complete a work in 10 days. B
in 28 days while 42 women can complete can complete of the work in 18 days and C
the same work in 26 days. 24 men started can do 11.11 % of the work in 4 days. If A
working and after working for 16 days all of starts working and he was assisted by B
them left. How many women should be put and C on every third day. In how days the
e) 7(1/33)) e) 7(5/7)
28) A and B can do a work in 20 days while 31) A and B can complete a work in 9 days.
B and C in 33
1
days and the work is A alone works for 6 days and B completes
3
completed by A, B, C by working for 10, 12, the remaining work in 13 days by doing
24 days. In how many days A alone would alone. In how many days B alone does the
e) 20 days e) 20 days
29) A and B, B and C do a work in 10 days 32) P and R complete a work in 24 days
and 15 days. If A works for 5 days and B doing together. If P works for 6.4 days and
works for 10 days and C completes the R for 20.4 days, they finish half work. In
remaining work in 10 days, then A and C how much time P alone can complete the
30) A can complete a work in 20 days. B complete a work than A and B working
can complete 20% of the work in 10 days together. B takes 4 hrs more to complete a
and C can complete it in 30 days. A and C work alone than A and B working together.
decided to work on alternate days In how many days A alone can do it.
joins them. In how many days the work will c) 25 days d) 24 days
efficiency and A left 4 days before the 34) A alone can do a piece of work in 25
They work together to get a total wage of and worked together for 4 days, and the
a) Rs. 2500 b) Rs. 1000 days. If the total wage is Rs. 6300, what is
Directions:(36-40):
Situation 2
Project Situation 1
40
1 S 60 S+9
3 𝑽𝟐 196 𝑻𝟐 324
Q.36) If 180 people were working for Q.38) If 0.5R people work on project 2 for
Project 1, how many days did it take to 80 days and then 0.5R people join the
complete the work? project after 80 days, how many days will
0.5V × 2T, then what is the number of days Q.39) If 270 people were working for
required by team M to complete Project V? Project 1, how many days did it take to
e) 8 days
Project 3?
e) 368 days
Answer key:
8. (d) 9. (c) 10. (a) 11. (a) 12. (c) 13. (b)
14. (c) 15. (d) 16. (c) 17. (d) 18. (a) 19.
(d) 20. (b) 21. (b) 22. (b) 23. (d) 24. (b)
25. (b) 26. (c) 27. (b) 28. (b) 29. (d) 30.
(c) 31. (d) 32. (a) 33. (d) 34. (c) 35. (c)
36. (d) 37. (c) 38. (b) 39. (c) 40. (b)