Pending Works by Contractor

The document contains a table with 4 rows listing different types of construction works including steel roof work, masonry works, masonry works, and defects rectification works. Each row includes details about the engineering submission status, any required site obstruction works, and remarks on the approval status and needed actions. The approval status includes works that are not yet resubmitted, ongoing, rejected, or completed. The remarks note issues like delayed submissions, unfinished formwork, and needed material testing. Required actions include submitting additional plans and addressing open non-conformance reports.

Uploaded by

36. Tengkea Ou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
213 views4 pages

Pending Works by Contractor

The document contains a table with 4 rows listing different types of construction works including steel roof work, masonry works, masonry works, and defects rectification works. Each row includes details about the engineering submission status, any required site obstruction works, and remarks on the approval status and needed actions. The approval status includes works that are not yet resubmitted, ongoing, rejected, or completed. The remarks note issues like delayed submissions, unfinished formwork, and needed material testing. Required actions include submitting additional plans and addressing open non-conformance reports.

Uploaded by

36. Tengkea Ou
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Works can be start by contractor

No Bldg Type of work Engineering submission


MOS
SHD
MAR

1 Steel roof work


MIR

Site obsturction
MOS

SHD

MAR
MIR
2 Masonry works

Site obsturction

MOS
A

SHD

3 Masonry works MAR


MIR

Site obsturction

MOS
SHD
MAR
MIR
Defects rectification
4
works

Site obsturction
Works can be start by contractor

Status of approval Remark Action


RR - Not yet resubmit
Done
Will be have more request as
On-going
new material arrived

1. PVR to submit MAR for


1. Some of steel material PVR
the material that not the
delivered not the same brand as
same brand - Testing for
Rejected requested.
each brand is required
2. Not yet deliverd for bolt
2. No information about the
materials
bolt by PVR

1. A wait of roof beam and slab to


finish concrete structure
Done
1. PVR to submit remaining
1. Basement floor - Approved
floor especially 1st floor to
On going with comments
prevent the delay after
2. Remaining floor - On going
formwork removal
Done
On going

1. Delay of SHD submission will


cause impact to the works on site
2. Defects work of slab L2 not yet
start
3. Formwork and props support
of slab L2 not yet finish - Expect
to finish by 31-Jan
4. Shortage of manpower on site

Done
1. PVR to submit remaining
1. Basement floor - Approved
floor especially 1st floor to
On going with comments
prevent the delay after
2. Remaining floor - On going
formwork removal
Done
On going
1. Not yet start mock-up partition
wall
2. Not yet finish basement block-
wall installation
Done
- - -
Done
On going
Contractor to finish NCR closure
of:
1. NCR40
2. NCR43
3. NCR44
4. NCR45
5. NCR48
Not yet start
6. NCR51
7. NCR52
8. NCR54
9. NCR55
10.NCR56
11.NCR57
12.NCR61