Activity Hazards Control Measures Remarks
No.
1. Delivery, storage Paint Cans & Thinners to be stored in steel Site Engineer/
and Handling of containers. Foreman
Paint spillage due to
Paint and Containers will be positioned away from any
accidental leakage,
Thinner. vehicle traffic to avoid damage from
storing damaged
collision.
container, wrong
Hand gloves shall be worn when handling
handling of material
paint cans to avoid cuts to the hands.
Task to be carried out with proper
supervision.
2. Paint Application No Hot work shall be permitted in the vicinity Site Engineer/
of paint or thinner storage areas. Foreman
All Combustible/flammable materials should be
Fire and Explosion due removed from the work area.
to Flammable Suitable fire extinguishers and fire protection
substances systems shall be provided in the work area.
Keep minimum quantity of flammable
materials at the work place.
Adequate training to be given to the workforce
regarding fire risks.
3. Paint application Adequate ventilation shall be provided on
the work place to extract fumes and blow
fresh air. Site Engineer/
Respiratory problems Adequate training / TBT shall be given to Foreman
workers regarding painting works.
Ensure usage of suitable PPEs such as
respiratory mask, hand gloves, safety
glasses.
Spillage and walkways polythene sheet shall be provided to avoid Site Engineer/
not clear or poor paint thinner spillage on the ground. Foreman
housekeeping Access routes shall be kept clear at all times.
All spillages and waste materials shall be
disposed of and / or cleaned up as per EAD
requirements.
4. Working at All personnel working 2 meters or above to Site Engineer/
Height and on wear Safety Harness and tied off to a suitable Foreman
Scaffoldings strong point.
Serious injuries or
All ladders used to be in the appropriate angle
death to personnel
and secured properly.
falling from height if
Only approved scaffoldings or working
not protected by platforms to be used.
handrails, guards or If mobile platforms used, ensure wheels are
fall protection locked when persons working on top.
If mobile platforms are moved to different
locations, ensure personnel are removed before
moving scaffolding to different location.
Falling objects from Ensure area is barricaded were work is Site Engineer/
height/scaffoldings. conducted at height. Foreman
Install appropriate warning signs "Falling
Personnel working objects"
under or nearby can No materials to be stored on top of scaffolds
sustain serious Ensure all scaffolds have toe boards installed to
injuries from falling prevent tools and materials from falling.
objects Any tools to be used on top of scaffoldings shall
be secured to prevent falling.