Project Charter and Preliminary Scope Statement Ref
Project Charter and Preliminary Scope Statement Ref
Signatures
_______________ _____________
Date: Date:
2. Project Preliminary Scope Statement. The Project Preliminary Scope
Statement provides an indication of the project deliverables and serves as a guide for developing
the detailed project scope statement and for planning the project. This document defines what
the project needs to accomplish for the project to be deemed complete. The project, in its
infancy, is defined in the preliminary project scope statement. Like its name implies, this
document is preliminary to the project work and much of the project planning.
The college does not have sufficient computer lab space to handle the
increased demand, and the systems in the labs are rapidly becoming obsolete.
A feasibility study was conducted to determine the computer lab needs of the
Need/Requirement college in more measurable terms. The result of this study was a
recommendation to undertake a project to double the number of computer
labs and computers in the college and update all the lab equipment to current
technology.
Project Objectives The objective of this project is to build ten computer labs at Punjab Business
and Technical College to increase the lab capacity by 100% and equip the labs
with technology that is no less than one year old before Fall classes start this
year.
Product Scope Definition The project will improve the IT standards of the College and will give more
opportunities of enhancing computer skills of the students and attracts new
students and bring business to the college with increase rate of admissions in
coming session. The College will build 10 computer labs so every student
should have his separate system with latest technology sufficient memory
space. These labs should be installed with HVAC system, best electric fittings
and stand by UPS and generators. These labs would be used by IT as well as
business students, so these all labs have computers with required
specifications and installed with all required software. In phase 1 we will
construct the building after completion of building in phase 2 we will install
HVAC system and do all require fixtures and finishing works including
installation of UPS and provide generator connections to the Labs. In Last
phase we will procure the computers and install them in lab with complete
specification.
Project Deliverables The primary deliverable of this project is ten new computer labs. Each of these
labs will include student workstations, at least one instructor workstation,
and at least one digital projector and screen. In addition to that all labs should
be installed with UPS for power backup. Complete documentations such as
feasibility reports, designs and drawings need to be maintained where as
separate maintenance and operation documents need to be made for each
lab.
Project Requirements All ten labs need to be completed in all aspects by end of march so they can
be used in the new session. All the labs need to be fully equipped with the
latest generation workstations with centralized AC system with all required
furniture and electric installations. These labs need to be spacious and
environment friendly.
The major stakeholders need that the work should be completed well in time
with good quality and within estimated cost.
Project Boundaries Lab Building should be in the college premises. Lab Building include Computer
halls with teacher and lab assistant rooms with attach washrooms. No student
washrooms were needed in the lab building as separate washroom complex is
present in near vicinity.
Product Acceptance Criteria For the design documents to be acceptable, all specifications must be met, and
the following criteria must also be achieved:
1) Each room will have its own package of design drawings, and files.
2) All drawings will include the scale, drafter, designer, building, room
number, symbols, and other key information to provide the user with
exact information to be able to follow the drawing to build the facility.
3) All construction specifications must meet generally accepted engineering
standards as defined in the Project Resource Manual produced by the
Construction Specifications Institute
For each computer lab to be acceptable, all specifications in its design
documents must be met.
For the maintenance documents to be acceptable, all specifications must be
met, and the following criteria must also be achieved:
1) Each room will have its own package of maintenance documents.
2) All construction specifications must meet generally accepted engineering
standards as defined in the Project Resource Manual produced by the
Construction Specifications Institute.
3) Hard copy of all drawings, CD disk containing digital documents
complying with requirements detailed above.
4) A minimum of two (2) printed & bound sets of all maintenance manuals
and one (1) set in digital form are provided.
Project Constraints
The following restrictions apply to the project:
The project must be completed Because classes begin the following week in the labs
no later than March 30th, 2023.
The project must only use Because the college must comply with all government procurement and
approved vendors in competition regulations.
accordance with the college’s
procurement policies and
standards.
Project Assumptions
The existing lab rooms have the Conducting a site review during development of the design specifications for
electrical, cooling, and network each lab.
capacity for the new lab
equipment.
The existing labs already have Conducting a site review during development of the design specifications for
security systems installed. each lab.
Fund Limitation Project should not exceed Total of PKR 100 Mn.
Approval Requirements Approval to start the project from the owner as he is providing the funds for
the project.
3. Comments on Construction Feasibility Study. I have downloaded the
feasibility study of Residential project i.e Silver Gracia in Ravet, Pune by BVG developers
presented by (Pranav B. Maske, 2021).
Comments: -
Feasibility study is mainly divided into 5 parts i.e., Economical Feasibility, Scheduling,
Legal, Technical and Operational Feasibility. In this study they mainly focused on two of
them that mainly affect the project Economic and Scheduling feasibility. Mainly we
measure the feasibility by three ways that are benefit to cost ratio, NPV and IRR. We called
the project as feasible if B/C is greater than 1, NPV should be more than 0 and for this
project they assumed IRR should be 10%. The first thing we have found in this project that
is the estimated duration of project is 3 years and the total cost required for the project is
estimated to be Rs. 1027.25Mn approx. the project will be feasible if it generates the
revenue that is more than the estimated values . In this study they have identify two most
critical variables which can affect the project cash flow.
a. Bookings by customers.
b. Delay in construction.
By analyzing above two variables the study finds out that when 77% customers book their
apartments then the developer will be on zero NPV and all above 77% booking s will be the
profit earned by the developer. Similarly, if the project is delayed it has been observed
that there is an increase of 10 to 15% in project cost per year for the delay period. By
analyzing the delay period, it has been observed that on 57 month of delay period the NPV
found to be zero whereas IRR will be 10%. It has been concluded from the stud y that the
project is feasible if the customers book min 77% of the apartments and the max delay
should not exceed 57 months.
References
Pranav B. Maske, D. A. (2021). FEASIBILITY STUDY FOR A RESIDENTIAL CONSTRUCTION PROJECT.
International Research Journal of Engineering and Technology (IRJET), 3984-3990.