SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH
Miscellaneous Structures

Quantity Quantity for


Item Quantity for Total Quantity
Description for Pipe Steps and Unit Remarks
No. Box Culvert of works
Culvert Other

1 Excavation for Structures Foundation Earth work in


excavation of foundation of structures in all types of soil,
including construction of shoring and bracing, removal of
stumps and other deleterious matter and backfilling with
approved Material, all complete as per design drawings, 5,847.32 1004.89 1210.00 8,062.21 Cum
technical specification and to the satisfaction of Engineer.
[SS/SP 900]

2 Providing and laying of Stone Soling/Pitching/ Packing


Works for levelling in line and level, all complete, as per
specification , drawing and instruction of Engineer. (SS- 731.04 179.29 605.00 1,515.33 Cum
1006)
3 Providing and placing machine mixed Cement Concrete
in M15/40 for PCC works including form works,
compaction, curing, testing, all complete, as per specification, 368.62 490.29 662.38 1,521.28 Cum
drawing and instruction of Engineer. (SS-2000)

4 Providing and laying machine mixed Cement Concrete


in M25/20 for RCC works including form works,
compaction, curing, testing, all complete, as per specification, 2,020.06 2,020.06 Cum
drawing and instruction of Engineer. (SS-2000)

5 Providing and laying machine mixed Cement Concrete


in M30/20 for RCC works in Crash Barriers including form
works, compaction, curing, testing, all complete, as per 96.15 96.15 Cum
specification, drawing and instruction of Engineer. (SS-2000)

Providing and laying , fitting and placing HYSD bar


reinforcement for RCC structure, all complete as per design
drawings, technical specification and to the satisfaction of 219.12 219.12 Mt
Engineer. [SS/SP 2000]
6
Assembling mechanical woven Gabion boxes/matresses,
placing in position including streching,forming compartments
all complete as per specification and drawing. (SS-2402) 11,399.00 11,399.00 Sqm
7
Providing and Filling Stone/ Boulder in gabion boxes /
mattress etc. including dressing, beding, bonding all 2,072.00 2,072.00 Cum
8 complete as per specification and drawing. (SS-2402)
9 Providing and Laying Reinforced Cement Concrete NP3 Flush
jointed Pipe for Culverts including fixing with cement mortar
1:2, all complete, as per specification, drawing and
instruction of Engineer. (SS-701)

a 90 dia Hume Pipe 340.00 340.00 Rm


b 60dia Hume Pipe 60.00 60.00 Rm
10 Random Rubble Masonry: Providing and laying of Stone
Masonry Work in Cement Mortar 1:4 in Foundation, all
complete as per design drawings, technical specification and 585.50 585.50 Cum
to the satisfaction of Engineer. [SS/SP 2600]

11 Providing and laying Brick Masonry Work in 1:4 Cement


mortar in structure complete, all complete as per design
drawings, technical specification and to the satisfaction of 1000 1,000.00 Cum
Engineer. [SS/SP 2500]

SOOSUNG/ERMC/TSE Miscellaneous Structures_Summary-1


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Summary Sheet for Quantity of Box Culvert


Item Quantity for One Box Culvert No of Box Culvert Total Quantity Total Quantity
Description Unit Remarks
No. 1.5x1.5 2.0x2.0 3.0x2.0 5.0x2.0 1.5x1.5 2.0x2.0 3.0x2.0 5.0x2.0 1.5x1.5 2.0x2.0 3.0x2.0 5.0x2.0 of works
1 Excavation for Structures Foundation Earth work in excavation of
foundation of structures in all types of soil, including
construction of shoring and bracing, removal of stumps and other
deleterious matter and backfilling with approved Material, all
complete as per design drawings, technical specification and to 167.79 183.94 217.54 399.90 4.00 8.00 6.00 6.00 671.15 1,471.52 1,305.24 2,399.41 5,847.32 Cum
the satisfaction of Engineer. [SS/SP 900]

2 Providing and laying of Stone Soling/Pitching/ Packing Works


for levelling in line and level, all complete, as per specification , 24.55 26.19 27.39 43.16 4.00 8.00 6.00 6.00 98.18 209.55 164.36 258.94 731.04 Cum
drawing and instruction of Engineer. (SS-1006)

3 Providing and placing machine mixed Cement Concrete in


M15/40 for PCC works including form works, compaction,
curing, testing, all complete, as per specification, drawing and 12.39 13.22 13.82 21.72 4.00 8.00 6.00 6.00 49.57 105.78 82.93 130.34 368.62
instruction of Engineer. (SS-2000)

4 Providing and laying machine mixed Cement Concrete in


M25/20 for RCC works including form works, compaction,
curing, testing, all complete, as per specification, drawing and 66.30 76.55 79.43 110.98 4.00 8.00 6.00 6.00 265.21 612.39 476.60 665.86 2,020.06 Cum
instruction of Engineer. (SS-2000)

5 Providing and laying machine mixed Cement Concrete in


M30/20 for RCC works in Crash Barriers including form works,
compaction, curing, testing, all complete, as per specification, 3.43 3.64 4.03 4.86 4.00 8.00 6.00 6.00 13.72 29.11 24.15 29.17 96.15 Cum
drawing and instruction of Engineer. (SS-2000)

6 Providing and laying , fitting and placing HYSD bar


reinforcement for RCC structure, all complete as per design
drawings, technical specification and to the satisfaction of 6.73 7.72 8.96 12.79 4.00 8.00 6.00 6.00 26.92 61.74 53.73 76.72 219.12 Mt
Engineer. [SS/SP 2000]

7 Assembling mechanical woven Gabion boxes/matresses,


placing in position including streching,forming compartments all 262.00 275.00 423.50 935.00 4.00 8.00 6.00 6.00 1,048.00 2,200.00 2,541.00 5,610.00 11,399.00 Sqm
complete as per specification and drawing. (SS-2402)

8 Providing and Filling Stone/ Boulder in gabion boxes / mattress


etc. including dressing, beding, bonding all complete as per 47.50 50.00 77.00 170.00 4.00 8.00 6.00 6.00 190.00 400.00 462.00 1,020.00 2,072.00 Cum
specification and drawing. (SS-2402)

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-2


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 1.5 m x 1.5 m


Item
Description No Length Breadth Height Area Quantity Unit Remarks
No.
1 Excavation for Structures Foundation
Earth work in excavation of foundation of
structures,including construction of shoring
and bracing, removal of stumps and other
deleterious matter and backfilling with
approved Material as per Drawing and
Technical Specifications. (SS-907)

Box Cell 1 10.00 0.48 0.47 2.26


Wing Wall U/S 2 4.24 2.10 1.50 26.73
Wing Wall D/S 2 4.24 2.10 1.50 26.73
Wing Wall Ends 4 1.00 1.80 1.50 10.80
Floor Apron, U/S 1 3.00 4.50 0.25 3.38
Floor Apron, D/S 1 3.00 4.50 0.25 3.38
Gabion Apron, U/S 1 2.00 9.50 1.00 19.00
Gabion Apron, D/S 1 3.00 9.50 1.00 28.50
Curtain Wall, U/S 1 9.50 1.00 2.23 21.14
Curtain Wall, D/S 1 9.50 1.00 2.73 25.89
Total 167.79 Cum

Providing and laying of Stone


Soling/Pitching/ Packing Works for
2 levelling in line and level, all complete, as
per specification , drawing and instruction
of Engineer. (SS-1006)

Box Cell 1 10.00 0.48 0.15 0.72


Approach Slab 2 10.00 3.50 0.15 10.50
Wing Wall U/S 2 4.24 2.10 0.15 2.67
Wing Wall D/S 2 4.24 2.10 0.15 2.67
Wing Wall Ends 4 1.00 1.80 0.15 1.08
Floor Apron, U/S 1 3.00 4.50 0.15 2.03
Floor Apron, D/S 1 3.00 4.50 0.15 2.03
Curtain Wall, U/S 1 9.50 1.00 0.15 1.43
Curtain Wall, D/S 1 9.50 1.00 0.15 1.43
Total 24.546 Cum

Providing and placing machine mixed


Cement Concrete in M15/40 for PCC
works including form works, compaction,
3 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Box Cell 1 10.00 0.48 0.10 0.48


Approach Slab 2 10.00 3.50 0.08 5.25
Wing Wall U/S 2 4.24 2.10 0.08 1.34
Wing Wall D/S 2 4.24 2.10 0.08 1.34
Wing Wall Ends 4 1.00 1.80 0.08 0.54
Floor Apron, U/S 1 3.00 4.50 0.08 1.01
Floor Apron, D/S 1 3.00 4.50 0.08 1.01
Curtain Wall, U/S 1 9.50 1.00 0.08 0.71
Curtain Wall, D/S 1 9.50 1.00 0.08 0.71
Total 12.39 Cum

Providing and laying machine mixed


Cement Concrete in M25/20 for RCC
works including form works, compaction,
4 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Side Wall 2 10.00 0.18 1.50 5.400


Bottom Slab 1 10.00 0.18 0.22 0.396
Top Slab 1 10.00 0.18 0.18 0.324
Haunch 4 10.00 0.20 0.2 0.5 0.800

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-3


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 1.5 m x 1.5 m


Corbel Rectangular part 2 10.00 0.30 0.30 1.800
Corbel Traingular Part 2 10.00 0.30 0.30 0.5 0.900
Approach Slab 2 10.00 3.50 0.25 17.500
Wing Wall Foundation U/S 2 4.24 2.10 0.25 4.45
Wing Wall Foundation D/S 2 4.24 2.10 0.25 4.45
Wing Wall Foundation Ends 4 1.00 1.80 0.25 1.80
Wing Wall Stem U/S 2 4.24 0.23 2.60 5.07
Wing Wall Stem D/S 2 4.24 0.23 2.60 5.07
Wing Wall Stem Ends 4 1.00 0.22 2.20 1.94
Curtain Wall Stem, U/S 1 9.50 0.25 1.60 3.800
Curtain Wall Stem, D/S 1 9.50 0.25 2.10 4.988
Curtain Wall Footing, U/S 1 9.50 1.00 0.40 3.800
Curtain Wall Footing, D/S 1 9.50 1.00 0.40 3.800
Total 66.30 Cum

Providing and laying machine mixed


Cement Concrete in M30/20 for RCC
works in Crash Barriers including form
5 works, compaction, curing, testing, all
complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Crash Barrier-1 (CB-1)


Top Trapezoidal Section 0.18 0.48 0.0864
Central Trapezoidal Section 0.30 0.26 0.0771375
Bottom Rectangular Section 0.40 0.08 0.03
Total 17.72 0.1935 3.43
Total 3.43 Cum

Providing and Filling Stone/ Boulder in


gabion boxes / mattress etc. including
6 dressing, beding, bonding all complete as
per specification and drawing. (SS-2402)

Gabion Apron, U/S 1 9.50 2.00 1.00 19.00


Gabion Apron, D/S 1 9.50 3.00 1.00 28.50
Total 47.50 Cum

Assembling mechanical woven Gabion


boxes/matresses, placing in position
7 including streching,forming compartments
all complete as per specification and
drawing. (SS-2402)

Total 262.00 Sqm

Bar Schedule for Box Culvert


Total Tot.
Length Weight/m
Bar Spacing Length weight
Description Dia (mm) Nos Remarks
Mark (mm)
mm (m) (kg/m) (kg)

Top Slab
100
100

TS1 1780 16 180 58 1980 114.84 1.58 181.4


100

100

TS2 4920 10 200 20 5120 102.4 0.62 63.5


100

TS3 1780 12 200 52 1980 102.96 0.89 91.6


100

100
100

TS4 4920 10 200 20 5120 102.4 0.62 63.5

Total 400

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-4


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 1.5 m x 1.5 m

Base Slab
100
1710
100

BS1 16 180 56 1910 106.96 1.58 169


100

9850
100

BS2 10 200 10 10050 100.5 0.62 62.3


100
100

BS3 1710 10 200 51 1910 97.41 0.62 60.4


100
100

BS4 9850 10 200 10 10050 100.5 0.62 62.3

Total 354

Side Walls (2 nos.)


575
1785

SW1 12 200 102 2935 299.37 0.89 266.4

575
1785

SW2 12 200 102 1785 182.07 0.89 162

9850
95
95

SW3 8 200 16 19890 318.24 0.4 127.3

200 330 300


SW4 16 200 102 1297 132.294 1.58 209
467

CB 10 200 204 630 128.52 0.62 79.7


630

Total 844.4
Total (TS+BS+SW) 1598.4

Curtain Walls
Downstream
2350

CD1 12 150 128 2650 339.2 0.89 301.9


300
100

CD2 10 180 15 18900 283.5 0.62 175.8


9350
250

CD3 10 180 53 2200 116.6 0.62 72.3


850

CD4 9350 10 180 12 9350 112.2 0.62 69.6


Total 619.6

Upstream
1850

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-5


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 1.5 m x 1.5 m


1850

CU1 12 150 128 2150 275.2 0.89 244.9


300
100

CU2 10 180 12 18900 226.8 0.62 140.6


9350
250

CU3 10 180 53 2200 116.6 0.62 72.3


850

CU4 9350 10 180 12 9350 112.2 0.62 69.6

Total 527.4

Approach Slab
100
100

AS1 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS2 9900 12 150 24 10100 242.4 0.89 215.7


100
100

AS3 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS4 9900 12 150 24 10100 242.4 0.89 215.7

Total 860.8
Total for Two Approach Slab 1721.6

Crash Barrier (Type:- CB-1)


928

575
C1 16 125 81 2032 164.592 1.58 260.1
225

304
915

C2 16 125 81 1415 114.615 1.58 181.1


500

C3 16 11 9960 109.56 1.58 173.1


9960
Total of 10 m 614.3 0.06143
For 17.72m Length 1088.54

Crash Barrier (Type:- CB-2)

575
C1 16 8 2205 17.64 1.58 27.9
250

555
915

C2 16 16 1645 26.32 1.58 41.6


730

C3 16 12 960 11.52 1.58 18.2


960
Total of 1 m 87.7
For 0m Length 0.00

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-6


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 1.5 m x 1.5 m


Crash Barrier (Type:- CB-3)
For 0m Length 0.00

Crash Barrier (Type:- CB-4)


For 0m Length 0.00

Wing Wall
1350 to

S1 12 160 34 2130 72.42 0.89 64.50


1750

580

100
2450 to

S2 12 160 34 3530 120.02 0.89 106.80


3250

580

100
2450 to

S3 12 160 34 3530 120.02 0.89 106.80


3250

580

S4 10 250 12 5250 63 0.62 39.10


5250
S5 10 250 12 5250 63 0.62 39.10
5250
100
100

F1 1800 to 2400 12 250 22 2300 50.6 0.89 45.00

F2 10 250 9 5250 47.25 0.62 29.30


5250
100
100

F3 1800 to 2400 12 250 22 2300 50.6 0.89 45.00

F4 10 250 9 5250 47.25 0.62 29.30


5250
F5 0 6 0 0 0 0.00
0
Total 504.90
Total for Four Wing Wall 2019.600 Mt
Total Rebar 6.731 Mt

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-7


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

200 x 200

3.50 m

180 0.25 m
0.30
m

1500 180
0.30 m 155

1500 480

205
220
400 255
75

Assumptions:
Box Culvert with Internal Cell Size = 1.5 m x 1.5 m Road Width (W)= 10000 mm
Clear Width (a)= 1500 mm Top Slab Central Opening = 0 mm
Clear Height (b)= 1500 mm
Side Wall Thickness (c)= 180 mm Depth of PCC on Bottom Slab= 100 mm
Top Slab Thickness (d)= 180 mm Depth of PCC on Other Components= 75 mm
Bottom Slab Thickness (e)= 220 mm Depth of Stone Soling= 150 mm
Fillet (f)= 200 x 200 mm Depth of Flexible Apron= 1.00 m
Length of Crash Barrier, CB-1= 17.72 m Width of Curtain Wall Stem= 0.25 m
Length of Crash Barrier, CB-2= 0.00 m Depth of Curtain Wall Stem, U/S= 1.60 m
Length of Crash Barrier, CB-3= 0.00 m Depth of Curtain Wall Stem, D/S= 2.10 m
Length of Crash Barrier, CB-4= 0.00 m Width of Curtain Wall Footing= 1.00 m
Length of Rigid Apron, AL= 3.00 m Depth of Curtain Wall Footing= 0.40 m
Width of Rigid Apron at Start, AW-1= 1.50 m
Width of Rigid Apron at Start, AW-2= 7.50 m Wing Wall Length, U/S= 4.24
Length of Curtain Wall U/S, CWL-1= 9.50 m Wing Wall Length, D/S= 4.24
Length of Curtain Wall D/S, CWL-2= 9.50 m Wing Wall End Length= 1.00
Length of Flexible Apron U/S, GWL-1= 2.00 m Wing Wall Start ht= 3.00
Length of Flexible Apron D/S, GWL-2= 3.00 m Wing Wall End ht= 2.20
Length of Aproach Slab= 3.50 m
Depth of Aproach Slab= 0.25 m
Height of Corbel Rectangle= 0.30 m
Height of Corbel Traingle= 0.30 m
Width of Corbel= 0.30 m

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-8


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 3 m x 2 m


Item
Description No Length Breadth Height Area Quantity Unit Remarks
No.
1 Excavation for Structures Foundation
Earth work in excavation of foundation of
structures,including construction of shoring
and bracing, removal of stumps and other
deleterious matter and backfilling with
approved Material as per Drawing and
Technical Specifications. (SS-907)

Box Cell 1 10.00 0.50 0.53 2.65


Wing Wall U/S 2 4.24 2.50 1.50 31.82
Wing Wall D/S 2 4.24 2.50 1.50 31.82
Wing Wall Ends 4 1.00 1.80 1.50 10.80
Floor Apron, U/S 1 3.00 6.00 0.25 4.50
Floor Apron, D/S 1 3.00 6.00 0.25 4.50
Gabion Apron, U/S 1 3.00 11.00 1.00 33.00
Gabion Apron, D/S 1 4.00 11.00 1.00 44.00
Curtain Wall, U/S 1 11.00 1.00 2.23 24.48
Curtain Wall, D/S 1 11.00 1.00 2.73 29.98
Total 217.54 Cum

Providing and laying of Stone


Soling/Pitching/ Packing Works for
2 levelling in line and level, all complete, as
per specification , drawing and instruction
of Engineer. (SS-1006)

Box Cell 1 10.00 0.50 0.15 0.75


Approach Slab 2 10.00 3.50 0.15 10.50
Wing Wall U/S 2 4.24 2.50 0.15 3.18
Wing Wall D/S 2 4.24 2.50 0.15 3.18
Wing Wall Ends 4 1.00 1.80 0.15 1.08
Floor Apron, U/S 1 3.00 6.00 0.15 2.70
Floor Apron, D/S 1 3.00 6.00 0.15 2.70
Curtain Wall, U/S 1 11.00 1.00 0.15 1.65
Curtain Wall, D/S 1 11.00 1.00 0.15 1.65
Total 27.394 Cum

Providing and placing machine mixed


Cement Concrete in M15/40 for PCC
works including form works, compaction,
3 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Box Cell 1 10.00 0.50 0.10 0.50


Approach Slab 2 10.00 3.50 0.08 5.25
Wing Wall U/S 2 4.24 2.50 0.08 1.59
Wing Wall D/S 2 4.24 2.50 0.08 1.59
Wing Wall Ends 4 1.00 1.80 0.08 0.54
Floor Apron, U/S 1 3.00 6.00 0.08 1.35
Floor Apron, D/S 1 3.00 6.00 0.08 1.35
Curtain Wall, U/S 1 11.00 1.00 0.08 0.83
Curtain Wall, D/S 1 11.00 1.00 0.08 0.83
Total 13.82 Cum

Providing and laying machine mixed


Cement Concrete in M25/20 for RCC
works including form works, compaction,
4 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Side Wall 2 10.00 0.20 2.00 8.000


Bottom Slab 1 10.00 0.20 0.28 0.560
Top Slab 1 10.00 0.20 0.25 0.500
Haunch 4 10.00 0.30 0.3 0.5 1.800

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-9


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 3 m x 2 m


Corbel Rectangular part 2 10.00 0.30 0.30 1.800
Corbel Traingular Part 2 10.00 0.30 0.30 0.5 0.900
Approach Slab 2 10.00 3.50 0.25 17.500
Wing Wall Foundation U/S 2 4.24 2.50 0.30 6.36
Wing Wall Foundation D/S 2 4.24 2.50 0.30 6.36
Wing Wall Foundation Ends 4 1.00 1.80 0.30 2.16
Wing Wall Stem U/S 2 4.24 0.26 2.85 6.29
Wing Wall Stem D/S 2 4.24 0.26 2.85 6.29
Wing Wall Stem Ends 4 1.00 0.22 2.20 1.94
Curtain Wall Stem, U/S 1 11.00 0.25 1.60 4.400
Curtain Wall Stem, D/S 1 11.00 0.25 2.10 5.775
Curtain Wall Footing, U/S 1 11.00 1.00 0.40 4.400
Curtain Wall Footing, D/S 1 11.00 1.00 0.40 4.400
Total 79.43 Cum

Providing and laying machine mixed


Cement Concrete in M30/20 for RCC
works in Crash Barriers including form
5 works, compaction, curing, testing, all
complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Crash Barrier-1 (CB-1)


Top Trapezoidal Section 0.18 0.48 0.0864
Central Trapezoidal Section 0.30 0.26 0.0771375
Bottom Rectangular Section 0.40 0.08 0.03
Total 20.80 0.1935 4.03
Total 4.03 Cum

Providing and Filling Stone/ Boulder in


gabion boxes / mattress etc. including
6 dressing, beding, bonding all complete as
per specification and drawing. (SS-2402)

Gabion Apron, U/S 1 11.00 3.00 1.00 33.00


Gabion Apron, D/S 1 11.00 4.00 1.00 44.00
Total 77.00 Cum

Assembling mechanical woven Gabion


boxes/matresses, placing in position
7 including streching,forming compartments
all complete as per specification and
drawing. (SS-2402)

Total 423.50 Sqm

Bar Schedule for Box Culvert


Total Tot.
Length Weight/m
Bar Spacing Length weight
Description Dia (mm) Nos Remarks
Mark (mm)
mm (m) (kg/m) (kg)

Top Slab
100
100

TS1 3420 16 140 74 3620 267.88 1.58 423.3


100

100

TS2 4920 12 180 40 5120 204.8 0.89 182.3


100

TS3 3420 12 200 52 3620 188.24 0.89 167.5


100

100
100

TS4 4920 12 180 40 5120 204.8 0.89 182.3

Total 955.4

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-10


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 3 m x 2 m

Base Slab
100
3350
100

BS1 20 140 72 3550 255.6 2.47 631.3


100

9850
100

BS2 12 180 20 10050 201 0.89 178.9


100
100

BS3 3350 12 200 51 3550 181.05 0.89 161.1


100
100

BS4 9850 12 180 20 10050 201 0.89 178.9

Total 1150.2

Side Walls (2 nos.)


1045
2415

SW1 16 180 112 4505 504.56 1.58 797.2

1045
2415

SW2 12 180 112 2415 270.48 0.89 240.7

9850
95
95

SW3 10 200 22 19890 437.58 0.62 271.3

200 350 300


SW4 16 200 102 1345 137.19 1.58 216.8
495

CB 10 200 204 899 183.396 0.62 113.7


899

Total 1639.7
Total (TS+BS+SW) 3745.3

Curtain Walls
Downstream
2350

CD1 12 150 148 2650 392.2 0.89 349.1


300
100

CD2 10 180 15 21900 328.5 0.62 203.7


10850
250

CD3 10 180 62 2200 136.4 0.62 84.6


850

CD4 10850 10 180 12 10850 130.2 0.62 80.7


Total 718.1

Upstream
1850

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-11


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 3 m x 2 m


1850

CU1 12 150 148 2150 318.2 0.89 283.2


300
100

CU2 10 180 12 21900 262.8 0.62 162.9


10850
250

CU3 10 180 62 2200 136.4 0.62 84.6


850

CU4 10850 10 180 12 10850 130.2 0.62 80.7

Total 611.4

Approach Slab
100
100

AS1 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS2 9900 12 150 24 10100 242.4 0.89 215.7


100
100

AS3 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS4 9900 12 150 24 10100 242.4 0.89 215.7

Total 860.8
Total for Two Approach Slab 1721.6

Crash Barrier (Type:- CB-1)


928

575
C1 16 125 81 2032 164.592 1.58 260.1
225

304
915

C2 16 125 81 1415 114.615 1.58 181.1


500

C3 16 11 9960 109.56 1.58 173.1


9960
Total of 10 m 614.3 0.06143
For 20.8m Length 1277.74

Crash Barrier (Type:- CB-2)

575
C1 16 8 2205 17.64 1.58 27.9
250

555
915

C2 16 16 1645 26.32 1.58 41.6


730

C3 16 12 960 11.52 1.58 18.2


960
Total of 1 m 87.7
For 0m Length 0.00

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-12


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 3 m x 2 m


Crash Barrier (Type:- CB-3)
For 0m Length 0.00

Crash Barrier (Type:- CB-4)


For 0m Length 0.00

Wing Wall
1400 to

S1 16 200 27 2380 64.26 1.58 101.50


2050

650

100
2500 to

S2 16 200 27 3900 105.3 1.58 166.40


3800

650

100
2500 to

S3 12 200 27 3900 105.3 0.89 93.70


3800

650

S4 10 250 14 5250 73.5 0.62 45.60


5250
S5 10 250 14 5250 73.5 0.62 45.60
5250
100
100

F1 1800 to 3200 12 250 22 2700 59.4 0.89 52.90

F2 10 250 11 5250 57.75 0.62 35.80


5250
100
100

F3 1800 to 3200 12 250 22 2700 59.4 0.89 52.90

F4 10 250 11 5250 57.75 0.62 35.80


5250
F5 0 6 0 0 0 0.00
0
Total 630.20
Total for Four Wing Wall 2520.800 Mt
Total Rebar 8.955 Mt

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-13


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

300 x 300

3.50 m

250 0.25 m
0.30
m

2000 200
0.30 m 155

3000 480

205
280
400 255
75

Assumptions:
Box Culvert with Internal Cell Size = 3 m x 2 m Road Width (W)= 10000 mm
Clear Width (a)= 3000 mm Top Slab Central Opening = 0 mm
Clear Height (b)= 2000 mm
Side Wall Thickness (c)= 200 mm Depth of PCC on Bottom Slab= 100 mm
Top Slab Thickness (d)= 250 mm Depth of PCC on Other Components= 75 mm
Bottom Slab Thickness (e)= 280 mm Depth of Stone Soling= 150 mm
Fillet (f)= 300 x 300 mm Depth of Flexible Apron= 1.00 m
Length of Crash Barrier, CB-1= 20.80 m Width of Curtain Wall Stem= 0.25 m
Length of Crash Barrier, CB-2= 0.00 m Depth of Curtain Wall Stem, U/S= 1.60 m
Length of Crash Barrier, CB-3= 0.00 m Depth of Curtain Wall Stem, D/S= 2.10 m
Length of Crash Barrier, CB-4= 0.00 m Width of Curtain Wall Footing= 1.00 m
Length of Rigid Apron, AL= 3.00 m Depth of Curtain Wall Footing= 0.40 m
Width of Rigid Apron at Start, AW-1= 3.00 m
Width of Rigid Apron at Start, AW-2= 9.00 m Wing Wall Length, U/S= 4.24
Length of Curtain Wall U/S, CWL-1= 11.00 m Wing Wall Length, D/S= 4.24
Length of Curtain Wall D/S, CWL-2= 11.00 m Wing Wall End Length= 1.00
Length of Flexible Apron U/S, GWL-1= 3.00 m Wing Wall Start ht= 3.50
Length of Flexible Apron D/S, GWL-2= 4.00 m Wing Wall End ht= 2.20
Length of Aproach Slab= 3.50 m
Depth of Aproach Slab= 0.25 m
Height of Corbel Rectangle= 0.30 m
Height of Corbel Traingle= 0.30 m
Width of Corbel= 0.30 m

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-14


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 2 m x 2 m


Item
Description No Length Breadth Height Area Quantity Unit Remarks
No.
1 Excavation for Structures Foundation
Earth work in excavation of foundation of
structures,including construction of shoring
and bracing, removal of stumps and other
deleterious matter and backfilling with
approved Material as per Drawing and
Technical Specifications. (SS-907)

Box Cell 1 10.00 0.50 0.50 2.50


Wing Wall U/S 2 4.24 2.50 1.50 31.82
Wing Wall D/S 2 4.24 2.50 1.50 31.82
Wing Wall Ends 4 1.00 1.80 1.50 10.80
Floor Apron, U/S 1 3.00 5.00 0.25 3.75
Floor Apron, D/S 1 3.00 5.00 0.25 3.75
Gabion Apron, U/S 1 2.00 10.00 1.00 20.00
Gabion Apron, D/S 1 3.00 10.00 1.00 30.00
Curtain Wall, U/S 1 10.00 1.00 2.23 22.25
Curtain Wall, D/S 1 10.00 1.00 2.73 27.25
Total 183.94 Cum

Providing and laying of Stone


Soling/Pitching/ Packing Works for
2 levelling in line and level, all complete, as
per specification , drawing and instruction
of Engineer. (SS-1006)

Box Cell 1 10.00 0.50 0.15 0.75


Approach Slab 2 10.00 3.50 0.15 10.50
Wing Wall U/S 2 4.24 2.50 0.15 3.18
Wing Wall D/S 2 4.24 2.50 0.15 3.18
Wing Wall Ends 4 1.00 1.80 0.15 1.08
Floor Apron, U/S 1 3.00 5.00 0.15 2.25
Floor Apron, D/S 1 3.00 5.00 0.15 2.25
Curtain Wall, U/S 1 10.00 1.00 0.15 1.50
Curtain Wall, D/S 1 10.00 1.00 0.15 1.50
Total 26.194 Cum

Providing and placing machine mixed


Cement Concrete in M15/40 for PCC
works including form works, compaction,
3 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Box Cell 1 10.00 0.50 0.10 0.50


Approach Slab 2 10.00 3.50 0.08 5.25
Wing Wall U/S 2 4.24 2.50 0.08 1.59
Wing Wall D/S 2 4.24 2.50 0.08 1.59
Wing Wall Ends 4 1.00 1.80 0.08 0.54
Floor Apron, U/S 1 3.00 5.00 0.08 1.13
Floor Apron, D/S 1 3.00 5.00 0.08 1.13
Curtain Wall, U/S 1 10.00 1.00 0.08 0.75
Curtain Wall, D/S 1 10.00 1.00 0.08 0.75
Total 13.22 Cum

Providing and laying machine mixed


Cement Concrete in M25/20 for RCC
works including form works, compaction,
4 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Side Wall 2 10.00 0.20 2.00 8.000


Bottom Slab 1 10.00 0.20 0.25 0.500
Top Slab 1 10.00 0.20 0.20 0.400
Haunch 4 10.00 0.20 0.2 0.5 0.800

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-15


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 2 m x 2 m


Corbel Rectangular part 2 10.00 0.30 0.30 1.800
Corbel Traingular Part 2 10.00 0.30 0.30 0.5 0.900
Approach Slab 2 10.00 3.50 0.25 17.500
Wing Wall Foundation U/S 2 4.24 2.50 0.30 6.36
Wing Wall Foundation D/S 2 4.24 2.50 0.30 6.36
Wing Wall Foundation Ends 4 1.00 1.80 0.30 2.16
Wing Wall Stem U/S 2 4.24 0.26 2.85 6.29
Wing Wall Stem D/S 2 4.24 0.26 2.85 6.29
Wing Wall Stem Ends 4 1.00 0.22 2.20 1.94
Curtain Wall Stem, U/S 1 10.00 0.25 1.60 4.000
Curtain Wall Stem, D/S 1 10.00 0.25 2.10 5.250
Curtain Wall Footing, U/S 1 10.00 1.00 0.40 4.000
Curtain Wall Footing, D/S 1 10.00 1.00 0.40 4.000
Total 76.55 Cum

Providing and laying machine mixed


Cement Concrete in M30/20 for RCC
works in Crash Barriers including form
5 works, compaction, curing, testing, all
complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Crash Barrier-1 (CB-1)


Top Trapezoidal Section 0.18 0.48 0.0864
Central Trapezoidal Section 0.30 0.26 0.0771375
Bottom Rectangular Section 0.40 0.08 0.03
Total 18.80 0.1935 3.64
Total 3.64 Cum

Providing and Filling Stone/ Boulder in


gabion boxes / mattress etc. including
6 dressing, beding, bonding all complete as
per specification and drawing. (SS-2402)

Gabion Apron, U/S 1 10.00 2.00 1.00 20.00


Gabion Apron, D/S 1 10.00 3.00 1.00 30.00
Total 50.00 Cum

Assembling mechanical woven Gabion


boxes/matresses, placing in position
7 including streching,forming compartments
all complete as per specification and
drawing. (SS-2402)

Total 275.00 Sqm

Bar Schedule for Box Culvert


Total Tot.
Length Weight/m
Bar Spacing Length weight
Description Dia (mm) Nos Remarks
Mark (mm)
mm (m) (kg/m) (kg)

Top Slab
100
100

TS1 2320 16 150 68 2520 171.36 1.58 270.7


100

100

TS2 4920 10 180 28 5120 143.36 0.62 88.9


100

TS3 2320 12 200 52 2520 131.04 0.89 116.6


100

100
100

TS4 4920 10 180 28 5120 143.36 0.62 88.9

Total 565.1

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-16


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 2 m x 2 m

Base Slab
100
2250
100

BS1 16 130 77 2450 188.65 1.58 298.1


100

9850
100

BS2 10 180 14 10050 140.7 0.62 87.2


100
100

BS3 2250 10 200 51 2450 124.95 0.62 77.5


100
100

BS4 9850 10 180 14 10050 140.7 0.62 87.2

Total 550

Side Walls (2 nos.)


745
2335

SW1 12 180 112 3825 428.4 0.89 381.3

745
2335

SW2 12 180 112 2335 261.52 0.89 232.8

9850
95
95

SW3 8 200 22 19890 437.58 0.4 175

200 350 300


SW4 16 200 102 1345 137.19 1.58 216.8
495

CB 10 200 204 686 139.944 0.62 86.8


686

Total 1092.7
Total (TS+BS+SW) 2207.8

Curtain Walls
Downstream
2350

CD1 12 150 134 2650 355.1 0.89 316


300
100

CD2 10 180 15 19900 298.5 0.62 185.1


9850
250

CD3 10 180 56 2200 123.2 0.62 76.4


850

CD4 9850 10 180 12 9850 118.2 0.62 73.3


Total 650.8

Upstream
1850

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-17


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 2 m x 2 m


1850

CU1 12 150 134 2150 288.1 0.89 256.4


300
100

CU2 10 180 12 19900 238.8 0.62 148.1


9850
250

CU3 10 180 56 2200 123.2 0.62 76.4


850

CU4 9850 10 180 12 9850 118.2 0.62 73.3

Total 554.2

Approach Slab
100
100

AS1 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS2 9900 12 150 24 10100 242.4 0.89 215.7


100
100

AS3 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS4 9900 12 150 24 10100 242.4 0.89 215.7

Total 860.8
Total for Two Approach Slab 1721.6

Crash Barrier (Type:- CB-1)


928

575
C1 16 125 81 2032 164.592 1.58 260.1
225

304
915

C2 16 125 81 1415 114.615 1.58 181.1


500

C3 16 11 9960 109.56 1.58 173.1


9960
Total of 10 m 614.3 0.06143
For 18.8m Length 1154.88

Crash Barrier (Type:- CB-2)

575
C1 16 8 2205 17.64 1.58 27.9
250

555
915

C2 16 16 1645 26.32 1.58 41.6


730

C3 16 12 960 11.52 1.58 18.2


960
Total of 1 m 87.7
For 0m Length 0.00

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-18


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 2 m x 2 m


Crash Barrier (Type:- CB-3)
For 0m Length 0.00

Crash Barrier (Type:- CB-4)


For 0m Length 0.00

Wing Wall
1400 to

S1 16 200 27 2380 64.26 1.58 101.50


2050

650

100
2500 to

S2 16 200 27 3900 105.3 1.58 166.40


3800

650

100
2500 to

S3 12 200 27 3900 105.3 0.89 93.70


3800

650

S4 10 250 14 5250 73.5 0.62 45.60


5250
S5 10 250 14 5250 73.5 0.62 45.60
5250
100
100

F1 1800 to 3200 12 250 22 2700 59.4 0.89 52.90

F2 10 250 11 5250 57.75 0.62 35.80


5250
100
100

F3 1800 to 3200 12 250 22 2700 59.4 0.89 52.90

F4 10 250 11 5250 57.75 0.62 35.80


5250
F5 0 6 0 0 0 0.00
0
Total 630.20
Total for Four Wing Wall 2520.800 Mt
Total Rebar 7.717 Mt

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-19


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

200 x 200

3.50 m

200 0.25 m
0.30
m

2000 200
0.30 m 155

2000 480

205
250
400 255
75

Assumptions:
Box Culvert with Internal Cell Size = 2 m x 2 m Road Width (W)= 10000 mm
Clear Width (a)= 2000 mm Top Slab Central Opening = 0 mm
Clear Height (b)= 2000 mm
Side Wall Thickness (c)= 200 mm Depth of PCC on Bottom Slab= 100 mm
Top Slab Thickness (d)= 200 mm Depth of PCC on Other Components= 75 mm
Bottom Slab Thickness (e)= 250 mm Depth of Stone Soling= 150 mm
Fillet (f)= 200 x 200 mm Depth of Flexible Apron= 1.00 m
Length of Crash Barrier, CB-1= 18.80 m Width of Curtain Wall Stem= 0.25 m
Length of Crash Barrier, CB-2= 0.00 m Depth of Curtain Wall Stem, U/S= 1.60 m
Length of Crash Barrier, CB-3= 0.00 m Depth of Curtain Wall Stem, D/S= 2.10 m
Length of Crash Barrier, CB-4= 0.00 m Width of Curtain Wall Footing= 1.00 m
Length of Rigid Apron, AL= 3.00 m Depth of Curtain Wall Footing= 0.40 m
Width of Rigid Apron at Start, AW-1= 2.00 m
Width of Rigid Apron at Start, AW-2= 8.00 m Wing Wall Length, U/S= 4.24
Length of Curtain Wall U/S, CWL-1= 10.00 m Wing Wall Length, D/S= 4.24
Length of Curtain Wall D/S, CWL-2= 10.00 m Wing Wall End Length= 1.00
Length of Flexible Apron U/S, GWL-1= 2.00 m Wing Wall Start ht= 3.50
Length of Flexible Apron D/S, GWL-2= 3.00 m Wing Wall End ht= 2.20
Length of Aproach Slab= 3.50 m
Depth of Aproach Slab= 0.25 m
Height of Corbel Rectangle= 0.30 m
Height of Corbel Traingle= 0.30 m
Width of Corbel= 0.30 m

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-20


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 5 m x 2 m


Item
Description No Length Breadth Height Area Quantity Unit Remarks
No.
1 Excavation for Structures Foundation
Earth work in excavation of foundation of
structures,including construction of shoring
and bracing, removal of stumps and other
deleterious matter and backfilling with
approved Material as per Drawing and
Technical Specifications. (SS-907)

Box Cell 1 10.00 0.58 0.67 3.89


Wing Wall U/S 2 7.07 2.50 1.50 53.03
Wing Wall D/S 2 7.07 2.50 1.50 53.03
Wing Wall Ends 4 1.00 1.80 1.50 10.80
Floor Apron, U/S 1 5.00 10.00 0.25 12.50
Floor Apron, D/S 1 5.00 10.00 0.25 12.50
Gabion Apron, U/S 1 4.00 17.00 1.00 68.00
Gabion Apron, D/S 1 6.00 17.00 1.00 102.00
Curtain Wall, U/S 1 17.00 1.00 2.23 37.83
Curtain Wall, D/S 1 17.00 1.00 2.73 46.33
Total 399.90 Cum

Providing and laying of Stone


Soling/Pitching/ Packing Works for
2 levelling in line and level, all complete, as
per specification , drawing and instruction
of Engineer. (SS-1006)

Box Cell 1 10.00 0.58 0.15 0.87


Approach Slab 2 10.00 3.50 0.15 10.50
Wing Wall U/S 2 7.07 2.50 0.15 5.30
Wing Wall D/S 2 7.07 2.50 0.15 5.30
Wing Wall Ends 4 1.00 1.80 0.15 1.08
Floor Apron, U/S 1 5.00 10.00 0.15 7.50
Floor Apron, D/S 1 5.00 10.00 0.15 7.50
Curtain Wall, U/S 1 17.00 1.00 0.15 2.55
Curtain Wall, D/S 1 17.00 1.00 0.15 2.55
Total 43.157 Cum

Providing and placing machine mixed


Cement Concrete in M15/40 for PCC
works including form works, compaction,
3 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Box Cell 1 10.00 0.58 0.10 0.58


Approach Slab 2 10.00 3.50 0.08 5.25
Wing Wall U/S 2 7.07 2.50 0.08 2.65
Wing Wall D/S 2 7.07 2.50 0.08 2.65
Wing Wall Ends 4 1.00 1.80 0.08 0.54
Floor Apron, U/S 1 5.00 10.00 0.08 3.75
Floor Apron, D/S 1 5.00 10.00 0.08 3.75
Curtain Wall, U/S 1 17.00 1.00 0.08 1.28
Curtain Wall, D/S 1 17.00 1.00 0.08 1.28
Total 21.72 Cum

Providing and laying machine mixed


Cement Concrete in M25/20 for RCC
works including form works, compaction,
4 curing, testing, all complete, as per
specification, drawing and instruction of
Engineer. (SS-2000)

Side Wall 2 10.00 0.28 2.00 11.200


Bottom Slab 1 10.00 0.28 0.42 1.176
Top Slab 1 10.00 0.28 0.36 1.008
Haunch 4 10.00 0.30 0.3 0.5 1.800

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-21


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 5 m x 2 m


Corbel Rectangular part 2 10.00 0.30 0.30 1.800
Corbel Traingular Part 2 10.00 0.30 0.30 0.5 0.900
Approach Slab 2 10.00 3.50 0.25 17.500
Wing Wall Foundation U/S 2 7.07 2.50 0.30 10.61
Wing Wall Foundation D/S 2 7.07 2.50 0.30 10.61
Wing Wall Foundation Ends 4 1.00 1.80 0.30 2.16
Wing Wall Stem U/S 2 7.07 0.26 2.85 10.48
Wing Wall Stem D/S 2 7.07 0.26 2.85 10.48
Wing Wall Stem Ends 4 1.00 0.22 2.20 1.94
Curtain Wall Stem, U/S 1 17.00 0.25 1.60 6.800
Curtain Wall Stem, D/S 1 17.00 0.25 2.10 8.925
Curtain Wall Footing, U/S 1 17.00 1.00 0.40 6.800
Curtain Wall Footing, D/S 1 17.00 1.00 0.40 6.800
Total 110.98 Cum

Providing and laying machine mixed


Cement Concrete in M30/20 for RCC
works in Crash Barriers including form
5 works, compaction, curing, testing, all
complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Crash Barrier-1 (CB-1)


Top Trapezoidal Section 0.18 0.48 0.0864
Central Trapezoidal Section 0.30 0.26 0.0771375
Bottom Rectangular Section 0.40 0.08 0.03
Total 25.12 0.1935 4.86
Total 4.86 Cum

Providing and Filling Stone/ Boulder in


gabion boxes / mattress etc. including
6 dressing, beding, bonding all complete as
per specification and drawing. (SS-2402)

Gabion Apron, U/S 1 17.00 4.00 1.00 68.00


Gabion Apron, D/S 1 17.00 6.00 1.00 102.00
Total 170.00 Cum

Assembling mechanical woven Gabion


boxes/matresses, placing in position
7 including streching,forming compartments
all complete as per specification and
drawing. (SS-2402)

Total 935.00 Sqm

Bar Schedule for Box Culvert


Total Tot.
Length Weight/m
Bar Spacing Length weight
Description Dia (mm) Nos Remarks
Mark (mm)
mm (m) (kg/m) (kg)

Top Slab
100
100

TS1 5640 20 160 64 5840 373.76 2.47 923.2


100

100

TS2 4920 12 160 74 5120 378.88 0.89 337.2


100

TS3 5640 10 200 52 5840 303.68 0.62 188.3


100

100
100

TS4 4920 12 160 74 5120 378.88 0.89 337.2

Total 1785.9

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-22


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 5 m x 2 m

Base Slab
100
5570
100

BS1 20 140 72 5770 415.44 2.47 1026.1


100

9850
100

BS2 12 160 36 10050 361.8 0.89 322


100
100

BS3 5570 10 200 51 5770 294.27 0.62 182.4


100
100

BS4 9850 12 160 36 10050 361.8 0.89 322

Total 1852.5

Side Walls (2 nos.)


1725
2665

SW1 16 140 144 6115 880.56 1.58 1391.3

1725
2665

SW2 12 140 144 2665 383.76 0.89 341.5

9850
95
95

SW3 10 180 24 19890 477.36 0.62 296

200 430 300


SW4 16 200 102 1539 156.978 1.58 248
609

CB 10 200 204 1167 238.068 0.62 147.6


1167

Total 2424.4
Total (TS+BS+SW) 6062.8

Curtain Walls
Downstream
2350

CD1 12 150 228 2650 604.2 0.89 537.7


300
100

CD2 10 180 15 33900 508.5 0.62 315.3


16850
250

CD3 10 180 95 2200 209 0.62 129.6


850

CD4 16850 10 180 12 16850 202.2 0.62 125.4


Total 1108

Upstream
1850

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-23


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 5 m x 2 m


1850

CU1 12 150 228 2150 490.2 0.89 436.3


300
100

CU2 10 180 12 33900 406.8 0.62 252.2


16850
250

CU3 10 180 95 2200 209 0.62 129.6


850

CU4 16850 10 180 12 16850 202.2 0.62 125.4

Total 943.5

Approach Slab
100
100

AS1 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS2 9900 12 150 24 10100 242.4 0.89 215.7


100
100

AS3 3400 12 150 67 3600 241.2 0.89 214.7


100
100

AS4 9900 12 150 24 10100 242.4 0.89 215.7

Total 860.8
Total for Two Approach Slab 1721.6

Crash Barrier (Type:- CB-1)


928

575
C1 16 125 81 2032 164.592 1.58 260.1
225

304
915

C2 16 125 81 1415 114.615 1.58 181.1


500

C3 16 11 9960 109.56 1.58 173.1


9960
Total of 10 m 614.3 0.06143
For 25.12m Length 1543.12

Crash Barrier (Type:- CB-2)

575
C1 16 8 2205 17.64 1.58 27.9
250

555
915

C2 16 16 1645 26.32 1.58 41.6


730

C3 16 12 960 11.52 1.58 18.2


960
Total of 1 m 87.7
For 0m Length 0.00

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-24


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Box Culvert

Detailed Estimate of Box Culvert 5 m x 2 m


Crash Barrier (Type:- CB-3)
For 0m Length 0.00

Crash Barrier (Type:- CB-4)


For 0m Length 0.00

Wing Wall
1400 to

S1 16 200 41 2380 97.58 1.58 154.20


2050

650

100
2500 to

S2 16 200 41 3900 159.9 1.58 252.60


3800

650

100
2500 to

S3 12 200 41 3900 159.9 0.89 142.30


3800

650

S4 10 250 14 8080 113.12 0.62 70.10


8080
S5 10 250 14 8080 113.12 0.62 70.10
8080
100
100

F1 1800 to 3200 12 250 33 2700 89.1 0.89 79.30

F2 10 250 11 8080 88.88 0.62 55.10


8080
100
100

F3 1800 to 3200 12 250 33 2700 89.1 0.89 79.30

F4 10 250 11 8080 88.88 0.62 55.10


8080
F5 0 6 0 0 0 0.00
0
Total 958.10
Total for Four Wing Wall 3832.400 Mt
Total Rebar 12.787 Mt

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-25


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

300 x 300

3.50 m

360 0.25 m
0.30
m

2000 280
0.30 m 155

5000 480

205
420
400 255
75

Assumptions:
Box Culvert with Internal Cell Size = 5 m x 2 m Road Width (W)= 10000 mm
Clear Width (a)= 5000 mm Top Slab Central Opening = 0 mm
Clear Height (b)= 2000 mm
Side Wall Thickness (c)= 280 mm Depth of PCC on Bottom Slab= 100 mm
Top Slab Thickness (d)= 360 mm Depth of PCC on Other Components= 75 mm
Bottom Slab Thickness (e)= 420 mm Depth of Stone Soling= 150 mm
Fillet (f)= 300 x 300 mm Depth of Flexible Apron= 1.00 m
Length of Crash Barrier, CB-1= 25.12 m Width of Curtain Wall Stem= 0.25 m
Length of Crash Barrier, CB-2= 0.00 m Depth of Curtain Wall Stem, U/S= 1.60 m
Length of Crash Barrier, CB-3= 0.00 m Depth of Curtain Wall Stem, D/S= 2.10 m
Length of Crash Barrier, CB-4= 0.00 m Width of Curtain Wall Footing= 1.00 m
Length of Rigid Apron, AL= 5.00 m Depth of Curtain Wall Footing= 0.40 m
Width of Rigid Apron at Start, AW-1= 5.00 m
Width of Rigid Apron at Start, AW-2= 15.00 m Wing Wall Length, U/S= 7.07
Length of Curtain Wall U/S, CWL-1= 17.00 m Wing Wall Length, D/S= 7.07
Length of Curtain Wall D/S, CWL-2= 17.00 m Wing Wall End Length= 1.00
Length of Flexible Apron U/S, GWL-1= 4.00 m Wing Wall Start ht= 3.50
Length of Flexible Apron D/S, GWL-2= 6.00 m Wing Wall End ht= 2.20
Length of Aproach Slab= 3.50 m
Depth of Aproach Slab= 0.25 m
Height of Corbel Rectangle= 0.30 m
Height of Corbel Traingle= 0.30 m
Width of Corbel= 0.30 m

SOOSUNG/ERMC/TSE Detailed Estimate_Box Culvert-26


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Pipe Culvert

Summary Sheet for Quantity of 90 dia and 60 dia Pipe Culvert

Quantity for One Total Quantity


Item No of Pipe Culvert Total Quantity Unit Remarks
Description Pipe Culvert of works
No.
90 dia 60 dia 90 dia 60 dia 90 dia 60 dia
1 Excavation for Structures Foundation Earth work
in excavation of foundation of structures in all
types of soil, including construction of shoring and
bracing, removal of stumps and other deleterious
matter and backfilling with approved Material, all
complete as per design drawings, technical 26.01 20.11 34.00 6.00 884.22 120.67 1,004.89 Cum
specification and to the satisfaction of Engineer.
[SS/SP 900]

2 Providing and placing machine mixed Cement


Concrete in M15/40 for PCC works including form
works, compaction, curing, testing, all complete, as
per specification, drawing and instruction of 13 9.26 34.00 6.00 434.75 55.54 490.29 Cum
Engineer. (SS-2000)

3 Providing and Laying Reinforced Cement Concrete


NP3 Flush jointed Pipe for Culverts including fixing
with cement mortar 1:2, all complete, as per
specification, drawing and instruction of Engineer.
(SS-701)

a 90 dia Hume Pipe 10 34.00 340.00 0.00 340.00 Rm


b 60dia Hume Pipe 10.00 6.00 0.00 60.00 60.00 Rm

4 Random Rubble Masonry: Providing and laying of


Stone Masonry Work in Cement Mortar 1:4 in
Foundation, all complete as per design drawings,
technical specification and to the satisfaction of 15.05 12.33 34.00 6.00 511.55 73.95 585.50 Cum
Engineer. [SS/SP 2600]

5 Providing and laying of Stone


Soling/Pitching/Packing Works for levelling in line
and level, all complete as per design drawings,
technical specification and to the satisfaction of 4.64 3.59 34.00 6.00 157.77 21.52 179.29 Cum
Engineer. [SS/SP 2600]

SOOSUNG/ERMC/TSE Detailed Estimate_Pipe Culvert-27


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Pipe Culvert

Detailed Estimate of Pipe Culvert of Dia 900 mm


Item No. Description No Length Breadth Height Area Quantity Unit Remarks
1 Excavation for Structures Foundation Earth
work in excavation of foundation of structures
in all types of soil, including construction of
shoring and bracing, removal of stumps and
other deleterious matter and backfilling with
approved Material, all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]

Central Portion 1 8.22 3.10 0.45 11.47


Head Wall 2 3.10 0.89 0.75 4.14
Wing Wall U/S 2 1.73 1.11 0.75 2.88
Wing Wall D/S 2 1.73 1.11 0.75 2.88
Floor Apron, U/S 1 1.50 3.97 0.30 1.78
Floor Apron, D/S 1 1.50 3.97 0.30 1.78
Shear key U/S 1 3.97 0.45 0.30 0.54
Shear key D/S 1 3.97 0.45 0.30 0.54
Total 26.01 Cum

Providing and placing machine mixed Cement


Concrete in M15/40 for PCC works including
form works, compaction, curing, testing, all
2 complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Central Portion 1 8.22 3.10 0.45 11.47


Head Wall 2 3.10 0.89 0.10 0.55
Wing Wall U/S 2 1.73 1.11 0.10 0.38
Wing Wall D/S 2 1.73 1.11 0.10 0.38
Total 12.79 Cum

Providing and Laying Reinforced Cement


Concrete NP3 Flush jointed Pipe for
Culverts including fixing with cement mortar
3 1:2, all complete, as per specification, drawing
and instruction of Engineer. (SS-701)

1 10.00 10.00 Rm

4 Random Rubble Masonry: Providing and


laying of Stone Masonry Work in Cement
Mortar 1:4 in Foundation, all complete as per
design drawings, technical specification and to
the satisfaction of Engineer. [SS/SP 2600]

Head Wall 2 3.10 0.67 2.10 8.72


Wing Wall U/S 2 1.73 0.80 1.55 4.32
Wing Wall D/S 2 1.73 0.80 1.55 4.32
Deduction
Head Wall -2 1.30 0.67 1.33 -2.31
Total 15.05 Cum

1 Providing and laying of Stone


Soling/Pitching/Packing Works for levelling
in line and level, all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2600]

Floor Apron, U/S 1 1.50 3.97 0.30 1.78


Floor Apron, D/S 1 1.50 3.97 0.30 1.78
Shear key U/S 1 3.97 0.45 0.30 0.54
Shear key D/S 1 3.97 0.45 0.30 0.54
Total 4.64 Cum

SOOSUNG/ERMC/TSE Detailed Estimate_Pipe Culvert-28


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Length of Pipe Culvert 10 Soling 0


Diameter of Pipe 0.9 PCC 0.45
Thickness of Pipe 0.2 Riprap Dep 0.3
Side Width 0.9 Shear Key 0.3
Height of Head Wall 2.1 Rpron Leng 1.5
Head Wall Top Width 0.45 Wing Wall 1.73
Head Wall Bottom Width 0.89
Depth of Shear Key

SOOSUNG/ERMC/TSE Detailed Estimate_Pipe Culvert-29


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Project Preparatory Consultant under SASEC Highway Improvement Project


Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH

Type : Pipe Culvert

Detailed Estimate of Pipe Culvert of Dia 600 mm


Item No. Description No Length Breadth Height Area Quantity Unit Remarks
1 Excavation for Structures Foundation Earth
work in excavation of foundation of structures
in all types of soil, including construction of
shoring and bracing, removal of stumps and
other deleterious matter and backfilling with
approved Material, all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]

Central Portion 1 8.22 2.20 0.45 8.14


Head Wall 2 2.20 0.89 0.75 2.94
Wing Wall U/S 2 1.73 1.05 0.75 2.72
Wing Wall D/S 2 1.73 1.05 0.75 2.72
Floor Apron, U/S 1 1.50 3.07 0.30 1.38
Floor Apron, D/S 1 1.50 3.07 0.30 1.38
Shear key U/S 1 3.07 0.45 0.30 0.41
Shear key D/S 1 3.07 0.45 0.30 0.41
Total 20.11 Cum

Providing and placing machine mixed Cement


Concrete in M15/40 for PCC works including
form works, compaction, curing, testing, all
2 complete, as per specification, drawing and
instruction of Engineer. (SS-2000)

Central Portion 1 8.22 2.20 0.45 8.14


Head Wall 2 2.20 0.89 0.10 0.39
Wing Wall U/S 2 1.73 1.05 0.10 0.36
Wing Wall D/S 2 1.73 1.05 0.10 0.36
Total 9.26 Cum

Providing and Laying Reinforced Cement


Concrete NP3 Flush jointed Pipe for
Culverts including fixing with cement mortar
3 1:2, all complete, as per specification, drawing
and instruction of Engineer. (SS-701)

1 10.00 10.00 Rm

4 Random Rubble Masonry: Providing and


laying of Stone Masonry Work in Cement
Mortar 1:4 in Foundation, all complete as per
design drawings, technical specification and to
the satisfaction of Engineer. [SS/SP 2600]

Head Wall 2 2.20 0.67 1.90 5.60


Wing Wall U/S 2 1.73 0.77 1.45 3.89
Wing Wall D/S 2 1.73 0.77 1.45 3.89
Deduction
Head Wall -2 1.00 0.67 0.79 -1.05
Total 12.33 Cum

1 Providing and laying of Stone


Soling/Pitching/Packing Works for levelling
in line and level, all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2600]

Floor Apron, U/S 1 1.50 3.07 0.30 1.38


Floor Apron, D/S 1 1.50 3.07 0.30 1.38
Shear key U/S 1 3.07 0.45 0.30 0.41
Shear key D/S 1 3.07 0.45 0.30 0.41
Total 3.59 Cum

SOOSUNG/ERMC/TSE Detailed Estimate_Pipe Culvert-30


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Length of Pipe Culvert 10 Soling 0


Diameter of Pipe 0.6 PCC 0.45
Thickness of Pipe 0.2 Riprap Dep 0.3
Side Width 0.6 Shear Key 0.3
Height of Head Wall 1.9 Rpron Leng 1.5
Head Wall Top Width 0.45 Wing Wall 1.73
Head Wall Bottom Width 0.89
Depth of Shear Key

SOOSUNG/ERMC/TSE Detailed Estimate_Pipe Culvert-31


SASEC Highway Improvement Project East-West Highway Kakarbhitta - Laukahi Sector

Name of Works and Location: Upgrading Kakarbhitta-Laukahi (Ch 45+000~85+000) Section of EWH
Ladder on the embankment
For 1 m Length
S. No. Description of works Unit No Length Width Height Quantity Remarks
1 Excavation for Structures Foundation Earth work in
excavation of foundation of structures in all types of
soil, including construction of shoring and bracing,
removal of stumps and other deleterious matter and
backfilling with approved Material, all complete as per
design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]
Cum 1 1.5 0.3 0.450
Additional quantity 40 10 400.000
2 Providing and laying of Stone Soling/Pitching/Packing
Works for levelling in line and level, all complete as
per design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2600]
Cum 1 1.5 0.15 0.225
Additional quantity 40 5 200.000
3 Providing and placing machine mixed Cement
Concrete in M15/40 for PCC works including form
works, compaction, curing, testing, all complete, as per
specification, drawing and instruction of Engineer. (SS-
2000)
Cum 1 1.5 0.15 0.225
1.5 0.021 0.032
Total PCC 0.257
Additional Quantity 40 5 200.000
4 Providing and laying Brick Masonry Work in 1:4
Cement mortar in structure complete, all complete as per
design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2500]
Cum 40 25 1000.000

Quantity for 1 m Total


S.No For Total 30 No Length length Quantity
1 Excavation for Structures Foundation Earth work in
excavation of foundation of structures in all types of
soil, including construction of shoring and bracing,
removal of stumps and other deleterious matter and
backfilling with approved Material, all complete as per
design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]
Cum 120 15 0.450 810.00
Additional quantity 400.00
Total 1210.00
2 Providing and laying of Stone Soling/Pitching/Packing
Works for levelling in line and level, all complete as
per design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2600]
Cum 120 15 0.225 405.00
Additional quantity 200.00
Total 605.00
3 Providing and placing machine mixed Cement
Concrete in M15/40 for PCC works including form
works, compaction, curing, testing, all complete, as per
specification, drawing and instruction of Engineer. (SS-
2000)
Cum 120 15 0.257 462.37
Additional quantity 200.000
Total 662.38
4 Providing and laying Brick Masonry Work in 1:4
Cement mortar in structure complete, all complete as per
design drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2500]
Cum Total 1000.000

SOOSUNG/ERMC/TSE Detailed Estimate_Steps-32