California Methods For Installing Residential Underground Service 063927

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

UG-1: Services

Greenbook
EDM

Prepared by: MZGD

METHODS AND REQUIREMENTS FOR INSTALLING RESIDENTIAL


UNDERGROUND ELECTRIC SERVICES 0 − 600 V 063927
TO CUSTOMER-OWNED FACILITIES
Asset Type: Electric Distribution Function: Design

Issued by: Lisseth Villareal (LDV2) Date: 03−25−22

Rev. #24: This document replaces PG&E Document 063927, Rev. #23. For a description of the changes, see Page 7.
This document is also included in the following manual:
• Electric and Gas Service Requirements (Greenbook)
• Electric Design Manual
Purpose and Scope
This document shows the methods and requirements for installing PG&E-owned, underground service cables in
customer-owned, residential, terminating facilities. See Document 058817 for terminating underground services.
General Information
1. Underground electric service laterals are normally installed in a PG&E service trench or in a joint trench with
natural gas and communication service facilities.
2. To determine the most satisfactory meter location, PG&E should be contacted for requirements while the
building is in the planning stage.
3. When it is necessary to install a service 75 feet or longer, the applicant must contact PG&E before ordering
the service riser, conduit, or termination enclosure. If the service riser and/or conduit specified in Table 3 on
Page 5 of this document will not accept the cable required to meet flicker and/or voltage drop requirements, a
larger conduit must be installed. This could require the installation of a larger termination enclosure.
4. Install a splice box whenever cable pulling tensions may be exceeded or whenever there is a change in cable
or conduit size.
5. Ensure that any new installed secondary distribution cable is not smaller, either in size or in number of runs,
than the largest new service that is on the load side of that new secondary system. For example, if the largest
service required will be 1−350 Al, then the secondary must be a minimum of 1−350 Al. The existing
secondary distribution system can remain as is if it can adequately supports any new services without causing
loading, voltage drop, and voltage flicker issues.
Residential Services Information
6. A ‘‘residential service’’ is a service supplying a single or multi-metered residential building. This document
addresses services through 600 amp, single-phase for 120/240 V. For three-phase residential services or services
larger than 600 amp, see Document 063928. Single-phase main service switches must not exceed 225 amps for
120/208 V services.
A. Standard voltage for single metered residential building is 120/240 V.
B. All single-phase, 120/208 V services require full-sized neutral.
C. 800 amp single phase services are not allowed. 800 amp rated services and larger must be three-phase, and
terminate in pad-mounted switchgear.
7. Minimum service requirements.
A. Install the number and size of conduits as shown in Table 3 on Page 5, based on the main service panel
rating. No more than seven service conduits, of any size, will be supplied from any one transformer.
B. Install the number and size of conductors, as shown in Table 3 on Page 5, to meet the individual initial
demand load. Take load characteristics and growth into consideration.
C. It is permissible to install a smaller transformer and fewer conductors to serve a long term initial load with the
intent of installing a larger transformer and additional conductors should future load increase occur.

Rev. #24: 03−25−22 063927 Page 1 of 7


UG-1: Services Methods and Requirements for Installing Residential
Greenbook Underground Electric Services 0 − 600 V
EDM to Customer-Owned Facilities
D. Always size the transformer pad to accommodate the largest transformer size necessary to serve the
combined ampacity of all services. Never exceed more than seven sets of conductors per transformer.
E. Vacant ducts, if any, are to be used to serve future load increases.
8. Residential design includes mobile home and mobile home parks parks that are individually metered and not
master−metered. For mobile home park design requirements see Document 052521, “Electrical Service
Requirements for Mobile Home Developments”.
9. Conduit is required for residential services, including multi-metered residential buildings.
10. The applicant must provide the trench, conduit, and backfill in accordance with Electric Rule 16 and PG&E
requirements. PG&E will furnish and install the service cables and make the connection at the point of service
delivery in the applicant’s service termination enclosure.
Qualification of material for use as backfill is the responsibility of the job foreman or, in the case of contract work, the
inspector or their designer. A visual inspection of the material is sufficient for evaluation of the material. The source of
the backfill, native or import, is immaterial to the suitability of the backfill for use in the trench. In new construction
areas, the developer may be required to have a soils report available, which will assist in determining if import backfill
is necessary.
11. Soil compaction must meet PG&E’s and any applicable federal, state, county, and local requirements. PG&E
specific soil compaction requirements are as follows:
A. Trenches that run across or along public roads and streets in the franchise areas must have soil compacted to
a minimum of 95% density.
B. Trenches that run across private properties and in all other areas must have soil compacted to a minimum of
90% density.
C. A compaction test report may be required by PG&E. This report must include the testing company information:
Name, Address, Contact information.
12. Service conduits installed through or under the applicant’s building foundation/slab must not exceed 20’ past
the outside wall of the building and must terminate into the electrical room. See Figure 4 in Page 6. The
installation requirements and conduit types for PG&E’s service conductors used in this application must be as
indicated below;
A. Conduits must not pass under or through one building to supply adjacent buildings.
B. UL651 approved PVC Schedule 40 or 80.
C. Galvanized Rigid Steel (GRS). GRS conduit is required when the conduit will be exposed, installed along walls
and low clearance ceilings, and may be subject to damage from vehicles, machinery, or tools.
13. To avoid cable insulation damage, the ends of conduits must be provided with a suitable fitting, such as a
bushing, hub, or end bell.
14. When an applicant’s main service panel is installed in an electric meter and service termination room, the room
must be built with one wall and a door that leads to the outside of the applicant’s building. See Greenbook
Section 5.3.4. Electric Meter Rooms.
15. When service terminations/connections are made at the customer termination can or pull section, whether the
service is left energized or de-energized,
A. Cover and seal all meter sockets with an approved blank-off cover (Pie Plate) or set the electric meter(s).
Material codes for electric meter socket covers are M249424 and M249559.
B. Seal all seal-able covers on the customer owned panel using PG&E approved seals.
16. Potential water intrusion into service conduits and meter termination facilities.
A. Water intrusion into service conduits and meter termination facilities may occur if the source side of the
service facilities (e.g., secondary splice box) is at an elevation greater than the meter termination facilities.
B. CPUC General Order 128, Rule 31.6 requires “Lateral ducts for services to buildings, through which water
may enter buildings, must be plugged or sealed at the customer meter panel and at the source end of the
service conduit.”
C. When the intrusion of water into the service and metering equipment can be reasonably expected through lateral
ducts, the conduits must be sealed at both ends using one of the PG&E approved sealing method shown in
Document 062288.

063927 Page 2 of 7 Rev. #24: 03−25−22


Methods and Requirements for Installing Residential UG-1: Services
Underground Electric Services 0 − 600 V Greenbook
EDM
to Customer-Owned Facilities
D. If the meter termination facilities are significantly lower than the source side facilities, use the Rayflate Duct
Sealing System (RDSS) conduit sealing system listed in Document 062288.
E. The applicant is responsible for providing a means to prevent the accumulation of excess water pressure in
the service conduit system. This is accomplished by the following methods:
(1) For wall-mounted service and metering equipment install an enclosure, outside, at the base of the riser to
the meter panel, or at a maximum of 6 feet away from the meter panel along the service run.
(a) Install a 26” deep #2 enclosure, and enter through the short walls making sure to maintain the 18”
minimum depth from finish grade to the top of the conduit. See Figure 1 on Page 3.
(b) Install the enclosure on a twelve-inch base of one-inch rock to aid in the drainage of the unwanted
water, align the conduits at either end to achieve a nearly straight through pull and install end bell
fittings on all conduits.
(c) Seal both ends of the service conduit from the drain enclosure to the customer meter panel.

18” Min.

2” to 4” 2” to 4”

12” high, 1” rock base

Figure 1
Conduit Installation in a Drain Box
(2) For indoor electric meter rooms below grade level, a reliable method of water mitigation and drainage
must be incorporated into the design of the meter room(s) to prevent the accumulation of water.
17. Prior to cable installation, all conduits must be proven free and clear by means of a mandrel or other methods
acceptable to PG&E. A polyester flat pulling tape, white with sequential footage markings every foot,
2,500 minimum tensile strength, and approved by PG&E (Code M560154), must be installed in all conduits and
attached to an end cap (see Document 063928).
Upgraded Panel
18. For upgraded panels where the new specified size of service conductor will fit in the existing conduit, it is not
necessary to upgrade the conduit to the currently specified size and number for the new panel if all of the
following are met:
A. The maximum conduit fill ratio is not exceeded.
B. The calculated cable pulling tensions along the conduit route is within limits of the new cable.
C. Copper or larger size of Aluminum cable is able to handle full load in existing number of conduits. See Table 1
below.
Table 1 Service Cable Size Allowed in Existing Conduit When Upgrading Panels
New Upgrade Minimum Aluminum or Copper Cable
Existing Service Required to Serve Maximum
Service Allowed Existing
Equipment Load AWG or kcmil1
Equipment Conduit Size
Rating (amps)
Rating (amps) and Number (Per Phase) Neutral
100−125 200−225 1−2” 1−4/0 Al 1−1/0 Al
200−225 320 1−3” 1−350 Al 1−4/0 Al
320 400 1−3” 1−750 Al 1−4/0 Al
400 600 1−4” 1−1000 Al2 1−350 Al
1 Mixing Aluminum and Copper cable runs for the same service is not allowed.
2 Center conduit underneath middle hot leg to allow flexibility to terminate the conductor.

Rev. #24: 03−25−22 063927 Page 3 of 7


UG-1: Services Methods and Requirements for Installing Residential
Greenbook Underground Electric Services 0 − 600 V
EDM to Customer-Owned Facilities

19. If the new panel is able to accommodate it, the existing service conductor may be reused provided it meets the load,
voltage drop, and flicker requirements of the new load. If the service conductor size must be upgraded, the existing
conduit must be proofed with a mandrel.
20. For existing panels that are less than 36” horizontally away from the gas service riser, it is allowed to use the existing
service conduit and extend new conduit of the same size and material to a new panel location that is 36” or more
away from the gas riser as long as all the parameters listed in Notes 18, 19, 20, and 21 are met.
A. For service runs that approach the front of the existing panel, directly or at an angle, the new conduit will need
to start back along the existing conduit and far enough away from the new panel location to minimize
additional bends in the conduit system.
B. The new total number of bends must be within the maximum 315° allowed for service conduit run. For further
information refer to Document 038193.
C. The new panel must be relocated no more than 20’ away from the existing panel.
21. For upgraded panels, splice boxes are not allowed on private property to accommodate customers’ existing
services. Service cable needs to be brought up to our current standard conduit service system from the
customer meter to PG&E point of secondary distribution.
22. Notes 18, 19, 20, and 21 do not apply to the following conditions:
A. Direct buried or Cable-In-Conduit (CIC) service cables. Direct buried and CIC service cables must be replaced
with approved service cable and installed in approved service conduit.
(1) Splice boxes between the customer panel, with existing DB or CIC cable, and PG&E secondary
distribution system are not allowed. See Note 22 above.
B. Upgraded electric meter panels that are within 36 inches of the gas service riser. The clearance requirements
in Greenbook Section 5.4.3., “Meter Set Clearance Requirements” must be met for upgraded and relocated
meter panels.
C. New upgraded panels with a Service Equipment Rating (amps) that is more than one upgraded size than the
existing panel, as specified in Table 3 on Page 5. For example, if an existing panel less than or equal to
100 amps is upgraded to a 400 amp panel instead of a 200 amp panel.
D. If the existing cable size is more than one size smaller than the cable required to serve maximum load for the
new panel, as specified in Table 3 on Page 5. For example, if the existing cable is #2 AWG aluminum and
new upgraded panel requires 4/0 aluminum.
Cover
23. A minimum of 24 inches of cover for secondary (0 - 750 V) electric service, or 36 inches minimum cover for
primary (over 750 V) is required. Cover is the distance from the outer surface of an underground facility to the
top of the final grade. The actual trench depth will be greater (approximately 30 inches or 42 inches minimum
respectively) to accommodate the underground facility, bedding, enclosures, riser sweeps, and joint trench
installations with other utilities.
Temporary Service
24. The policy of using permanent service panels to supply temporary power is expanding. Schedule 40 or 80
PVC riser conduit may be damaged by staples and nails, and this has resulted in damage to service cables.
Therefore, for those locations where cable will be installed or that will be energized prior to completion of the
wall, the conduit must be Schedule 40, rigid steel conduit, to protect the service cables from damage caused
by siding nails, etc. Refer to Greenbook Section 5.9.1., “Temporary Service Using Permanent Service Panels”.
Table 2 Service Conduit Types Approved for Underground Application
Specification 3
Type
(must be marked on conduit)
Hot-Dip, Galvanized, Rigid Steel ANSI Spec. C80.1
PVC, Co-extruded Cellular Core PVC, Schedule 40 or 80 UL 651, or ETL conforms to UL 651
3 The entire “conduit system” must meet the specifications listed above. The conduit system includes conduits, conduit
bends, conduit fittings or couplings and all related components (e.g., end bells and cable protectors) that are needed
to install PG&E cables and conductors.

063927 Page 4 of 7 Rev. #24: 03−25−22


Methods and Requirements for Installing Residential UG-1: Services
Underground Electric Services 0 − 600 V Greenbook
EDM
to Customer-Owned Facilities

Table 3 Service Conduit Types Approved for Underground Application Cable and Conduit Requirements
for Residential Services
Aluminum Cable Required
Service Equipment Conduit Size Minimum Minimum to Serve Maximum Load
Rating (amps) 1 and Number 2 Vertical Horizontal AWG or kcmil 6
Radius Radius
(Per Phase) Neutral
100−125 1−2” 24” 36” 1−1/0 1−#2
200−225 1−3” 24” 36” 7 1−4/0 1−1/0
320 3 1−3” 24” 36” 7 1−350 1−4/0
400 4, 5 1−4” 36” 36” 1−750 1−4/0
600 4, 5 2−3” 24” 36” 7 2−350 2−4/0
1 Service rating must be the termination section, pullcan, service section, or main service switch continuous current
rating, whichever is greater.
2 See Note 3 on Page 1 for size and distance limitations, Note 12 on Page 2 for conduit type allowed on or within
buildings, and Table 2 above for conduit type allowed underground.
3 Require manual bypass facilities.
4 Require transformer rated meter.
5 Requires two bolt terminations and cable to spade connectors. Lay-in lugs are not allowed.
6 Cable size shown in Table 3 is the minimum size cable that must be used.
7 Available only on 90 degree bends.

Service Installation
Notes
1. A Vertical 90° manufactured sweep is required to be installed to meet trench grade. The riser conduit must not
protrude away from the wall or mounted panel.
A. Couplings on the riser conduit installed inside the building foundation must be no higher than flush with the top
of the concrete. Couplings installed outside building foundation must be installed a minimum of 6” below final
grade.
2. The conduit end must extend at least 12 inches away from the foundation. Install the sweep in the direction of the
service trench. If a deeper trench is required, the sweep must extend to the same depth as the conduit in the
trench.
3. A minimum of 24 inches of cover must be maintained from the top of conduit to final grade.
4. See Greenbook Section 5.4.3. for electric service and metering room requirements.
5. See Greenbook Section 3.2.2. for establishing PG&E and applicants underground electric service responsibilities.

Rev. #24: 03−25−22 063927 Page 5 of 7


UG-1: Services Methods and Requirements for Installing Residential
Greenbook Underground Electric Services 0 − 600 V
EDM to Customer-Owned Facilities
Service Installation (Continued)

Outer
Building Wall 48” Min.
48” Min. 66” Preferred
66” Preferred Conduit Strap 75” Max.
75” Max. installed at
Outer Mid-Distance between
Coupling Building Wall End of Meter and Final
Final Grade Building Grade
Building
Foundation
Foundation
Final
24” Min. 6” Min.
Grade
24” Min.
Coupling

12” Coupling
12” Coupling
Min. Min.

Figure 2 Figure 3
Recessed-Mounted Service Termination Enclosure Surface-Mounted Service Termination

Outer Building Wall

Switchboard

Inner Building Wall

Cable Termination
Compartment (side view)

To Customer’s Indoor
Termination Enclosure
Up to 20’ Beyond the
Building Outside Wall
Final Grade
Building Foundation

24” Min. Coupling Coupling

Full 90° Bend required


Figure 4
Indoor Service Termination and
Metering Enclosure in Electric Room

063927 Page 6 of 7 Rev. #24: 03−25−22


Methods and Requirements for Installing Residential UG-1: Services
Underground Electric Services 0 − 600 V Greenbook
EDM
to Customer-Owned Facilities
References Location Document
Secondary Electric Underground Enclosures . . . . . . . . . UG-1: Enclosures/Greenbook . . . . . . . . . . . . . . . . 028028
Minimum Requirements for the Design and
Installation of Electric Conduit, Insulated Cable,
and Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . UG-1: General/Greenbook . . . . . . . . . . . . . . . . . . . 038193
Electrical Service Requirements for Mobile Home
Developments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Greenbook/EMWP . . . . . . . . . . . . . . . . . . . . . . . . . 052521
Terminating Underground Electric Services
0−600 Volts in Customer-Owned Facilities . . . . . . . . . UG-1: Services/Greenbook . . . . . . . . . . . . . . . . . . 058817
Underground Conduits . . . . . . . . . . . . . . . . . . . . . . . . . . . . UG-1: Conduits/Greenbook . . . . . . . . . . . . . . . . . . 062288
Methods and Requirements for Installing
Non-Residential Underground Electric Services
0−600 Volts to Customer-Owned Facilities . . . . . . . . . UG-1: Services/Greenbook . . . . . . . . . . . . . . . . . . 063928

Revision Notes
Revision 24 has the following changes:
1. Updated Note 5 on Page 1.
2. Revised Note 6 on Page 1 to add limit to single-phase service for 120/200V.
3. Modified Note 7A on Page 1.
4. Added compaction requirements to Note 10 on Page 2.
5. Modified Note 11 on Page 2.
6. Moved section of what used to be part of Note 12 to new Note 13 on Page 2.
7. Added new Note 15 on Page 2.
8. Re−structured Note 16 on Page 2.
9. Added Note 18C on Page 3.
10. Added new Figure 1 on Page 3.
11. Added new Table 1 on Page 3.
12. Added new Notes 20 and 21 on Page 4.
13. Added Note 22A1 on Page 4.
14. Added Note 1A under Service Installation on Page 5.
15. Modified Figures 2, 3, and added Figure 4 on Page 6.
16. Moved Reference sections to the end of the document before Revision notes on Page 7.
17. Added document 038193 to Reference Section on Page 7.

Rev. #24: 03−25−22 063927 Page 7 of 7

You might also like