Gate - Civil Engineering: Concrete Structures (RCC & PSC) Construction Materials and Management
Gate - Civil Engineering: Concrete Structures (RCC & PSC) Construction Materials and Management
Activity 5 – 6
LFT = TL
EST = TE
LST
EFT
18 28 30 40
C (18;30)
5 6
12 (28;40)
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 16
Maximum Available time
Interfering Float
(EST)j = TEj
(EFT)i TLj
10 22 32 46
TE= 10
TE= 32
10 11 14 15
TL= 18 12
TL= 46
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 17
Maximum Available time
Minimum Available time
Free Float, FF
Tail slack Si
FID tij
Activity 10-11
Activity 11-14
Activity 14-16
TEi
TLi
TEj
TLj
10 18 20 32 46
TE= 10 TE= 32
10 11 14 15
TL= 18 12
TL= 46
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 18
2. Free Float
• It is defined as the amount of time by which an activity can be delayed without
affecting the EST of succeeding activity.
• It is that portion of total float that can be used by an activity without delaying any
succeeding activity.
Free Float for i-j FF = TE j – (TE i + tij )
FF = EST of successor activity (j-k) – activity EFT of present Activity i – j
FF = FT –Sj
where. Sj = slack for event or slack of head event of activity i-j
TE i TE j TE k
i j k
tij
TL i TL j TL k
• Free float is the amount of time an activity can be delayed without affecting the
commencement of a subsequent activity at its EST, but may affect the float of a
previous activity.
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 19
3. Independent Float
• It is the amount of time by which an activity can be delayed when all the preceding
activities are completed as late as possible and all succeeding activities started as
early as possible.
• Independent float is the excess of minimum available time over the required activity
duration.
• If activity c-d is under consideration, and activity b-c finish as its latest possible time
TLi and succeeding activity j-k start at its earliest time TEj
Difference between (TEj – TLi) and tij is known as Independent float for activity i-j
Independent float for i-j,
FID = (TE j – TL i ) – tij
FID = FF –Si
where Si is the slack for event i or slack for tail event of activity i – j
• Independent float doesnot affect the float of preceding and the succeeding activities
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively
a. 0.25 and 1 b. 1 and 1 c.B.0Jayarami
Prof. and 0 Reddy d. 81 and 0
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 30
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 31
Ans. c
Path Duration
A-B-C-E-F-J-K-L 1+7+30+25+7+7+3+1=81
A-B-C-Dummy-G-H-I-K-L 1+7+30+0+25+7+7+3+1=81
A-B-D-G-H-I-K-L 1+7+30+25+7+7+3+1=81
All the possible paths are critical and all activities are critical. Hence, total floats of
activities 5-7 and 11-12 are 0 and 0 respectively.
Ans. 7 to 7 (or) 11 to 11
Ans. 14 to 14
The minimum time (in days) for completion of the project is …..…
Ans. 39 to 40
0.882
6 6 6 6
Let Sj be the length of the shortest path from P to node j. Which of the following
equations can be used to find SG? ME 2008
a. SG Min SQ , S R
b. SG Min SQ dQG , S R d RG
c. SG Min SQ dQG , S R d RG d. SG Min dQG , d RG
Ans. c
Prof. B. Jayarami Reddy
Y.S.R. ENGINEERING COLLEGE OF YOGI VEMANA UNIVERSITY, PRODDATUR
6/5/2020 58
Linked answer questions 20 and 21
Consider a PERT network for a project involving six tasks (a to f)
Expected task time Variance of the task time
Task Predecessor
(in days) (in days2)
a - 30 25
b a 40 64
c a 60 81
d b 25 9
e b,c 45 36
f d,e 20 9
a2 c2 e2 2f
25 81 36 9 151 days