Method Statement For Configuration of The TTP Substations in Scada in The RCC
Method Statement For Configuration of The TTP Substations in Scada in The RCC
CONSULTANT :
GOPA-INTERNATIONAL ENERGY CONSULTANTS GMBH-
GERMANY
CONTRACTOR :
CHINA ELECTRIC POWER EQUIPMENT AND TECHNOLOGY CO.,
LTD,
PROJECT :
Design, Supply and Installation of 400 kV Air Insulated
Substation (AIS) for Temane Transmission Project (TTP),
Lot 1
RCC SCOPE OF WORKS:
PHASE 1: SCADA INTEGRATION OF 5 NEW SUBSTATIONS
IN EXISTING RCC SCADA SYSTEM
CET-PRO-STE-001
CSD code:
T T P - 1 - K S O - S U - 5 1 3 0 - M - 0 3 4 - 0 0
Document Title METHOD STATEMENT FOR INSTALLATION OF RCC
SCADA CONFIGURATION FOR TTP SUBSTATIONS
Document CET-PRO-STE-001 Revision Number 00
Number Language English
IFU - Issued for Use Next Review Date 08/12/2023
Document
Status
This Revision
Document Tamele
Control
Review:
Authorized
Yu yang
Approver:
Revision History
Revie Revision Revision
Author Approver Status Description
wer Number Date
G. Mungwiro Yu Yang Rev.00 For approval New Doc
2
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA DATABASE AND HMI Issue Date: 06 Dec 2023
CONFIGURATION FOR THE TTP SUBSTATIONS
INTO RCC SCADA
Table of Contents
1 PURPOSE AND BASIC DESCRIPTION .................................................................................................................. 5
2 SCOPE, DELIVERY TO SITE, LOCATION OF WORKS ..........................................................................................5
2.1 Scope, Delivery To Site, Location Of Works .......................................................................................................5
2.2 Delivery Timeline ................................................................................................................................................ 5
2.3 RCC SCADA Database and HMI Installation: Task List .....................................................................................6
3 OBJECTIVES ............................................................................................................................................................ 7
4 DEFINITIONS ........................................................................................................................................................... 7
5 CONTRACTOR/SUBCONTRACTOR ROLES AND RESPONSIBILITIES ..............................................................9
6 CET MAIN RESOURCE ALLOCATION FOR RCC INSTALLATION .................................................................... 11
6.1 Proposed CET Personnel ................................................................................................................................. 11
Table 1 - Engineering Personal Allocated ........................................................................................................................................................ 11
7.2 Testing Phase:- Mimics, RTU Communication And Point-To-Point Tests ....................................................... 16
7.2.1 Testing Phase:- Mimic Tests ................................................................................................................................................................... 17
7.2.2 Testing Phase:- RTU Communication And Protocol Tests ......................................................................................................................18
7.2.3 Testing Phase:- RTU -SCADA DB Point-To-Point Tests ........................................................................................................................19
7.2.3.1 Digital Inputs Point-To-Point Tests ....................................................................................................................................................... 19
7.2.3.2 Analog Inputs Point-To-Point Tests .....................................................................................................................................................20
7.2.3.3 Command Output Point-To-Point Tests ............................................................................................................................................... 20
3
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA DATABASE AND HMI Issue Date: 06 Dec 2023
CONFIGURATION FOR THE TTP SUBSTATIONS
INTO RCC SCADA
4
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA DATABASE AND HMI Issue Date: 06 Dec 2023
CONFIGURATION FOR THE TTP SUBSTATIONS
INTO RCC SCADA
This method statement defines methods to be adopted for the implementation of Phase 1 of
the RCC Project Scope. There will be Hardware/Software replacement in this phase, just
the configuration of the RCC SCADA Database and HMI components to include the
mentioned Substations, and the necessary Point-to-Point Tests to verify the correct
integration of the Substations, allowing EDM to monitor and Control (where relevant) the
Substations from the RCC
5
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
1 Insertion of the Database and HMI Configuration into the Standby SCADA CET/EFACEC
Server at RCC
2 Startup the Standby Server, and force a commutation to make it ONLINE CET/EFACEC
3 Verify successful communication of SCADA with all existing Substation RTUs as CET/EFACEC
before, with correct Grid data updates as seen on Operator Workstations.
Also confirm that the off-site MV Server (CCD) is synchronized and serves the
MV-Room workstations with Login desktops for the Operators
4 Verify that the new TTP Substation RTU’s are visible in SCADA, and their CET/EFACEC
Communication status is correct.
5 If the Site (substation) installations have been completed, and the CET/EFACEC
Telecommunications Link is completed, verify that the communication is healthy
for the TTP Substations, one by one.
6 Verify that substation status data is updated correctly in SCADA, for each online CET/EFACEC
TTP substation. Checks should be made in both HMI and Data lists.
7 Insertion of the Database and HMI Configuration into the Main SCADA Server at CET/EFACEC
RCC, and start it up as OFFLINE. Confirm that it successfully
synchronizes/updates with the ONLINE Server.
8 If Tasks 5 & 6 are satisfied for each substation the SAT Point-to-Point tests to be CET/EFACEC at RCC,
carried out, checking every configured data point for correct status, value or &
operation (for Indications/Alarms, Measurements and Controls respectively). CET/NR on each
These tests will be done according to the annexed SAT Test Protocol. The substation site at a time.
results to be recorded in the Data lists to be attached to the SAT Protocol, (HITACHI to be on support
and at the end the SAT Protocol to be signed and approved by all parties or standby to guarantee
(Contractor/Sub-contractor, OE, Client). Any remarks, deviations or snags link availability)
to be agreed and noted, and resolution agreed as necessary.
6
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
3 OBJECTIVES
The objective of this method Statemnet is to guarantee the corrrect and smooth execution of
the task of insertion of the DB and HMI configurations into the RCC SCADA system, without
causing any unforeseen or prolonged shutdowns to the RCC Operations.
4 DEFINITIONS
5
Term Definitions
EDM’s Regional Control Centre (sometimes currently referred to as NCC,
RCC National Control Centre), situated in the EN2 road in the Maquinag district
of Maputo
The new Cabinet to be installed in the RCC under the scope of this project,
(HITACHI)
housing a 2 PABXs and an Network Management System Server (NMS)
TELECOMMUNICATIONS
for management and maintenance of the Grid Telecommunications
CABINET/PANEL
network.
Hitachi Company, Supplier of Telecommunications equipment and
HITACHI Energy engineering services, subcontracted under this project to supply and
configure the Telecomms equipment
EFACEC EFACEC Company, a Portuguese firm, manufacturer and supplier of the
EFACEC Automation SCADA system that is used in EDM RCC.
Systems With local presence in Mozambique
Human-Machine Interface, referring to the Hardware and associated
software running on it) used to present process data/information to the
HMI
human operator, and by which the Operator can interact with or make
interventions (controls) to the controlled process.
Supervisory Control and Data Acquisition / Energy Management System:
Suite of computer-based Application software, running on specialized
SCADA / EMS hardware and with remote Communication to process/sites, from where
data is acquired, and then processed and stored/presented to Operator for
process monitoring, and controls can be sent to the process.
An applications suite of SCADA/EMS software, in use at EDM RCC,
SCATEX engineered and supplied by EFACEC Automation Systems (Portugal)
7
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
8
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
POSITION
ROLE DESCRIPTION OF TASK
TITLE
CET Site Responsible for organizing on-site construction
Manager Ensuring the management
quality, safety, Responsible for on-site coordination and
progress of the management
construction Control the project quality technology, progress
and safety
Organize subcontractors to implement MS and
carry out construction according to work
procedures.
Monitor the Health, Safety, Environmental and
Social aspects at site.
Ensure the implementation of the CESMP and
Health Safety and Environmental standards.
Ensuring the Participate in the preparation of the method
CET Site
quality and statement.
Electrical
safety of the Verify that the wiring diagrams are correct, and
Engineer
construction that the installation and wiring are according to the
drawings.
Responsible for quality and technical management
Responsible for the implementation and inspection
of the method statement
Cooperate with Assist civil engineers in project quality control.
CET Site
the civil&- Keep construction records
Supervisor
electrical & Participate in engineering technology management
engineer and
OE to check and
record the
activities
CET Quality Ensure that the Supervise and inspect the installation quality.
9
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
POSITION
ROLE DESCRIPTION OF TASK
TITLE
Control procedures and Organize project quality acceptance and interact
Engineer methods of with OE.
quality control Collect and organize installation/wiring records,
are correct, and test reports and other papers.
check the
quality of
activities
CET Foreman Supervising Monitors the machinery activity and plans for the
timely arrival of personnel, materials, equipment
and services at the site.
For the organization, coordination and dispatch of
machinery and resources, the construction shall be
carried out according to the method statement.
Promote safety and environmental awareness
complying Mozambican legislation and WB
standards
10
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
1 Name
Company EFACEC
Designation
Specialisation
2 Name
Company EFACEC
Designation
Specialisation
11
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
Safety Safety
Gaiter Harness
12
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
a. Add to the system the remote terminal units for each of the following substations.
7.1.2 RCC SCADA: New and Edited Mimics for New TTP Substations.
a. Add to the system the Main and Detail Bay Mimics for the following sites.
i. Maputo 400kV substation upgrade
ii. Matalane 400/66 kV substation
iii. Chibuto 400/275 kV substation
iv. Vilanculos 400/110 kV substation
v. CTT Switchyard at Temane.
13
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
a. Work shall principally be carried out on the two SCADA Servers (one at a time),
located in the Server Room at the RCC.
b. The work can be performed from one of the offices allocated by EDM, and the
connection to the Servers will be over the Network.
c. It will only be necessary to go into the Server Room to perform manual switch-
overs between the Servers, when necessary.
d. The foreseen date for the Installation is 17 January, 2024, (subject to EDM
approval)
e. Actual start of Communications and Point to Point Testing (Section 7.2 below,
Testing Phase) will depend on TeleComms Scope (Installation, Cabling and
commissioning) both in RCC and in the substations, and the Transmission
network connecting to the substations, having been duly completed. Individual
Substations can be tested once the Communication is complete for that
substation, independent of the other substations.
14
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
15
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
a. The installation shall be made first in the Standby (OFFLINE) server, while
SCADA Services in the RCC continue to run on the ONLINE Server.
b. Only after the Standby Server successfully starts up with the new configuration,
will the SCADA system be stopped in the ONLINE server, forcing a commutation
to the newly configured Server.
c. It is during this step (Steps 5-7 in 7.1.4above) that SCADA Services shall ever be
stopped, while the newly configured Server acquires fresh data from all the RTUs
e. During this step all alarms will be regenerated because of the cold start.
The The following are the expected documents to be issued and used in the course of the
installation and commissioning works are:
4. AS23003433 – SAT Report for Phase 1 - a copy or section for each Substation.
Extracts of the latest versions of the following documents shall also be used, streamlined and
provisioned for marking the signals as they are checked.
16
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
In this section the focus is going to be in the navigation between mimics, links, filters, etc.
1. Confirm from Grid Electric mimic is possible to open each substation mimic.
4. In the substation mimic, confirm that is possible to open the detail mimic of each bay.
5. Confirm the filter functions are opening the correct windows (alarms, digitals lists and
analogs lists).
17
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
TeleComms: That disturbances in the RTU or Communications link status shall be reflected
as failure in communications with specific RTU, and the corresponding data shall be marked
accordingly.
2. We want to make sure EDM will provide the test workstation.In the Communications
mimic left click in this controlled station (RTU) Scan and select the option “INH” and
then “Execute”.
a) Confirm that the command is executed and the controlled station (RTU) is
Inactive – now there are no communications between the control center and the
substation. Confirm that an alarm appears, indicating that the scanning of this
substation is inhibited;
3. In the workstation confirm that the substation diagram is updated accordingly – all the
telemetered entities appear in white color, meaning that the RTU is off scan.
4. Restore the communications with the control station by executing the command
“ACT” in the RTU Communications diagram.
a) -Confirm that the substation diagram for this RTU is updated accordingly.
5. Shutdown the RTU at the remote site, or disconnect the communications channel.
b) Confirm that an alarm is generated stating the communication loss with the
substation RTU.
a) Confirm the system executes a general control and refreshes all the data-points
for that RTU.
18
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
1. To check that for each specified and configured data point, changes in remote plant
equipment status/values are correctly reflected in RCC SCADA HMI, Data lists,
Events, Alarms etc.,
2. In the case of Controls the RCC Operator can issue commands and the targeted
plant equipment shall be correctly maneuvered by such command.
Planned point-to-point testing and commissioning foreseen for each site is the following:
1. In the workstation open “Lists” and select the Digitals List for this substation.
a) In this list confirm that all telemetered digitals belonging to this RTU are valid.
2. In the workstation open “Lists” and select the Events List and Timetags List for this
substation.
3. On remote site, change the state of a digital input (directly in the equipment if
possible):
a) and confirm that the state in the workstation is updated accordingly both in the
digitals list and in the mimic diagram in cases where the entity is represented
there.
c) Confirm that the timetag list is updated accordingly, including correct time-stamp.
d) Confirm that in case there is an alarm configured for the new state, the alarm
state is also shown in the diagram representation of the equipment, and the
diagram representation blinks while the alarm is not accepted.
e) Confirm that alarms appear in the alarm list if the present digital state is
configured to generate an alarm.
4. Confirm that each event that is generated is recorded in the event log;
Repeat the testing from point number 1 for other digital inputs according to this
substation I/O list.
19
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
1. In the workstation open “Lists” and select the Analogs List for this substation.
a) In this list confirm that all telemetered analogue inputs belonging to this RTU are
valid.
2. In the RTU choose an analogue and force its value to be 0%, then 50% and finally
100% of its full-scale Engineering Value. In the workstation verify that these values
are updated accordingly both in the lists and diagram(s).
3. -When applicable, confirm that the alarms are generated in the workstation and
presented in the alarm list.
4. -Confirm that each event that is generated is recorded in the event log;
Repeat the testing from point number 1 for other analogue inputs according to this
substation I/O list.
1. In the workstation open “Lists” and select the Events and Timetag List for this
substation.
3. In the substation change the Local/Remote of the RTU to the Local state.
a) Confirm that a new event appears in the workstation event list indicating that the
substation is in Local command mode.
4. Try to send a control from the workstation to the RTU and confirm that the control is
disabled,
a) Confirm that an event appears in the workstation event list indicating the
substation is in Remote command mode.
6. In the substation diagram in the workstation open a control execution window for a
breaker.
7. In the workstation execute the control and confirm that the control is well executed in
the equipment.
Repeat the testing from point number 1 for other Controls according to this
substation I/O list;
20
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
21
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
22
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
employee is under the influence of alcohol or drugs may initiate a test. The request must be
made through team leader who will liaison with HSE Specialist to have the test conducted.
11.7 Incident Reporting
Although no Incidents of personnel injury are foreseen, the Sub-contractor will ensure that
identified incidents are reported, recorded, investigated and that all root causes and
contributing factors are identified within the site.
24
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
In the case of an environmental incident occurring, the incident area will be made
safe by controlling and containing the relevant substance or emission where it is
practicable to do so. Those involved must only control the incident scene to the level
that they are capable of.
In the event of a fatality or other serious incident the following members of CET senior
management team will be contacted as soon as possible and in all cases within 2 hours of
the incident:
o CET Project Manager
o CET HSE Specialist
o CET Site Manager
o Sub-contractor Project Manager
In the event of a fatality or other serious incident requiring statutory notification and
investigation, the scene of the incident and records of the initial response and
investigation shall be preserved.
All incidents involving injury, environmental harm and/or property damage and/or a
near miss are to be investigated as soon as possible following notification of the
occurrence.
11.9 Reporting and recording
Once an incident (injury) has occurred and any initial actions to make the area safe have
been implemented, those involved will report the incident to their relevant direct line
reporting, supervisor and/or Foreman, or Manager (if relevant) immediately taking into
account the following minimum requirements;
Incident details and classification
Immediate action(s) taken to make the area safe and prevent reoccurrence whilst the
investigation takes place (if applicable)
Witnesses (if applicable)
Injury/Illness details (if applicable)
Near miss details (if applicable)
Environmental details (if applicable)
Once the details are known the incident will be recorded on an Incident Notification Report
Form by the supervisor in charge or the HSE Officer and sent to the HSE Manager within the
shift of the occurrence.
Note:
Incident details are to be recorded within the shift in which they occurred and are to
be reported to the following personnel immediately as they are known;
o Site Manager/Subcontractor Supervisor / Foreman;
o Nurse (in the case of an injury incident);
o CET Site Engineer
o Contractor HSE Officer
25
METHOD STATEMENT FOR CET-PRO-STE-001
INSTALLATION SCADA
Issue Date: 06 Dec 2023
DATABASE AND HMI
CONFIGURATION FOR THE TTP Revision: 00
SUBSTATIONS INTO RCC SCADA
26