Scaffolding Schedule-To Be Done

The document contains details of scaffolding work including erection and removal of internal and external scaffolding. It lists 9 tasks with information on diameter, height, materials required, duration, planned and expected start and finish dates. It shows that most tasks are delayed compared to the planned schedule, with delays ranging from 1 to 22 days. A Gantt chart is also included showing the planned and expected timing of the 9 scaffolding tasks.

Uploaded by

Mohamed Rizwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
184 views4 pages

Scaffolding Schedule-To Be Done

The document contains details of scaffolding work including erection and removal of internal and external scaffolding. It lists 9 tasks with information on diameter, height, materials required, duration, planned and expected start and finish dates. It shows that most tasks are delayed compared to the planned schedule, with delays ranging from 1 to 22 days. A Gantt chart is also included showing the planned and expected timing of the 9 scaffolding tasks.

Uploaded by

Mohamed Rizwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Scope

703 Internal Scaffloding Erection 703-Internal Scaffloding Erection


510 External Scaffolding Erection 510-External Scaffolding Erection
703b Internal Scaffloding Erection 703b-Internal Scaffloding Erection
464 External Scaffolding Removal 464-External Scaffolding Removal
534 External Scaffolding Erection 534-External Scaffolding Erection
406 External Scaffolding Erection 406-External Scaffolding Erection
14-101 External Scaffolding Removal 14-101-External Scaffolding Removal
504 External Scaffolding Removal 504-External Scaffolding Removal
600 External Scaffolding Removal 600-External Scaffolding Removal

424 External Scaffolding Erection 424-External Scaffolding Erection


703b External Scaffolding Erection 703b-External Scaffolding Erection
912 External Scaffolding Removal 912-External Scaffolding Removal
671 External Scaffolding Erection 671-External Scaffolding Erection
671 Internal Scaffloding Erection 671-Internal Scaffloding Erection
468 External Scaffolding Erection 468-External Scaffolding Erection
458 Internal Scaffloding Erection 458-Internal Scaffloding Erection
P.Start P.End Duration A.Start A.End
22-Sep-22 4-Nov-22 21 28-Sep-22 80% 703
5-Nov-22 15-Nov-22 10 510
5-Nov-22 17-Nov-22 12 703b
21-Oct-22 27-Oct-22 7 464
10-Nov-22 23-Nov-22 13 534
25-Nov-22 6-Dec-22 11 406
27-Nov-22 30-Nov-22 4 14-101
8-Dec-22 12-Dec-22 5 504
12-Dec-22 19-Dec-22 8 600

424
703b
912
671
671
468
458
8 days
8 Hrs
FRAME PLANKS
S.No Task Name Dia, m Ht ,m Duration Expected Start Expected Finish Planned Finish Delay
M3 M2
1 703-Internal Scaffloding Erection 51.2 16.5 34900 5138 30 days 9/28/2022 11/26/2022 11/4/2022 -22
2 703b-Internal Scaffloding Erection 22.5 17.2 6768 1342 12 days 10/31/2022 11/13/2022 11/17/2022 4
3 406-External Scaffolding Erection 33 32 5039 2339 11 days 11/27/2022 12/8/2022 12/6/2022 -2
4 464-External Scaffolding Removal 43.9 19.5 3938 1713 5 days 11/2/2022 11/7/2022 10/27/2022 -11
5 510-External Scaffolding Erection 10.7 11 731 272 10 days 11/8/2022 11/19/2022 11/15/2022 -4

6 14-101-External Scaffolding Removal 4 days 11/20/2022 11/23/2022 11/30/2022


7
7 534-External Scaffolding Erection 50 19.5 4424 1937 13 days 11/24/2022 12/8/2022 11/23/2022 -15
8 504-External Scaffolding Removal 24.4 12.2 1493 667 5 days 12/9/2022 12/13/2022 12/12/2022 -1
9 600-External Scaffolding Removal 43.9 14.6 2949 1331 8 days 12/14/2022 12/22/2022 12/19/2022 -3