Scaffolding Schedule-To Be Done
Scaffolding Schedule-To Be Done
424
703b
912
671
671
468
458
8 days
8 Hrs
FRAME PLANKS
S.No Task Name Dia, m Ht ,m Duration Expected Start Expected Finish Planned Finish Delay
M3 M2
1 703-Internal Scaffloding Erection 51.2 16.5 34900 5138 30 days 9/28/2022 11/26/2022 11/4/2022 -22
2 703b-Internal Scaffloding Erection 22.5 17.2 6768 1342 12 days 10/31/2022 11/13/2022 11/17/2022 4
3 406-External Scaffolding Erection 33 32 5039 2339 11 days 11/27/2022 12/8/2022 12/6/2022 -2
4 464-External Scaffolding Removal 43.9 19.5 3938 1713 5 days 11/2/2022 11/7/2022 10/27/2022 -11
5 510-External Scaffolding Erection 10.7 11 731 272 10 days 11/8/2022 11/19/2022 11/15/2022 -4