LAB Exercises
LAB Exercises
Initiation 2 days
SelectLocation 1 day
Define Layout 1 day 2
Design 3 days
Draft Design 2 days 3,2
Review and finalize design 1 day 5
Design completed 0 days 6
Materials Preparation 5 days
Identify Materials 2 days 3,2
Purchase Materials 3 days 9
Construction 7 days
Cut wood 1 day 10
Buid platform 2 days 12,6,10
Add walls 2 days 13
Page 2 of 14
Module 3- LAB 1
SETTING UP A PROJECT
Learn how to add Holidays to the company calendar.
earn how to make a custom calendar.
Learn how to set the Project Start date.
Learn how to set constraints.
Page 3 of 14
Module 4- LAB 1
Describe which project functions are turned off for tasks using Manually Schedule mode.
Change the task mode from Manually Schedule to Auto Schedule and back.
Identify tasks that are in Manually Schedule mode by the task mode column and shape on the
Gantt c
Describe situations that are particularly appropriate for using Manually Schedule.
Describe the limitations that a user must be aware of when using Manually Schedule mode.
Page 4 of 14
Module 5- LAB 1
Page 5 of 14
Module 6- LAB 1
Page 6 of 14
Module 7- LAB 1
Page 7 of 14
Module 8- LAB 1
Page 8 of 14
Module 9- LAB 1
Reviewing changes that can have a positive or negative impact on the project plan.
Step 3:Add critical and free slack columns on task sheet( identify slack)
Step 4:Assign resource A to task 2 and task 4
Step 5:View and track task schedule with task inspector
Step 6: Review the project by changing the task schedule
Page 9 of 14
Module 10- LAB 1
Step 3: View the over allocation in team planner view/ resource usage view / resource sheet
Step 4: Solve over allocation manually or with resource leveling tool
Page 10 of 14
Module 11- LAB 1,2&3
Step 3: Set tasks 1,2 and 3 are completed 100% and took only one day to complete
Step 6: Analyze the report views to understand the impacts of entering actuals
Page 11 of 14
Module 12- LAB1
Challenge
Page 12 of 14
Module 13- LAB1
Challenge
Step 1: Open projects "Sub project A" and "Sub project B"
Step 5: Assign resources to the projects and check whether it reflects in the subprojects
Page 13 of 14
Module 14- LAB1
Advanced topics
Challenge
Step 2: Create a macro to highlight and group the critical tasks (Save the macro in global file) criticalpath.mpp
Software.mpp
Page 14 of 14