Artificial Support of Slopes
Artificial Support of Slopes
CANADA C
DEPARTMENT OF
ENERGY, MINES AND RESOURCES
MINES BRANCH
OTTAWA
JULY 1970
HALIFAX
1735 Barrington Street
MONTREAL
"Eterna-Vie Building, 1182 St. Catherine St. West
• OTTAWA
171 Slater Street
TORONTO
221 Yonge Street
WINNIPEG
Ma ll Center Bldg., 499 Portage Avenue
VANCOUVER
657 Granville Street
Information Canada
Ottawa, 1970
FOREWORD
mines. Approximately 200 million tons of ore and 250 million tons of waste
are currently being excavated from these open pits, which generate by these
operations about 700 million dollars per annum. The cost of mining this ore
is strongly influenced by the slope angle that is used for the pit walls.
designing optimum slope angles are being obtained, but the technical problems
systems was fully approved. In the light of the modest amount of work that has
now been done on this development, I am gratified to see the prospects that
As has been the experience of the Mines Branch in much of its research,
the active participation in this work by an operating company has been most
ohn Convey,
irector
Ottawa, July 1970
AVANT-PROPOS
de développement doivent donc choisir avec soin les travaux auxquels elles comptent
dans des mines à ciel ouvert. On extrait actuellement quelque 200 millions de
tonnes de minerai et 250 millions de tonnes de déblais de ces mines à ciel ouvert,
dont les opérations annuelles représentent une valeur d'environ 700 millions de
des quelques travaux déjà réalisés en ce sens, je suis heureux de constater qu'il
s'est révélée fort utile. Nous sommes d'avis que l'industrie en général, ainsi que
by
ABSTRACT
Part III considers the design and costing of support systems for
optimized.
y
Direction des mines
par
MsumÉ.
linéaire.
Abstract
Résumd (French) iv
PREFACE ix
•••■ Introduction 33
Plans for the Installation 34
Instrumentation 36
Construction Sequence 37
Critique on Construction Experience and Item Costs 39
Site Preparation 39
Anchor Holes 39
Welded Wire Mesh 41
Steel Rod Stringer Beam and Abutments 43
Concrete Stringer Beam and Abutments 44
Anchors 45
Assembly and Installation of Anchors 46
Grouting of Anchors 50
Tensioning of the Anchors 52
Final Grouting 53
Conclusion and General Comments 53
Results of Instrumental Studies 59
Instrument Layout 59
Cable Anchor Tensions 59
Extensometer Measurements 69
• Concrete Strain Gauges 69
Plate Load Tests 79
set
Television Viewing of the Boreholes 79
Instrumentation Costs 79
•
vi
CONTENTS (Concluded)
Page
Introduction 80
The Hypothetical Problem 80
Slope Stability Analysis 80
Bench Stability Analysis 86
Cost Analysis 92
ACKNOWLEDGEMENTS 102
REFERENCES 102
APPENDICES. 103-145
■■•. ■••■•■•
4
vi i
FIGURES
No. Page
TABLES
No. Page
PREFACE
resulting from the decreased cost of excavating superfluous waste rock and
also, perhaps, from increased profits due to additional ore excavation at the
toe. Most slope research work has therefore been directed towards the de-
safety.
are used successfully, not only for maintaining safe working conditions, but
also for reducing the amount of waste rock excavated. It is thus quite con-
and for stabilising dam abutments,they have not, as yet, been used in open-pit
systems should be designed and on the costs. The latter is particularly im-
portant in mining since,if the support costs are greater than the economic
gained.
open-pit mine of, say, 600-ft dept11, an artificial support system allowing the
0
average slope angle to be increased from 45 to 50 0 would cost approximately
$1000 per linear foot of pit wall. This could result in a decrease in waste
excavation costs of $2000 per linear foot of wall (at $0.34 per ton) or, alter-
wall through increased ore extraction (at $1.20 per ton). The change in net
revenue could thus be between $1000 and $6,700 per linear foot of wall. With
such a support system can be designed with reasonable confidence, since it does
not require new technological developments but would merely adapt established
The first part of this report deals with the design concepts
lines for design purposes. Any final design will always require a consider-
a trial installation of a support system was planned. The second part of this
report gives details of this trial,which was carried out in cooperation with
an iron ore open-pit mine. The support system is described and details of its
breakdown of construction costs is given and basic data for estimating con-
are considered and examples are given of how the analysis presented in
slopes. The data derived in Part II are then used to estimate costs of these
the consideration of hard rock slopes in which there are no major structural
weaknesses. The walls of an open pit in such a rock mass can be considered to
joint planes. On excavation of ore or waste, the confining stress on these blocks
is removed, thus permitting some expansion and opening of joints and bedding
planes. Damage from blasting, weathering, etc., on these open joints leads to the
development of loose rock that will fall down any slope steeper than the angle of
repose of such loose blocks. Consequently, for any extensive rock slope steeper
than the angle of repose of this loose rock, some method should be provided to
surface expansion and that are preloaded, can provide some constraint to the
surface rock that has expanded as a result of the excavation of the adjacent
between these anchors it can contain the immediate surface loose that is
these ends. In this figure the slope has an overall angle of cco. It is
assumed that there is a plane at some angle i ° beyond which the rock may still .
to install a series of deep bolts or cables which are anchored in this solid
rock mass and to apply sufficient pre-load to these cables to support all the
2
WELDED MESH
COVERING
SURFACE
GROUTED
ANCHORAGE
II
/ /
1/
over the surface and supported by horizontal stringers between the cable
terminations would help control the immediate surface loose and would supply
GENERAL ASSUMPTIONS
(i) It was assumed that there is a plane at some angle i° beyond which the
rock can be regarded as a competent mass. The choice of the angle i° will be
considered later.
(ii) It was assumed that the plane at i° passing through the toe of the
(iii) It was assumed that the mass of loose rock between i and a can be
regarded as a rigid body sliding on the plane at io and that the coefficient
rock masses even of the same general type. When the pit wall is composed of
degree of alteration of these different rock types also adds to the uncer-
applicable to the whole open pit,even with the most elaborate field measure-
method would only apply for the location represented by the testing site.
4
assume, at the preliminary design stage, that 11 is given by the easily obtain-
between rough sawn surfaces of rocks (2,3,4). For instance, Patton (3)
unstable slopes compares favourably with the values obtained from sliding
(iv) It is assumed that the cohesion on the plane at i ° is zero. The wall
joint planes. Even without support, cohesion might exist on these planes,
failure surface does not coincide with the joint planes, then some cohesion
minimize the lateral expansion of the surface block; and the existing cohesion
cohesion in practice should therefore add to the safety factor of the design.
(v) Some assumption must be made as to how the applied cable force is
distributed in the rock mass. Since the size of the bearing plate at the
cable end is relatively small, the cable force may be regarded as a point
assumed incipient failure plane at i °,it was assumed that the total force
from all cables was uniformly distributed over the plane at i ° . Whilst
component of weight down the slope, T, becomes greater than the resisting
unity these forces cancel out when g = tan i. For any initial arbitrary
angle i ° , the excess shear force, fe, acting down the slope, per unit cube,
Now,for a slope of depth Z feet and overall slope angle n ° with an incipient
Hence, if the volume of rock can be regarded as a rigid body sliding on the
plane at 1. 0 , the total excess shear force, Fe, per unit thickness of section,
6
CABLE ANCHORS
INCIPIENT
FAILURE PLANE
2
Z ( I I
2 \tani tana/ 2
The average excess shear stress, , over the plane at i = Fe/A where A
is the area of this plane and equals Z/Sin i. Hence the average excess
Fe = r
tC t i - Cot a} [Sin2 i - gSin i Cos i) (4)
r° = A " 2 °
g. For any particular slope angle a and coefficient of friction g,there will
be some value of i° at which the excess shear stress reaches a maximum value.
This maximum value should be determined and the support system designed so
that this maximum excess shear stress is eliminated by the applied forces.
2
[Cot i-Cot Œ J t2 5 in i Cos i - gCos 2 i + gSin2
i.e., 0 =. [gCot i - + Cot i[Sin 2i+pCos 2il - Cot a[Sin 2i+gCos 211
Cot i-1
i.e . , Cot a = Cot i + { 4
(5)
Sin 2i+gCos 2i}
stress is a maximum for any values of a and g. This angle i has been cal-
i.
90 /
/
/
/
/
0 80
._ /
... /
tit /
z /
a /
_1 70 / /1- =1.0
a.
(I)
/-"--9
U)
Lu
ix 60 )1 ' 8
}-
cn At. :: •6 .5
tr
< ---17-
-1-1- 4-P. r-
i 50
cn ke '1
(I)
in
w
0 40
X
tii
2
D
> 30
)..:-<
a
2
1-1- 20
0
Lu
_1
o
z 10
a
I t I I t I I I I
10 20 30 40 50 60 70 80 90
SLOPE ANGLE a°
0
For example: If the overall slope angle is 55 and pl. = 0.7, then, from T
0
Figure 5, the plane of maximum excess shear stress occurs at i = 45 . Like-
Hence, given a and 1.J., the angle of the plane of maximum excess
shear stress can be determined from equation (5) or from Figure 5. From
this value of using equation (4) the magnitude of this maximum excess
shear stress can be calculated. It is this value of the excess shear stress
exactly eliminate the maximum excess shear stress on the plane at Suppose,
Figure 6). Let the lateral spacing of the cables be 1. Assuming that the
total applied force,nP , is uniformly distributed over the area of the in-
cipient failure plane at then the total stress o- acting on this plane is
given by:
nP nP Sin i
-
1(a/Sin i) a 1
Thus, resolving into stress components normal and tangential to the plane at
• o .
glves:
nP . .
The normal component of stress on the plane ubi = Sin Sin (i +
j.
pp
and the tangential component of stress on the plane T = - Sin i Cos (i + A).
al
a = VERTICAL SPACING
I = LATERAL SPACING
Hence the total shear resistance mobilized by the cable forces, Tp, is given
by:
Tp T
-np
i.e., T = Sin i [Cos (i + ) + g Sin (i+A) I (6)
p al
applied forces to the horizontal. However, TP will reach a maximum, for a given
zero gives:
Cos i Cos A]
[tan A + tan Ji
i.e. — {l-tan A tan i} — tan (i + (7)
i.e. The shear resistance mobilized by the cable forces reaches a maximum
45 + A = 35 o ; o
i.e. i.e. A = -10 ;
'up dip'. Now from a practical point of view this may not be possible, since
down dip. This, whilst not the ideal solution, would be a much preferred
A = 35 ° ),
mobilized by the cable forces should exactly equal the average excess shear
stress in the plane at Thus equating Tp = Te, from equations (4) and (6),
gives:
This equation defines the relative horizontal and vertical cable spacings
required to support the rock slope with a safety factor of unity. From a
should be either full-bench or half - bench height. The lateral spacing is then
full-bench spacing and the pit wall has benches all of equal height, then
there will be (n-1) benches and the vertical spacing a = Z/n-1, where Z is
the pit depth. Likewise, if the cables are spaced vertically every 1/2 height
given by:
(n-1)
where n = number of cables and - number of benches.
2
The above criteria are derived for a safety factor of unity. The safety
the excess shear stresses Te. Hence, from equations (4) and (6):
reduced.
assumed,in the above analysis,that the plane of maximum excess shear stress is
the plane beyond which the rock may be considered to be solid competent mass
and that this plane at i ° is the incipient failure plane. Now,if the slope
this tacit assumption is valid. Thus in this case the cable lengths should be
recommended length, x ft, for the cable anchorage. If the cables are numbered
- (r 1) a} Sin (a i)]
- -
Lr = (12)
Sin a 5in(ii-b)
15
- ,
.<,. . --
,
,..-i
/ /.....„.., . .,. . . ,
.---"--
'
that the incipient failure plane might be the plane through the toe oriented
at po. Although this latter plane is not the plane of maximum excess shear
thought that the cable anchors should be extended beyond the plane at 0 °
the toe. Nevertheless, the cable anchor loads and spacing would throug still
be designed to eliminate the maximum excess shear stress on the plane at i0o .
equation 12.
practical to install. This minimum length depends mainly on the cable chosen
but can, for most cables, be taken as (15 x) ft. Where x is the recommended
length for grouted anchorage, this minimum length should always be used when
the calculated length given above in equation (12) yields a lower value.
This cable has a maximum initial tensioning load of 390,000 lbs; however, it
is generally good practice to allow an extra safety factor here and to tension
to approximately 15% lower than this value (or as recommended by the manu-
facturer). Thus the design load P for this cable could be chosen as 340,000
lbs.
17
rock mass contained within the 90 0 cones about the cables is supported by the
cable forces. However, the individual benches are still unsupported. Some
mesh laid over the slope face and tied down by horizontal stringers running
between the cable anchor points along the toes of the benches. Ideally these
elements should also be designed to resist the load of the rock mass which
might fail. The volume of rock which is unsupported by the cable forces is
in the wedge LMNO in Figure 9. For design purposes it is assumed that this
■ ••
rock fails through the toe of the bench along a plane at some angle e to
the horizontal. As before, consider the excess shear forces acting on this
plane. Let a° be the overall pit slope, let w be the bench width, let A be
the angle of the cables with the horizontal, and let y be the rock density in
lbs/cu ft.
As before (Figure 3), the excess shear force per unit block
The volume of rock, V, per unit section thickness is the volume of the
wedge MLPN in Figure 9 when Cpt, and is the volume of the wedge LMN in
Figure 10 when cP>a. The total excess shear force, Fe, on the plane at cp° ,
. ."
, .
e • :•.'• •
45 °
— W giV,LYN7
5 4
deetfelo
,
e•
a t.
\ •
,1
.
!
/.
,
_ !-• ,
o,
5°
4Ncf,0
0#
/ V= 1/2 ax ; x= W —
a Cot cib
a Cot a
y ; y = (a Cot a— a Cot 9)
>1
NML and NLP in Figure 9. Let w be the bench width and let NP = c, then:
Vi = 1/2 aw (15)
a 1
Sin(135-a-A) — Sin a • Sin(45 + a + cp)
]2c a Vf2
l'e ' tCos(a+A) + Sin(a4-A)1 Sina [Cos(a-licp) + Sin (a-Fc.c)]
and the average excess shear stress on this plane, Te , = Fe/c, assuming
SinŒ ay
where k 1 =El
2 and k2 — 2 (21)
tCos(a+A) + Sin(a+A)i Sin a
rc.ê will reach a maximum value at some angle cp when aTe/p = 0. Ideally the
support for the benches should be designed to resist this maximum excess
shear stress. The value of cp for which Te reaches a maximum has been determined
21
1.■
Hence cl) may be calculated and, using this value of eP, the maximum excess shear
and the average excess shear stress, Te, on the plane NL is given by:
, 2
yy Sin el) {Sin - eos _ tSin m -(p./2) Sin 2ce}.
Te - (24)
a - a
Te =
2
fSin2 eP -
2
Sin 2colfw - a Cot + a Cot crol
2 s.Cos cp
+ Sin eta
a p. 2 Sin elp Cos m Cos eP
Sin cp 2 Sin cp
g
agCc2)t
--Y [Siem(w-a Cot a) - Sin
- 2 e g2 - J — ap.(1-Sin 2m)]
'-ue • 1. 2 Sin cl) Cos cP(w-a Cot Œ + ag) - 2 Cos 2cpM1- - Cot -
2 2 2
bp 2
This equation defines the angle cp at which Te reaches a maximum when CP > Œ.
Assume that the wire mesh is laid over the bench and tied
into the toe of each bench as illustrated in Figure 11. Assume that,if
mesh, and assume that these tension forces act at the toe of each bench in
the direction of the deep cable anchors to which the mesh is attached.
RF - 2 T [Cos (cp +C
- ) + Sin (cp + A))
))
Thus the average resisting 'shear stress, TF, mobilized by the mesh is given
by:
11E. Sin
TF. C = 2T (Cos (cP +A) + g Sin (cP+A).1 Sin CP
(28)
a a
Thus for a safety factor of unity the shear resistance that can be mobilized
by the mesh should be equal to the maximum excess shear stress Te. Hence:
(i) when cp < a Te = TF, which from equations (20) and (27) gives:
a_y fw Sin a[Cos (a+L.,o) + Sin (a+p)] Sin (a-cp)] (Sin cp - gCos
2 a [Cos (a+A) + Sin (a+)1 Sin a
T
(Sin CD - gCos , a Sin (a-cp)[Cos (a+A) + Sin (a+)1 "m"
4 [Cos(cp+A) + gSin (cp+A)J Lw ' Sin 2 [cos (a+m) + sin (a+f-15)1]
of the mesh and (To is the yield strength of the cold-drawn mesh material,then:
Ao (30)
o-0
A
= 4u0 [Cos
( Sin cP-g Cos cio)
(cp+A) + gSin (cp+)1 cw aSin(a-cp)[Cos(a+A) + Sin(a+A)1
Sin2 a [Cos(a+cP) + Sin(a+p)j]
(31)
For design purposes the lateral strands of the mesh are not assumed to
(ii) when cp > a Te = TF, which from equations (25) and (28) gives:
2 2 (32)
2
[Cos (cP+A) + j Sin (cp-I A) 1 Sin cP
-
and from equations (30) and (32), the area of steel A o is given by:
Again, the lateral strands of the mesh are not assumed to contribute to the
strength.
y = 165 lbs/cu ft, and 0-0 for cold-drawn steel is 71,000 lbs/sq in. The
angle cp at which the excess shear stress in the bench reaches a maximum must
be determined from either equation (22) or equation (26). For this example
it was shown in Appendix II that, using equation (22), cro - 48 °48' which is
<a° . Hence, using equation (31) for the case cp < a, the area of steel mesh
of welded wire meshes, TableA3.2 gives weight of this welded wire fabri.c,
and Table A3.3 gives the areas of cross section of welded wire fabric. In
this example, referring to Table A3.1, a mesh style 216-28 having a longitudinal
section area of 0.325 sq inch would be adequate. This mesh has 6 longitudinal
strands of No.2 wire (0.2625 in.diameter) per foot, and transverse wires,
spaced 16 inches apart, of No. 16 wire (0.062-in. diameter). The mesh weighs
26
119.4 lbs per 100 sq ft. If a choice of styles is available it would be best
to select the lightest mesh with adequate longitudinal strength. Whilst the
required from the above calculation may be so large that a suitable mesh is
not available (even assuming it may be easily installed). It may not, there-
(b) It was assumed that the bench would fail along its complete length. In
failure is much more likely. This,of course, varies both from mine to mine and
(c) The lateral strands will add some strength to the mesh.
(d) Even partial support given by a light-weight mesh would give a better
matter of course. The mesh would at least assist in protection from loose
falling rock.
a
is probable that in many cases the mesh actually selected will not provide
complete bench support and,indeed, as will be seen below, even if the mesh
mesh in place along the entire span, 1, between the cable anchors. The mesh
zontal beam.
T1 2 (34)
M=—
10
where T= the load per foot acting on the beam (i.e. T = the mesh tension
given by either equation (29) or (32), if the mesh were designed to resist
this beam can be designed by the standard techniques to resist the maximum
flexural bending moment (5). These design techniques will not be dealt with
in detail here since they are included in many text books (5). To illustrate
assume that the ultimate compressive strength of the concrete g = 2,500 psi,
and assume that the minimum yield strength of the steel reinforcing bars is
= 33,000 psi. The area of reinforcing steel required in the concrete beam
28
is given by:
A = (35)
s f j d
where M= the bending moment; j = ratio arm of the resisting couple to the
effective depth (5) (for approximate design purposes j can be taken as 7/8);
and d is the distance from the compression face of the beam to the plane of
the centroid of the tensile steel, or the "effective depth" [for an 18-inch
beam and steel bars set 11/2 inches from the tension surface, d = 16.5 inches].
ceding example it was found that the area of mesh required was 0.3 sq inch.
Thus , . from equation (30), the mesh tension T = the load on the beam per foot
Hence, from equation (34), assuming that the span 1 = 40 ft, the maximum
m T12 _ 21,300 x 40 x 40 x 12
= 41 x 106 in lbs.
10 10
Hence the area of steel required in the beam is given by equation (35) as:
41 x 106
A =
A5 = 86 sq inches.
33,000 x 7/8 x 16.5
would thus require 86 of No. 9 steel bars. This is obviously completely im-
design and to estimate the safety factor of the bench support actually
29
provided:
Choose the beam dimensions and the quantity of steel; then from equation (35)
M = A s fs j d (36)
Using this value of M,the load per unit length of the beam,T, can be cal-
10M 10A
s sf' j d
T = (37)
12 - 12
Hence,from equation (3), the area of mesh required to support this beam load
10As j d
A.0 - (38)
=-Ero To 12
(
Now the safety factor of the bench, SFB, can be defined as the ratio of the
mobilized resisting stress, TF, to the excess shear stress on the plane at
ce. Hence:
40 A s f. i d [Cos(cp+A) + gSin(cP4A)1
SFB — a y 1 2 [Sin cp(w-aCot a+au) - Cos cp(uw-au Cot a-a) - au Cosec cpj1 (40)
8 of No. 10 bars). Let the beam be 18 in. x 18 in., let d = 16.5 in., and
assume j = 7/8, g = 33,000 psi, cso = 71,000 psi. Assume a = 50 ° , a.= 66 ft,
w = 10 ft, A = -10 ° , 1 = 40 ft, u = 0.8 and y = 165 lbs/cu ft. In this case,
as shown previously, cp = 48 0 48 1 .
Then, from equation (38), the area of mesh steel required is given by:
i.e. from Appendix III, either mesh style 33-1212 or mesh style 66-99 is
suitable since they have area of 0.035 sq. inch. However, mesh 33-1212 is
lighter (24.74 lbs/100 sq ft) than 66-99 mesh (25.03 lbs/100 sq ft); thus the
33-1212 mesh would be selected. This mesh is not strong enough to support the
complete bench; the safety factor is given by equation (39) since cp < a:
2
20.10.33,000.7/8.16.5 Sin 50[Cos(38 °48') +.8 Sin (38 °40
S FB —
66 x 40 x 40 x 12 x165 1.405in2 50+66Sin 1 ° 12 1 [Cos4O+Sin 40J1 x I.
= 0.07
31
by the mesh support is low and the bench cannot be regarded as completely
fall of loose pieces of rock. In other examples this factor might be con-
siderably higher; since the limiting factor of this support is the maximum
bending moment that the beam can tolerate,then obviously the span 1 of the
beam between the cable anchors has a large influence on the bench stability
safety factor. The shorter is this span the greater will be this safety
factor (i.e.,the horizontal stringer will be more rigid). This span 1 is,
however,decided on the basis of the slope stability analysis and not from
to reduce this span below the maximum allowed by the slope stability analysis,
since this would increase considerably the amount of drilling required for
CONCLUSION
volved in the analyses, the validity of which are in some cases dubious. At
the most,these analyses can only be regarded as establishing guide lines for
that this approach does illustrate the practicability of using deep cable
the analysis shows that complete bench support is probably unobtainable, the
use of wire mesh does offer a small degree of bench support which must in
general be some improvement on current practice. The mesh does give a pro-
32
tection to men and machinery against small, but nonetheless hazardous, rock
falls. The next section of this report therefore describes a trial instal-
6
33
INTRODUCTION
as follows:
support system.
(iv) To instrument the supports and the rock slope to assess the effective-
methods of construction might equally well be used both methods have been
horizontal. Two of these are installed at the top of the bench and two
below, both pairs being spaced 50 ft apart. Each pair of cable anchors is
connected together with horizontal stringers, and mesh is laid to cover the
whole bench.
(a) The bench is covered with Style 66-44 welded steel fabric mesh having
individual wires, 0.225 in. diameter, spaced 6 in. apart in both directions.
horizontal wires, the meshes are overlapped at the sides and bound together
with No. 9 wire. At the top and at the toe the mesh is connected to the
horizontal stringers.
(b) Two different types of horizontal stringers were used. At the toe of
concrete beam. This beam is nominally 16 in. square and contains six No. 10
reinforcing bars, three at the front and three at the back. The mesh is extended
about 5 ft beyond the beam and is embedded in the concrete. The reinforcing
bars are extended into and cased within the concrete cable anchor pads. On
35
the upper bench the horizontal stringer comprises five No. il bars only, which
are cased into the concrete cable anchor pads at each end. The mesh passes
(c) The cable anchor pads were made from reinforced concrete, the bearing
for use with 270K Freysinnet 12-strand cables (7). To measure the applied
cable force and its changes with time, a load cell was installed at each
cable anchor pad. The cable passes through the hollow-bodied load cell
which is located between the cable anchor pad and the Freysinnet locking cone
(d) The cable chosen for the deep anchors was a 12-strand (0.5-in , dia , per
strand) 270K cable (see Appendix I). Two holes sizes were chosen for installing
the cables; the smallest size was NX casing (3.5-in , dia.) and the largest was
HX (3.89 in.). These CATO sizes were chosen to investigate whether or not
it was easier to install the cables in the large holes or whether the smaller
size was adequate. The four deep anchors were each of different lengths in
holes. The shortest cable was 33 ft; this was about the minimum length suit-
able for any installations, allowing about 20 ft for the grouted anchorage and
13 ft of free cable. The longest cable chosen was 195 ft, which is the
maximum that would be required in a support system for an open pit of 800-ft
Freysinnet cable was not used. Instead, a solid "stressteel bar" (8), 1 3/8 in.
diameter, was used as the anchor. This alternate type of anchor does not have
36
the same capacity as the cable anchors but does offer some advantages with
The two shorter anchors were deliberately placed on the same side
assessing the relative effectiveness of anchor length. All the anchors were
INSTRUMENTATION
(a) The cable tension would be monitored. This should give information as
(b) Borehole extensometers were used to monitor the ground movement with time.
(c) Since the operation of tensioning the cable against the concrete anchor
pads is, in effect, a plate load test, it was decided to measure the
surface displacement of the ground around the pads during several cycles
(d) Strain gauges were installed in the concrete forming the lower horizontal
(e) Core from the cable anchor holes and the extensometer holes was examined
to be sure that the cables were anchored in solid ground and to determine
37
ground. In addition, it was decided to examine the interior of the cable anchor
was commercially available, a cell was specially designed for this purpose.
These cells were able to discriminate load changes of approximately + 300 lbs
and had an overall accuracy of approximately + 3000 lbs 670 full capacity).
(ii) Mines Branch vibrating wire extensometers, which can be used with
up ,to four wires in any one borehole, were selected for measuring the ground
these instruments. Appendix VII gives the sensitivities of the instruments used.
(iv) Examination of the inside of the cable anchor holes was carried
of Ontario. It was suitable for insertion into NX, or larger, holes. This
work was carried out by BEM° on contract and under supervision of Mining
CONSTRUCTION SEOUENCE
1. A section of pit wall, 50 ft long and extending from one bench to another
38
over a height of 66 ft, was cleaned and scaled in preparation for the
project.
2. A contractor was brought in to diamond-drill the holes for the four cable
3. A panel of welded wire mesh was assembled which would cover the 50-ft
width from the toe of the upper bench to the toe of the lower bench.
This panel was assembled from 5-ft widths of mesh, overlapped and wired
together to make up a single unit over the whole area. This panel was
then rolled up and placed on the upper bench of the site. It was fastened
at the top in the desired position by short rock bolts and was then rolled
over the bank so that it lay in the desired location for the installation.
4. The cable anchors and the rod were assembled on site and installed into
four holes, two on the upper bench and two on the lower bench. These
5. Forming and reinforcing steel were constructed at the head of each anchor
anchors could be stressed. This concrete formwork also joined the anchor
cased.
steel rods passing over the 50-ft test width and through the concrete
abutments which provide the anchorage for these rods. The steel mesh
was wired to these steel rods along the whole width of the bench section.
7. On the lower bench, the wire mesh passed under the formwork for the
horizontal stringer so that when the concrete was poured the mesh would
8. Concrete was then poured for the abutments and the horizontal stringer.
9. After the concrete had cured, the four anchors were stressed by means of
a hydraulic jack to the required load, and the cable ends were locked in
position.
10. The cable support system was then allowed to stand for a period of 9
the end of this period the cables were slackened, the load cells were
the cables was grouted with portland cement grout over its full length
Site Preparation
Normal scaling and cleanup were carried out in the area before
commencement of the other activities. It was thought that the work done here
would be satisfactory for a major support system and that therefore no extra
Anchor Holes
(3.89 in. diameter) and NX casing (3.5 in. diameter). The 196-ft and 33-ft
holes were drilled HX size, whilst the 55-ft and 110-ft holes were NX casing
HX 3.89-inch-diameter holes
four anchor holes. The better efficiency was obtained by the drilling con-
tractor on the larger-size holes (HX) because of the availability of the proper
type of bits and core barrel. With the 3.5-Ln. (NX casing) size,core recovery
and bit life were poor because standard coring bits and corebarrel were not
available and were not worth obtaining for such a small footage. On a major
efficiency would be expected and the drilling costs per.foot would be exPected
attained for viewing with the television camera. However, on a major pro-
would be useful. It is thought that, for certain types of rocks and for
to diamond drilling.
A panel of welded wire mesh 5 5,1i ft wide was installed over the
test area,extending from the lower beam to the upper beam. It was fastened
to these beams so that the mesh would prevent chunks of loose rock from falling
clown the slope and would give support to a portion of the berm in the event
of its failure.
lengths which would extend from above the upper stringer,across the berm,and
down the bank to just below the lower stringer. These lengths of mesh were
overlapped by six inches and were wired together with No. 9 annealed galvanized
wire. The wiring of the mesh was conducted in a level area away from the
test site. After the wiring was complete,the panel of mesh was rolled up and
transported to the upper bench of the test site, using a front-end loader.
There it was positioned, using a crane, and fastened to the rock with two short
bolts. It was then rolled across the berm and over the bank. This procedure .
The most effort required concerning the mesh was the wiring to-
new procedure was devised: The annealed wire was cut into 6-in , lengths and
bent double to form a U with two 3-in. legs. The wire was twisted with an
electric power drill. A 3/8-in.-dia. shaft, 6 in. long, with a head that
had two 1/4-in. holes, 3/4 in. apart, was held by the chuck of the drill
(see photographs 18-21,Appendix VIII). The U-shaped wire was placed at the
junction of the two wires of each of the adjoining widths of mesh, the ends of
the wire were inserted into the 1/4-in. holes on the twisting tool and the
drill was turned on until the wire was tightly twisted. This operation was performed
by one or two men placing the wire ties and a third man operating the drill.
Labour 4 man-hours
Labour 39 man-hours
(4) Materials
consuming job. The wiring of the lengths of mesh could be organized into a
more efficient than the patented commercial device for the same purpose.
The wiring together of the ends of two lengths, where the mesh
laid over one bench joins that over the next bench, could be done in a
longitudinal strength.
was experienced above; a technique for doing this would have to be developed.
The upper stringer beam used to support the welded wire mesh was .
composed of five 56-1t-long,No. 11 A432 steel rods. These rods were held in
position by the concrete abutments at each of the anchors. The welded wire
mesh passes under these rods and was fastened to them with No. 9 galvanized
iron wire. The rods were fastened to the reinforcing steel in the abutmentà
44
Labour 50 man-hours
Concrete Work
Labour 10 man-hours
Labour • 32 man-hours
project with a greater number of abutments would quite likely result in more
reinforced concrete integrated with the concrete abutments for the anchors.
The main structural steel members are six No. A432 steel rods,56 feet long.
The welded wire mesh was positioned to pass through the concrete which,
Concrete Work
Labour 15 man-hours
The wall configuration in this area was more regular than on the
upper bench, resulting in more efficient operation for the forming and the
Anchors
The main support for the system is created by the installation and
tendons, and one was a high-tensile steel bar, 1 3/8 inches in diameter, called
a "Stressteel" bar.
Materials for the 12/0.5 tendons were shipped to the job site in
bulk and assembled by a crew of two men and an experienced supervisor from
Hole depth 33 ft
into a 3.89 - in. hole. A diamond drill hole of n-in , diameter would'
Three men assembled this anchor from the bulk source of material
A three-man crew was able to assemble this anchor from bulk and
were required to assist in pushing the anchor down the hole. At 170 ft the
hole passed through a fault extending for approximately 4-5 ft; this fault
produced caving ground in the hole. It was difficult to push the anchor
through this caved ground; nevertheless,by brute force with seven men pushing
on the anchor,it was forced to within 2 ft of the bottom of the hole where,
insertion. Due to the weight and length of the anchor it is suggested that
holes, the holes should be grouted where caving ground is indicated by the
good. Above this depth the anchor hole diameter is probably best increased
were drilled,it is anticipated that the hole surface would be rougher than
cable tendons, the above labour hours have been plotted against hole depth
in Figure 12. This figure indicates that these costs might be estimated on
and installation.
Hole depth 55 ft
Three men could assemble and install this anchor with no difficulty
in one hour. The unit installed came in a maximum length of 20 ft. Lengths
of 40 ft are normally available and would reduce installation time and cost
to some degree. Couplings used on the stressteel bar were of the grip type
possible to remove the grout tube, which was not possible with this installation.
less,than those for the cable tendons. Also from this one experience,
it appears that the bar is easier to install and that probably a 3.5-in.
hole (or perhaps even smaller) could be used to considerably greater depths
than with the cable tendons. It should be borne in mind, however, that the
stressteel bar has a capacity of only about the load of the cable tendons
used; hence, whilst installation costs are lower with the stressteel bars,
19
18
17
16
15
14
13
12
15
/ SLOPE = -090 man-hours/ft
cn II 166
0 I o
Z9 / X
2
8
Œf
I I I l l I I I I 111 111 111 I
VI
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210
HOLE DEPTH, FEET
almost twice the number would be required to apply the same total support
bars would be less than those for the cable tendons, unless bars of much
higher capacity became available.
for each additional 40 ft or less should be added for thread and coupler.
smoothly, and it is unlikely that much room for improvement is available for
could be purchased more economically than was possible for this trial.
Grouting of Anchors
covered the bottom 20 feet of the anchors. The following grouting . equipment
was supplied by Conenco Canada Ltd., who supervised the grouting work:
pound of Sika Intraplast expansion grout per sack (87 1i'lbs) of High-EarlY-
51
grout was poured into the tank of the pump; this was the average quantity
required to grout one anchor. After the grout had been pumped in, the
grouting tube was slowly pulled out before the grout had set. The grout tubes
were removed from all holes but the hole with the bar where the
size of the couplings had jammed the grout tube between them and the wall.
a large scale when more than one anchor could be reached from one set-up.
It is the opinion of the Conenco personnel that the leaving of the grout tube
in a 12/0.5 tendon during tensioning would only result in damage to the tube
and render it useless for additional grouting. They suggest that additional
a
of the hole after tensioning. -
The grout was allowed to set for 28 days before the cables were
tensioned.
52
personnel. They used hydraulic jacks and pumps supplied by Conenco which
load; it was then unstressed in increments down to almost zero load. This
displacement of the surface rock as the load was cycled. These measureMents
during this "plate load test" enabled an estimate of the in-situ modulus
pleted,the anchor was loaded and locked at its design load. From 4 to
5 hours were required to complete this procedure for each 12/0.5 tendon.
About 2 hours was required to complete the same procedure with the rod.
, and tackle, or some other convenient means of handling the jack for a 12/0.5
tendon, would be able to set up, tension, lock, and dismantle one cable in
hours. Two men could set up, tension, lock, and dismantle for a stressteel
process once the proper techniques have been learned. To achieve the
and equipment on the job site and to be able to move them from one site to
Final Grouting
After cable tensioning, the whole system was left and its behaviour
was monitored over a period of 9 months. The load cells were then retrieved
from the cable ends by relaxing and retensioning the cables. The holes
were then grouted over their entire length in order to protect the cables
and the bar from corrosion. In normal practice this would be done immediately
The holes were grouted by inserting short plastic pipes into the
collars of the holes and sealing these in position with quick-setting mortar.
Using the same cement mix as previously and the same pump and mixing equip-
ment, all four holes were grouted in one shift of approximately 6 hours,
mantling time. A total of 21 bags of grout were used for the 347 ft of
The work done on the trial installation was carried out by men
power, transportation of men and materials, and the use of tools and shops,
have not been charged against the project. Neither have the supervision
end control mentioned above been charged to the project. In all job
50% at a tradesman's rate (carpenter, steel man, etc.) and 50% at a helper's
rate. The cost of this labour would vary with individual companies and
per hour. This would also vary with area, company, and size of equipment.
(not necessarily applicable to this or any other mine) have been assumed,
together with an allowance of 15% extra to cover the cost of fringe benefits,
etc. A total construction cost of this project has then been derived, using
The table below indicates the percentage of the overall costs made
1. Site preparation
account for over 50% of the total. Thus any economies in this work would be
best achieved by reducing drilling costs. This makes a very strong case for
The next most expensive item is the wire mesh installation at 17.1%
of the total costs. Of this wire mesh cost,approximately 43% (7.4% of overall
therefore be obtained by reducing this figure through the use of wider mesh
56
not appear to leave much room for potential economies. It is doubtful that the
Whilst the fixed cost per anchor of end fittings, etc.,might well be re-
duced by bulk buying,it is doubtful that this would reduce significantly the
total costs.
in using concrete stringer beams or steel rod stringer beams. Whilst the
concrete beams do cost a little more, they also give a better support to the
irregular and not excessive, it was found more efficient to perform the work
with regular company personnel rather than contract it out. This was shown
in this project,where the Company was able to integrate the work on the
would be much more regular and would have to be integrated into production
production, it would again seem advisable to carry out this work with mine
costs of such a support system have been derived. These are summarized below:
1. Site Preparation
3. Wire Mesh
Labour
Allow 1.2 man-hours per foot of beam
(include abutment formwork). 1.2 man-hours/foot
Concrete work
Allow $23.00/cu yd for concrete. $23.00/cu yd
6. Grouting of Anchors
7. Tensioning Anchors
Grout materials: Allow 14i /ft of hole. $.12 per foot hole
are based on those from the trial installation. For a larger project,these
experience dictates.
Instrument Layout
four load cells were installed under the cable-anchor heads of each of the
anchors. The load-cell numbers and the anchor depths are indicated in this
showing the location of the anchors within these holes and the orientation
of these holes. The strain gauges installed within the concrete stringer
beam were numbered and installed in the pattern and positions indicated in
Figure 15.
Cable No. 1 (33 ft) was tensioned to 302,850 lbs and the Freysinnet
cone was locked, causing the load to drop to 209,930 lbs. Shims were then
introduced between the cone and the load cell,and the cable tension was then
increased to the "initial load" of 267,600 lbs. This cable was then left in
position and the cable tension variations during the ensuing 9 months were
-
L = LOAD CELL
X = EXTENSOMETER
C = CONCRETE STRAIN GAUGE
•
XI-2 XI-1
I X 31
WIRE
1-1
ANCHOR DEPTH
248 ft
1-2 200 ft
1-3 115 ft
1-4 59 ft
2-1 200 ft
2-2 135 ft
2-3 79 ft
2-4 43 ft
31 140 ft
3-2 87 ft
3-3 50 ft
3-4 25 ft
4-1 200 ft
4-2 150 ft
X2.1
4-3 120 ft
X4-4 4-4 66 ft
5' 5
25'
(a) PLAN
8,1
13" 10" 14"
— — 101/2"
—
Cla2 C38(4 C5&6 C78i8 C9&10
1 observed, and are plotted on Figure 16. This cable tension remained stable
Cable No. 2 (110 ft) was tensioned to a load of 319,700 lbs and the
Freysinnet cone was locked,causing the load to drop to 281,380 lbs. Shims
were then introduced to increase the cable tension to the "initial load" of
309,250 lbs. This cable lost load rapidly and continuously over the 9 - month
observation period, and at the end of the time had lost over 307. of the
lbs and the bolt was locked. No loss of load was experienced due to locking
of the bolt. A slight loss of load was experienced over the 9-month period,
but at the end of this tim ,, the load was still approximately 103,000 lbs.
which dropped to 261,900 lbs when the Freysinnet cone was locked. Shims
were introduced between the cone and the load cell,raising the load to the
"initial value" of 299,660 lbs. During the first month of observation this
observations:
load, the act of locking the cone and wedge relaxes some of this tension.
This relaxation can be a significant portion of the design load and is pro-
bably greater for the shorter cables. After locking the cable, shims can be
310 r
300
290
280
270
x \ x/
e
/X es\x...........9( X .,
I`x----
_.....X.,..x
------x ....e
.
LOAD
X
X
- + 1 0/0
_ _10/0
-CI
- 260
0
0
be 250
OC
240 20
0-- C1 •
230 10 / •
Id*
•
-Os
TEMPERATURE
220 0
- - 0-
10 -10
Figure 16. Load cell No. 1 - 33-ft cable - initial load 267,600 lbs.
5
111
310 r
3001-
290
\X 3eNir,......J \
X
280 1-
2701
260 -
\ LOAD
0 \
X
.< 250 -
0
°C
240 20
0--0
i ct
230- 10 \
0
`c,
2201- 0
TEMPERATURE
0'
210 —10
Figure 17. Load cell No. 2 - 110-ft cable - initial load 309,250 lbs.
160
150
140
130
120
Jte \ x
LOAD
*— 110
to
X
X
• 100
oc
90 20
Q- -0
A
80 10
'0(
0-
TEMPERATURE
70 0
60 —10
Figure 18. Load cell No. 3 - 55-ft rod - initial load 113,500 lbs.
k" 110
• •
310
300
290
LOAD
280 x X
x
270
- 260
< 250
o
-1
OC
240 20r
- C?
230 10
■
••••. TEMPERATURE
220 o -
***0- -----
210 -10
llllllllllllllllll
It a., • tt • 1
200 20 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
5 10 15 20 25 5 10 15 20 25
SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE
Figure 19. Load cell No. 4 - 195-ft cable - initial load 299,660 lbs.
68
inserted between the wedge and the bearing plate (or load cell), which will
increase the load towards the design load. However, this load will only be
not normal practice to use such a load cell on every anchor,as the costs
on the cable when finally installed will not be accurately known and it
may enable some allowance to be made for the relaxation during locking.
(h) The above problem was not experienced with the stressteel bar; no
(c) After shimming, load cell No. 1 on the 33-ft cable remained stable
throughout the observation period. However, load cell No. 2 on the 110-ft
cable showed a continuing load loss. This was believed to be due to slip
in the anchorage, either at the bottom in the grout anchor or at the top
between the cone and wedge. In normal practice, however, the entire cable
would be grouted over its whole length immediately after final tensioning.
The'rod and the 195-ft cable both showed some loss of load during
the first few weeks; thereafter the load remained stable. This load loss is
3 load cycles during the plate-load tests, did not exhibit this effect since
most of the compaction would have occurred during these presetting load
highest level for several cycles, in order to reduce the load loss after setting.
69
Extensometer Measurements
caused much condensation of water and subsequent freezing within the units,
in many cases preventing the vibrating wires from moving, and stiffening the
springs with ice. In consequence, at this time the readings became erratic
and in many instances the wires could not be read. Extensometer No. 4
showed erratic readings from a much earlier date. It is obvious that this
behaviour was not a reflection of movement within the slope,since the re-
corded movements are not reflected in the different wires in the same hole.
that can be drawn from these measurements is that it is probable that little
pairs of concrete strain gauges embedded in the concrete stringer. With the
9 month observation period. For some unknown reason,gauge No. 9 showed high
800
700 ..•-•"••
.••••
.•'•
600 . • • " • MUST BE MISBEHAVING
SINCE NOT REFLECTED IN OTHERS
500
400
in
-t
300 •
DIS PL ACEMENT x10
•
• ■
• ■
200 •
e" ■
•""
100 • - --- - -- -- •
••••••
NOT READING
-100
- 200
—300
—400
—500
—600
—700
—800
—900
,.t.1 ■ •••••
—1000 5 10 15 20 25
5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE
• •
•
1200 — LEGEND
1100 - 21 0 to 200 ft
2.2 0 to 135 ft
1000 -
2-3 0 to 79 ft
900 - 2-4 ----- 0 to 43 ft
800 -
700 -
600 -
500 -
400 -
DIS PL ACE ME N T x 1 0in
-3.
300 -
200 -
100 -
o --- .
—100
—200
—300
—400
—500
—600
—700
—800
—900
■ 18,1111. 1 ■ 1111
• t9111t1 ■ 11., /t/ .1118
—1000 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
JANUARY FEBRUARY MARCH APRIL MAY JUNE
SEPTEMBER OCTOBER NOVEMBER DECEMBER
3100
3000
2900
1500
.1400
1300 ......
DISPLACE ME N Tx10 - 3in
120.0
1100
1000
LEGEND
900 31 0 to140 ft
3-2 0 to 87 ft
800
3•3 0 to 50 ft
700 3.4 • -• 0 to 25 ft
600
500
, .
400 ,
,/
300 ,
200
/
- -
j
100
..
1400
1300
1200
• '•
•••
•.
1100
1000 • 2000-
900 I : 900-
800 800-
700 1700-/
•
600
LEGEND
DI SPL ACE M EN T x10in
41 0 to 200 ft
-3
200
100
- 100
- 200
-300
- 400
•
-500
- 600
-700
1 till
.5 10 15 20 25 510 15 20 25 510 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 3 10 15 20 25 5 10 15 20 25 5 10 15 20 25
SEPTEIM3ER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE
900
800
LEGEND
X X GAUGE 1
700
0----0 GAUGE 2
600
500
400
300
200
(.0
10
100
- -_® --------- -0- -
0
- 100
- 200
- 300
7 - 400
-500
ct.
›
- 600
-700
- 800
-900.
-1000
I I II
5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE
10 0 0
900 LEGEND
800 x--X GAUGE 3
— --0 GAUGE 4
700
600
0 500
C)
400
Iii
X X
300
X
200
o — -----
----
17)cr -100
-200
Z - 300
0
Fn -400
co
w
gr -500
a_
2
0 -600
U
- 700
-800
- 900
- 1000
I 1 I 1 I -- ---
900 LEGEND
800 X X GAUGE 5
- -0 GAUGE 6
700
600
0 500
7
400
;-
300
1'4 'el
0
200
- 100
- 200
t - 300
CO M PRES SI O N
- 400
- 500
- 600
- 700
-800
-1000
1,11,1. el t .12,11, t el
t Jr /11111
50 15 20 25 510 15 20 25 510 15 20 25 5 10 15 20 23 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 23 5 10 15 20 25
SEPTEMBER OCTOBER NOVENIBER DECEMBER JANUARY FEBRUARY MARCH . APRIL MAY JUNE
7
1
1000
900
LEGEND
800 X--+X GAUGE 7
---0 GAUGE 8
700
600
500
400
300
200
0
- 100
- 0
, -100
cn
- 200
-300
COM PRES SION
-400
- 500
-600
- 700
-800
-900
-1000
510 15 20 25 510 15 20 25 50 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
SEPTEMBER OCTOBER NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL MAY JUNE
8-- — —0 GAUGE 10
1700
1600
1500
o
Z.7) 1400
1300
Î
1200
1100
— 1000
. at.
900
CC
800
I-
. CO
700
600
t
500
400
300
200
100
—100
=2-'4
—200 5 10 15 20 25 5 10 15 20 25
5 10 15 20 25 510 15 20 25 50 15 20 25 510 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25 5 10 15 20 25
SEPTEMBER OCTOBE-R NOVEMBER DECEMBER JANUARY FEBRUARY MARCH APRIL . MAY JUNE
not reflected in the behaviour of gauge No. 10 adjacent to it. These erratic
readings from this gauge must be attributed to some malfunction of the gauge.
The plate load tests carried out during the cable tensioning are
modulus of the surface rock of: E - (2.12 + 0.51) x 105 psi with a coefficient
Instrumentation Costs
this project.
80
INTRODUCTION
estimate data derived in Part II will then be used to estimate the costs of
and that the benches will be 50 ft high and 30 ft wide. Assume that the slope
Consider the preliminary design of a support system to stabilize this pit slope
experiment to be g = 0.75. Let y the density of the rock be 165 lbs/cu ft.
which has been plotted in Figure 5 for all values of g and a. Hence the values
350 0 0 60o
a 40 ° 45 50 ° 55
o o 0
i 341/2 0 371/2 40 ° 42 44 46 °
From equation (7), the optimum angle A of the cables is given by:
g = tan (i +
Hence, for all values of and g = 0.75, i.e. tan -1 0.75 = 37 ° . See below:
o 350 0 0
a 40 0 45 50 ° 55 60 °
o o 0
i° 341/2 ° 371/2 40 ° 42 44 46 °
o o o
A optimum 2 -3 -8° -13 ° -18 ° -23
o o o
A chosen +2 -3 ° -8 -10 ° -10 ° -10
3. Calculate the average excess shear stress, per unit thickness, in the
plane at i°
where Z = depth of 500 ft, y = 165 lbs/cu ft, substituting these values into
o 0 55o
ao 35 40 ° 45 50° 60 °
0
Note that the excess shear stress when a is 35 is negative, i.e. ,
the natural shear resistance of the slope has not been overcome, and thus the
slope would be safe without support at this angle. The shear stress will
become positive (i.e. excess about the natural resistance) when p. = tan i,
-1 0•
i.e., when i = tan 0.75 = 37 We need not,therefore,consider the case of
0
a = 35 any more.
The shear stress which must be mobilized by the cables must be 1.5
times the excess shear stress Te in order to obtain a safety factor of 1.5.
o 0
55 o
40 0 o
a 45 50 0 60
Tp lbs/sq ft 61.5 522 1260 2235 3420
Assume that there are ten 50-ft benches in the 500-ft depth,
i.e., that there are 11 cables required in each vertical section for full bench
spacing (n = 11, a =50 ft). Choose the maximum capacity cables to give
maximum load with minimum drilling costs, i.e. 270K 12/0.5 strand cable,with
n P Sin i
1 = [Cos (i+s) + Sin (i+ )}
a Tp
o o 0
a. 40 0 45 ° 50 55 60 °
.o o
1 371/2 40 0 42 0 44 ° 46 °
o o
-3 ô-10o
-8 ° -10 -10 °
1 ft 920 ft 114 ft 50 ft 29 ft 22 ft
uniformly distributed over the plane at i° could not possible apply in this
closely spaced (say 50-100 ft), but this would increase drilling costs con-
siderably and might well adversely effect the economics of the operation.
will still be carried out,using the excessive spacing since it may well
From equation 12, the length of the rth cable is given by:
when r is the cable number, counted from the crest and x is the recommended
length of grouting for the cable anchorage, say 20 ft, Now the beds dip into
the pit at 40 0 from the horizontal,so that in some cases considered p is i the
that the cables are anchored beyond the bedding planes which pass through the
toe. If this equation yields a length of < (15 + x) = 35 ft, then a minimum
cable length of 35 ft should be used. Hence the cable lengths for each hole are:
84
o
Cable No. a - 40 0 a = 45 0 a = 50 0 a = 55 0 cc = 60
9 35 * 43.5 64 83.5 99
10 35 * 35* 42 52 59.5
11 35 * 35 * 35 * 35* 35*
,
(a) if cp < a
Sin a ay
where 1(1 = and k -
z tCos
Cos (a+A) + Sin (a+A.)1
[ • 2 2 Sin a
or (b) if CD >
a 400
45 ° 50 ° 55
0
60 °
are valid. Hence in these cases we must calculate Te for both solutions and
(a) if cP < cc
Te = {k1 [Cos(a-4) + Sin (a-l-q))] + k 2 Sin (cc- q))} { Sin CP - g Cos cpj (19)
or (b) if cp > a
Thus, substituting for valid valuesof cP and w = 30 ft, y = 165 lbs/sq ft,
Œ
ID 0 o o
40 ° 45 50 55 ° 60
cp from (22) Invalid Invalid 47 ° 54' 49 ° 30' 50 ° 36'
i.e., in this example the maximum Te values are always those given by equation (25).
3. Calculate the mesh tension T for idealized support (i.e. for safety factor of 1)
a Te
(28)
T [Cos (cP-Fz,) + g Sin (CP+A) I Sin CP
cio T lbs
40 48 ° 6' 13,600
45 52 ° 30' 25,700
50 56 ° 15' 33,800
55 60 ° 30' 54,800
60 64 ° 6' 71,000
88
A0
_o
if uo = 71,000 psi,then:
50 33,800 0.476
55 54,800 0.772
60 71,000 1.00
meshes are not sufficiently strong to completely support the bench. For the
0
40 0 and 45 cases the available meshes will be heavy. Further, since they
will be loading beams of fairly wide span it is almost certain, without further
resist the bending moments imposed by these mesh loads. Hence it is not
possible to completely support these benches for any of these cases. Let us
what mesh size would allow the full strength of this beam to be utilized and
5. Horizontal Stringers
concrete beam size 18 in. x 18 in. containing 8 of No. 10 bars (10 sq inches); let
mesh steel required to be fully loaded in order to fully load this beam is
89
10 A, j d
Ao uo 1 2 '
Thus, for the spans 1 required for the cable spacings,this yields the following
values:
Due to the very large spans for the lower a values, the area of
steel required to fully load the beam is very small and is below that of a
suitable available mesh. In these cases a very light-weight mesh has been
chosen merely to control loose rock; it could not possibly provide significant
0
bench support. For the 55 and 60 0 cases,available meshes would allow the
beam to be fully loaded and would thus allow some small amount of bench support
to be obtained. Let us now calculate the bench support safety factor for these
cases.
Firstly, given the above mesh areas we can calculate the mesh tension,
TF
and the safety factor S FB = 7-e. where Te is the previously calculated value of
Hence,
a A T lbs YEF Te S FB
-7 -2 -4 -6
40 6.5x10 4.6x10 8.5x10 250 3.4x10
-5 -2 -4
45 4.3x10 3.05 6x10 504 1.2x10
-3 -3
50 2.2x10 159 326 685 4.8x10
-2 -2
55 6.65x10 4760 100.5 « 1155 8.7x10
-1 -1
60 1.16x10 8240 177 1520 1.16x10
From this it is seen that for a = 40, 45 ° and 50 ° the bench support
be only to prevent small rocks frow falling. For the cases of a = 55 0 and 60 ° a
means of bench support is, in the cases considered here, not justified. The
laying of a light-weight mesh over the surface might be useful to help control
loose rock. However, benches are normally designed to catch and thus help
control loose rock; in consequence, the use of even a light-weight mesh for this
purpose may not be justified. If, on the other hand, the slope were to be
that mesh would provide a very good method to control loose rock and, since the
loads on the mesh without benches would be much less, might well give sufficient
resistance to prevent failure of the ground not supported by the cable anchors.
91
-.. for this exercise at least, that mesh is installed to control the loose rock.
-
I'.
92
cOST ANALYSIS
Using the cost analysis figures derived in Part II, the costs of
supporting these hypothetical slopes at cc = 40, 45, 50, 55 and 60 ° have been
calculated and are listed in the Table 4. Figure 29 shows the resulting cost
per linear foot versus slope angle. It is seen from this figure that the cost
per linear foot of the support system increases rapidly with increase of the
slope angle.
angle of 371/2 0 had no support been used,then there will be a saving of costs
through not ekcavating excess waste rock (in these cases, no allowance will be
made for possible increased revenue from the ability to excavate deeper ore levels
where O is the angle at which the slope would have been mined without use of
support ( O = 37k ° in this case). Table 5 gives the volumes saved and,
assuming an excavation cost of $0.34 per ton, lists the expenditure saved. IL
ference between the expenses saved and the support costs,then Table 5 also lists
this profit margin. Figure 30 shows the profit per linear foot versus slope
0
angle. It is seen from this figure that there is some angle (Cc= 53 in this
case) when the profit per linear foot is optimized, i.e. if a steeper slope
angle were chosen the increased cost of the support system would outweigh the
savings due to not excavating waste rock. Likewise, if a lower slope angle
TABLE 4; COST ESTIMATES
a . 60o
ITEM, RATE,ETC. a - 40 0 $ a - 45' $ a 50 ° $ O. = 55 ° $ $
3. MESH choose 5-ft- Span 920 ft Span = 114 ft Span = 50 ft Span = 29 ft Span = 22 ft
wide mesh, allow 6- No. widths230 No. widths=29 No. widths=13 No. widths=7 No. widths=6
inch overlap. 10-ft sq ft/bench sq ft/bench sq ft/bench sq ft 'bench sq ft bench
overlap on ends. = (100)x5x230 = 100x5x29 (100x5x13) = (100x5x7) = 100x5x6
Cost $150/ton x 10 benches x 10 benches x 10 benches x 10 benches x 10 benches
22-616 mesh=12.92 22-1616 mesh=12.92 22-1616 mesh=12.92 66-53 mesh=48.77 316-610 mesh =451
lbs. per100 sq.ft. lbs per 100 sq. ft. lbs per 100 sq ft. lbs per 100 sq.ft. lbs per 100 ''sq ft.
Total weight Total weight Total weight Total weight Total weight
= 74.5 ton at = 9.3 tons at = 4.2 tons at = 8.5 tons at = 6.75 tons at
$150/ton 11,200 $150/ton 1,400 $150 / ton 650 $150 / ton 1,300 $1501ton 1,000
Equipment at 8 hrs/ 10 panels, 8 hrs 10 panels, 8 hrs 10 panels, 8 hrs 10 panels, 8 hrs 10 panels, 8 hrs
panel at $10/hour at $10/hr 800 $10ihour 800 *10 / hour 800 $10ihour 800 $10,hour 800
. 4. HORIZONTAL STRINGERS
Forming & Steel work 8 No. 10 bars x 8 No. 10 bars x 8 No. 10 bars x 8 No. 10 bars x 8 No. 10 bars x
Steel at $150;ton 920ft at 4.31bs/ft 114ft at 4.31bs/ft 50ft at 4-31bs / ft 29ft at 4.31bs ft 22ft at 4.31bs ; ft
X 11 stringers x 11 stringers x 11 stringers x 11 stringers x 11 stringers
= 18.7 tons ' = 1.17 tons = 0.5 tons = 0.3 tons = 0.23 tons
• 175 at $150/ton 75 at $150/ton 45 at $150iton 35
at $150/ton 2,800 at $150 / ton
Forming at $1/ft 920 ft x 11 10,200 114 ft x 11 1,250 50 ft x 11 550 29 ft x 11 320 22 ft x 11 240
Labour 1.2 hrs/ft footage =920x11 footage =114x11 footage =50x11 footage =29x11 footage = 22x11
hrs = 10,200 hrs hours = 1,250 hours = 550 hrs hours = 320 hrs hours = 240 hrs
5,100 at $2.50 12,750 625 at $2.50 1,560 275 at $2.50 690 160 at $2.50 400 120 at $2.50 300
5,100 at $3.10 15,800 625 at $3.10 1,940 275 at $3.10 855 160 at $3.10 495 120 at $3.10 340
15 7, overhead 4,270 15 7, overhead 525 15 7 overhead 230 15 7, overhead 135 15% overhead 95
- . I
Table 4, cont d-
4. HORIZONTAL STRINGERS
(cont i d) .
Labour 1.25 hrs/cu hours = 1040 - hours = 130 hours = 56 hours = 34 hours . 25
Yd 520 at $2.50 1,275 65 at $2.50 160 28 at $2.50 70 17 at $2.50 45 13 at $2.50 35
520 at $3.10 1,610 65 at $3.10 200 28 at $3.10 90 17 at $3.10 55 12 at $3.10 40
15% overhead 435 15% overhead 55 15% overhead 20 15% overhead 15 15 7, overhead 10
. 5. CABLE ANCHORS 11 anchors x • $40.50 495 11 anchors x $40.50 495 11 anchors x S40.50 495 11 anchors x $40.50 495 11 anchors x $40.50 495
$40.50 per anchor 581 ft at $1.20/ft 700 884ft at 1.20/ft 1,060 1445 ft at 1.20.ft 1,735 198C0-2 ft at 1.20'ft 2,380 2409 ft at 1.20/ft 2,900 I
(.0
plus 1.20/ft. hours = 52 hours = 80 hours = 130 hours = 178 hours = 217 -1=.
Labour 0.09 hrs/ft 26 at $2.50 65 40 at $2.50 100 65 at $2.50 165 89 at $2.50 225 109 ai $2.50 270 1
26 at $3.10 80 4 0 at $3.10 125 65 at $3.10 205 89 at $3.10 275 108 at $3.10 335
lepoverhead 25 15% overhead ' 35 15% overhead 55 15% overhead 75 15% overhead 90
- . .
6. GROUTING 11 anchors x 6 hrs 11 anchors x 6 hrs 11 anchors x 6 hrs 11 anchors x 6 hrs 11 anchors x 6 hrs
. 6 man-hours/anchor = 66 hours . 66 hours = 66 hours . 66 hours :' 66 hours
. 33 at $2.50 80 33 at $2.50 80 33 at $2.50 80 33 at $2.50 80 33 at $2.50 80
3 3 at $3.10 100 33 at$3.10 100 33 at $3.10 100 33 at $3.10 100 33 at $3.10 100
15% overhead 30 15% overhead 30 15% overhead 30 15% overhead 30 15% overhead 30
Cement $5/hole 11 holes at $5 55 11 holes at $5 55 11 holes at $5 55 11 holes at $5 55 11 holes at $5 55
Equipment rental $60
/month assume 1 • .
month per level 11 levels at $60 660 11 levels at $60 660 11 levels at $60 660 11 levels at $60 660 11 levels at $60 660
- c on clurlf.d
e( a
IL
Table 4 (concluded)
...
8. FINAL GROUTING .035 x 581 .035 x 8841/2 .035 x 1445 .035 x 1980'2 .035 x 2409
.035 man—hrs/ft ,.. 20 hours = 31 hours = 51 hours = 70 hours = 84 hours
10 at $2.50 25 16 at $2.50 40 26 at $2.50 65 35 at $2.50 90 42 at $2.50 105
10 at $3.10 30 15 at $3.10 45 25 at $3.10 80 35 at $3.10 110 42 at $3.10 130
157. overhead 10 157. overhead 15 157. overhead 25 157. overhead 30 15% overhead 350
grout at $0.12/ft
(min $5) 581 x 0.12 70 8841/2 x 0.12 105 1445 x 0.12 175 19801/2 x 0.12 240 2409 x 0.12 290
Mixer & pump $60/
month assume 1 month/
level 11 levels 660 11 levels 660 11 levels 660 11 levels 660 11 levels 660
(.71
96
2000 r
1900
1800
1700
1600
1500
1400
e: 1300
4,
F.: 1200
o
o
IL 1100
w l000
900
0- 800
0 700
o
600
500
400
300
200
100
0
40° 45° 50° 55° 60°
a SLOPE ANGLE
Figure 29. Support costs per linear foot versus slope angle.
TABLE 5: EXCAVATION SAVING AND PROFIT/LINEAR FOOT, BY USE OF SUPPORT
SLOPE ANGLE VOLUME EXCAVATION SAVED * V Cu V tons EXCAVATION SUPPORT COSTS PROFIT PER
o yds at 2.23tons/cu yd SAVINGS AT PER LINEAR FT LINEAR FT
a V =±[Cot 0-Cot ajcu ft/linear ft $0.34/ton
2
1000
900
800
PRO FIT $ PE RLI NEARFT
700
MK
600
500
400
300
200
100
45° 50°
a SLOPE ANGLE
Figure 30. Profit per linear foot versus slope angle.
99
were chosen,the full benefits of waste rock excavation saving would not be
The above analysis has been carried out assuming that horizontal
stringers and mesh have been used to control the loose surface rock unsupported
by the deep cable anchors. If it is deemed that the bench design is adequate
to control this loose rock, then the mesh and stringers need not be used. In
such a case,lable 6 lists the overall support costs, the profits, etc.
Figure 31 compares the profit margins for the cases of mesh and no mesh over
the benches. The latter case optimizes at a slightly lower angle (52 ° ) and
respectively, the profit is increased from approximately $980 per ft with mesh
`zr
TABLE 6: SUPPORT COSTS, EXCAVATION SWINGS AND PROFIT PER LINEAR FOOT -
IF NO MESH USED WITH SUPPORTS •
SLOPE ANGLE TOTAL SUPPORT COST COST/LINEAR FT EXCAVATION SATM:3-'S, PROFIT PER PROFIT PER INCREASED PROFIT
o (NO MESH OR STRINGERS) OF SUPPORTS $/LINEAR FOOT LINEAR FT LINEAR FT . WHEN NO MESH
Cc (NO MESH) (WITH MESH) USED'S/FT
1300
1200
1100
1000
cr 900
4
•ct
800
o_
700
I-
I 600
o
500
400
200
100
0
40 0 45° 50 0 550 60°
a SLOPE ANGLE
ACKNOWLEDGEMENTS
The work and report were completed with the assistance of many
individuals on the staffs of the Company and the Mines Branch's Mining
REFERENCES
5. Urquhart, L.D., O'Rourke, C.E. and Winter, G., "Design of concrete struc-
tures", McGraw-Hill Co. Ltd., New York, 6th Edition, 1958.
Sr 1/4.
103
Number of Strands 6 8 9 12 6 8 9 12
Maximum Initial*
Tensioning Load(Lb.) 172,800 230,400 259,200 345,600 198,2.10 264,320 297,360 396,480
(80% of Ultimate)
Tendon Weight
(Lb./Ft.) 2.96 3.95 4.45 5.93 3.15 4.20 4.73 6.30
(without enclosure)
* II> The magnitude of effective design forces attainable with post-tensioning tendons
is a function of length and curvature of the tendons as well as the friction character-
istics of the enclosure.
See calculation of elongations and pressures for Freyssinet post-tensioning cables (Reference 7).
104
APPENDIX II: BENCH STABILITY ANALYSIS: ANGLE ce AT WHICH THE EXCESS SHEAR -
STRESS Te REACHES A MAXIMUM
're = Ik1 [Cos (a+cp) + Sin (a+p)] + k2 Sin (a-c,0 )] [Sin cP-11 Cos 0 (A2.1)
where k = w Sin Œ ay
1 and k2 (A2.2)
2 [Cos(a+A) + Sin (Œ+A) f 2 Sin a
bTe r
= [k1[ -Sin(Œ+m) + cos(a+cp)] - k 2 cos(a-cp)itsin cp-11 cos + [k i [cos(al-cp)
àcp
= k i lCos 2cp Cos a-Sin 2p Sin a) + ki[Sin 2cp Cos a + Cos 2p Sin ai
-k 2 [Sin 2c,0 Cos a - Cos 2cro Sin al + 11k 2 {Cos 2cp Cos a + Sin 2cP Sin al
= Cos 2cp [1( 1 Cos a + 1( 1 Sin a + p.ki Sin a - 'A l Cos a + k 2 Sin a + p.k 2 Cos a)
- 11(2 Sin al
=0
165 Sin(50) x 40
then k1 =
2 (Cos(40) + Sin(40)) — 1795
66 x 165
k2 — = 7110
2 Sin 50
Te = f1795(Cos 98 °48' + Sin 98 °48') + 7110 Sin(50-48 °48')1 (Sin 48 °48'-.8 Cos48 °48)
Weight Weight
per 100 Spaving ,,r SteelWire
Sret. . r r a. prr 100 Spacing of
Steel Wire
Seer. Area.
Square Wiren Stpiare Indu , Square Wiren Square Inches
Feet inhwhen Gauge No. per rmll Feet in f Gauge No. per Foot
Style Bentdon Si de Ilu•ril on
Net Ni
Width Width
a no" of fde
Lmie. Trann. Longit. Lonait. Trann. Longit. Longit, Trans. Longit. Trans.
--
22-1616* 13 2 2 16 lb .018 .018 412-1212* 13 4 12 12 12 .026 .009
22-1414* 21 2 2 14 14 .030 .030 412-1112* 16 4 12 11 12 .034 .009
22-1313* 2 2 13 13 .039 .039 412-1012 19 4 12 10 12 .043 .009
22-1212* 37 2 2 12 12 .052 .052 412-912 22 4 12 9 12 .052 .009
22-1111* 48 2 2 11 11 .068 A168 412-812 25 4 12 8 12 .062 .009
22-1010 60 2 2 10 10 .086 A/86 412-711 4 12 7 11 .074 .011
24-1414* 16 4 14 14 .030 .013 412-610 36 4 12 6 10 .087 .014
24-1314* 19 2 4 13 Ut .039 .015 412-510 42 4 12 5 10 .101 .014
24-1212* 28 2 4 12 12 .052 .026 412-57 45 4 12 5 7 .101 .025
212-38 105 2 12 3 • 8 .280 .021
412-49 49 4 12 4 9 .120 .017
212-06 166 2 12 0 6 .443 .029
216-812 46 2 16 8 12 .124 .007 416-1012' 18 4 16 10 12 .043 .007
216-711 .55 2 16 11 .118 .008 416-912 21 4 16 9 12 .052 .007
216-610 65 2 16 6 10 .171 .011 416-812 25 4 16 8 12 .062 .007
TABLE A3.2
Approximate Weights in Pounds per 100 Square Feet - Based on 60' width c. to c. of outside longitudinal wirea.
Weight of Longitudinal Members
Steel Wire •
Gauge Spacing
Numbers
2" 3' 4' 6' 8" 10' 12'
. . .
TA B LE A3.3
0000000 .1900 .18857 .6104 1.1:31 .751 .366 .377 .283 .226 .189 .141
000000 .4615 .16728 . - .3681 1.001 i .669 , ' .302 .335 .251 .201 .167 .125
00000 .1305 .14556 J .1943 .873 . .582 .437 .29.1 .218 .175 .146 .109
0000 .3938 .12180 • .4136 ; .731 .487 .365 • .244 .183 .146 .122 .091
E
000 .3625 .10321 .3505 .619 .413 .310 .206 .155 .124 .103 .077
00 .3310 • .086049 .2922 • .516 i 344 ' .258 .172 .129 .103 .086 .065
.3065 • .073782 .2506 -.443 .; .295 .221 .148 .111 .089 .074 .055
1 .2830 .062902 .2136 .377 . .252 .189 .126 .094 .075 .063 .047
2 .2625 .051119 .1838 .325 .216 .162 .108 .031 .065 .054 .041
.2500 .019087 .1667 .295 . .196 . .147 .098 .074 .059 .049 .037
3 .2437 .016645 .1534 .280 .187 , .140 .093 .070 .056 .047 .035
4 .2253 .039867 .1331 .239 .159 .120 • .080 .060 .048 .040 .030
5 .2070 .033654 .11.13 .202 .135 , .101 .067 .050 .040 .034 .025
6 .1920 .028953 .0t»332 .174 • .116 .087 .058 .043 .035 .029 .022
7 .1770 .021606 • .08350 .148 .098 .074 .049 .037 .030 .025 .018
8 .1620 .020612 j .07000 .124 .082 .062 .041 .031 .025 .021 .015
9 .1183 ' .017273 .03866 ; .104 .069 .052 .035 .026 .021 .017 .013
10 .1350 .014314 .01861 :086 . .057 .043 .029 .021 .017 .014 .011
11 .1205 .011104 .03873 .068 • .016 :034 .023 .017 .014 .011 .009.
12 .1055 , .0087417 .02969 .052 .035 ' .026 .017 .013 .010 .009 .007
13 .0915 - • .0065755 .02233 .039 " .026 .020 .013 .010 .008 .007 .005
14 . .0800 .0050266 .01707 " .030 .020 .015 .010 .008 ; .006 .005 .004
15 .0720 .0010715 .0138:3 .024 " .016 .012 .008 .006 .005. .004 .003•
16 .0625 .0030680 .01042 .018 .012 .009 . .006 .005 .004 .003 .002
I
:
* Based on the number of eighths of an inch included in the nominal diameter of the
bars. The nominal diameter of a .deformed bar is equivalent to the diameter of a
plain.bar having the sanie weight per foot as the deformed bar. Bar No. 2 in plain
rounds only. All others in deformed rounds.
t APproximate to the nearest in.
No. 4 0.39 0.58 0.78 0.98 1.18 1.37 1.57 1.77 1.96 2.16 2.36 2.55 2.75 ,
No. 5 0.61 0.91 1.23 1.53 1.84 2.15 2.45 2.76 3.07 3.37 3.68 3.99 4.30
No. 6 0.88 1.32 1.77 2.21 2.65 3.09 3.53 3.98 4.42 4.86 5.30 5.74 6.19
No. 7 1.20 1.80 2:41 3.01 3.61 4.21 4.81 5.41 6.01 6.61 7.22 7.82 8.42
No. 8 1.57 2.35 3.14 3.93 4.71 5.50 6.28 7.07 7.85 8.64 9.43 10.21 11.00
No. 9 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00 12.00 13.00 14.00;
No. 10 2.53 3.79 5.06 6.33 7.59 8.85 10.12 11.39 12.66 13.92 15.19 16.45 17.72
No. 11 3.12 4.68 6.25 7.81 9.37 10.94 12.50 14.06 15.62 17.19 18.75 20.31 21.87
•. ■
110
Ultimate Maximum
Strength Recommended Recommended
Nominal Guaranteed Initial Tensioning Final Design
Nominal Nominal I
Minimum Load-0.7 f's Load-0.6 Ést
Bar Weiaht Area
Sq.
Size Pounds
REGULAR I SPECIAL REGULAR 1 SPECIAL g REGULAR SPECIAL
0" I Lin/Ft. Inches
160 ksi 101.5 ksi g 112 ksi 87 ksi 96 ksi
145 ksi V
(All units in values of 1000 pounds)
.67 .196 28 31 20 22 17 19
1/2
1.04 .307 45 49 31 34 27 30
%
3/4 1.50 .442 64 71 45 50 39 42
tDesign properties indicated are in accordance with ACI tensioning load to obtain actual final design load. Actual
Building Code 318-63, Sections 2606 and 2607. Temporary final design load, after losses are accounted for, may be
jacking stresses up to 0.8f's are permitted to 'overcome less than 0.6f's.
losses due to tendon friction, anchorage seating and elastic
shortening. Losses due to creep, shrinkage and steel relax- See Specifications page 27 for a full description of
ation should be deducted from the recommended initial physical properties.
a
111
capacity of 500,000 lbs (250 tons), to monitor the tension on the cables over
tensile steel (Atlas SPS 245) which has a yield strength of 140,000 psi was
chosen for the load-bearing member. The load cell dimensions were designed to
Figure A6.1 shows a section through the load cell. The load cell
is basically a hollow steel cylinder with the top and bottom taking the form
of the letter "I" for better stress distribution in the steel. The cable
passes through the centre of the cell and the dimensions of the central hole
were chosen so that the standard Freysinnet cone, which anchors the cable, would
fit on top of the cell and by bearing directly on the cell transmit the cable
load to it.
check and to give a safeguard against any possible breakdown. The measuring
systems are vibrating-wire strain gauges and resistance strain gauges. Since
eccentric loading on the cell was a distinct possibility, four vibrating wires
and four sets of strain gauges were placed at 90 0 intervals around the central
The accuracy and range of the vibrating wires depend on the wire
« length; this length was pre-calculated from the elastic properties and dimen-
sions of the steel cylinder. Temperature change should not affect the
I •-)
COVER
CLAMP'
:to
VIBRATING WIRE
MAGNET cb
8.25" DIA.
6.375" DIA.
tn
o
VIBRATING WIRES
>—
0
cu 200 6 Li
I-
-1
u.. 0
—
W
° 400
4 O
W
•z1C
C.)
CD
600 2
CD
Cr Er
800 o
0 50 100 150 É oo 250
LOAD TONS
vibrating-wire readings since the vibrating wire and the steel cylinder have
The accuracy and range of the resistance gauges were also estimated
for design from the properties of the cylinder. Two 120-ohm gauges were bonded
in the vertical position and two similar gauges were bonded in the horizontal
compensation gauges. All the resistance strain gauges were wired in a simple
Wheatstone bridge network,so that the strains from each of the 90 0 interval
positions were averaged. The strain gauge output was read with a potentiometer
rather than the more usually used strain indicator. This enabled a constant
current supply to be used rather than the normal constant voltage supply. The
maximum design capacity. Both uniform and eccentric loads were applied to
the cell during these tests, the load being applied through the Freysinnet
cone arrangement used with the cables. In addition, three load cells were sub-
jected to a constant load of 250 tons for a period of 4 days to determine the
amount of hysteresis recorded by both the resistance and vibrating wire gauges*;
this may be a feature of the steel used in the cell. The strain gauge cali-
bration curve is slightly non-linear at loads below 75 tons and linear between
this value and 250 tons. Since the in-situ cable load was about 200 tons,
114
the strain gauges were operated over the linear portion of the curve. The
vibrating-wire calibration curves are non-linear over the loading range. Con-
in the cells. The calibration curves for uniform and eccentric loads were
250 tons, the maximum variation of the strain gauge read-out was 0.09 millivolt,
vibrating wire and the strain gauges was found to be better than + 300 lbs
for all cells,and their overall accuracy was better than + 3000 lbs.
11.5
7. Television Photo of a Joint Parallel to 8. Core from the Same Position as Photo 7,
the Hole Axis. Showing Longitudinal Joint.
,
9. Cable Anchor Assembly - 12 Strand Cable 10. Cable Anchor Assembly - Cutting Strands
Assembled an Site from Individual Strands. to Length.
11. Cable Anchor Assembly- Strand Spacer. 12. Cable Anchor Assembly- Positioning the
Strands on the Spacer.
13. Assembled Cable Showing Spacer in 14. Installing the Cable.
Position and Nose Cone.
15. Stressteel Rod - Female Coupling, 16. Stressteel Rod - Male Coupling,
17. Installing the Stressteel Rod. 18. Mesh Lengths Laid Out and Wired
Together on the Surface,
23. Wire Roll Anchored Temporarily 24. Wire Mesh Rolled Over Bench Edge.
by Short Bolts.
I a
.
f
• •
27. Form Work for Horizontal Concrete 28. Concrete Strain Gauges in Bricks to be
Stringer - Lower Bench. Cast into the Stringer.
411
"
teMb ....110
.•
S.
,
. .
Cara
29. Concrete Stringer Poured, 30. Form Work for Anchor Pads on Top
Bench and Steel Bar Horizontal Stringer.
31. Extensometer Installations (Top Bench). 32. Extensometer Installations (Lower Bench).
33. Beam and Studs for Surface Displace- 34. Beams and Studs for Surface Displace-
ment Measurements - Lower Bench. ment Measurements - Upper Bench,
M. Dial Gauges Probing Surface Studs. 36. Cable Anchor Tensioning Jack,
37. Strand Attachment to Jack. 38. Load Cell Between Concrete Pad
and Tensioning Jack,
39. Cone and Wedge to Lock Cable. 40. Use of a Chair to Release Cone and
Wedge Lock,
N a
•
41.Cable Tensioned and Locked. 42. Stressteel Anchor and Load Cell-
a
APPENDIX IX: CONSTRUCTION COSTS OF TRIAL INSTALLATION
1. Site preparation
3. Wire Mesh
Concrete work
m
Labour, 10 man-hours [5 hrs at $2.50/hr,
5 at 3.10/hr + 15%1 $ 32.00
6. Anchors
7. Grouting of Anchors
a
8. Tensioning Anchors
Total
Type 1. 12/0.5 tendon
TOTAL $8173.00
132
anchors against the concrete anchor pads is, in effect, a plate load test.
around the pads during several cycles of loading on each pad prior to final
distances from the anchor pads by probing steel studs set 6 inches into the
surface rock at various distances from the anchor pads. These studs were
concrete at approximately 8 ft from the anchor pads. It was assumed that the
support 8 ft away was outside the influence of the load on the rock. Figure
Whilst it was planned to carry out these tests on all four anchor
pads,in fact only two were successfully completed. It was found that the displace-
ment base set up around the 55-ft hole was not stable and in consequence
erratic dial gauges readings were obtained. Tests at this site were therefore
was possible to load the cable during the up cycle satisfactorily, the stretch
of this long cable was such that the ram extension was fully used up and the
cable had to be locked, the rani retracted and then loading recommenced half-
way up the loading cycle. This readjustment of the ram during the cycle
LOAD APPLIED BY CABLE
r
MIILMIW IT,
le
ALUMIN UM BEAM DIAL GAUGES PROBING STUDS
BEAM SUPPORT,
CONCRETE ANCHOR PAD
STEEL SET IN CONCRETE
produced problems during the down cycle, as it was found to be very difficult
to unlock the cable for relaxation in the middle of the down cycle. A ram with
a longer extension was not available; thus,this test was discontinued after
one complete load application and a reduction to half level. The cable was then
loaded to its final tension. This completion of only 3/4 of a load cycle was
cable and on the 110 ft cable. These results are now presented and interpreted.
Figure A 10.2 shows typical load-deformation plots for the first pins on either
side of the concrete "plate", for each of the three load cycles. It is seen
due to closing of joint and fissures, etc. Thereafter the second and third
cycles are fairly repeatable. From these graphs for all the measuring studs,
the displacements were plotted against their distance from the loading point
for three load levels at 100,000 lbs, 200,000 lbs, and 300,000 lbs. Figure A10.3
shows these displacements for the first cycle, and for the mean values of
the second and third cycles, for the tests at the 33-ft cable site. The rock
assumed), that this footing is rigid,and that V is the Poisson's ratio, then it
has been shown (9) that the displacement of the surface at any point at radius
Q(1-V2 ) Sin
d -
ITRE
LEGEND
—X-- I st cycle
- - -0- - 2nd cycle
3rd cycle
400 r 33-ft cable: No.I load cell 400 33-ft cable: No.I load cell
Pin I left Pin 2 right
I strand of cable broke
3501- 350
X 101 /)(x b
/ /
/ t1
/ . „e, / 1
300 300 / I
/ 4
•e
0 •
/ I •
; i• 1:
LBS
1, /
LBS
I 1 1 t '
250 / ? 4 250 r 4
3
0
/ X 0 .-
.
3
/ :1 / f .
CABL E L O ADx10
4 ir 1
CABL E L OADx10
/
0 °1 ,
200E / / i 200 / x ■eF F—.
/ î) (.0
i • ln
0
i
i
41
:I•• f
I
I
0
/
/
.
•
-
I
I
150E- f / 1 150
4.
o/
/
,.. I I
0
0
/ A/ I
/ •/ /
1001- / / 100 / 4 /
/ .
o • e • 1
/ in:
501- /
A
I
I..
:
(i.- i
,
X
4,
,
_„- 20 minute wait,
between cycles
50
/ ••
,
,
o
i
•
••••
10 15 20 25 30 35 40 45 50 55 0 5 10 15 20 25 30 35 40 45 50 55 60 65
-3
DISPLACEMENT x 10-3 IN. DISPLACEMENT x10 1N.
/ 7 _ , .- --o
0 """•,4e.s 20+ ...-
cr)
30- =
(_)
40- 0
LEGEND re) i / 0
50- I
0
_
• 100,000 LBS
60-
■■■ •• • 200,000 LBS 1
1 70 1 33-ft cable -1st cycle
O 300,000 LBS 1
80
E = (1-30 ± 0-61) x10 5 p.s.i. i.e. ±47%
INCHES INCHES
60 50 40 30 20 10 0 10 20 30 40 50 60
---- -0-- CD
- -.e I0
-"ce- —
Cr. ----
(19
/ ""
20 /' 0
x10 -3 IN CH ES
\
\ \ 30
40
50
POINTS INDICATE EXPERIMENTAL RESULTS.
80
E= (2.32 ± 0.58) x 10 5 p.s.i. i.e.± 25°70
Figure A10.3. Surface displacements during plate load testing„ 33-ft cable site.
137
E was calculated for each point at radius r for each of the three applied
loads,using the measured deflection d at that point. Table A10.1 gives the
results of these calculations for the first load cycle and for the mean dis-
placements from the second and third load cycles. It is seen from this table
that a relatively wide range of moduli are derived from these calculations.
There is a tendency for the high value of modulus to be derived from the low
inches were ignored and the remainder were averaged. These average values so
obtained were:
5
for the first cycle: E - 1.30 + 0.61 x 10 psi
a
5
for the second and third cycles: E = 2.32 + 0.58x 10 psi
Using these values of the modulus, the displacements for all points under each
of the 3 loads were calculated and have been plotted as solid lines in
Figure A10.3. It is seen that these values give reasonable overall agreement
Figure A10.4 gives the similar results for the 100-ft cable site.
plate,due to a large joint intervening between the plate and the first stud.
5
1st cycle: E - (1.27 + 0.45) x 10 psi
(a) •
Pin No. r inches Measured dx10 - in. Calculated Ex10 5 psi Measured dx10 -3 in Calculated Ex10 5psi* Measured dx10 -3 in Calculated Ex10 5 psi*
5L 51.75 0 - o -- o -
4L 42.5 2.5 2.71 5 2.71 6 3.38
3L 33.25 7 1.25 12 1.47 15 1.74
2L 27.75 10.5 1.00 20 1.06 25 1.27
1L 21.25 14 1.04 26 1.13 35.5 1.24
1R 21.50 16.5 0.85 34 0.82 46.5 0.90
2R - 29.50 14 0.71 28.5 0.70 39 0.87
3R 37.75 6 1.28 15 1.02 20 1.15
4R 45.25 4.5 1.41 9.5 1..33 . 13 1.45
5R 53:50 4.0 1.33 7.5 1.42 11 1.45
..
-3 5
1st cycle. Mean Modulus (when d > 5 x 10 in) = (1.30 + 0.61) x 10 psi; coefficient of variation = 477
(13 )
33 ft cable: Load cell No. 1. R = 12.25 inches 0.33
-3 5 -s
2nd & 3rd cycles: Mean Modulus (when d > 5 x 10 in.) = (2.32 + 0.58) x 10 p i; coefficient of variation =± 2551.
/ -1
* Calculated from E -
Q(1-y7 ) Sin (R, r)
nRd
a
• ,
À, •Ir
(
tor
• 1 le
INCH ES INCHES
60 50 40 30 20 10 0 10 20 30 40 50 60
,
- 10
—
— --
e '`\‘
20 7 —
.so 30i
\
INCHES - INCHES
60 50 40 30 20 10 0 10 20 30 40 50 60
I _ , F r r
—0—
10+ ■•••••
20 — /
cn
w
\ \ 30 i
u
\\ \ Z /
40 _
1 rn / NO DISPLACEMENTS OCCUR ON RIGHT
1 50— 10 /
1 — HAND SIDE.
1 x I
60
110-ft cable —2nd a 3rd cycles
70+
80+
E = (1-92 0.25) x 10 5 p.s.i. i.e. ±I8-5%
Figure A10.4. Surface displacements during plate load testing - 110-ft cable site.
140
Table A10.2 summarizes these results. Since the 1st cycle results
L
thought that the average of the 2nd and 3rd cycles from each set of results
. 424%.
rock is very much less than would be determined from laboratory measurements.
TABLE A10.2: MODULI DETERMINED FOR SURFACE LOADING AND DISPLACEMENT MEASUREMENTS •
5
33 ft E = (1.30 _+ 0.1)
6 x 10 psi + 0.58) x 10 5 psi
E = (2.32 _
5 5
110 ft E = (1.27 _
+ 0.45) x 10 psi E = (1.92 _
+ 0.35) x 10 psi
holes by down-hole viewing. Four holes were surveyed with the Ontario
Hydro television camera. The purpose was to look at the rock mass that
was to be anchored in situ and to assess the value of the camera as a tool to
drill holes. Since the anchor holes were drilled with H casing (31/2-inch dia-
meter),eccentric spacer rings were required to locate the camera the proper
distance from the wall of the hole. Through the use of a mirror and different
light sources, the camera can be adjusted to view straight ahead (i.e. down the
hole) or at right anglesto the hole axis. Down-the-hole viewing was unsuccess-
ful in this trial mainly because of the larger diameter of the holes. The field
of view, perpendicular to the hole axis, covers about 1/3 of the circumference
contrast, and shape of the object viewed. Clear water is an absolute necessity.
The anchor holes had not been washed sufficiently; motion of the camera caused
a suspension of fine sediment to cloud the image. When clear water conditions
prevail, linear features with high colour contrast can be observed to a minimum.
width of 1/100 inch. Surface relief (i.e. open fractures, loose grains, etc.)
illustrated in Figure A11.1 which shows the television image of a 1/4 - inch grid.
142
the application of this logging technique. Axial distance was measured by the
number of rods in the hole; rotational position was taken as the midpoint
between limits of slack on the marked rods. The individual rods are 3 feet
•
bcrree.i.,gaa.m.arrafflort."FiWere
;
in length and are equipped with a very secure and easily engaged coupling.
Since the viewing was done in sub-horizontal holes, the rotational and axial
friction on the camera and the rods was at a maximum. Measurements of slack
in the couplings are summarized in Table A11.1. As the camera was pushed into
the hole, the trailing cable was taped to the rods about every 15 feet. This
explains the significant difference of the axial slack per coupling observed
TABLE A11.1
Slack in Rod Couplings
(
Axial Rotational
Per coupling 1/8" 10°
a and the average slack over 33 couplings. The rotational slack became quite
small sand-size grains could be seen rolling down the side and coming to rest
on the bottom at the same time the operator pushing the camera was sure that
the camera was facing up. Positioning errors due to axial and rotational slack
and by mounting some dip- or trend-measuring device. Both methods have been
used with the Ontario Hydro television camera in vertical holes. The accuracy
deals with the discontinuities in the rock mass. The data required for fabric
a'
145
. Load Cells
. Extensometers
. Television Survey
. Concrete gauges
TOTAL 18,302.60
KB:DFC:MG/br
21
y\ept
p
LtioLieel