Construction Project Schedule Example-Residential Building: Civilverse Admin 2 May 2021
Construction Project Schedule Example-Residential Building: Civilverse Admin 2 May 2021
Construction Project Schedule Example-Residential Building: Civilverse Admin 2 May 2021
Building
civilverse.org/construction-project-schedule-example
1. Introduction
2. Planning for Construction Project Schedule Example
1. Scope Definition
2. Stakeholders
3. Work Breakdown Structure
3. Developing Construction Project Schedule
1. Defining Activities
2. Sequencing
3. Duration Determination
4. Determination of Critical Path
1. Introduction
A project schedule is an integral part of project management. The project schedule
enables the project manager to place the work scope over a timeline. This way the entire
scope completion can be visualized over time and the start and the completion of activities
can be determined. A well-made and well-maintained schedule helps the project manager
to make the decisions within the deadlines and under the budget.
1/7
The various tools can be used to make a project schedule. The simplest tool being
Calendar and the most used being the Gantt Chart. The popularity of the Gantt Chart is
due to its simplicity and the visualization it offers. It has horizontal bars for each activity
spread over the timeline. The resources can be determined and allotted to each activity.
The resource can be either men, machinery, or material.
The Gantt Chart also helps in determining the cost of the project. The cost of each
resource is determined per unit usage and multiplied by the total number of units and
their usage time for each activity. The summation of the cost of each activity gives the
total cost of the project. The advantage of calculating the project cost with the Gantt Chart
is that it helps in determining the cash requirement over the period of time. Also, the
expensive activities can be determined and special care can be given to them to keep them
under the budget.
The article enlists the steps and detailed construction project schedule example of G+2
residential building.
All things being equal, Winner will be the General who spends more time in Planning
Every project is unique in nature thus every project needs to have a proper plan to execute
it. The planning phase for the construction project schedule example is divided into three
main parts for easier understanding- Scope Definition, Stakeholders, and WBS.
The building is to be constructed in RCC with a shed at the top. The foundation type will
be isolated footing and combined footing. The plinth level to be located 0.3m above the
NGL. The floor heights above the ground floor will be 3m. The staircase to be made in
concrete.
The finishing works include the blockwork, plaster, distemper, and painting. Additionally,
tiling of floors and skirting, sanitary fittings, electrical fittings, shed truss erection,
sheeting work of the shed, and the false roofing below the shed.
2.2 Stakeholders
The key stakeholders with their roles and responsibilities in the given project are as
follows.
2/7
Project Owner- The owner has awarded the contract to the contractor. The owner has
provided the land for the construction, land to accommodate the construction manpower,
a single point for water, and a single point for power. The Project owner has provided
mobilization advance to the contractor and will timely clear the bills raised by the
contractor.
Contractor- The contractor to construct the building as per the design and drawings
within the cost, time, and quality standards. The material, machinery, and manpower are
to be brought by the contractor. The contractor will raise the monthly bills to the owner
against the work done.
District & Other Authorities- The design has been approved by the concerned
authorities along with all the statutory clearances required to construct the building.
The work breakdown structure (WBS) is a scope statement of a project divided into small
and manageable parts. For the construction project schedule example, the WBS is shown
as below-
3/7
The project work has been mainly divided into two major packages- structural works and
finishing works. The Structural work of the building has been further divided into the
foundation, plinth level, first floor, tie beams, and truss/sheeting works. The Finishing
Works have also been divided into several parts such as blockwork/plastering,
plumbing/sanitary, electrification, doors & windows fixing, and Painting/finishing jobs.
The WBS elements can be used as the milestones for the project schedule. The elements
can be equipped with the assumptions and constraints, resources required, cost estimates,
quality requirements, associated schedule activities, agreement information, etc.
The activities are such decided that no activity has a duration of more than 44 days. If so,
the activity should be further split into smaller activities. The activities for each WBS
element are mentioned below-
Plinth Level: Columns up to Plinth Beam Bottom –>Backfilling & Compaction –>Plinth
Beam Reinforcement & Shuttering –>Casting Plinth Beam with RCC –> Ground Soling
and Compaction
First Slab: Columns up to First Slab Bottom –>Shuttering & Reinforcement of Beams &
Slab –> Casting with RCC –>Deshuttering
Second Floor Tie Beams: Columns up to Tie Beam Bottom –>Shuttering &
Reinforcement for Tie Beams –> Casting of Tie Beams with RCC
Truss & Sheeting Work: Truss Erection above Tie Beams –>Sheeting Work
Blockwork, Plastering, False Ceiling Work & Tiling: Blockwork and Plaster for
Ground, and First Floor –> False Ceiling Work for the First Floor –>Tiling for Ground,
and First Floor.
Plumbing & Sanitary: Plumbing & Sanitary Works at Ground, and First Floor.
4/7
Doors & Windows Fixing: Doors and Windows Fixing of Ground, and First Floor.
Painting & Finishing Works: Paint of Ground, and First Floor –>Final Cleaning of
Ground, and First Floor.
3.2 Sequencing
Sequencing is the process of aligning the activities into their order of execution. In
sequencing, the dependencies of the activity are also decided and the activities are
interlinked with each other.
The activities are interlinked with interdependencies such as FS, SS, FF, and SF with
suitable lead and lag. However, as per DCMA guidelines, 90% of the total activities should
be linked with the FS relationship, and the rest with either SS or FF but not SF.
The DCMA also recommends not to use lag in the schedule instead, an intermittent
activity should be used. However, if unavoidable not more than 5% of activities should
have lag. The use of lead should also be minimized as it affects the critical path.
5/7
Finishing Work Activity Relationship
6/7
Duration Estimation for Finishing Works
To determine the critical path, the activities with zero float and their interdependencies
should be identified.
The Critical Path Length Index (CPLI) is the sum of remaining working days on the
critical path and total float divided by the total remaining days. The target CPLI should be
1.
Still curious? Learn How to check schedule quality? or Try Work Breakdown Structure
(WBS) 101.
Happy Engineering!!
7/7