Construction Project Schedule Example-Residential Building: Civilverse Admin 2 May 2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Construction Project Schedule Example-Residential

Building
civilverse.org/construction-project-schedule-example

Civilverse Admin 2 May 2021

Table of Contents for Construction Project Schedule Example-

1. Introduction
2. Planning for Construction Project Schedule Example
1. Scope Definition
2. Stakeholders
3. Work Breakdown Structure
3. Developing Construction Project Schedule
1. Defining Activities
2. Sequencing
3. Duration Determination
4. Determination of Critical Path

1. Introduction
A project schedule is an integral part of project management. The project schedule
enables the project manager to place the work scope over a timeline. This way the entire
scope completion can be visualized over time and the start and the completion of activities
can be determined. A well-made and well-maintained schedule helps the project manager
to make the decisions within the deadlines and under the budget.

1/7
The various tools can be used to make a project schedule. The simplest tool being
Calendar and the most used being the Gantt Chart. The popularity of the Gantt Chart is
due to its simplicity and the visualization it offers. It has horizontal bars for each activity
spread over the timeline. The resources can be determined and allotted to each activity.
The resource can be either men, machinery, or material.

The Gantt Chart also helps in determining the cost of the project. The cost of each
resource is determined per unit usage and multiplied by the total number of units and
their usage time for each activity. The summation of the cost of each activity gives the
total cost of the project. The advantage of calculating the project cost with the Gantt Chart
is that it helps in determining the cash requirement over the period of time. Also, the
expensive activities can be determined and special care can be given to them to keep them
under the budget.

The article enlists the steps and detailed construction project schedule example of G+2
residential building.

2. Planning for Construction Project Schedule Example

All things being equal, Winner will be the General who spends more time in Planning

Sun Tzu in ‘The Art of War’

Every project is unique in nature thus every project needs to have a proper plan to execute
it. The planning phase for the construction project schedule example is divided into three
main parts for easier understanding- Scope Definition, Stakeholders, and WBS.

2.1 Scope Definition


The project is a residential G+1 building located in the suburban area of an Indian city.
The building will be used as a bachelor hostel having eight rooms and two common toilet-
bathroom on each floor, a total of sixteen rooms, and four toilets and bathrooms.

The building is to be constructed in RCC with a shed at the top. The foundation type will
be isolated footing and combined footing. The plinth level to be located 0.3m above the
NGL. The floor heights above the ground floor will be 3m. The staircase to be made in
concrete.

The finishing works include the blockwork, plaster, distemper, and painting. Additionally,
tiling of floors and skirting, sanitary fittings, electrical fittings, shed truss erection,
sheeting work of the shed, and the false roofing below the shed.

2.2 Stakeholders

The key stakeholders with their roles and responsibilities in the given project are as
follows.

2/7
Project Owner- The owner has awarded the contract to the contractor. The owner has
provided the land for the construction, land to accommodate the construction manpower,
a single point for water, and a single point for power. The Project owner has provided
mobilization advance to the contractor and will timely clear the bills raised by the
contractor.

Contractor- The contractor to construct the building as per the design and drawings
within the cost, time, and quality standards. The material, machinery, and manpower are
to be brought by the contractor. The contractor will raise the monthly bills to the owner
against the work done.

District & Other Authorities- The design has been approved by the concerned
authorities along with all the statutory clearances required to construct the building.

2.3 Work Breakdown Structure-

The work breakdown structure (WBS) is a scope statement of a project divided into small
and manageable parts. For the construction project schedule example, the WBS is shown
as below-

WBS of a G+1 Residential Building

3/7
The project work has been mainly divided into two major packages- structural works and
finishing works. The Structural work of the building has been further divided into the
foundation, plinth level, first floor, tie beams, and truss/sheeting works. The Finishing
Works have also been divided into several parts such as blockwork/plastering,
plumbing/sanitary, electrification, doors & windows fixing, and Painting/finishing jobs.

The WBS elements can be used as the milestones for the project schedule. The elements
can be equipped with the assumptions and constraints, resources required, cost estimates,
quality requirements, associated schedule activities, agreement information, etc.

3. Developing Construction Project Schedule Example

3.1 Defining Activities


The activities in a project are the smallest level of breakdown of the WBS elements. It can
be said that the activities sum up to be a WBS element. The activities are decided either by
Expert Judgement, Decomposition, Rolling Wave Planning, or Meeting between the client
and the contractor.

The activities are such decided that no activity has a duration of more than 44 days. If so,
the activity should be further split into smaller activities. The activities for each WBS
element are mentioned below-

Activities for Structural Work-

Foundation: Excavation –>PCC –>Reinforcement & Shuttering –>Casting with RCC

Plinth Level: Columns up to Plinth Beam Bottom –>Backfilling & Compaction –>Plinth
Beam Reinforcement & Shuttering –>Casting Plinth Beam with RCC –> Ground Soling
and Compaction

First Slab: Columns up to First Slab Bottom –>Shuttering & Reinforcement of Beams &
Slab –> Casting with RCC –>Deshuttering

Second Floor Tie Beams: Columns up to Tie Beam Bottom –>Shuttering &
Reinforcement for Tie Beams –> Casting of Tie Beams with RCC

Truss & Sheeting Work: Truss Erection above Tie Beams –>Sheeting Work

Activities for Finishing Work-

Blockwork, Plastering, False Ceiling Work & Tiling: Blockwork and Plaster for
Ground, and First Floor –> False Ceiling Work for the First Floor –>Tiling for Ground,
and First Floor.

Plumbing & Sanitary: Plumbing & Sanitary Works at Ground, and First Floor.

Electrification: Electrification of Ground, and First Floor.

4/7
Doors & Windows Fixing: Doors and Windows Fixing of Ground, and First Floor.

Painting & Finishing Works: Paint of Ground, and First Floor –>Final Cleaning of
Ground, and First Floor.

3.2 Sequencing

Sequencing is the process of aligning the activities into their order of execution. In
sequencing, the dependencies of the activity are also decided and the activities are
interlinked with each other.

The activities are interlinked with interdependencies such as FS, SS, FF, and SF with
suitable lead and lag. However, as per DCMA guidelines, 90% of the total activities should
be linked with the FS relationship, and the rest with either SS or FF but not SF.

The DCMA also recommends not to use lag in the schedule instead, an intermittent
activity should be used. However, if unavoidable not more than 5% of activities should
have lag. The use of lead should also be minimized as it affects the critical path.

To avoid the lead, we shall use intermittent activity in this example.

The relationships among the project activities are given below-

Structural Work Activity Relationship

5/7
Finishing Work Activity Relationship

Download Construction Project Schedule Excel File

3.3 Duration Determination


The duration estimation of project activity is a critical task as the scheduling success
depends on it. As per DCMA guidelines, no activity should have a duration higher than 44
days. If so, the activity should be divided into two or more activities of lesser duration.

The duration of an activity can be determined by either expert judgement or historical


data of similar nature of activity.

The duration of each project activity is as follows-

Duration Estimation for Structural Works

6/7
Duration Estimation for Finishing Works

4. Determination of Critical Path


A critical path in a project schedule is the longest chain of activities required to complete
the project. The duration of the critical path is the minimum time for a project to be
completed. The activities lying on the critical path are called critical activities and they
have zero floats. If the duration of a critical activity is changed, its effect can be seen on
the entire project completion date.

To determine the critical path, the activities with zero float and their interdependencies
should be identified.

The Critical Path Length Index (CPLI) is the sum of remaining working days on the
critical path and total float divided by the total remaining days. The target CPLI should be
1.

Read more about project schedule here.

Still curious? Learn How to check schedule quality? or Try Work Breakdown Structure
(WBS) 101.

Happy Engineering!!

7/7

You might also like