Problem14.
12
a,
b)
LEVEL 1 Period in Weeks
Item ID: B 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 0 0 200 0
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 100 100 100 100 100 100 100 100 0
Net Requirements 0 0 0 0 0 0 100 0
Safety Planned Order
0 0 0 0 0 0 100 0
Stock:0 Receipts
Planned Order 0 0 0 0 100 0 100 0
Releases
Period in Weeks
Item ID: C 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 0 0 200 200
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 50 50 50 50 50 50 50 50 0
Net Requirements 0 0 0 0 0 0 150 200
Safety Planned Order
0 0 0 0 0 0 150 200
Stock:0 Receipts
Planned Order
0 0 0 0 150 200 100 100
Releases
Period in Weeks
Item ID: J 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 0 0 0 100
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 100 100 100 100 100 100 100 100 100
Net Requirements 0 0 0 0 0 0 0 0
Safety Planned Order
0 0 0 0 0 0 0 0
Stock:0 Receipts
Planned Order
0 0 0 0 0 0 0 50
Releases
Period in Weeks
Item ID: K 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 0 0 0 100
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 100 100 100 100 100 100 100 100 100
Net Requirements 0 0 0 0 0 0 0 0
Safety Planned Order
0 0 0 0 0 0 0 0
Stock:0 Receipts
Planned Order
0 0 0 0 0 0 0 50
Releases
LEVEL 2 Period in Weeks
Item ID: D 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 100 0 100 0
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:1 On Hand 50 50 50 50 50 50 50 50 0
Net Requirements 0 0 0 0 100 0 50 0
Safety Stock:0 Planned Order Receipts 0 0 0 0 100 0 50 0
Planned Order 0 0 0 100 0 50 0 30
Releases
Period in Weeks
Item ID: E 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 100 0 100 10
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 75 75 75 75 75 75 75 75 -25
Net Requirements 0 0 0 0 100 0 0 12
Safety Stock:0 Planned Order Receipts 0 0 0 0 100 0 0 12
Planned Order
0 0 100 0 0 125 300 0
Releases
Period in Weeks
Item ID: F 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 300 400 200 30
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:2 On Hand 75 75 75 75 75 75 0 0 0
Net Requirements 0 0 0 0 225 400 0 30
Safety Stock:0 Planned Order Receipts 0 0 0 0 225 400 0 30
Planned Order 0 0 225 400 0 300 600 0
Releases
Period in Weeks
Item ID: G 1 2 3 4 5 6 7 8
Lot Size:L4L Gross Requirements 0 0 0 0 150 200 100 15
Scheduled Receipts 0 0 0 0 0 0 0 0
Lead Time:1 On Hand 75 75 75 75 75 75 0 0 0
Net Requirements 0 0 0 0 75 200 100 15
Safety Stock:0 Planned Order Receipts 0 0 0 0 75 200 100 15
Planned Order
0 0 0 75 200 100 150 30
Releases
Problem14.26
1.
Period 1 2 3 4 5 6 7 8 9 Total
Demand 0 15 0 20 0 10 0 0 25
Planned receipt 0 15 0 20 0 10 0 0 25
Planned release 15 0 20 0 10 0 0 25 0
Beginning Inv. 0 0 0 0 0 0 0 0 0
Ending Inv. 0 0 0 0 0 0 0 0 0
$20
Setup cost $200 $0 $200 $0 $0 $0 $200 $0 $800
0
Carrying cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Stockout cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$800
2.
Average weekly demand (D) = (0+15+0+20+0+10+0+0+25)/9 = 7.778
Holding cost per item per week (H) = $10
Setup cost (S) = $200
EOQ = (2.D.S/H)1/2 = SQRT(2*7.778*200/10) = 17.64 or 18 (rounded off)
Period 1 2 3 4 5 6 7 8 9 Total
Demand 0 15 0 20 0 10 0 0 25
Planned receipt 0 18 0 18 0 18 0 0 18
Planned
18 0 18 0 18 0 0 18 0
release
Beginning Inv. 0 0 3 3 1 1 9 9 9
Ending Inv. 0 3 3 1 1 9 9 9 2
Setup cost $200 $0 $200 $0 $200 $0 $0 $200 $0 $800
$9
Carrying cost $0 $30 $30 $10 $10 $90 $90 $20 $370
0
Stockout cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,170
(c)
Time between orders (TBO) = EOQ/D = 17.64 / 7.778 = 2.26 or 2 (rounded
off). So, club the demands for the two
periods starting from period 2.
Period 1 2 3 4 5 6 7 8 9 Total
Demand 0 15 0 20 0 10 0 0 25
Planned receipt 0 15 0 20 0 10 0 25 0
Planned release 15 0 20 0 10 0 25 0 0
Beginning Inv. 0 0 0 0 0 0 0 0 25
Ending Inv. 0 0 0 0 0 0 0 25 0
Setup cost $200 $0 $200 $0 $200 $0 $200 $0 $0 $800
Carrying cost $0 $0 $0 $0 $0 $0 $0 $250 $0 $250
Stockout cost $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$1,050
(d)
Lot-for-lot is the lowest cost plan with total cost = $800.