MPSC Paper 2 Final
MPSC Paper 2 Final
MPSC Paper 2 Final
CIVIL ENGINEERING
PAPER - II
ACE Engineering Academy has taken utmost care in preparing the MPSC - 2018 Main
Examination solutions. Discrepancies, if any, may please be brought to our notice.
ACE Engineering Academy do not owe any responsibility for any damage or loss to any person
on account of error or omission in these solutions. ACE Engineering Academy is always in the
fore front of serving the students, irrespective of the examination type
(GATE/ESE/PSUs/PSC/GENCO/TRANSCO etc..).
All Queries related to MPSC - 2018 (Main) Solutions are to be sent to the following email address
[email protected] | Contact Us : 040 - 48539866 / 040 - 40136222
MPSC – 2018 (MAIN) Examination
Paper –II (Questions with Detailed Solutions)
01. For finding out time 't2' required to achieve 50% consolidation of 1 m thick clayey strata resting on
impermeable rock at bottom and sandy soil at top, a laboratory consolidation test was carried out,
using 1 cm thick sample obtained from the same strata. Time 't1' was taken by it to achieve 25%
consolidation, under double drainage condition, in the laboratory.
t
Choose the correct value of ratio 2 from the following:
t1
(a) 4,00,000 (b) 16,000
(c) 1,60,000 (d) None of the above
01. Ans: (d)
02. The distance 'D' between centers of piles with top diameter 'd' should not be less than (from
practical consideration)
(a) 2d (b) 3d (c) 4d (d) 5d
02. Ans: (b)
03. Match List-I and List-II and select the correct answer using the codes given below:
List-I (Construction Type)
A. Cut-off trench of a dam to be constructed across flowing river
B. Shallow foundation of a bridge pier
C. Sequential repetition of underwater foundation work
D. Control of groundwater to prevent entry into deep excavation
List-II (Suitable Cofferdam Type)
1. Cellular sheet pile cofferdam
2. Embankment type of cofferdam
3. Single wall sheet pile cofferdam
4. Floating steel cylinder cofferdam
Codes:
A B C D A B C D
(a) 4 3 2 1 (b) 2 1 4 3
(c) 2 3 1 4 (d) 3 4 2 1
05. Let E2 and E1 represent compaction energy deployed for compacting soil as per modified
compaction test and standard compaction test, as per IS:
E
Choose from the following correct ratio of 2 :
E1
1
(a) About 4 times
2
1
(b) About 3 times
2
(c) About 2 times
(d) None of the above
05. Ans: (a)
2682 (kg / m 3 )
4.5 times
596 (kg / m 3 )
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
:3: MPSC – 2018 (MAIN)-Paper-II
06. On the same soil sample, both Standard and Modified Proctor compaction tests are conducted in
the laboratory. The values of Optimum Moisture Content (OMC) and Maximum Dry Density
(MDD) for modified test compared to those for standard compaction test will respectively
(a) Increase, Increase (b) Decrease, Increase
(c) Increase, Decrease (d) No change, Increase
06. Ans: (b)
Sol:
Modified
Density
W.C
OMC decrease
MDD increase
07. If the permeability, shrinkage and swelling of a compacted soil having same density on dry side of
optimum moisture content is compared with compaction on wet side of optimum, the variation in
these properties will be
(a) more, less, higher (b) more, more, higher
(c) more, more, less (d) less, less, higher
07. Ans: (b)
Sol: During drying, soil compacted in the wet side tend to show more shrinkage than those compacted
in the dry side.
Swelling: Due to higher water deficiency and partially developed water films in the dry side, when
given access to water, the soil will soak in much more water and then swell more.
Permeability is also more.
08. An embankment has a slope of 30o which was constructed with soil having C = 30 kN/m2, = 20o
1
and = 15 kN/m3. The height of embankment is 20 m. Using Taylor's stability no. , the factor
40
of safety with respect to cohesion is
(a) 0.25 (b) 2
(c) 4 (d) 1.5
08. Ans: (c)
C
Sol: S
Fc H
1 30
40 Fc 15 20
Fc = 4
(V1 V2 ) 2
(c) h L (d) None of the above
2g
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
:6: Civil Engineering
(V1 V2 ) 2
Head loss at sudden enlargement h L
2g
Depth
yc
Ec
Specific Energy, E
The critical depth has a Froude number equal to one and corresponds to the minimum energy a
flow can posses for a given discharge.
14. In a rectangular channel section, if the channel depth is 2.0 m, the specific energy at critical depth
is
(a) 3.0 m (b) 1.33 m
(c) 2.5 m (d) 1.5 m
14. Ans: (a)
3
Sol: E c yc
2
3
2
2
Ec = 3 m
21. During suction stroke of a reciprocating pump, the separation may take place
(a) at the end of suction stroke (b) in the middle of suction stroke
(c) at the beginning of suction stroke (d) None of the above
21. Ans: (c)
N Q N P
(c) N s (d) N s
H 3m/ 4 H 5m/ 4
22. Ans: (c)
25. In the inlet part of the jet impinging on a Pelton bucket, the velocity of whirl Vw1 is equal to
(a) absolute velocity of jet at inlet V1 (b) relative velocity of jet at inlet Vr1
(c) zero (d) None of the above
25. Ans: (a)
Sol: Vw1 = V1
26. If the turbine has kinetic energy and pressure energy of water at its inlet, then such turbine is
known as
(a) impulse turbine (b) reaction turbine
(c) Pelton wheel turbine (d) low head turbine
26. Ans: (b)
Sol: Refer solution of Q.27
33. Flowing is not the method of apportionment of total cost of multipurpose reservoir
(a) Remaining benefit method (b) Use of facilities method
(c) Equal apportionment (d) Direct method
33. Ans: (d)
Sol: The method of apportionment of total cost of multipurpose reservoir
1. Remaining benefit method
2. Use of facilities method
3. Equal apportionment
4. Alternative justifiable expenditure method
34. Owing to the storage effect, the peak of the outflow hydrograph will be smaller than that of the
inflow hydrograph. This reduction in peak value is known as
(a) Lag (b) Attenuation
(c) Routing (d) Prism storage
34. Ans: (b)
Sol: Attenuation: When a flood hydrograph is routed through a reservoir, owing to the storage effect,
the peak of the outflow hydrograph will be smaller than that of the inflow hydrograph. This
reduction in the peak value is called ‘attenuation’.
37. The ratio of the quantity of water stored in the root zone of the crops to the quantity of water
actually delivered in the filed is
(a) Water conveyance efficiency
(b) Water application efficiency
(c) Water use efficiency
(d) None of the above
37. Ans: (b)
Sol: Water application efficiency (a):
Q plant
a 100
Q field
Qplant = discharge to the root zone of soil during irrigation
Qfield = discharge delivered to field
40. A channel designed by Lacey's theory has a mean velocity of one m/s. The silt factor is unity. The
hydraulic mean radius will be
(a) 2.5 m (b) 2.0 m
(c) 1.0 m (d) 0.5 m
40. Ans: (a)
Sol: Lacey's regime theory V = 1 m/s, f = 1
V2 1
Hydraulic mean radius R 2.5 2.5 2.5 m
f 1
43. In case of non-availability of space due to topography, the most suitable spillway is
(a) Straight drop spillway (b) Shaft spillway
(c) Chute spillway (d) Ogee spillway
43. Ans: (b)
Sol: Shaft spillway:
Also called “drop inlet spillway ” or “morning glory spillway”.
It has horizontally positioned lip through which water enters and then drops through a vertical or
sloping shaft, and then to as horizontal conduit which conveys the water past the dam.
A shaft spillway can be used where there is no adequate space for other types of spillways.
On an earth dam location, if there is no enough space or if the topography prevents the use of the
chute spillway, the best alternative would be the use “shaft spillway”.
44. The channel after obtaining its section and longitudinal slope will be said to be in
(a) Initial regime
(b) Permanent regime
(c) Final regime
(d) Absolute regime
45. The silt load in the stream does not depend upon
(a) nature of the soil in the catchment area (b) topography of the catchment area
(c) intensity of rainfall (d) alignment of dam
45. Ans: (d)
46. Match the design speed recommended for various roads by IRC 86:1983
List-I List-II
A. Collector roads 1. 30 kmph
B. Local roads 2. 80 kmph
C. Arterial roads 3. 60 kmph
D. Sub-arterial roads 4. 50 kmph
Codes:
A B C D A B C D
(a) 2 1 4 3 (b) 3 1 2 4
(c) 4 1 2 3 (d) 2 4 3 1
46. Ans: (c)
47. IRC recommended % value of camber for different types of road surface can be arranged in
descending order of following roads
1. Water bound macadam road
2. Thin bituminous surface road
3. Cement-concrete road
4. Earth road
(a) 4, 2, 3, 1 (b) 3, 1, 2, 4
(c) 4, 1, 2, 3 (d) 3, 2, 1, 4
47. Ans: (c)
Sol: Recommended values of camber for different types of road surfaces:
Range of camber in areas of rainfall range
S.No Type of road surface
Heavy Light
Cement concrete and high type
1 1 in 50 (2%) 1 in 60 (1.7%)
bituminous surface
2 Thin bituminous surface 1 in 40 (2.5%) 1 in 50 (2.0 %)
48. The expression for the length of a transition curve (Ls) in meters is
V3 V3
(a) L s (b) L s
CR 16CR
V3 V3
(c) L s (d) L s
24CR 46.5CR
where
C = Rate of change of radial acceleration in m/s3
R = Radius of the circular curve in metres, and
V = Speed of vehicle in kmph
48. Ans: (a)
Sol: Length of Transition Curves (Ls) based on rate of change of radial (or centrifugal) acceleration:
v3
Ls
CR
Where,
v = Velocity in ‘m/sec’
R = radius of curve in ‘m’
C = rate of change of centrifugal acceleration in m/s3
3
v3 V 1 V3 V3
Ls ≃
CR 3.6 CR 46.656CR 46.5CR
Where,
C = Rate of change of radial acceleration in m/s3
R = Radius of the circular curve in metres, and
V = Speed of vehicle in kmph
49. The design speed adopted for design of rotaries in urban areas of India is
(a) 30 kmph (b) 40 kmph
(c) 50 kmph (d) 60 kmph
pointing downward
a = p – 35 ≯ 40 ; b = p – 15 ≯ 40
c = wL – 40 ≯ 20; d = Ip – 10 ≯ 20
p % Fines passing 75µ sieve
wL Liquid limit
Ip Plasticity index
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
: 24 : Civil Engineering
55. A bridge has a linear waterway of 150 metres constructed across a stream whose natural linear
waterway is 200 metres. If the average flood depth is 3 metres and average flood discharge is 1200
m3/sec, the velocity of approach is
(a) 2.0 m/sec (b) 2.66 m/sec
(c) 6.0 m/sec (d) 8.0 m/sec
55. Ans: (b)
Sol: Linear water way, L = 150 m
Let A Waterway
Average depth of flood, d = 3 m
Flood discharge, Q = 1200 m3/s
A
We've L A L d 150 3 = 450 m2
d
Q Q 1200
A v = 2.67 m/s
v A 450
56. The width of carriageway required will depend on the intensity and volume of traffic anticipated to
use the bridge.
1. Except on minor village roads all bridges must provide for at least two lane width
2. The minimum width of carriageway is 4.25 m for one lane bridge
3. The minimum width of carriageway is 3.75 m for one lane bridge
4. The minimum width of carriageway is 7.5 m for two lane bridge
Which of the statements given above is/are incorrect?
(a) Only 1 (b) Only 1 and 3
(c) Only 1, 3 and 4 (d) Only 3
56. Ans: (d)
Sol: On bridges, carriage way width(CW) with rised kerbs will be used.
Hence width of CW = 4.25 m for one-lane bridge
= 7.5 m for two-lane bridge
= n × 3.5 + 0.5 for multi-lane bridge
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
: 26 : Civil Engineering
57. Which of the following shall be considered while designing high level bridges for buoyancy effect?
(a) Full buoyancy for the superstructure
(b) Full buoyancy for the abutments
(c) Buoyancy forces due to submerged part of the substructure and foundation
(d) Partial buoyancy for superstructure
57. Ans: (c)
Sol: As per IRC, Buoyancy forces due to submerged part of the substructure and foundation will be
used in design.
58. The normal depth of scour for alluvial rivers is determined by Lacey’s formula
3
f Q
(a) 0.475 (b) 0.475
Q f
f Q
(c) 0.4753 (d) 0.4753
Q f
58. Ans: (d)
Sol: Lacey’s formula for normal scouring depth in alluvial streams
1/ 3
Q Q
d 0.475 K = 0.4753 K
f f
Where,
d = Depth of scouring in metres
Q = Discharge in cumecs
f = Lacey’s silt factor
K = a constant. It varies according to the type of river flow
60. The maximum scour depth dm for condition of flow at noses of piers is
(a) 1.50 d (b) 1.75 d
(c) 2.00 d (d) 2.75d
60. Ans: (c)
Sol: Lacey’s formula for normal scouring depth in alluvial streams
d max K d
Where,
d = normal scouring depth
K = a constant. It varies according to the type of river flow
K = 1.27 for straight reach
= 1.50 for moderate bend
= 1.75 for sharp/severe bend
= 2.00 for 90 bend and at the nose of piers
= 2.75 for up stream noses of guide banks.
Therefore 2times maximum scour depth.
61. For high level bridges, the freeboard should not be less than
(a) 200 mm
(b) 400 mm
(c) 600 mm
(d) 800 mm
62. As per IRC specifications, the minimum cement content in concrete is _______ for major bridges.
(a) 340 kg/m3 (b) 350 kg/m3
(c) 360 kg/m3 (d) 370 kg/m3
62. Ans: (c)
Sol: As per IRC 112:Code of practice for concrete road bridges
Minimum cement content for PCC is
250 kg/m3 - for minor works
360 kg/m3 - for major bridges
Minimum cement content for RCC is
310 kg/m3 - for minor works
380 kg/m3 - for major bridges
63. For IRC class A and B loading, the impact factor, for R. C. C. bridges having spans more than 45
metres, is taken as
(a) 0.078
(b) 0.088
(c) 0.098
(d) 0.154
63. Ans: (b)
65. From the economy point of view, tunneling is advisable when the depth of open cut is more than
(a) 6 m (b) 12 m
(c) 18 m (d) 24 m
65. Ans: (c)
Sol: AS per economy consideration, tunnel is advisable if the depth of open cut is more than 60 ft
(= 18.3m).
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
: 30 : Civil Engineering
67. Which of the following methods is suitable for the construction of large-sized railway or highway
tunnels?
(a) Forepoling method (b) American method
(c) Case method (d) Full face method
67. Ans: (b)
Sol: Forepoling Method:
Slow and tedious method requiring skilled miners.
Suitable for tunnels of small dimension, for laying of sewers, gas pipes at ordinary depths.
American Method:
Suitable for large sized railway/highway tunnels.
Case/Army Method:
Suitable for constructing tunnels of small length and fairly shallow depth.
Simple and economical method
Mainly used for laying underground sewers.
Codes:
A B C D A B C D
(a) 2 1 4 3 (b) 1 2 3 4
(c) 3 4 1 2 (d) 4 3 2 1
68. Ans: (a)
Sol: Circular Shape:
Best theoretical section for resisting internal and external pressures.
Provides great cross section area for least perimeter.
D
Best suited in non cohesive soils.
Egg Shape:
r
Maintains self-cleaning velocity of flow of sewage in dry and rainy seasons.
3r
Circular side walls resists internal and external pressures.
r/2
Lesser cross section at bottom and higher cross section at top.
69. In order to maintain the desired shape of the tunnel, the cross section of the tunnel must be checked
at a regular interval of
(a) 2 m to 3 m (b) 4 m to 6 m
(c) 5 m to 7 m (d) 8 m to 15 m
69. Ans: (a)
Sol: Cross section of tunnel must be checked at regular interval of 2-3 m for maintaining shape of
tunnel.
70. Assertion (A): Faces for attacking the excavation and construction of tunnels are opened by
constructing pilot tunnels.
Reasoning (R): Pilot tunnels are suitable at locations when horizontal approach to the centre line
of tunnel is shorter than deep vertical shafts.
(a) Both (A) and (R) are true and (R) is the correct explanation of A
(b) (A) is true and (R) is false
(c) (A) is false and (R) is true
(d) Both (A) and (R) are false.
70. Ans: (a)
Sol: Pilot tunnels are used in locations, where horizontal approach to the centreline of the tunnel is
shorter than deep vertical shaft, which will obtain additional faces for attack.
Main tunnel
Pilot Tunnel
71. Which of the following methods is generally considered the most efficient system for ventilation of
tunnels?
(a) Driving a shaft through the tunnel
(b) Driving a drift through the top portion
(c) Blow in method
(d) Combination of blowing and exhausting
71. Ans: (d)
Sol: Natural ventilation system (by shafts at regular interval and drift from portal to portal) are effective
only for short tunnels.
Mechanical ventilation uses devices like electric fans, exhaust and blowers.
Types:
(a) Blowing: Fresh clean air is blown to the working face, with the help of pipes.
When it flows back to the portal, it takes dust and gases with it.
(b) Exhausting:
It incorporates an exhausting duct near the working face, into which, the foul air and dust
are let out.
By this fresh air is maintained within the tunnel.
(c) Combination of Blowing and Exhausting:
This concept is developed, so that advantages of each system can be combined to make
system of higher performance.
After explosion (or) blasting, the exhaust system will operate for 15 to 30 minutes. This will
remove harmful air immediately.
After this, the blowing system works continuously to supply the fresh air till the next
blasting.
72. In case of long tunnels, the drainage system consists of sump wells which are located at regular
intervals of about
(a) 50 m to 100 m (b) 100 m to 200 m
(c) 200 m to 300 m (d) 300 m to 500 m
ACE Engineering Academy Hyderabad|Delhi|Bhopal|Pune|Bhubaneswar|Lucknow|Patna|Bengaluru|Chennai|Vijayawada|Vizag|Tirupati|Kukatpally|Kolkata|Ahmedabad
: 35 : MPSC – 2018 (MAIN)-Paper-II
76. Sewer lines having difference of more than 600 mm in the water lines and invert level of two
sewers are connected with a
(a) Siphon (b) Manhole
(c) Inspection chamber (d) Drop manhole
76. Ans: (d)
78. For rapid sand filter, sand should have the following specifications:
(a) Effective size 0.1 – 0.5 mm
Uniformity co-efficient = 2 to 4
(b) Effective size 0.2 – 0.5 mm
Uniformity co-efficient = 2 to 3
(c) Effective size 0.45 – 0.7 mm
Uniformity co-efficient = 1.3 to 1.7
(d) Effective size 0.7 – 0.9 mm
Uniformity co-efficient = 1 to 5
78. Ans: (c)
79. If waste water is disposed off into a natural stream, the maximum dissolved oxygen depletion
occurs in the zone of
(a) degradation (b) active decomposition
(c) clearer water (d) recovery
79. Ans: (b)
Sol: The dissolved oxygen reduce to 0 in the zone of active decomposition.
81. The waste water treatment unit which is installed to remove floating substances like grease, oil,
fats, waxes, etc. is
(a) skimming tank
(b) detritus tank
(c) sedimentation tank
(d) None of the above
81. Ans: (a)
Sol: A skimming tank is a chamber so arranged that the floating matter like oil, fat, grease etc. rise and
remain on the surface of the waste water (sewage) until removed, while the liquid floors out
continuously under partitions (or) baffles.
84. The length of a simple circular curve of radices R metres and intersection angle D degrees will be
D D
(a) R. (b) .R.
2 180 2
D
(c) .R. (d) .R.D
180 4 180
84. Ans: (d)
Sol: Length of the curve:
Let the length of the curve T1 CT2 be l and let R be its radius.
Hence l = R ‘ ’ radians
= R × is in degrees
180 o
90. The expression for sensitivity of the bubble tube (α) can be taken as, ____________
Where n = No. of divisions s = Net staff reading
d = Distance R = Radius of curvature
l = Length of one division
s
(a) 206265 seconds
nd
d
(b) 206265 sec onds
ns
nD
(c) radiance
R
s
(d) .
nR D
(a) e ( L2 D 2 ) 2 (b) e ( L) 2 ( D) 2
(c) e L D (d) e ( L) 2 ( D) 2
D
C E
B e A
A –D –L
Closing Error
94. In order to compute the quantities of R.C.C. beams, lengths of beams are measured to the
(a) nearest millimetre
(b) nearest half centimetre
(c) nearest centimeter
(d) nearest inch
94. Ans: (a)
Sol: For accurate estimation the length, breadth and height are measured to the nearest 0.001 m =
nearest millimeter.
96. Which of the following types of contract is used for execution of large works financed by public
bodies or the government?
(a) Item rate contract (b) Percentage rate contract
(c) Cost plus type contract (d) Target contract
96. Ans: (b)
Sol:
In Government works profit percentage is given as profit to the contractor'
Cost plus is not used in government works and item rate, target cannot be fixed for huge
projects perfectly.
97. Assertion (A): Earnest money deposit is usually 1% to 2% of the total estimated cost of work.
Reasoning (R):Earnest money deposit prevents unnecessary and unhealthy competition.
(a) Both (A) and (R) are true (b) Both (A) and (R) are false
(c) (A) is true and (R) is false (d) (A) is false and (R) is true
97. Ans: (a)
Sol: Earnest Money Deposit (EMD) is must (1-2)% of project cost and is need to be submitted along
with tender document so that only worthy persons goes for tendering.
EMD is refundable for those who do not get contract.
98. Equation for cement requirement in tones for four-storey R.C.C. framed building (super structure)
recommended by C. B. R. I. is
(a) 0.153 A + 0.57 (b) 0.145A + 0.54
(c) 0.182 A – 0.35 (d) 2.26A + 66.8
(where A is plinth area in sq.mt)
98. Ans: (c)
Sol: Cement required in tonnes = 0.0204A – 0.014
A = plinth area
Approximately answer is (c).
99. While submitting tender by three envelope method, which envelope contains rates/amount offered
by the tenderer?
(a) Envelop :3 (b) Envelop nos: 1 and 2
(c) Envelop :1 (d) None of the above
99. Ans: (a)
Sol: Envelope I - Document related to eligibility criteria
Envelope II - Technical bid
Envelope III - Financial bid
100. The length of L-bend for Tor steel to be provided at each end of the reinforcing bars is
(a) 12 times diameter (b) 6 times diameter
(c) 3 times diameter (d) 150 mm
100. Ans: (b)
Sol:
6 6