I, Frehiwot Kefyalew, the under signed, declare that this thesis entitled “ERP Project
Implementation in ethio telecom: An Inquiry into the Performance, Challenges and
Prospects” is my original work. I have undertaken the research work independently with
the guidance and support of the research supervisor. This study has not been submitted
for any degree or diploma program in this or any other institutions and that all sources of
materials used for the thesis has been duly acknowledged.
This is to certify that the thesis entitled: ERP Project Implementation in ethio telecom:
An Inquiry into the Performance, Challenges and Prospects submitted in partial
fulfillment of the requirements for the degree of Masters of project management of the
Postgraduate Studies, St. Mary;s University and is a record of original research carried
out by Frehiwot Kefyalew SGS/0216/2012A, under my supervision, and no part of the
thesis has been submitted for any other degree or diploma. The assistance and help
received during the course of this investigation have been duly acknowledged. Therefore,
I recommend it to be accepted as fulfilling the thesis requirements.
___________________________ __________________________
External Examiner Signature
_____________________________ ______________________
Internal Examiner Signature
_____________________________ ______________________
Dean, SGS Signature
Table of Contents
ACKNOWLEDGEMENTS ................................................................................................. I
ABBREVIATIONS ............................................................................................................ II
ABSTRACT...................................................................................................................... III
1.3.Research Questions................................................................................................ 5
1.7.Limitation of Study................................................................................................ 7
REFERENCE ............................................................................................................ 72
APPENDIX I .................................................................................................................... 75
LIST OF TABLES
Table 4.8 the Rate of Training, Documentation and Knowledge Transfer ....................... 50
I
ABBREVIATIONS
ERP Enterprise resource planning
II
ABSTRACT
The purpose of the study was to assess the implementation of Enterprise resources
planning (ERP) and evaluate the overall the performance, challenges and prospect of
implementing Enterprise Recourses planning (ERP) in ethio telecom. In addition,
challenges encountered during ERP implementation and to suggest practical
recommendations which can help to have effective implementation of ERP. To address
the objectives, descriptive research design was used in order to elaborate the existing
phenomenon as it exists. The source data were both primary and secondary source of
data and also a mixed research method (i. e. an approach of both quantitative and
qualitative data collection methods) were used to collect data from management,
administrators, supervisor and specialist. The data gathered through questionnaire were
analyzed using frequency and percentage value of the respondents using SPSS. The
reliability of the data was analyzed by using cornabach’s alpha. Furthermore, the
participants were selected using simple random sampling method, 104 participants were
selected from the total population of 140. The participant includes the department of ERP
section, PRO, supply chain, human resource and managements. Consequently, results
show that the deployed ERP system is not properly implemented and practiced on the
basis of the selected effectiveness variables; it is observed that the ERP system is not
effective across the divisions the system is implemented. In addition, problems which
hinder the practice of the system were identified. As a result, lack of appropriate training
for all system users was identified as the most serious problem while proper support from
the integrators side. Hence, the researcher has recommended that the company should
re-consider its system with regard to the support of top management in assisting
successful implementation of ERP in ethio telecom. Moreover, user interface of the
system should easily be understandable; there should be mechanism so that users can
work on the system without any challenge. Finally, the company should give emphasis for
the reporting formats so that any decision maker or external stakeholder can the
reporting formats should be easily understandable.
III
CHAPTER ONE
INTRODUCTION
1.1. Background Of the Study
1
implementation of ERP projects is a major event in the life of an organization. An ERP
system is expected to change a lot of business, processes, and activities within the
organization and often initiated with much expectation about the benefits and the
transformation that the project would bring to the organization (Ibrahim, 2010). As
technical knowledge is required, strategic, organizational and people-related factors are
significant in the success of an ERP project. Strong top management commitment is a
most important issue in successful ERP implementation, as it involves of a lot of changes
in the organization. Also, effective communications, effective project management,
training and implementation team are essential throughout an ERP project in order to
bind the various activities together (Ibrahim, 2010).
As clearly explained above regarding the topic different authors by different country
(specially developed countries) and sector context tried to assess the problem they
observe and filled the gap (practical and academic). But, a country like Ethiopia the
implementation the ERP system is a recent phenomenon. Thanks to globalization many
multinational companies start to invest in the third world country for their own advantage
and countries also start to get benefit from their involvement. When they came, they don
‘t only brings the business idea and finance only rather they bring their rich experience in
the area including internal processes. Currently, for any company to be successful, being
meticulously strategic in automating the major work processes is highly imperative; one
of the characteristics of being strategic is using the best automation tool on its inside
operation. Actually, there is no single globally agreed best tool which can incorporate on
all organizations – it’s about how the tools are being implemented by their users!
In addition to the tools being used, the most important success-factor for any big
company in implementing ERP system is mainly depend on how well the company’s
requirement has been defined; if the requirements are not properly defined and organized,
it might be the root cause for the failures of the tool. Ethio-telecom has an ambition of
being a world class company & in order to be a world class company, it decided to use a
more sophisticated automation tool so that its internal work process is shifted from
2
routine tasks to strategic ones. Mainly the benefit which is expected from ERP system is
realized only when it is implemented considering all the pre and post implementation
activities. Otherwise, the system could be a curse to and drag the whole enterprise into
spiraling inefficiency. Planning for ERP systems and their implementations requires an
integrated approach to meet the requirements of various functional areas. In general;
independent of the size of the company, an Enterprise Resource Planning system can
either boost or doom a company, if implemented successfully or unsuccessfully
respectively.
So, the motive of this research is to fill the above-mentioned gap for both academicians
and practitioners. Since telecom companies are highly dependent on technologies the
company (ethio-telecom) is not new to implement new technology-based system. But
regarding ERP system, it is new phenomena. So, the researcher ‘s interest and motive is
to assess the practices and challenges of implementing the system, to show the potential
benefits and challenges and finally to recommend possible solution(s). This research
adopts a case study approach to investigate the practice and challenges of ERP- Oracle
System in Ethio Telecom focusing mainly on automating the major support activities of
the company like project roll out, human resources, and supply chain management.
Today, many public and private organizations worldwide are implementing ERP systems
in place of the functional legacy systems that aren’t anymore well-compatible with
modern business environment. ERP system is a modular integrated business software
system that facilitates an organization to use its resources efficiently and effectively. The
integration brought by ERP enables organizations to respond to competitive forces and
market opportunities, to improve product portfolio, to reduce carrying costs and to
maintain supply chain relations strictly. Enterprise resource planning (ERP) system has
been one of the most popular business management systems, providing benefits of real-
time capabilities and seamless communication for business in large organizations (Mishra
et al. 2011).
3
However, not all ERP implementations have been successful. Since ERP implementation
affects entire organizations such as process, people, and culture, there are a number of
challenges that companies may encounter in implementing ERP systems (Ibrahim, 2010).
Ibrahim (2010) noted that ERP systems offer benefits in terms of strategic, operational,
managerial, organizational and technical related issues. ERP can also aid to reduce
overtime, improve return on investment and improved decision making due to availability
of timely and appropriate information. Moreover, ERP systems assist to reduce the
requirements of employees and help organizations reduce data transfer time (Gupta et al.,
2004). The success of an ERP implementation depends on how quick the benefits can be
reaped from it.
Despite the significant benefits that ERP software packages provide in managing and
integrating cross-functional business processes there are several difficulties and barriers
that relate to such an implementation. The major challenge is to integrate existing legacy
systems and other applications with the ERP system to provide a common interface.
Moreover, ERP systems are complex and implementing one of them can be a
challenging, time consuming and expensive project for ever organization (Davenport,
1998). Addressing the difficulties of ERP implementation helps to plan better and
facilitate a more successful ERP implementation (Ibrahim, 2010). Regarding the
challenges of ERP, as different scholars have categorized them above, some are internal
company problems (weaknesses of inside stakeholders) & some are External problems.
Among the internal problems, lack of skill of users, change resistance, lack of
commitment of top management/implementers & the implementation process itself are
among the major ones. On the other hand, the module nature and standardization issue
are mentioned as external challenge Shiri (2012).
4
has a mission to connect every Ethiopian through information communication
technology, provide telecommunication services and products that enhance the
development of the nation and build reputable known its customer’s consideration.
However, it was very challenging to continue with the existing management style and
technology as a result of the dynamic environment of the sector. Implementation of ERP
system in ethio telecom is not about replicating other company’s product rather it’s about
customizing & applying the tool in line with the nature (demographics and law) of the
country, structure of the company, policies and procedures and internal processes.
Having the above stated research problem in mind, this study was conducted to answer
the following research questions:
✓ What is the nature of the whole process of the ERP system implementation in
ethio telecom?
✓ To what extent the ERP project implementation become how was it measured?
✓ What were the challenges faced during the implementation of ERP project?
✓ What is the future prospect and benefits expecting from ERP implementation?
✓ What are ERP system implementation constraints in ethio telecom?
The general objective of this study is to assess and evaluate the overall the performance,
challenges and prospect of implementing Enterprise Resource Planning (ERP) in ethio-
telecom and to recommend possible solutions for the gap.
5
1.4.2. Specific objectives
➢ To assess the overall ERP system implementation process in the ethio telecom;
➢ To identify ERP system implementation challenges peculiar to ethio telecom
other than the common ones due to the very nature of the company.
6
management groups of employees from Human resources, ERP section, Project team &
Supply chain.
Questionnaires were not replied on time because some of the employees were out of their
principal work place for field works in relation to the on-going telecom expansion
project. As a result, the response rate is to some extent negatively affected.
Some of the employees were not volunteers to fill the questionnaire because they are
busy of their daily routine. Moreover, some of them seem bored of feeling lots of
questionnaire from different researchers every year.
The research report comprises five chapters; the first chapter contains introduction of the
study which consists of background of the study, statement of the problem, research
questions, and objectives of the study, significance of the study, limitation of the study,
scope of the study and organization of the paper. The next chapter which is chapter two
contains assessment of different literatures both on the area which discusses various
theories and concepts on Enterprise Resources Planning system and related empirical
reviews in relation to the company’s actual situation. In the third chapter the research
methodology and design has been detailed and the sample size and was also determined.
In the fourth chapter, data presentation, discussion and analysis were done. The last
chapter provides conclusions and recommendations on the basis of the analysis made in
the preceding chapter.
7
CHAPTER TWO
REVIEW OF RELATED LITERATURE
This chapter presents the review of related literatures and imperial facts. It includes the
conceptual understanding of what ERP mean, and the benefits to be obtained through
ERP implementation, the historical background of the system, the conceptual
understanding of ERP system, common ERP platforms, and ERP implementation success
will be indicating under literature review part. On the other hand, the reason behind ethio
telecom goes for ERP implementation has been assessed under the Imperial review part.
8
the ideas mentioned above the major characteristics of ERP systems are: a packaged
software system designed for the client environment, the integration between the modules
and across entire organization, access to data in real time, data storing and retrieving
processes in an enterprise-wide database, and management and analysis functionalities.
Moreover, ERP systems are expected to have additional characteristics such as support
for multiple currencies and languages (but not Amharic), which is critical for
multinational companies, and support for specific industries.
Hence; companies who are implementing the ERP system are benefiting from the single
integrated system by transforming or reengineering their mostly legacy information
system. And it is also defined as a method for the effective planning and controlling of all
the resources needed to take, make, ship and account for customer orders in a
manufacturing, distribution or service company. ERP systems are configurable
information systems packages that integrate information and information-based processes
within and across functional areas in an organization (Henry S., 2002).
Enterprise Resource Planning (ERP) systems provide integration and optimization of
various business processes, which can lead to improved planning and decision quality,
and a smoother coordination between business units, resulting in higher efficiency and a
quicker response time to customer demands and inquiries. It is also a software solution
that integrates business functions and data into a single system to be shared within a
company. In the past two decades, companies around the world have implemented ERP
Systems. ERP systems are software packages that enable companies to integrate their
business processes and all the information relevant to their organization. With ERP
systems, firms are able to manage all their resources (i.e. physical or intangible assets,
finances, human resources, production, etc.) more effectively. The ERP system not only
aids in standardizing business processes across an enterprise but also helps management
increase their visibility of the business by providing real-time financial and production
information. (Seddon, Shanks & Sylvia 2013).
An ERP system is a packaged business software system that allows a company to
automate and integrate the majority of its business processes, and share common data and
9
practices across the entire Enterprise. ERP also accesses information in a real-time
environment. Many companies use ERP software to integrate the enterprise-wide
information and process for example their financial, human resources, manufacturing,
logistics, sales and marketing functions. ERP is designed mainly to provide a total,
integrated company’s resource to manage the business process efficiently and effectively
(Seddon, Shanks &Sylvia 2013).
2.1.1. ERP overview
Enterprise resource planning (ERP) is an industry term for the broad set of activities that
helps an organization manages its business. An important goal of ERP is to facilitate the
flow of information so business decisions can be data driven. ERP software suites are
built to collect and organize data from various levels of an organization to provide
management with insight into key performance indicators. An Enterprise resource
Planning (ERP) system is packaged business software that integrates organizational
processes and functions into a unified system. In traditional IT systems, each of the
system components are found separated as applications by their own with one database
system for each of them. However, ERP system integrates all of the components through
one central database which is common for all the modules.
10
applied in small, medium and large-scale business organizations for a better management
of the operational activities. Such software can deliver consistent data across all business
functions in real time. Real time refers to data and processes that are always current.
Apart from the ideas mentioned above the major characteristics of ERP systems are: a
packaged software system designed for the client environment, the integration between
the modules and across entire organization, access to data in real time, data storing and
retrieving processes in an enterprise-wide database, and management and analysis
functionalities. Moreover, ERP systems are expected to have additional characteristics
such as support for multiple currencies and languages (but not Amharic), which is critical
for multinational companies, and support for specific industries. Hence; companies who
are implementing the ERP system are benefiting from the single integrated system by
transforming or reengineering their mostly legacy information system. And it is also
defined as a method for the effective planning and controlling of all the resources needed
to take, make, ship and account for customer orders in a manufacturing, distribution or
service company. ERP systems are configurable information systems packages that
integrate information and information-based processes within and across functional areas
in an organization (Henry S., 2002).
11
2.2.2. Benefits of ERP
What are some of the perceived benefits that lead corporations to commit to the
implementation of ERP in their organizations? As indicated by Olliver and Romm
(2002), “in common with other types of investment activity the adoption of an ERP
system is a purposive intervention by an organization for bringing about a new state of
affairs that is judged to be superior to the current state”. Botta-Genoulaz, Millet, and
Garbot (2005), indicate that two distinct streams are observed from the literature. The
first one focuses on the fundamental corporate capabilities driving ERP as a strategic
concept, and the second, on the details associated with implementing an information
system and their relative successes and costs. Problems of sociological and cultural
factors influencing the implementation success as well as the implementation steps have
been addressed earlier in literature.
As indicated by Chen (2001), “planning for ERP adoption generally occurs when an
organization realizes that current business processes and procedures are incompetent for
their current and or future strategic needs”. As the result of various external and internal
forces, ethio telecom operating environment is changing and their working systems are
becoming “incompetent”. They are not able to maximize their efficiency and therefore,
profit. Any tools that would enable these organizations to reverse this trend must be
considered. In order to promote the use of ERP by ethio telecom, a more comprehensive
look of the potential benefits that could be achieved must be completed. Ross, (1999:11)
articulated that that as a business and strategic perspective implementing ERP is seen as
way to improve corporation’s effectiveness and efficiency, reduce their operating,
personnel, inventory and IT costs, and improve their productivity, business growth,
production scheduling, delivery time, customer service, and overall quality. Additionally,
data visibility and timely information is important to make better business decisions. It is
clear that ERP system investments have been categorized as strategic in nature. Literature
review identifies the common goal to be an increase in company sales, reduction in
production cost, reduction of lead times, and improvements in customer relationships.
12
In general ERP systems enhance inter-organization communication and collaboration
between different functions and locations for the integrated decision-making process.
Standardization of the processes across the unit’s works in favor of collaboration as it
reduces the number of conflicts between the processes. The single database system
encourages communication across locations and functional units through sharing the
information. With ERP systems companies are using the same database, which can be
accessed on-line, in real-time and simultaneously by many users. Since, virtually all users
have access to the same information it improves companies planning and control
practices.
And some of the benefits that could be realized in ethio telecom environment as a result
of ERP implementation could be as follows: -
For the last couple of years, the business environment is becoming increasingly complex
in terms of operational and functional work units and these units are requiring more and
more inter-functional dataflow for decision making, timely and efficient procurement of
product parts, management of inventory, accounting, human resources and distribution of
goods and services. In this context management of organizations need efficient
information systems to improve competitiveness, and it is obvious that the capability of
providing the right information at the right time brings tremendous rewards to
organizations in a global competitive world of complex business practices.
13
As indicated by Fiona (2002:35), ERP Systems are now ubiquitous in large businesses
and the current move by vendors is to re-package them for small to medium enterprises
(SMEs). This migration as many consequences that have to be addressed through
understanding the history and evolution of ERP systems and their current architectures.
The advantages and disadvantages of the ERP systems will impact their penetration in
this new market. The market position and general strategy of the major systems providers
in preparation for this push are described. The growth and success of ERP adoption and
development in the new millennium will depend on the legacy ERP system's capability of
extending to Customer Relationship Management (CRM), Supply Chain Management
(SCM) and other extended modules, and integration with the Internet-enabled
applications.
Starting in the late 1980s and the beginning of the 1990s new software systems known in
the industry as Enterprise Resource Planning (ERP) systems have surfaced in the market
targeting mainly large complex business organizations. These complex, expensive,
powerful, proprietary systems are off-the-shelf solutions requiring consultants to tailor
and implement them based on the company’s requirements. In many cases they force
companies to reengineer their business processes to accommodate the logic of the
software modules for streamlining data flow throughout the organization. These software
solutions, unlike the old traditional in house designed company-specific systems, are
integrated multi-module commercial packages suitable for tailoring and adding “add-ons”
as and when required. (Ibid, 2002:39)
14
requirements according to the master production schedule. Following this route new
software systems called Manufacturing Resources Planning (MRP II) were introduced in
the 1980s with an emphasis on optimizing manufacturing processes by synchronizing the
materials with production requirements. MRP II included areas such as shop floor and
distribution management, Project management, Finance, Human Resource and
Engineering. ERP systems first appeared in the late 1980s and the beginning of 1990s
with the power of enterprise-wide inter-functional coordination and integration. Based
on the technological foundations of MRP and MRP II, ERP systems integrate business
processes including manufacturing, distribution, accounting, financial, human resource
management, project management, inventory management, service and maintenance,
transportation providing accessibility, visibility and consistency across the enterprise.
During the 1990s ERP vendors added more modules and functions as “add-ons” to the
core modules giving birth to the “extended ERPs”. These ERP extensions include
advanced planning and scheduling (APS), e-business solutions such as customer
relationship management (CRM) and supply chain management (SCM). (Ibid, 2002:6)
15
2.2.4.1. ERP implementation challenges
Hence; depending on the degree of failure according to our existing practical situations
here are the major ERP challenge areas: -
✓ Complexity
The complexity of the system implementation arises from the fact that companies have to
integrate ERP software with hardware, operating systems, and database management
systems and so on. Further, it initiates the changes throughout the entire organization. As
ERP software comes in a ready-made package companies are required to adjust their
businesses to fit the system requirements. The reasons being that even with the today’s
art of technology ERP systems do not fit all the requirements of a company. Moreover,
changes in one component might cause the collapse of the whole system, which is
designed as an integration of separate modules.
The total implementation costs of ERP include software, hardware, consulting and
internal personnel costs, which usually sum to 2-3 % percent of the company’s revenues
(Chen, 2001). The huge investment has to be weighed against the future economic and
strategic benefits that the system should eventually provide. However, the benefits might
be difficult to quantify. Non-financial benefits such as improved customer response,
strengthened supplier relationships through information sharing and real-time access to
operating and financial data can be vital for the growth of many companies but are hard
to convert to monetary profits in the cash flow statements. Moreover, it might take years
16
for the companies to take the advantage of the all-capabilities ERP systems provide. In
addition to what has been mentioned above Markus M. (2000), explain that success
depends from the point of view from which you measure it. It can be viewed from many
dimensions: in technical terms, in economic, financial or strategic business terms, in
terms of smooth running of business operations, from the point of view of managers and
employees or from the point of view of customers, suppliers and investors.
✓ Time
On time and within the budget is another success criterion, which in practice is no easy to
achieve. Meeting deadlines is a primary concern of the ERP project management as any
delay costs the company additional money. The amount of time needed for project is
often underestimated. In length, the whole implementation process can take up from three
to five years. Chen (2001); explained that, considering today’s business dynamics
companies cannot afford spending too much time on the technology implementation in
spite of all the benefits as competitors might have enough time to overtake them.
Moreover, lengthy implementations can increase the risk of project failure; reduce the
management and staff commitment, decline productivity and delivery performance and
cause the loss of the customers.
✓ Training
Welti N. (1999); indicated that training and change management are matters that affect all
the phases of the ERP implementation project. Not surprisingly, there are many
challenges related to training as each user group has different needs, preferences and
learning potential. For instance, the steering committee members need to have a good
project overview and general idea about the functionality of the system. Project leaders
instead require in-depth knowledge about system’s functionality and project
management. Users have to learn only those functions that are related to their tasks in
addition to the understanding the new processes and procedures.
17
Moreover O’Leary D. E. (2000); also explained that training is expensive and
underestimating the needs and the requirements are the reasons for exceeding the budget.
Skilled employees tend to switch their jobs and training of new employees will remain a
continuous effort. However, the importance of training cannot be neglected and it is not
something that should be conducted only before or after the implementation but rather it
has to be present in each part of the ERP life cycle. Moreover, ERP training has been
identified as a critical requirement in ERP implementation and this has led to creation of
an entire industry providing ERP training.
The implementation of ERP system has a major impact on the company and its
employees. The sources and types of resistance to change are many. In general, after the
implementation of the ERP system the performance of the company gets worse before it
gets better in the stabilization process. It is hard for the people to change from the old
way of doing things, which they were good at into new ways.
The people, who perceive change as negative, wish to hold on to the old way of doing
things. Employees can claim to be computer illiterate, say that they did an excellent job
before ERP system, and feel uncomfortable to trust the computers, be afraid of failure
and have a common belief that their jobs are threatened by the new automated system
(Ross, 1999: 51). Determining who resisting changes are may help to understand the
employees’ resistance to the ERP system. Management might resist the process changes
ERP requires. They are ready to change their technological platform but not the
18
organizational processes. However; implementing ERP means changing your business
processes to fit the company’s defined business requirements not another thing around.
Middle level managers feel uncomfortable with the change because their job postings can
be eliminated as decisions making is pushed down to operational level (ibid, 1999: 63).
In order for the ERP implementation to be successful, top management must analyze
these sources of resistance and develop a strategy to overcome them. Building a user
acceptance, the new system and new way of doing things is a major challenge for the
companies. A commonly used strategy to increase user acceptance is training the users
through in-house programs and courses. ERP skills are in shortage as there are a small
number of people who have a good understanding of business and ERP systems.
Organizations have to conduct training for project teams, implementers and users. Some
organizations develop key users that accordingly assist other users and so forth.
As per Welti N. (1999); there are people who are looking forward to the new system.
They perceive change as positive. The wider use of data throughout the company, access
to the data across different departments and locations, easier contacts with colleagues,
task enhancement possibilities and fast access to customer data increases the individual’s
insight into company’s operations and brings in satisfaction based on new opportunities
the system offers.
19
components and primarily focus on external (front-office) operations. Core ERP
components are accounting and finance (FI), human capital management (HCM) and
logistics (LOG) which contains production and materials management. Extended
components are modules such as business intelligence, customer relationship
management and portal. These core and extended ERP modules are themselves
comprised of different sub-modules. Finance core module includes general ledger,
receivables, payables, asset management and related sub-modules. Payroll, personnel
planning and time management are some of the sub modules in human resources core
module while materials management and production planning are sub-modules of
logistics core component (Ibid). Some of the ERP main modules are explained as here
below.
➢ Financial accounting - FI
This module collects all the data relevant to financial accounting into an integrated
General Ledger. It provides comprehensive and consolidated financial reports and
integrates the different sources of financial data including Accounts Payable, Accounts
Receivable, Asset Management and Treasury. It also provides up-to-date or real time
information for enterprise-wide control and planning. The FI module is for external
reporting purposes and it is compatible with the international accounting standards
Poston R., Grabski S. (2001).
➢ Controlling – CO
CO module includes a variety of planning and controlling tools for enterprises following
a uniform system of reporting. It provides comprehensive reports to support most
common cost accounting issues. Controlling module is usually for internal reporting
purposes Poston R., Grabski S. (2001).
20
➢ Human capital management – HCM
HCM is the other common ERP module. ERP HCM module is used as the core employee
record with details of personnel actions, benefits administration and payroll, position
management and compliance with government regulations. HCM consists of three sub
modules namely Organizational Management (OM), Time Management (TM) and
Payroll (PY) Poston R., Grabski S. (2001).
➢ Materials management – MM
➢ Production planning – PP
➢ Project system – PS
Project system module coordinates and controls all phases of a project with direct
cooperation with Purchasing and Controlling, from quotation to design and approval, to
resource management and cost settlement Poston R., Grabski S. (2001).
The core and sub-modules of ERP system are summarized as in table 2.4.1.1below. In
traditional IT systems, each of the system components are found separated as applications
by their own with one database system for each of them. However, ERP system integrates
all of the components through one central database which is common for all the modules.
21
Table 2.1 the core and sub-modules of ERP system
22
and then make that data available for use throughout the firm; by all appropriate users.
ERP system mostly runs on a three-tiered client/server system with three layers of logic.
This is a graphical user interface (GUI) or a web browser which allows users the ability
to access and analyze information and system functions (Rashid et al., 2002).
It consists of business rules, functions, logic, and programs where business processes and
end users interact with the system (Rashid et al., 2002).
• Master data is data in database tables which are used as references for day to day
business transactions.
• Transaction data is data which contains the day to day business activities.
• Configuration data is data in tables which contain the settings and configurations
of the system to suit and fit to the business logic of the company.
ERP system is used not only as operational or transactional system, but also as
controlling and executive decision support system. According to Chung, the data and
information in ERP systems is divided into three layers as operational system
(transactional data entry layer), tactical system (controlling layer) and strategic or
Executive Information Systems (EIS) layer as in.
23
2.3.2 Pros and cons of ERP systems
There are different initiatives and reasons for acquiring ERP systems. ERP systems have
the advantage of seamless integration between all parts and processes of a company, and
this in turn gives the possibility of proper control. They are used to control and reduce
data redundancy and accuracy. Redundant tasks will be removed and the efficiency of the
company increases. The other advantage of ERP systems is that easier and timely reports
functionality. Users can get self-services of data needs and access. They can run their
own reports and have better access to their data and the ability to manipulate and report
on this data.
24
Table 2.2: ERP System benefits in different dimensions
Dimensions Benefits
Productivity improvement
Cost reduction
Quality improvement
Operational Customer satisfaction
Decision making
Resource management
Managerial Performance management
Business growth
Business cooperation
Strategic Business leadership
Business change flexibility
IT Infrastructure IT co
On the other hand, ERP systems have some drawbacks and limitations. These systems
are usually complex. Regardless of their long-term benefits and reduced maintenance
costs, initial one-time implementation is expensive. And even if data accuracy and
integration is achieved by ERP systems, it is hard to correct or amend data once it is
maintained in the system as it will affect many modules and processes. While ERP
systems have more efficient methods, freedom and self-creativity practice with the
system is minimal (Ibid). Limitations of ERP systems are discussed and summarized
below.
Even if ERP systems can save costs in long term, initial implementation is too expensive.
This cost depends on the scope and number of ERP modules which are selected and
installed, size of the company, use of consultants, software license and hardware and
length of the implementation time. As ERP systems are integrative and complex, it takes
long time to implement these systems. ERP implementation costs millions of dollars and
takes 1-3 years of time (Whyte & Fortune, 2002).
25
• Business process re-engineering and customization
ERP systems are developed based on industry best practices. If these best-practice
solutions in the ERP system do not match the business processes, then organizations are
required to reengineer their business processes to fit these best practices. However,
changing all processes may lead to a loss of competitive advantage. Strategic processes
which give competitive advantage to a company should not be changed. In this case, the
ERP system must be customized and configured properly to fit the business processes
(Whyte & Fortune, 2002). Configuration refers to setting and filling of parameters and
tables in the system whereas customization is changing the code of the system. On the
other hand, customization of the ERP software is limited and major change is not
allowed. In addition, customization has problems related to upgrading. When the ERP
software is upgraded by the vendor, all customizations may have to be re-checked. So,
there should be clear and prior decision about the processes to be preserved and those to
be re-engineered (Whyte & Fortune, 2002). User interface and usage ERP systems can be
difficult to use. They are too restrictive and rigid (highly controlling) and do not allow
much flexibility in implementation and usage. Moreover, users may have to go through
many screens in order to maintain a single data set. This is because screens are developed
based on the program flow and logic. It is when they are used more and more that ERP
systems are appreciated by users (Whyte & Fortune, 2002).
The system can suffer from the weakest-link problem. Inefficiency in one department or
at one of the partners may affect other participants. So, the integrated links need high
accuracy in other applications to work effectively. There are frequent compatibility
problems with the various legacy systems of the partners (Whyte & Fortune, 2002).
26
• Responsiveness
ERP systems have low response time to user actions and information requests. Due to
the complexity and user interface screens, ERP systems usually take long time to respond
to data entry and report generation processes (Whyte & Fortune, 2002).
ERP technology selection is a crucial and paramount consideration for enterprise level
decision makers in organizations aspiring to sustain staying competitive since, it is a
serious investment decision. As investment in ERP systems implementations projects in
organizations are strategic and highly risky because of the complexity involved, high
implementation cost and change management issues it is crucial to select ERP software
that fits with organizational goals and objectives for successful implementation S. Ranjan
et al (2012).
Radut and Codreanu (2012) argued that the most important part of adopting an ERP
system is the selection part and the selection process should be specific to organization as
it takes into account the requirements of the organization and should be an analytical
method based on criteria. The most important of which are functionality, technology and
expertise, flexibility and application scalability, costs, implementation and ease of use.
Their offering is a simple sequential qualitative model with selection
criteria/characteristics composed of six attributes, namely functionality, reliability,
efficiency, usability, maintainability, and portability. Johansson et al. (2011) studied
relationship between factors influencing selection of implementation approach and
companies’ ability to stay within budget when implementing ERPs. The main findings
are that:
27
Garg and Khurana (2013) presented the ERP product selection criteria for Indian SMEs.
The finding of this research will help the marketing and sales team of ERP product
companies to improve upon the key points and also enable end users to make informed
decisions in selecting the ERP package for the organization. Ratkevicius et al. (2012)
presented analysis of different classifications of the fundamental criteria for the ERP
system selection process, and defines two main groups – software-related, and
implementation-related. The significance of ERP system functionality as the principal
software-related ERP selection criterion is emphasized. Eleven other criteria were
defined as important to consider, such as the total costs of the ERP implementation
project, vendor reputation, ERP reliability, ease of integration with other systems,
technology advance, scalability, upgrading ability, customization/parameterization
possibilities; ease of use; flexibility and modularity. The importance of all-round
knowledge for a successful ERP implementation is emphasized, including ERP software
functionality, project and change management, business processes, organization of
training etc. All these areas are closely connected with implementation-related ERP
selection factors: organizational fit, end-user readiness, training, system support quality.
Priority Name
1 Lack of senior manager commitment
2 Ineffective communications with users
3 Insufficient training of end-users
4 Failure to get user support
5 Lack of effective project management methodology
6 Attempts to build bridges to legacy applications
7 Conflicts between user departments
8 Composition of project team members
9 Failure to redesign business process
10 Misunderstanding of change requirements
28
2.3.4 Change management challenges in ERP implementation
29
an ERP implementation project, realize the path for delivering the new processes and
ERP solution into production operations, and gain ‘reach’ into the organization. It also
addresses how resistance to change affects ERP implementation and how to mitigate
these challenges.
➢ Complexity
The complexity of the system implementation arises from the fact that companies have to
integrate ERP software with hardware, operating systems, and database management
systems and so on. Further, it initiates the changes throughout the entire organization. As
ERP software comes in a ready-made package companies are required to adjust their
businesses to fit the system requirements. The reasons being that even with the today ‘s
art of technology ERP systems do not fit all the requirements of a company. Moreover,
changes in one component might cause the collapse of the whole system, which is
designed as an integration of separate modules.
The total implementation costs of ERP include software, hardware, consulting and
internal personnel costs, which usually sum to 2-3 % percent of the company’s revenues
(Chen, 2001) The huge investment has to be weighed against the future economic and
strategic benefits that he system should eventually provide. However, the benefits might
be difficult to quantify. Non-financial benefits such as improved customer response,
30
strengthened supplier relationships through information sharing and real-time access to
operating and financial data can be vital for the growth of many companies but are hard
to convert to monetary profits in the cash flow statements. Moreover, it might take years
for the companies to take the advantage of the all-capabilities ERP systems provide. In
addition to what has been mentioned above Markus M. (2000), explain that success
depends from the point of view from which you measure it. It can be viewed from many
dimensions: in technical terms, in economic, financial or strategic business terms, in
terms of smooth running of business operations, from the point of view of managers and
employees or from the point of view of customers, suppliers and investors.
➢ Time
On time and within the budget is another success criterion, which in practice is no easy to
achieve. Meeting deadlines is a primary concern of the ERP project management as any
delay costs the company additional money. The amount of time needed for project is
often underestimated. In length, the whole implementation process can take up from three
to five years. Chen (2001); explained that, considering today ‘s business dynamics
companies cannot afford spending too much time on the technology implementation in
spite of all the benefits as competitors might have enough time to overtake them.
Moreover, implementations can increase the risk of project failure; reduce the
management and staff commitment, decline productivity and delivery performance and
cause the loss of the customers.
➢ Training
Welti (1999); indicated that training and change management are matters that affect all
the phases of the ERP implementation project. Not surprisingly, there are many related
trainings as each user group has different needs, preferences and learning potential. For
instance, the steering committee members need to have a good project overview and
general idea the functionality of the system. Project leaders instead require in-depth
knowledge system ‘s functionality and project management. Users have to learn only
31
functions that are related to their tasks in addition to the understanding the new processes
and procedures. Moreover, O ‘Leary (2000); also explained that training is expensive
underestimating the needs and the requirements are the reasons for exceeding the budget.
Skilled employees tend to switch their jobs and training of new employees will remain a
continuous effort. However, the importance of training cannot be neglected and it is not
something that should be conducted only before or after the implementation but rather it
has to be present in each part of the ERP life cycle. Moreover, ERP training has been
identified as a requirement in ERP implementation and this has led to creation of an
entire industry providing ERP training.
Nelson (2004); investigated the importance of the key activities in enterprise system
implementations, and when their effect is most critical across the ERP system life cycle.
Even though the critical success factors of ERP implementations are well covered, the
temporal importance of key activities is less understood.
The role of training is well covered in the management of the information systems
literature. Lacks of user training and understanding how software system is changing the
business processes have been the foremost reasons for ERP implementation failure. Due
to ERP system complexity training is essential at the acceptance stage and at the latter
stages of the life cycle.
32
➢ Management of expectations
Right ERP package selection determines the overall success of the project and therefore,
it should be emphasized at the initiation and adoption phases.
➢ Project management
Project management activities spread out throughout the project life cycle. However,
effective project management including project planning and control activities,
organizational, political and human issues and many more is critical from the initiation to
acceptance stage but less significant during reutilization and infusion.
➢ Customization
The amount of customization needed to the software has to be handled at the early stages
of the implementation process. Minimal customization brings usually better results as it
means less costs, shorter implementation time, less dependence on vendor services such
as system maintenance and upgrades, and et cetera.
Timely and accurate data in a single consistent format is a fundamental requirement for
the effectiveness of ERP systems and data issues are especially critical from the initiation
to adaptation stages and less important during the system acceptance and use.
33
➢ Business process reengineering/transformation
➢ Dedicating resources
Having sufficient resource available for the project is crucial to guarantee success.
Resource requirements have to be set up early in the process.
1. The right selection of implemented modules that fit functional and organizational
needs
2. Configuring key technical aspects such as functionality, portability, scalability,
modularity, versioning, upgradeability, accessibility, flexibility, security, presence
and maintainability.
34
Second, leaders must be able to restore the knowledge gap toward ERP system that may
arise at two levels:
35
CHAPTER THREE
METHODOLOGY
Research methodology is the set of processes, methods, tools and techniques deployed
and used to conduct a research and reach to the final output of the study. The methods
and techniques used for this research are explained here below.
The objective of the research is to assess and describe the performance, challenges and
prospect of implementing ERP in ethio telecom. The research study adopted a descriptive
survey research design. Descriptive research design provides a comparative approach to
the ERP systems in automating and integrating management practices of ethio telecom.
This methodology also helped the researcher in using comparative statistical methods to
analyze the research subject in the case of ethio telecom. Best and Kahn (2006) says
research can be qualitative, if it describes events and persons scientifically without the
use of numerical data while quantitative research consist of research in which data can be
analyzed in terms of numbers. Mixed approach is an approach, which combines both
qualitative and quantitative ones. Thus, the study applied mixed approach that is
quantitative and qualitative approaches as research methodology. Mixed approach helps
to gain a better understanding of the phenomenon under study by obtaining data from
different sources, such as interviews, questionnaire and document which help to capture
diverse ideas about the same issue and assist in cross-checking the results, and
consequently helps to increase the validity, reliability of the findings and comforts data
analysis. To this end primary data source were integrated to be able to provide adequate
discussion and to get current information about what has already been discovered. Thus,
the study used the quantitative approach. On the other hand, to look at the humanistic
aspect of Kaizen and to have a rich understanding of people’s attitudes of Kaizen
challenge, qualitative approaches were used. In an attempt to complement and validate
one research method with the other in order to compare results in different context,
research triangulated via using primary data source specifically, questionnaire.
36
3.2. Sampling Technique
The population for this study comprised all the heads of department in particular human
resource, ERP, PRO and supply chain. A purposive sampling technique was employed in
the study. This method of sampling was chosen since it allows individuals to be chosen at
random and not more than once to prevent a bias that would negatively affect the validity
of the result of the experiment.
Generally, representatives of the total population have been included in the research
study. All parties involved in the implementation process of Enterprise Resources
planning System are represented by the sample. As a division human resources, ERP
section, PRO and supply chain are major source of information. The organization has
four hierarchical levels. These are, manages, administrators, specialist and supervisors.
Among this hierarchal level manger and administrators are key users of ERP. As result of
this statement show that the majority of key user taken as for respondent and the other
taken randomly, therefore out of 104 randomly select sample a 33 of them are from key
user and the rest of 71 of them are supervisors and specialists. In determining the actual
sample size, the researcher taken in to account that the minimum required returned
sample size, type of data analysis to be used and the expected rate of missing data.
Because of the geographical, time, cost and transportation constraint, the study was
concentrated on Addis Ababa. Moreover, studying different zones and, regions would not
bring significant different since company follows centralized management system most
of the activities are similar. As a result, almost all ERP user head office of ethio -telecom
were taken as a population for this study.
The research study relied on both primary and secondary data sources. Primary data was
gathered using structured five-point scale Likert questionnaire. In addition to the primary
data, secondary data from journals and e-books was also used to provide comparative
perspectives to the study.
37
3.4. Data Presentation and Analysis
The collected data would be presented by using tables and charts that to be expressed in
the form of frequency, percentage and mean. Then, descriptive analysis technique was
applied to manipulate the organized data using SPSS (of appropriate version) as the main
tool. The output obtained from the system will be analyzed quantitatively.
The study was in line with the organizations policy in relation to any intellectual property
rights of the organization. Also, in regards privacy of the respondents, their responses are
strictly confidential and their response used for academic purposes only.
According to Kothari, (2004), Validity is the most critical criterion and indicates the
degree to which an instrument measures what it is supposed to measure. Validity can also
be thought of as utility. In other words, validity is the extent to which differences found
with a measuring instrument reflect true differences among those being tested. As stated
above, questionnaire was used to collect the primary data (see Appendix). Meanwhile,
the questionnaire was adopted from Adopted from Beadles, Lowery, & Johns, (2005),
Batool, Sajid, & Raza (2012), and Shiri (2012) scientific Standardize questionnaires.
Validity and reliability was taken into consideration in the study in order to determine its
objectivity, level of trustworthiness and credibility. This study made use of face validity
where a panel of experts gave their input as to whether the instrument met the criterion
while Cronbach’s alpha (α) values were computed to test reliability where a score of
more than 0.7 is considered acceptable. Scrutiny of the study by colleagues, peers and my
supervisors was also used to gather and challenge assumptions made. Data was analyzed
using descriptive statistics, and factor analysis.
38
3.7. Chronbach’s Alpha Analysis
Cronbach’s alpha is a measure of internal consistency, that is, how closely related a set of
items are as a group. It is considered to be a measure of scale reliability. A “high” value
for alpha does not imply that the measure is one-dimensional.
Here;
Cronbach's
Alpha Based on
Cronbach's Standardized
Alpha Items N of Items
.870 .885 47
The reliability statics will be defined using the Cronbach’s alpha analysis. Alpha
coefficient for the 47 items is 0.870, based on the standard alpha coefficient for the 47
items 0.870, suggesting that the items have relatively high internal consistency.
39
CHAPTER FOUR
DATA PRESENTATION AND ANALYSIS
4.1. Introduction
This chapter deals with the presentation, analysis and interpretation of the data collected
through questionnaire and document analysis from ethio telecom employees. The data
was then coded and checked for any error and omission (Kothari, 2004). This chapter
presented and analyzed the data collected to seek appropriate answer for the basic
question distributed to collect data from employee and management bodies. I use Likert
scale with 5 points i.e. strongly agree (5), agree (4), neutral (3), disagree (2), strongly
disagree (1). The first part presents the profile of respondents showing gender, age group,
level of education, work experience, and position of respondents using cross tabulation.
The second section presents analysis of the study variables by using tables and consisting
of percentages and mean. And it has also contained the discussion of results and overall
responses.
The information generated to address the stated research objectives is solicited from
respondents with diverse demographic characteristics. The first part of the questionnaire
consists of the demographic information of the participants. This part of the questionnaire
requested a limited amount of information related to personal and professional
characteristics of respondents. These variables were included: gender, age, educational
level, experience, department and position.
40
4.2.1. Demographic information of the respondents
Male 53 50.96
Female 51 49.04
The data obtained from the respondents Table and Figure 4.2.1.1, 53 (51%) of the
respondents were male while 51 (49%) were female. This shows that there is slight
differences in the distribution of the respondents in the study area were male as compared
to female respondents.
30-35 24 23.1
36-40 16 15.4
Above 41 16 15.4
As revealed in the table and figure 4.2.1.2, out of the total respondents, 48 (46.2%) of
them are below and 30 years of age, 24(23.1%) of respondents are in the age range of 31-
41
35, 16(15.4%) of respondents are in the age range of 36-40 and the remaining 16(15.4%)
are in the age range of over 40 years. This outcome indicates that almost half of the
respondents are categorized under the productive age group.
Below Diploma 0 0
Diploma 2 1.9
BA/BSC 66 63.5
Masters 36 34.6
PhD 0 0
Seeing in the above table and figure 4.2.1.3, the educational level of respondent
66(63.5%) of respondents had attained bachelor’s degree as their highest level of
education 36(34.6%) of them had attained masters’ level of education and the rest
2(1.9%), 0(0%) and 0(0%) had attained diploma, below diploma and PhD level of
education respectively. This information shows that the respondents have enough
knowledge to contribute positively to this study.
As revealed in the Table and figure 4.2.1.4, out of the total respondents, 41(39.4%) of
respondent have less than 5-year experience, 22(21.2%) respondents have 6-10 years’
experience, 12(11.5%) have 11-15years’ experience, 16(15.4%) respondents have
experience from 16years up to 20years and lastly 13(12.5%) respondents have above 21
years’ experience in the sector. Company employee’s large percentage has 5 years and
minimum percentage has above 21 years’ experience.
42
Table 4.4 Respondents by experience
6-10 22 21.2
11-15 12 11.5
16-20 16 15.4
Above21 13 12.5
Experience
Level Total 104 100
Seeing the above table and figure 4.2.1.5, department of respondent 22(21.2%) of
respondents were from Human resource department, 29(27.9%) of them were from ERP
section and the rest 32(30.8%) and 21(20.2%) were from pro and supply chain
department respectively.
PRO 32 30.8
43
(Source: Own Survey).
As the above table and figure 4.2.1.6 indicates, Job position Level of the respondent in
this study was randomly selected. Admin’s, specialist, supervisors and managers were
responding to the provided questioners. In regards of that, from 104 respondents,
44(42%), 20 (19%), 26(25%), 14 (14%) were admins; specialist, supervisors and
managers respectively were the respondent numerically.
This part covers the data presentation and analysis on process ERP system meets the
benefit of customer satisfaction to contribution the company in achieving the goal of
being world class telecom service provider.
44
There are some F 2 5 15 17 65 104 4.327 1.019
functional areas
% 1.9% 4.8% 14.4% 16.3 62.5%
still using both
%
the manual and
automated
working system
ERP F
implementation in
% 1% 2.9% 6.7% 24% 65.4%
the company is
the best solution
in satisfying the
customer demand
For the question which concerns about the benefits realized by the company with that of
the stated expectation? Out of the total sample population, 67 (64.4%) and 24(23.1%) of
the respondent has strongly agreed and agreed respectively that the system has been
45
providing the benefits expected from it and they are fully satisfied with the outcomes.
Above on that, out of the total sample population, 2(1.99%), 4(3.8%) and 7(6.7%) of the
respondent were strongly disagree, disagree and neutral respectively on the above
question.
Regarding the question which tells about the contribution of the system towards
achieving the company’s vision? Out of the total sample population 70(67.3%) and
24(23.1%) of the respondents has strongly agreed and agreed respectively that the system
has a high contribution in achieving company’s vision. Out of the total sample population
1(1%) and 3(2.9%) of the respondents were strongly disagreed and disagreed respectively
that implementing the ERP system has no any contribution in achieving the company’s
vision. The respondents from the total sample population 6(5.2%) were given neutral
response for the above question which implies that, they have no clue about the ERP
system.
On the other hand, for the questions which indicate that, rather than using the ERP
system in all functional areas is there some functional areas which are still using both the
manual and automated working system? out of the total sample population 65(62.5%)
and 17 (16.3%) of the respondent were strongly agree and agree respectively that they
confirmed there are still some functional areas which were use both manual and
automated system. respondents believed that the deployed ERP system makes the entire
company business process fully automated (specifically on the divisions that the system
has been already deployed). From this fact, we can deduce that majority of the
respondents believe that the ERP implementation does not make the company working
process fully automated and there are some tasks that has been handled manually even if
the system is already there to support the daily routine. Other than that, 2(1.9%), 5(4.8%)
and 15(14.4%) of the respondents were strongly disagree, disagree and neutral
respectively.
In the case of customer satisfaction, ERP implementation in the company is the best
solution in satisfying the customer demand? Out of the total population 69(65.4%) and
46
25(24%) of the respondents were strongly agreed and agreed respectively that the system
create a best solution in satisfying customer demand. Besides that, 1(1%), 3(2.9%) and
7(6.7%) were giving there respond strongly disagree, disagree and neutral towards the
question.
The points mentioned in the above table about non-value adding jobs and processes are
reduced after ERP implementation? Out of the sample population 65(62.5%) and
28(26.9%) of the respondents were agreed that the system minimizes the non- value
adding jobs and process. On the other hand, 1(1.9%), 3(2.9%) and 6(5.8%) respondents
out of the total population strongly disagree, disagree and give neutral response
respectively towards the above question.
For the final question on the implementation levels were, The Company apply and utilize
all the features of ERP system? Form the total sample population 14(13.5%) and
24(23.1%) were strongly agree and agree respectively that ethio telecom has utilizes all
the features of ERP system. proportion of the employees from both sides believe that the
company is not exhaustively utilizing all the features of ERP system even if the package
is already procured by huge investment. Were as, 46(44.2%) and 16(15.4%) were
strongly disagree and disagree that the company were not fully apply the system and were
not utilize all the features of the system. Beside on that also 4(3.8%) of the respondent
were given neutral for the above question.
47
4.2.3. Respondents’ perception towards the competence of ERP implementation
level
Enterprise Resource Planning (ERP) systems are very popular systems for information
management in the global business environment. The questions investigate the
competency of the project team on the ERP integration contributes to ERP
implementation strategy in the case of ethio telecom.
48
knowledge
Regarding the question about the ERP project has been the top and only priority for the
team? 12(18.3%) of the respondents are strongly agree and 19(11.5%) of respondents are
agree this shows that most i.e., 31(29.8%) of the respondents were agreed. This shows
that, the team has been giving priority for the project of ERP. Rather than that, from the
total sample population, 41(39.4%) and 17(16.3%) were responds that they were strongly
disagrees and disagrees that the team were not giving a priority for the project of ERP.
And the rest respondents 15(14.4%) has no clue on the situation.
The points mentioned in the above table about the adequacy and experience of the project
team member on the key issues relating to ERP implementation? Out of the total
population 48(46.2%) are strongly agree and 31(29.8%) of respondents are agree. This
shows that the overall majority i.e., 79(76.0%) of the respondents find it that the
knowledge, skill and experience of the project team is adequate in the key issues relating
to the system. Were as 1(1%), 12(11.5%) and 12(11.5%) of the respondents were
strongly disagree, disagree and neutral for the above question respectively.
The table above deals with the question about the technical knowledge of project team
member’s competency? In return 46 (44.2%) of the respondents are strongly agree and 38
(36.5%) of respondents are agree this shows that the overall majority i.e. 84(80.7%) of
49
the respondents find it that the project team were competent in regards of technical
knowledge of the system. Were as, out of the total sample population 2(1.9%), 3(2.9%)
and 15(14.4%) were respond strongly disagree, disagree and neutral on the project team
competency towards the technical knowledge of the implementation.
The points mentioned in the above table the project team members have carefully been
selected based on their knowledge and ability to accept change? In return 52 (50%) of the
respondents are strongly agree and 31(29.8%) of respondents are agree this shows that a
total of 83 (79.8%) of the respondents find it that the project team members were selected
carefully by taking consideration of their adequate skill, theoretical and technique skill
towards the implementation. Were as, out of the total population, 1(1%), 9(8.7%) and
11(10.6%) were strongly disagree, disagree and neutral in the above question
respectively.
Generally, from the total sample population 41.2% of the respondents were strongly
agreed on the adequacy and competency of ERP project team in all technical skill and
knowledge needed for the implementation of ERP system.
50
Table 4.8 the Rate of Training, Documentation and Knowledge Transfer
User training and Strongly Disagree Natural Agree Strongly N Mean S.D
education Disagree Agree
training
51
been built by the % 48.1% 15.4% 14.4% 12.5% 9.6%
organization
functional
experts.
In regards of the adequacy of training towards ERP system implementation, out of the
total sample population 57(54.8%) and 21(20.2%) were strongly disagreed and disagreed
respectively on the raised question. this implies that training wasn’t given exhaustively
for all users. The above data indicates that, ethio telecom did not deploy an intensive
training program in order to equip those employees who are expected to work on the
52
system as main tool. Were as, 5(4.8%), 11(10.6%) and 10(9.6%) were responded strongly
agree, agree and neutral respectively.
The table above deals with the question about Organization has provided all resources
required for training? Out of the total sample population 53(51%) and 22(21.2%) of the
respondent were strongly disagree and disagreed respectively that the there is no resource
provided for the specific training of the system. were as, the rest respondent, 6(5.8%),
12(11.5%) and 11(10.6%) were strongly agreed, agreed and neutral on the raised
question.
The points mentioned in the above table were, is the training given on the system was
adequate and useful to your functional module? Out of the total sample population,
48(46.2%) and 17(16.3%) of the respondents were strongly disagree and disagree
respectively. This indicates that, 65(62.5%) out of 104(100%) respondent believes that
the training which has been given for the employees were inadequate and it is not useful
for a specific functional module. rather than that, out of the total sample population
8(7.7%), 18(17.3%) and (13(12.5%) were strongly agree, agree and neutral respectively
on the adequacy of the training and usefulness of the training towards there functional
module.
As seen in the above table, the respondents were questioned that if there is enough time
allocated for the purpose of ERP training? Out of the total sample population, 54(51.9%)
and 19(18.3%) respondents were strongly disagreed and disagreed respectively. Above
half (73 respondents) of the sample population disagreed on the raised question. This
implies that there is no scheduled time for the training of ERP system. Were as, 5(4.8%),
11(10.6%) and 15(14.4%) respondents were strongly agreed, agreed and neutral
respectively for the above question.
On the other hand, the question which says Training materials had been built by the
organization functional experts? Out of the total sample population 50(48.1%) and
16(15.4%) were strongly disagreed and disagreed respectively on the issue. This leads out
53
of the total sample population 66(63.5%) were disagreed that the training materials were
not build by functional experts. Beyond that, 10(9.6%), 13(12.5) and 15(4.4%)
respondents were strongly Agree, agree and neutral respectively on the raised question.
For the question about Training program was handled by highly qualified consultants and
trainers? Out of the total sample population, 52(50%) and 13(12.5%) of the respondents
were strongly disagreed and disagreed respectively. This shows that from 104
respondents 65 respondents were disagreed that the training program were not consulted
by highly qualified consultants and trainers. Besides that, 3(5.8%) and 17(16.3%) were
strongly agreed and agreed respectively that there are a highly qualified consultants and
trainers for the training program. And the rest 16(15.4%) has no clue about the training
program of ERP system.
In the case of the level of in-dependency on integrates are still high? Out of the total
respondent 49(47.1%) and 9(8.7%) of the respondents were strongly disagreed and dis
agreed respectively. This implies that, because of the inadequacy of the training the level
of dependency on integrates were still high. Were as, 10(9.6%), 16(15.4%) and
20(19.2%) were respond strongly agree, agree and neutral respectively towards the above
question.
The final question in the section of training, documentation and Knowledge Transfer
were, the functional and technical support of integrator is successful in relation to
knowledge transfer? From the total sample population of 49(47.1%) and 9(8.7%)
respondents were strongly disagreeing and disagree respectively. this shows that from out
of 104 respondents 58 respondents were dis agree. which implies that, because of
inadequacy of the training there is no successful relationship between functional and
technical supports integrator with that of knowledge transfer. Besides that, 9(8.7%),
24(23.1%) and 13(12.5%) were respond strongly agree, agree and neutral respectively for
the raised question.
54
Generally, the survey of the above section i.e., training, documentation and Knowledge
Transfer about the ERP system in ethio telecom leads the research to conclude that, there
is lack of training which was observed as one common constraint for ERP
implementation in ethio telecom. By this, it could be said that, from the total sample
population 75% of the respondents believe that, imparting training program and
additional enhancement training program is highly required. Finally, the above issues
which basically lack training can also be considered as one of the challenges for
successful implementation of ERP system in ethio telecom.
Compatibility issues with ERP modules usually lead to issues in integration of modules.
Companies associate different vendors to implement different ERP modules, based on
their competency. Therefore, it is very essential that there is a way to handle
compatibility issues in dealing with implementation of technologies such as ERP
solutions. In this study to deal with the issues of compatibility, user friendliness, ease of
understandability and ease of understandability of the reporting formats were used as
yardsticks.
55
challenge
Regarding the question which says User’s interface of the system is easily
understandable? Out of the total sample population 35(33.7%) and 16(15.4%)
respondents were strongly disagreed and disagree respectively. This implies that from
104 respondents 51 of them were disagreed this leads the research to conclude that the
user’s interface of the system were not easily understandable. Beside on that, 8(7.7%),
30(28.8%) and 15(14.4%) respondents were given strongly agreed, agreed and neutral for
the question raised.
In the case of users, can users work on the system without any challenge? Out of the total
population 39(37.5%) and 22(21.2%) of the respondent were strongly disagree and
disagree respectively. This implies that the data gather from the respondent leads the
research to conclude that 61 of the respondents were disagreed that users were face
challenges when they intended to work ERP system. Were as, 4(3.8%) and 20(19.2%)
were strongly agreed and agreed that all the users can work the system without any
challenge to be faced. And the rest of the respondent 19(18.3%) were neutral for the
raised question.
Seeing the above table, the reporting formats are easily understandable by external users
and decision makers? Out of the sample population 13(12.5%) and 49(47.1%) of the
respondents were strongly agreed and agreed respectively. This shows that, most of the
respondent (62 respondents out of 104 sample population) the reporting mechanism were
56
easily understandable. Were as, 27(26%) of the respondent were neutral which means the
respondents has no clue about report. Besides that, 5(4.8%) and 10(9.6%) of the
respondents were disagree on the raised question.
Generally, in compatibility issue with ERP module from the above discussion,
compatibility is recognized as one major challenge and constraining successful ERP
implementation in the company
This part covers the presentation and analysis of ERP implementation evaluation process.
expenses
57
ERP is F 2 2 13 46 41 104 4.173 .8640
integrated in the
whole business
% 1.9% 1.9% 12.5% 44.2% 39.4%
process
satisfaction
Concerning the question which was raised about Overall, ERP implementation was
successful? Out of the total sample population, 35(33.7%) and 50(48.1%) of the
respondent strongly agreed and agreed respectively. This shows that, out of the total
sample population of 104 respondents, 85 of them were agreed that the ERP
implementation in ethio telecom is successful. Ware as, 6(5.8%) and 16(12.5%) of the
respondents were disagreed and give neutral response towards the question raised
respectively.
In regards of the question which says the organization Service is improved after using
ERP? 37(35.6%) and 55(52.9%) respondent were strongly agreed and agreed respectively
out of the total sample population. This implies that the services which were being
provided by the organization were improved after the implementation of the ERP system.
The rest respondent were given their response towards the above question were 1(1%),
2(1.9%) and 9(8.7%) were strongly disagree, disagree and neutral respectively.
58
For the question which says ERP allows for better control of business operating
expenses? Out of the total population, 45(43.3%) and 47(45.2%) of the respondent were
strongly agreed and agreed respectively, this implies that the system can allow a better
control of business operating expenses. Regardless of that, 2(1.9%) and10 (9.6%) of the
respondents were disagreed and given a neutral response respectively for the raised
question.
By the same manner for the question arises related with ERP system, is it integrated in
the whole business process or not? The respondent out of the total sample population of
104, 41(39.4%) and 46(44.2%) were strongly agreed and agreed respectively that the
ERP system were integrated in the whole business process. Apart from that, 2(1.9%),
2(1.9%) and 13(12.5%) of the respondents were given strongly dis agree, disagree and
neutral response for the raised question respectively.
Employees were also asked whether ERP has improved customer satisfaction or not? Out
of the total population, 39(37.2%), 49(47.1%), 1(1%), 2(1.9%) and 13(12.5%) were
respond that strongly agree, agree, strongly disagree, disagree and neutral for the above
question respectively. 88 of the respondent out of 104 sample population were agreed that
the system had improved the satisfaction of customers towards the service.
Regarding the observation of employees about ERP system were easy to operate and user
friendly or not? Out of the total sample population, 42(40.4%) and 7(6.7%) of the
respondent were strongly disagreed and disagreed respectively, this implies that, 49
respondents were not agreed that the system is friendly rather they think it is difficult to
operate and it is unfriendly to the users. Were as, 17(16.3%), 27(26%) and 11(10.6%) out
of the total population responds strongly agree, agree and neutral for the raised question
respectively.
Generally, depict of ERP system were not easy to operate and unfriendly to the users, the
survey analyzed that out of the total respondent of 104, 39 and 47 of them were strongly
59
agreed and agreed respectively. This implies that 89 respondents were agreed on the total
improvement ethio telecom by using the system of ERP is successful in all aspects.
This part covers the presentation and analysis of overall perceptions of employees about
the deployed ERP system.
60
(Source: Own Survey).
To have an overall view about the system the research raised the above-mentioned
questions, and regarding whether ERP implementation reduces the financial cycle closing
time or not,46 (44.2%) of respondents have agreed that deployed ERP system reduces the
financial cycle closing time. With similar fashion, the research has raised a question
whether the decision-making cycle time has been reduced or not. Thus, 46 (44.2%) of
management respondents replied that the decision cycle time has been reduced after ERP
implementation. In addition, employees were requested to indicate that whether the
procurement cycle time is reduced or not 52 (50%) of respondents have agreed and
similarly a question related to the pay slip generation has also been raised. Finally, a
question was raised about if there is an improvement in tracing employees’ detail. Hence,
47 (45.2%) of employees agreed that there is an improvement in tracing different
employment related records of the employee.
This part covers the presentation and analysis of prospect of ERP implementation.
61
with a % 0% 0% 4.8% 35.6% 59.6%
centralized
database
makes it more
secured
Regarding the question which says in the future ERP helps in handling all business
operations? Out of the total population, 65(62.5%) and 27(26%) of the respondent were
strongly agreed and agreed respectively that the system will handle all business operation
in the future. Besides that, 2(1.9%) and 10(9.6%) of the total sample population were
respond disagree and neutral respectively for the raised question.
Regarding the observation of employees towards the future ERP system with a
centralized database makes it more secured? Out of the sample population 62(59.6%) and
62
37(35.6%) of respondents were strongly agreed and agreed respectively that the system
can be secured by centralized databases in the future. Apart from that, 5(4.8%) of the
respondent give neutral for the specific question.
On the other hand, the employee was asked that, in the future ERP solutions provide
reduced operational and management cost? Out of the total population, 63(60.6%) and
33(31.7%) of the respondent were strongly agreed and agreed respectively the system can
provide a better solution by minimizing both operational and management cost. Other
than that, 1(1%) and 7(6.7%) of the respondents were strongly disagree and neutral for
the given question respectively.
For the question which says in the future ERP provides the system with improved
profitability and growth? 67(64.4%) and 31(29.8%) of the respondent were strongly
agreed and agreed respectively. This shows that from the total sample population of 104,
98 of the respondents were agreed that ERP provides the system with improved
profitability and growth in the future. Were as, 6(5.8%) of the respondent were neutral in
the regard of the above question.
Generally, the survey of the research can conclude that out of the total population 64 and
32 respondents were strongly agreed and agreed respectively in all the raised questions
respectively. This implies that the ERP system in the future can fulfill all the features
basically, handling all business operations, the system can be secured by centralized
databases, can provide a better solution by minimizing both operational and management
cost and also provides the system with improved profitability and growth for the
company.
63
4.2.9. Respondents perception towards ERP implementation constrains
This part covers the presentation and analysis of ERP implementation constrains.
64
bridges to legacy % 1% 42.3% 19.2% 26% 11.5%
application
For the question which says Ineffective communication with users? Out of the total
population, 28(26.9%) and 44(42.3%) were strongly agreed and agreed respectively that
there is a huge gap in effective communication with users in ethio telecom. Were as,
3(2.9%), 11(10.6%) and 18(17.3%) were strongly disagree; dis agreed and neutral
response towards the raised question.
65
In the case of insufficient training of end users, the responses were, 37(35.6%),
48(46.2%), 3(2.9%), 2(1.9%) and 14(13.4%) strongly agree, agree, strongly disagree,
disagree and neutral respectively. This indicates that out of the total population 85 of the
respondent were agreed that there is insufficient training for the end users.
For the question of that says failure to get user support? The response were, 30(28.8),
48(46.2%), 0(0%), 15(14.4%) and 11(10.6%) strongly agree, agree, strongly disagree,
disagree and neutral respectively. This shows that out of the total sample population, 78
of the respondents were agreed that they were failed to get support from the users.
Concerning the question which was raised about Attempts between bridges to legacy
application? The response were, 12(11.5%), 27(26%), 1(1%), 44(42.3%) and 20(19.2%)
strongly agree, agree, strongly disagree, disagree and neutral respectively.45 of the
respondent out of 104 total population sample were disagreed that there are brides in
attempting legacy applications were as 39 of the respondents were agreed that there is no
brides in attempting legacy applications.
For the question which tell that Conflicts between user departments? The response were,
21(20.2%), 48(46.2%), 4(3.8%), 13(12.5%) and 18(17.3%) strongly agree, agree,
strongly disagree, disagree and neutral respectively. The above data implies that, 69 of
the respondents out of the total sample population were agreed that there is a conflict
between users in the departments.
In the case of Composition of project tram members, the response were, 9(8.7%),
24(23.1%), 2(1.9%), 51(49%) and 18(17.3%) strongly agree, agree, strongly disagree,
66
disagree and neutral respectively. It implies that out of the sample population, 59 were
disagreed the question, which means they believe that the composition of project team is
poor.
Regarding the question Failure to redesign business process, the response were,
11(10.6%), 19(18.3%), 5(4.8%), 51(49%) and 18(17.3%) strongly agree, agree, strongly
disagree, disagree and neutral respectively. It implies that out of the sample population,
56 respondents were disagreed on the raised question. They believed that there is no such
thing called failure in the redesigning of the business process.
The final question were Misunderstanding of (resistance to) change requirement? The
response were, 22(21.2%), 48(46.2%), 3(2.9%), 14(13.5%) and 17(16.3%) strongly
agree, agree, strongly disagree, disagree and neutral respectively. It implies that out of the
sample population, 70 of the respondents were agreed that there is a misunderstanding of
change requirement.
67
CHAPTER FIVE
SUMMARY, CONCLUSION AND RECOMMENDATION
5.1. Summary of Findings
In this research, Values were ingrained in every sample individual and this study presents
some insights to understand this individual and how values are reflected in the
interactions within their understanding towards the system of ERP. The objectives of this
study were to assess and evaluate the overall performance, challenges and prospect of
implementing Enterprise Recourses planning (ERP) in ethio telecom and to recommend
possible solutions for the gap. Depending on the data presentation, nearly 62.5% of the
respondents believed that the deployed ERP system doesn’t make the working process
fully automated, especially in the area it’s deployed. Almost 78% of the sample
proportion responded that from the individual as well as company perspective, ERP helps
them by enhancing their efficiencies. Similarly, ERP implementation also contributes a
lot in achieving the company vision (being a world class telecom service provider) even
if there are things to be done for the better achievements and benefits to be realized from
the system.
From the system user friendliness perspective, 57% of the respondents believe that the
systems user interface, the navigation panels and the navigation steps are not difficult to
understand and work on it, but from the reporting perspective more than half of both the
respondents believe that the reporting formats are difficult to understand by decision
makers as well as external stakeholders.
Regarding the system utilization point of view 36.6% of the respondents have stated that
there are number of ERP features which is not yet exploited by the company even if the
entire package of the system has been procured. Regarding mix up usage of both the
manual and automated working process, more than 80% of the respondents from both
side believe that the company is now utilizing both the manual as well as system based
working process for the day to day activity of the company even if a full-fledged system
68
is already introduced. As per the results of the study major challenges to ERP
implementation were identified. Accordingly, lack of top management support, the rate of
training, documentation and knowledge transfer, compatibility issues with ERP module
were found major challenges in ERP implementation in ethio telecom. Moreover, the
analysis results showed that misunderstanding of change requirements, ineffective
communications with users, lack of management support, insufficient training of end
users, failure to get user support, conflict between user departments, application were
computed to be major challenges determining the success of the implementation of ERP.
5.2. Conclusion
69
an ERP system implementation can easily be scuttled. Also, unless, organizational
structure and culture is streamlined, an ERP system may precipitate a crisis in an
organization. (Brown et al, 2003, 10). Beside on that, Management has to consider the
time available for the implementation of the system. ERP implementation projects are
known to take longer than other ordinary Information management systems. But the
management or the project team should have to aware each employee by deploying
trainings with skilled personnel in order to provide adequate knowledge transfer for the
users. However, because of the complexity involved in implementing ERP applications,
the organization should have well-choreographed plans. The implementation of the
system requires closer coordination among all stakeholders. Necessarily, the project
management should be left to experts. However, the participation of all employees is very
vital. The time spent on ERP implementation may cost the company business. Therefore,
contingent plans have to be instituted to deal with any possible inconveniences to
business due to ERP implementation. Finally, as overall observations of the system in
this particular study, it was tried to conduct focus group discussion so as to identify ERP
system implementation challenges/constraints which are distinguishable to ethio telecom.
Regardless of that, ERP implementation has supported the company by reducing the
financial cycle time, decision making cycle time, procurement lead time and pay slip
generation time. In addition, it improves the efficiency of tracing employee’s detail.
70
5.4. Recommendation
1. An ERP implementation partner or project manager shall do the scope of the project
based on the organization’s team very precisely. Further, they shall have done the
responsibilities of the individual team members and prepare the resources required. A
project manager shall present the scope and resources required list to senior leadership to
get the buying over the proposed budget and time availability of the project before
starting it.
2. Users training and change adaption management: All ERP software users must be
trained with new systems and job responsibility so that they can adopt the change easily
over the period.
3. Future growth plan and its scale: Future business expansion scope shall be outlined to
skip from new change shall not set back our requirements for several weeks, months, or
years ahead.
71
REFERENCE
Aladwani, A.M. 2001. Change management strategies for successful ERP
implementation. Business Process management journal, 7(3):266-275
Batool, S., Sajid, M., & Raza, S. (2012). Benefits and Barriers of Human Resource
Information System in Accounts Office & Azad Jammu & Kashmir Community
Development Program. International Journal of Humanities and Social Science,
211-217.
Batool, S., Sajid, M., & Raza, S. (2012). Benefits and Barriers of Human Resource
Information System in Accounts Office & Azad Jammu & Kashmir Community
Development Program. International Journal of Humanities and Social Science,
211-217.
Beadles, N., Lowery, C., & Johns, K. (2005). The Impact of Human Resource
Information Systems: An Exploratory Study in the Public Sector.
Communications of the IIMA, (pp. 39- 46).
Chen I. J. (2001): Planning for ERP systems: analysis and future trend. Business Process
Management Journal, Vol. 7, No. 5, pp. 374-386
Davenport, T. (1998) ‘Putting the enterprise into the enterprise system’,Harvard Business
Review,Vol. 76, No. 4, pp.121–131.
Davenport, T., Harris, J. and Cantrell, S. (2002) the Return of Enterprise Solutions,
Accenture.
Davis, F., Bagozzi, R. and Warshaw, P. (1989) ‘User acceptance of computer technology:
a comparison of two theoretical models’, Management Science, Vol. 35, No. 8,
pp.982–1003.
Deloitte Consulting (1998) ‘ERP’s second wave: maximizing the value of ERP-enabled
Processes’.
Dong, L. (2001) ‘Modeling top management influence on ES implementation’, Business
Process Management Journal, Vol. 7, No. 3, pp.243–250.
72
Esteves, J., Pastor, J. and Casanovas, J. (2002) ‘Measuring sustained management
support in ERP implementation projects: a GQM approach’, Proceedings of the
Eighth Americas Conference on Information Systems, pp.1381–1389.
Gupta, B. (2013). Human Resource Information System (HRIS): Important Element of
Current Scenario. IOSR Journal of Business and Management (IOSR-JBM), 41-
46.
Ibrahim, A. (2010). What Organizations Should Know About Enterprise Resource
Planning (ERP) System. European, Mediterranean & Middle Eastern Conference
on Information Systems 2010 (EMCIS2010), (pp. 1-16). Abu Dhabi.
Kothari, C. R. 2004.Research Methodology, 2nd ed. New Delhi: New age international
limited.
Markus M. L., Axline S., and Petrie D., Tanis C. (2000): Learning from the adapters’
experiences with ERP: problems encountered and success achieved. Journal of
Information Technology, Vol. 15, pp. 245-265
Mital A. (1997): What role for humans in computer integrated manufacturing?
International Journal of Computer Integrated Manufacturing, Vol. 10, No.1-4,
pp. 190-198
Norasmah, H. O., & Sabariah, I. (2007). Tahap tingkah laku kognitif keusahawanan di
kalangan pelajar dan remaja. In N. H. Othman, & H. Harun (Eds.), Keusahawanan
Remaja Malaysia (pp. 78-102). Serdang: Penerbit Universiti Putra Malaysia.
Norasmah, H. O., & Salmah, I. (2011). Kecenderungan terhadap pemilihan kerjaya
keusahawanan mengikut persepsi peserta skim usahawan siswa. Jurnal Teknologi,
56, 47-63.
O‟Leary D. E. (2000): Enterprise recourse planning systems: systems, life cycle,
electronic commerce and risk. Cambridge University Press
Ross J. W. (1999): Surprising facts about implementing ERP. IT Pro, July/August
Sakaran, U. (2003). Reserach Methods for Business. John Wiley and Sons,
Inc.
73
Sarker, S. and Lee, A. (2003) ‘Using a case study to test the role of three key
social enablers in ERP implementation’, Information & Management, Vol. 40,
No. 8, pp.813–829.
Welti N. (1999): Successful SAP R/3 implementation: Practical management of ERP
projects, Pearson Education Limited
Whyte, D. & Fortune, J. (2002). Current practice in project management – an empirical
study International journal of project management, 20:1-11
74
APPENDIX I
Dear Respondent
The main purpose of this questionnaire is to gather information about “ERP Project
Implantation as an inquiry of the Performance, Challenges and Prospects in the case of
ethio telecom”. The research is planned to be conducted for the in partial fulfillment of
the requirement for the degree of Masters of Art in project management. The survey is
intended to assess and evaluate the overall the performance, challenges and prospect of
implementing Enterprise Resource planning (ERP) in ethio telecom. It will be a great
contribution if you may complete all the items covered in the questionnaire. The
information you are going to give here is very important for the study; any information
you fill in this questionnaire will be kept confidential and used only for this study.
I thank you in advance for sharing your valuable experience and time in completing the
questionnaire.
Contact Addis
Frehiwot K.
Mobile - + 251923161673
E- mail- [email protected]
75
Part I: Demographical Information: - Please put ‘X’ in the box
1. Gender
☐ Male ☐ Female
2. Age
3. Educational Status
☐ BA/BSC ☐Masters
☐PhD
4. Experience
☐ 11-15 ☐ 16-20
☐ 21 and above
5. Division
6. Position
76
☐ Admin ☐ Supervisor
☐ Specialties ☐ Manager
Please put “X” the alternative of your choice, the numbers below has been defined with
their respective equivalent meaning to ease the questionnaire for each respondent.
1 = Strongly Disagree
2 = Disagree
3 = Neutral
4 = Agree
5 = Strongly Agree
1. Process
How much effective is the current deployed ERP system in transforming the legacy of manual working
condition in to automated system at ethio telecom
# Item 1 2 3 4 5
1 The organization is obtaining the benefits expected from ERP implementation
3 There are some functional areas still using both the manual and automated working
system
4 ERP implementation in the company is the best solution in satisfying the customer
demand
5 Non-value adding jobs and processes are reduced after ERP implementation
77
6 The company apply and utilize all the features of ERP system
2. Competence
To what extent do you agree on the following statements regarding project tem competences
# Item 1 2 3 4 5
1 The ERP project has been the top and only priority for the team
2 The project team members had knowledge of the key issues relating to ERP
implementation
3 The project team had experienced in previous ERP implementations
4 The project team members had business and technical knowledge
5 The project team members have carefully been selected based on their knowledge
and ability to accept change.
3. User training and education
To what extent do you agree on the following statements regarding user training and education
# Item 1 2 3 4 5
1 Training was given exhaustively for all users.
2 Organization has provide all resources required for training
3 The training given on the system was adequate and useful to your functional
module
4 Enough time was allocated for ERP training
5 Training materials had been built by the organization functional experts
To what extent do you agree on the following statements regarding on system easiness
# Item 1 2 3 4 5
1 Users interface of the system is easily understandable
2 Users can work on the system without any challenge
78
3 The reporting formats are easily understandable by external users and decision
makers
5. ERP implementation evaluation
To what extent do you agree on the following statements regarding on ERP implementation evaluation
# Item 1 2 3 4 5
1 Overall, ERP implementation was successful.
2 The organization Service is improved after using ERP
3 ERP allows for better control of business operating expenses
4 ERP is integrated in the whole business process
5 ERP has improved customer satisfaction
6 ERP system is easy to operate and user friendly.
6.Overall impact of ERP implementation
# Item 1 2 3 4 5
1 ERP reduced the financial cycle closing time
79
Part III: Related to feature prospects of ERP implementation
Kindly indicate the extent to which the following aspects influence the feature prospects
of company after the implementation process.
1 = Strongly Disagree
2 = Disagree
3 = Neutral
4 = Agree
5 = Strongly Agree
80
Part IV: Related to challenges constraints in implementation
The following table ERP implementation constrains so called as risk factors is listed and
please ranks them one up five according to your division. One is very low and five very
High.
81