Isp 640
Isp 640
CS240
BACHELOR OF INFORMATION TECHNOLOGY (HONS.)
Assume you have to complete project ABC within 6 months. Given the following information as
part of the payment received for one particular phase of a project ABC.
(15 marks)
b) Based on the report above, do you need a project review and what purpose does it serve?
Yes, I need a project review. This is because to not only show evidence that the project
work has been completed, but also that the work has been completed according to
certain standards or agreed-upon requirements.
(5 marks)
QUESTION 2 (10 MARKS)
Your project has a budget of RM320,000.00 and is 25 percent complete. You have spent
RM75,000.00 on your project. However, due to some rework and additional time from a
vendor, your project is supposed to be 30 percent complete by this time.
Therefore, for this project calculate the following and explain your results.
i. Earned Value.
𝟐𝟓
Earned Value (EV) = × 𝟑𝟐𝟎, 𝟎𝟎𝟎
𝟏𝟎𝟎
= RM 80,000
= RM 5,000
Hence, the project’s Cost Variance is RM 5,000 and you are under budget
since it is positive.
iii. Cost Performance Index.
𝟖𝟎,𝟎𝟎𝟎
Cost Performance Index = = 1.07
𝟕𝟓,𝟎𝟎𝟎
This means you are earning 1.07 for every 1 spent since the Cost Performance
Index is greater than one. This means you are under budget.
𝟑𝟎
Planned Value (PV) = × 𝟑𝟐𝟎, 𝟎𝟎𝟎
𝟏𝟎𝟎
= RM 96,000
𝟖𝟎,𝟎𝟎𝟎
Schedule Performance Index = = 0.83
𝟗𝟔,𝟎𝟎𝟎
The project is behind schedule since the Schedule Performance Index is less
than one.
(10 marks)
QUESTION 3 (20 MARKS)
a) Given the following information for the one-year project, answer the following
questions.
i. What is the cost variance, schedule variance, cost performance index (CPI),
and schedule performance index (SPI) for the project?
(8 marks)
ii. Based on the answer above, how is the project doing? Is it ahead of schedule
or behind schedule? Is it under budget or over budget?
Based on the answer above the project is behind schedule and it is also over
budget for the project.
(2 marks)
iii. Use the CPI to calculate the estimate at completion (EAC) for this project.
Explain whether the project performing better or worse than planned?
(3 marks)
iv. Use the schedule performance index (SPI) to estimate how long it will take to
finish this project.
(1 mark)
v. Explain how earned value management (EVM) can be used to control costs
and measure project performance.
EVM control costs and measure project performance by the technique that
integrates the cost, scope, and schedule of the project into a single parameter
as it provides the status of the performance of the project. Also, based on
planned and actual values, EVM predicts the future and enables project
managers to adjust accordingly.
(2 marks)
(4 marks)
QUESTION 4 (20 marks)
Given the information for eight-months project, answer the following questions. The total
planned cost of the project is RM200,000. The table below shows the data collected to date.
The plan is for the project to be completed after eight months. The earned value report in
the table below shows the data that been collected for the first four months of the project.
Month Planned Value (PV) Actual Cost (AC) Earned Value (EV)
1 10,000 10,000 10,000
2 30,000 20,000 25,000
3 50,000 50,000 60,000
4 70,000 90,000 70,000
5 130,000
6 170,000
7 190,000
8 200,000
a) What is the schedule performance index (SPI) and cost performance index (CPI) for month
3? In month 3 is the project ahead or behind schedule? Is it under or over budget?
= In month 3 the project is ahead of the schedule and the project is under budget.
(4 marks)
b) What is the cost variance (CV) and schedule variance (SV) for month 4? In month 4 is the
project ahead or behind schedule? Is it under or over budget?
CV = 70,000 – 90,000
= -20,000
SV = 70,000 – 70,000
=0
(3 marks)
c) What is the estimate at completion (EAC) at month 4 if the cost performance index will
remain the same for the remaining part of the project?
(5 marks)
d) During month 5, it is found that some of the work that was reported complete in month 2
was considered unacceptable. It will require RM5,000 to fix the problem and make this work
acceptable. The work is scheduled to be done in month 6. No other work is reported to be
completed during month 5. What is the EV for month 5?
(2 marks)
e) What factors need to be known in order to be able to calculate the Estimate to Complete
(ETC)?
The factors that need to be known is budget at completion, earned value, and
the actual cost
(3 marks)
f) Explain what happens during the process to determine the project budget.
The project budgeting is a process during which the charge of the individual work is
probable throughout the project. This is mainly performed based on the WBS.
Through the process of project budgeting, a cost baseline is formed so as to
calculate the performance and the support requirements.
(3 marks)