Value Engineering
Value Engineering
Engineering
QUALITY ASSURANCE and Quality
Assurance
Objectives
Structure
L.D. Miles defined Value Analysis in his book Techniques of Value Analysis
and Engineering (1961) as "an organised creative approach which has for its
purpose the efficient identification of unnecessary cost i.e., cost which
provides neither quality, nor use, nor life, nor appearance, nor customer
features”. Various other definitions are proposed such as “an organised
systematic study of the function of a material, component, product or service,
with the objective of yielding value improvement through the ability to
accomplish the desired function at the lowest cost without degradation in
quality". Thus the basic objective of VE/VA is to achieve equivalent or better
performance at a lower cost while maintaining all functional and quality
requirements. It does this largely by identifying and eliminating hidden, invisible
and unnecessary costs. We may simply perceive VE as the systematic
application of recognised techniques to identify the functions of a product or
service and provide those functions at the lowest total cost.
One of the important reasons behind poor value in products, systems and
procedures that we come across is the lack of organised effort in devising such
systems. Many times the designs are created under highly compressed time
frame and the designer may play safe by giving product designs with sole
306 emphasis on technical feasibility and may prescribe thicker, costlier materials
and other unnecessary features which are not needed by the customer. Value
Engineering
Sometimes, ad hoc decisions get permanency due to lack of review of product and Quality
designs. Often lack of consultation with others contributes to poor value. Lack of Assurance
information, wrong beliefs, habits and attitudes are some of the other reasons.
The term ’ Value' is used in many different ways and is frequently confused with
the monetary price or cost of an item. However value is not synonymous with
cost.
Value may be perceived as the ratio of the sum of positive and negative aspects
of an object. Thus value can be considered as a composite of quality and cost. It
is more in terms of worth or utility. Thus a ratio of quality to cost can be treated
as the value of a product. If its costs can be reduced for same quality or
quality can be improved with same cost, then the value improvement can be
said to occur. The term value can be divided into following types:
a) Use Value: The properties and qualities which accomplish a useful purpose
or service.
b) Esteem Value: The properties, features or attractiveness which cause us
to want or own it.
c) Cost Value: The sum of labour, material and various other costs required to
produce it.
d) Exchange Value: The properties or qualities which enable us to exchange it
for something else we want.
Function:
Value Tests
By applying the value tests we may come across poor value areas which are
responsible for unnecessary costs. These could be in the design of the
product, , procurement, handling and storage of materials, production
processes, packaging and distribution of the final product. Once we are able to
identify poor value areas, we can focus our attention on these so this these
unnecessary features can be eliminated
309
Capacity Planning, Another way to identify the poor value areas is through function cost matrix
Work and Job
Design & Value approach. If a function is relatively less important but accounts for a larger
Engineering percentage of product cost then it is a potential area for value improvement.
By determining alternative cheaper ways to achieve that function we can reduce
the cost and improve value.
In this unit we shall briefly outline the salient features of three different
approaches to conduct a VE programme. These are:
Since the Job Plan due to Mudge is a very well recognised approach, we will deal
with it in this section. The seven phases of Job Plan are:
The general phase plays vital role throughout and provides a good base for other
phases to succeed.
Brief description of each phase together with associated VE techniques are given
in the following sub-sections.
Throughout the application of the entire Job Plan the techniques of this phase
must be diligently applied to create the right environment for Value
Engineering job plan to be effective. There are five techniques associated with
this phase:
Once the techniques of the information phase have been used to secure pertinent
data, the function phase of the Job Plan can be used.
The objectives of this phase are to define the functions that a product actually
performs and is required to perform as well as to relate these functions to the cost
and worth of providing them.
312
The two techniques of this phase are a major part of the functional approach. Value
Engineering
When combined with the other techniques of the Job Plan it produces a and Quality
systematic approach which is different and more productive than any other Assurance
Product Function
a) Mirror Reflect light
b) Brake Arrest motion
c) Clutch Transfer power
d) Erection tube cover Shield Tube
e) Cigarette lighter Provide ignition
f) Light bulb Emit light
g) Screwdriver Transfer torque
h) Coffee cup Hold Liquid.
Function description should be derived for the product and all its components.
The evaluation process also helps to find out whether it is a primary (basic)
function or a secondary function. The basic function will have the highest
score in the above- mentioned process of evaluation. The technique not only
establishes the basic and secondary functions but also identifies those functions
which are present because of specifications and requirements or present design
approach. Generally, a product or component will have only one basic function
and a number of secondary functions. If you have more than one basic function,
it must be a mere restatement of the other.
Example 11.2: Here we illustrate the application of function phase on the item.
‘Door Assembly' of a refrigerator. The two-word definition of each part or
component of the door assembly is shown in Table 1 in the form of Functional
Analysis Worksheet. The paired comparison of various functions is shown in
Table 2. Figure I shows the graphical display of the relative importance of
various functions which identify them as basic and secondary. You can also
distinguish functions which are there due to present design approach as well as
due to specifications and requirements. The basic function of the door assembly
emerges as ‘Provide Security’ with the highest score.
Having defined the functions, the next step is to establish the worth of each
function. The objective is to determine the poor value functions and to obtain a
reference point from which the cost of alternatives can be compared.
314
Value
Engineering
and Quality
Assurance
33
(1) % weight (A) 100 1.85
178
12
% weight (B) 100 6.7 ..etc
178
(2) Cost to be calculated from the available price break-
up of the component part of the Door-Assembly of
the refrigerator.
We conclude from Table 2
Worth 18.5
(3) Value Index for A 0.83 that while item A has poor
Cos t 22.3 value and high cost items C,
6.7 1 and K all have poor
Value Index for B 1.72.....and so on.
3.9 values.
(The greater, the better).
Example 11.3: Table 3 shows a Function Cost matrix for a typical product
(compass). It describes in two-words the function of a component. Its
percentage importance (I) as obtained by paired comparison and percentage cost
(C) obtained by allocating cost to attaining that function by that component.
The Value index is given by I/C. A low value of I/C ratio shows a poor value
area.
a) Establish positive thinking: Here we divorce the judicial part of the mind
from the creative part by insisting that we do not attempt to judge an idea
simultaneously when it is being created.
b) Develop creative ideas: This is done by cultivating uninhibited thinking
and developing a multitude of ideas and approaches for accomplishing the
defined functions. The desired thing at this point is a large number of
ideas, no matter whether they look ridiculous. A number of check-lists and
idea-stimulators could be used for the purpose.
E) Evaluation Phase
The objective of this phase is to select for further analysis the most promising of
the ideas generated during the creative phase and to subject the ideas to a
preliminary screening to identify those which satisfy the following criteria:
• Will it work?
• Is it less costly than the present design?
• Is it feasible to implement?
This phase of the Job Plan together with its supporting techniques must be
undertaken with both care and diligence, for it is here that the judicial part of
the mind is brought into active use. There are four techniques associated with
this phase:
a) Refine and combine ideas: The ideas must be practicable and to make
them so we may have to refine an idea or combine two or more than two
ideas.
b) Establish cost on all ideas: As an idea or combination of ideas is being
refined, an estimated cost should be calculated. What are the potential
costs of implementing the idea and what are the resultant savings
implied?
c) Develop function alternatives: This makes further use of the
information developed in the evaluation of functional relationships to
mould the individual functional solutions into total solutions.
d) Evaluate by comparison: When these rough total solutions and their
related estimates of costs have been established they are compared to
determine which one will provide the greatest value advantage. 317
Capacity Planning, The evaluation of value alternatives may have to be done on multiplicity of
Work and Job
Design & Value attributes-both tangible and intangible. The decision matrix approach can be a
Engineering very effective way of multi-criteria evaluation. Here each criterion is assigned a
relative importance and a normalised value score is allocated to each alternative
on each attribute. The total weighted score is obtained for each alternative and
the greatest score determines the preferred alternative.
Example 11.4: For the compass of Example 11.3 suppose the criteria for
evaluation are: Ease of use, Ease of manufacturing, Safety, Quality and
Attractiveness with the relative percentage weightage of 15, 30, 20, 25 and 10,
respectively. Then the four value alternatives can be compared by using
decision-matrix approach as shown in Table 4. As can be seen value alternative
A2 is the best as it gives the greatest total weighted score.
Table 4
Decision-Matrix to evaluate value alternatives for a compass
ATTRIBUTES
Sr. Value Ease Ease of Safety Quality Attract- Total
N Alternat of use Manufat- (20) (25) iveness Score
o. ive (15) curing (10)
(30)
1 A1 100 30 50 70 100 61.50*
2 A2 80 100 100 50 50 79.50**
3 A3 30 50 70 100 70 61.50
4 A4 50 60 80 50 60 57.00
*(15×100+30×30+20×50+25×70+10×100) / (15+30+30+25+10)=61.50
** A2 is the best alternative, being the maximum scorer.
F) Investigation Phase
The three techniques of this phase further refine the selected ideas into workable
and acceptable solutions providing lower cost methods for performing the
desired function. The three techniques are:
G) Recommendation Phase
This is the final phase of the Job Plan in which the finally selected value
alternative is recommended for acceptance and implementation. It is vital in
the sense that the entire project of conducting VE would succeed only if the
recommendation is accepted. Many a time the acceptance of the suggested
alternative depends upon the way it is presented to the management. The two
techniques associated with this phase are:
Example 11. 5: We take the same phase. After successfully carrying out VE
Job Plan, the improved example as ’Door Assembly' of a refrigerator which
was given for functional analysis design of the ‘Door Assembly’ was
suggested. Figure II shows the existing design and the proposed design. By
the porposed improved design of the door assembly of refrigerator by VE
there would be a saving of considerable amount to the company
manufacturing the unit in its factory per year. The new design will perform
its role well without jeopardizing the functions to be accomplished by such as
assembly.
319
Capacity Planning,
Work and Job
Design & Value
Engineering
Example 11.6: The fig III shows a typical part redesigned with
manufacturing considerations. The revised design has much less number of
parts and hence much reduced cost compared to the original design.
Original Design
Revised Design
320
Other Variants of Job Plan Value
Engineering
and Quality
Some other variants of the Job Plan described above have also been reported. Assurance
These are: DARSIRI method and FAST. The FAST is the most powerful of
these and will be discussed in detail in the next section. DARSIRI is essentially
similar to the Job Plan of Mudge described above. The seven steps involved are-
D (Data Collection), A (Analysis), R (Record of Ideas), S (Speculation), I
(Investigation), R (Recommendation) and I (Implementation).
The parts of the ball pen and functions of parts are shown in Table 5
Table 5
Provide grip
Control flow
The answer is “to communicate ideas”. This function is shown on the left of
the FAST diagram.
The answer is by performing the functions “contain ink and control flow”
which represented right side of basic function.
Next question is how do we control flow and contain Ink? Then the answer is
to position refill, i.e., by making use of spring whose function is to provide
tension, which is represented in the Fig. . Then the other functions are
to be considered. The question ‘when do we improve look? All the time
(ans). The all time functions are placed on the right hand top corner of the
diagram. The other functions are represented as shown in order to determine
the scope of the problem, the FAST diagram includes scope rules (Vertical
broken lines). The left scope line is placed between the basic function under
consideration (make marks) and highest order basic function (Communicate
Ideas). The scope line on the right hand is determined by drawing a vertical
broken line to the left of the function that is suitable input to the system "In
this case, provide part is the suitable input." Design parameters, are placed
322
inside the scope lines. In the next phase, the generation of alternative ways of Value
Engineering
performing desired function is taken up. By observation of adjacent functions and Quality
on the FAST diagram many new ideas may be found to combine. This leads Assurance
iii) Problem: Reduce the manufacturing cost of gasoline tanks for the landing
aircrafls.
i) lndividuals involved in VE usually have other jobs and are already busy.
ii) Teams may be inherently conservative, non-coherent and may avoid
decisions and waste time.
iii) Individual members of the team may have vested interests in resisting
changes.
In this unit we will describe the assessment, control and management of the
quality function in an industrial organisation. We will develop a simple
working definition of quality and then outline the assurance aspects of quality
management.
While this unit will outline methods and techniques which are useful in
quality control and quality management, a successful quality improvement
will depend on the skill and efficiency of the manager in using these
techniques.
One of the accepted definitions of quality is fitness for use. An equally good
definition is conformance to requirements. Note that in both the definitions
quality is defined relative to use, rather than as a general characteristic that
may be intangible. By this simple, yet practical definition, if a product or
service lives up to expectations, it is of high quality. On the other hand, extra
fine finish or using materials that are far stronger than required does NOT
325
Capacity Planning, add quality to an item unless it somehow causes the item to conform to its
Work and Job
Design & Value requirements better.
Engineering
"Quality is free, but it is not a gift". This statement sums up the opinion that
effective, permanent quality improvement is difficult to achieve, but more
than pays for itself in increased productivity.
Quality control on the other hand, begins with assessment, and includes
action taken to eliminate unacceptable quality. The typical quality control
programme is based on periodic inspection, followed by feedback of the
results and changes or adjustments whenever necessary. Quality assurance
includes quality control, but it also refers to emphasis on quality in the design
of products, processes and jobs and in personnel selection and training. Total
quality control refers to the managerial commitment to quality so as to
include the quality aspect in every functional area of work, production,
marketing, finance and personnel. It also includes behavioural science based
techniques like Quality Circles and Zero Defect Programmes. Naturally, the
management of quality is an extensive area of study.
Also, quality begins at the product concept stage and extends throughout the
development, production, delivery and use of an item. Causes of poor quality
can occur anywhere in the organisation, from top management to the shop
floor worker, in accounting, production, sales, service or any other functional
area of management (including the quality control function itself!). Some
quality problems have roots outside the organisation, such as defective
supplies from a vendor or incorrect specifications from a customer.
The idea of sampling inspection is to inspect only a small portion of the lot
and infer the quality of the lot, based on the quality of the sample.
Acceptance is based on the inference made from the sample and hence the 327
Capacity Planning, technique is known as Acceptance Sampling. Typically a lot is specified by
Work and Job
Design & Value its size (N) and the fraction (f) of defectives that are expected to be present
Engineering (at the most) in the lot. The principles of statistics are used in the inference
process.
Two things must be kept in mind. In order that sampling inspection might
work, the sample must be representative of the lot. Typically this is ensured
by choosing the sample at random so that every portion of the lot has equal
representation in the sample. Such a sampling is known as Random
Sampling. Second, a sample is only representative and not identical (in
characteristic) with the lot. In the inference process, therefore, a few good
lots may be rejected and a few bad lots may be accepted. We can control such
sampling errors, but they cannot be eliminated. In fact in the design of
sampling plans we will ensure that the errors are kept below certain
acceptable levels.
Sampling Plans
The sampling plan is supposed to separate good lots from bad ones. As
mentioned earlier there are bound to be sampling errors. We will now study
the probabilities of such error graphically, using an Operating
Characteristic Curve.
328
Value
Engineering
and Quality
Assurance
Figure V shows OCC for two single sampling plans A and B with n = 35,
c = 1 and n = 150, c = 6, respectively. For example, suppose that a lot with
f = 10 per cent defectives is considered to be a bad lot and a lot with f = 2 per
cent defectives is considered to be a good lot. From Figure V, it is clear that
sampling plan A would stand a 14 per cent chance of accepting a bad lot. The
same unfortunate error can occur with the sampling plan B, with larger
sample size also, but the probability of error is much smaller. In fact it is only
1 per cent. The sampling plan B is also better at not rejecting good lots (f = 2
per cent). Sampling plan A has 16 per cent chance of rejecting a good lot
whereas sampling plan B has only 3 per cent chance of rejecting a good lot.
You have to design a sampling plan (n, c) that has an OCC that meets certain
pre- specified requirements. Generally the design is based on the following
criteria that are related to the probability of making either of the following
errors: accepting a bad lot and rejecting a good lot . The criteria are
established subjectively and ultimately should reflect the cost of accepting a
bad lot or rejecting a good lot.
329
Capacity Planning,
Work and Job Needless to say before and values can be specified, one has to decide
Design & Value
Engineering what is a good lot and what is a bad lot. Invariably this is done by specifying
the lower/upper limits of fraction defective (f), as illustrated below:
AQL (Acceptable Quality Level) the fraction defective (f) that the user
considers acceptable. Thus if a batch were known to have a fraction defective
equal to AQL, it should not be rejected.
LTPD (Lot Tolerance Per cent Defective) the fraction defective that defines a
bad lot or one that should be rejected. Of course AQL must be less than
LTPD.
Example 11.7
Solution. To design the sampling plan, follow the instruction at the bottom of
the chart Table 6 (Here the notation µ is the same as our notation m = mean
value). Note that we have to read off = 0.01 and (1–) = 0.095 rows only.
First find a c value for which µβ/µα< 0.10/0.02 = 5 (= LTPD/AQL) Starting
With c = 0 we read off µβ = 4.6052 and µα = 0.0513
(satisfied).
330
Hence sampling plans with size in the range of 146 to 165 will satisfy the Value
Engineering
and Quality
requirement. The exact value of and for any sampling plan can be Assurance
determined using Thorndike chart again.
1) To plot an OC curve for a given sample plan (n, c): (a) Find the column
for your c value. (b) Divide each number in that column by n. The
results are the f values for the horizontal axis. (c) The Pa values for the
vertical axis, are in the far left column.
2) To – find – a – single – sampling – plan :
(a) Find – c – for – which – µβ / µα < LTPD/AQL.
(b) Then choose any n between µβ = µβ / LTPD and µα / µα /AQL
3) To find the acceptance probability for a given n, c and f = (i) Multiply
(n) (f). (ii) In the appropriate c column, find values above and below nf.
(iii) In the Pa column read upper and lower limits for Pa in two rows
from step (ii) (interpolate, if required).
The inspection process rejects lots with high fraction defectives. After
rejection either you may stop, or you may continue the inspection of all the
items in the rejected lot and all defective items are replaced with good items.
Such a policy is known as Rectifying Inspection.
The most critical incoming fraction defective f gives the worst outgoing
quality. On the average, the value of that critical f is not important but the
corresponding outgoing fraction defective generally known as average
outgoing quality limit (AOQL) is extremely useful. No matter what the
incoming fraction defective is, the long-run average outgoing fraction
defective will not be worse than AOQL.
sampling plan rather than trying to decide on values of AQL, LTPD, and
. Dodge and Romig (1959) present tables that are designed for this purpose.
In fact these tables meet the requirement of a specified AOQL and minimise
the expected number of items inspected per lot.
The OCC approach and AOQL based approach are but two of the many other
approaches that can be used to design a sampling plan. Choice among them is
a match of personal experience, the exact situation and the objectives of the
organisation. Regardless of the approach, all sampling plans have both an OC
curve and an AOQ curve, so the principles discussed in this unit can be used
to evaluate any sampling plan.
All products and services have a certain amount of natural variability because
of variations in the input as well as imperfections in the process. For
example, different quality of raw materials could have been used and
different quantities of chemicals could have been used in the process. This
It can be shown that variations of more than 3 from the process average are
very unlikely. In fact it is about 0.25 per cent if the process follows the
normal distribution and definitely less than 5% for most processes. The solid
lines represent the tolerances specified by the intended use of the product.
Control Chart
The most common device used for this purpose is Shewart Control Chart
introduced in 1931. The control chart is a visual display of the result of an
inspection process incorporating carefully derived limits to indicate
unusual behaviour. A control chart can be based on categorical information
334 or actual measurement. Accordingly, they are called control chart for
variables (controlling quality through measurement) and control chart Value
Engineering
for attributes (controlling quality through counting). Since control chart and Quality
for variables are more commonly used and more powerful, we will describe Assurance
them first.
The control chart is based on the idea that the average of a sample of several
items will tend to cancel out the normal process variability, so that
undesirable changes in the process will be more visible. We will illustrate the
idea through an example.
This chart is used for quality characteristics which are specified as variable,
i.e., on the basis of actual measurement readings taken. The purpose or
objectives of this chart are:
(a) To establish whether the process is in statistical control or not.
Here, the factors and known as the statistical factors depend on the
number of units per sample. Larger the number, the closer the limits. The
value of the factors and can be obtained from Statistical Quality
Control tables. However, for ready reference these are given below in tabular
form in Table 8. As long as and limits values for each sample are within
the control limits the process is said to be in statistical control.
335
Capacity Planning, Table 8: Statistical factors for computing control lines and control limits
Work and Job
Design & Value for , R and s charts
Engineering
No. of A2 D1 D2 D3 D4 d2*
Units in
a sample
2 1.88 0 3.687 0 3.27 1.13
3 1.02 0 4.358 0 2.57 1.69
4 0.73 0 4.698 0 2.28 2.06
5 0.58 0 4.918 0 2.11 2.33
6 0.48 0 5.078 0 2.00 2.53
7 0.42 0.205 5.203 0.08 1.92 2.70
8 0.37 0.387 5.307 0.14 1.86 2.85
9 0.33 0.546 5.394 0.18 1.82 2.97
10 0.31 0.687 5.469 0.22 1.78 3.08
11 0.29 0.812 5.534 0.26 1.74 3.17
12 0.27 0.924 5.592 0.28 1.72 3.26
13 0.25 1.026 5.846 0.31 1.69 3.34
14 0.24 1.121 5.693 0.33 1.67 3.41
15 0.22 1.207 5.737 0.35 1.65 3.47
6R
*Process Capability = 6
d2
The various reasons for the process being out of control may be:
(i) faulty tools (ii) sudden significant change in properties of new materials in
a new consignment (ii) breakdawn of lubrication system (iv) faults in timing
of speed, mechanism etc. Tracking of these causes is sametimes simple and
straight forward but when the process is subject to the combined effect of
many factors, then it may be a lengthy and complicated business.
Example 14. The following record taken for a sample of 5 pieces from a
process each hour for a period of 24 hour.
Figure. VIII
Now and charts are plotted on the graph as shown in Fig. VIII taking
abscissa as sample number and ordinates as and respectively.
Inference. Let us look at the Fig. VIII. In the chart, most of the time the
plotted points representing average are well within the control limits but in
Samples 10 and 17, the plotted points fall outside the control limits.
337
Capacity Planning, It means something has probably gone wrong here with the process and
Work and Job
Design & Value a check is needed to prevent the appearance of defective products ( rectifying
Engineering inspection).
If the causes have been eliminated, the sample nos. 10 and 17 will stay well
within the control limits, but if more points fall outside the control limits then
a thorough investigation should be made, even if it is necessary to shut down
production temporarily until every thing is adjusted again and no more points
fall outside.
Consider XYZ Company that uses an automatic machine to fill 1kg. boxes of
sugar. The tolerances are specified as 1.000 kg. on the lower side (legal
requirement) and 1.005 kg. on the high side (no point,wasting sugar). Since
the spread is only 0.005 they selected a machine that has a natural process
variability of = 0.0003. The three sigma limits of the machine therefore are
3(.0003) = .0009 kg. above and below the mean. The spread is .0018 which is
narrower than the specified tolerance of .005. They adjust the machine to fill
boxes with an average 1.0025 kg. half way between the tolerance limits.
An x̅ Chart (Average Control Chart) was set-up to detect when the machine
goes out of control. In order to reduce the natural process variability, samples
of n = 5 boxes were weighed, and the average weight per box, x̅, was
recorded for each sample.
Figure IX shows the control chart used for this machine and the four points
plotted on the chart represent the values from four samples (a total of twenty
1 kg. boxes). We shall examine the details of the chart. There is an apparent
trend in x̅. The sample seem to be getting progressively heavier. However,
despite the appearances, the trend in fig. IX, it may be due to random
fluctuations. It is for this reason that we must incorporate the concept of
statistical significance in our discussion. The standard deviation of the
sample average is expressed through the formula x
n
•
•
• •
The fourth sample falls is on the control limit and therefore there is a strong
statistical evidence that more sugar is put into the boxes than what was
intended and the machine needs adjustment. The R Chart (Range Control
Chart) is also used to control the processes. The range of a sample is the
'The control limits for R chart are determined differently. There is no need for
Sample size D3 D2
2 0 3.686
3 0 4.358
4 0 4.698
339
Capacity Planning, 5 0 4.918
Work and Job
Design & Value 6 0 5.078
Engineering 7 0.205 5.203
8 0.387 5.307
9 0.546 5.394
10 0.687 5.469
There are several other control charts, including the p-chart which is used to
control the process when the measurement is by attributes. In other words the
decision is only to decide whether or not the sample item is acceptable. No
measurement is taken. For example in using the GO/NO GO gauges one gets
only such a measurement.
This is based on the fact that the number of defectives has the binomial
probability. The control chart is used just like an x̅ chart, except that the
fraction defective p is calculated rather than X for each sample of n items and
a lower control limit is often omitted.
This is based on the fact that the number of defectives has the binomial
probability. The control chart is used just like an X chart, except that the
fraction defective p is calculated for each sample of n items and a lower
control limit is often omitted.
Sample sizes are typically larger for p-charts than for x̅ -charts. Since the
information content of a yes/no measurement is much smaller than the actual
variable measurement, the required sample size can be computed
approximately from the following formula.
For example, consider ABC Company that makes ready-made shirts. It has
been found that 4 per cent of the shirts are defective when the process is
under control. ABC Company wants to be able to detect a shirt to 12 per cent
defective on the basis of one sample of n items. Here p0=0.04,p1=0.12
340
therefore n=197 from the above formula. Hence the upper control limit is Value
Engineering
equal to and Quality
Assurance
i.e 8.19%
These packages are likely to take much of the chores associated with the
lengthy calculations and make the application of quality control techniques
far more easy and yet effective.
11.17 SUMMARY
Value Engineering/Value Analysis is a systematic and organised effort to
identify the functions of a product, system or procedure and to attain that
function with minimum cost without jeopardising quality, aesthetics and
appearance etc. The Systematic procedure is known as VE Job Plan. Its phases
include General Information, Function, Creation, Evaluation, lnvestigation
and Recommendation. Each phase has a set techniques associated with it.
FAST diagram is another powerful technique for VE. Other important
techniques are functional analysis, function-cost matrix, paired comparison and
decision matrix. Value Engineering requires a good team spirit and an effective
organisation. Benefits of VE in cost reduction and value improvement are
tremendous. 1t is equally applicable to hardware and software projects.
Quality is fitness for use. Using this definition leads to many opportunities to
improve both quality and productivity simultaneously. Many quality
problems have causes that cross departmental boundaries. So a good quality 341
Capacity Planning, management system must make the entire organisation responsible for
Work and Job
Design & Value quality. Statistical methods are important tools for quality control. They
Engineering separate random variations from real assignable causes of deviations from
normal. Acceptance sampling helps in deciding the quality of a large batch
(lot) from an inspection of small sample. The operating characteristic curve
(OCC) precisely gives the risks associated with any sampling plan. The
design of a sampling plan can be based on Operating Characteristic Curve as
well as Average Outgoing Quality. Control charts display the results of
inspecting a continuous process. This provides convenient and rapid feedback
suggesting when feedback, overhaul or adjustment, may be needed. The
design of control chart is based on sound statistical principle regarding the
behaviour of sample mean.
Function Cost Matrix: A tool for identifying poor value areas by showing
percentage importance of a function in a product and percentage cost spent in
accomplishing that function.
Mental Roadblocks: Conditions of mind due to beliefs, resistance and fear etc.
which retard creativity and idea generation.
Primary (Basic) Function: It is the basic or specific purpose for which the
component or assembly was designed.
342
Paired-Comparison: A technique of determining relative importance of Value
Engineering
functions in Value Engineering by comparing two functions at a time. and Quality
Assurance
Secondary Function: A function which does not directly contribute to the
basic function or is only needed to support the achievement of a primary
function playing enabling role.
Unnecessary cost: Also termed as hidden or invisible cost which does not
improve the quality, features required by customer or the product utility but only
increase the cost; for example, materials handling cost.
Use value: The properties which accomplish a use, work or service. The use
value is equal to the value of the functions performed.
Control Limits: Limits if exceeded imply that the process is out of control.
11.19 SELF-ASSESSMENT
QUESTIONS/EXERCISES
Value Engineering
1) Identify five products in your day-to-day life and determine reasons for
poor value in them. 343
Capacity Planning, 2) Applying the Function Analysis approach write down the basic functions
Work and Job
Design & Value of the following objects in two words:
Engineering
i) Umbrella
ii) Ash Tray
iii) Paper Weight
iv) Wrist Watch
v) House.
Thomas organised a display of all bought out parts and sub-assemblies and the
fancy Drill-A-Thon, made of castings, stampings and turnings to draw the most
attention. It had been designed and turned over to a supplier before
purchasing became a separate profit centre under the president. In response to
his queries to improve the assembly he got the following responses from three
visiting salesmen.
The first company said that they would really gain price advantage if plastic
instead of metal was accepted. The second company offered to make the product
with fewer parts while the third company suggested that the best way was to
assemble it within and they would supply parts at rock bottom prices.
Vice President of the Deen Dayal Industries Pvt. Ltd. who are the present
suppliers rang up to Thomas to express his concern in offering the products his
344
company had been supplying for long to others and wondered whether these Value
Engineering
newcomers could make a better offer. He expressed a desire to be given a and Quality
chance to reduce cost by trying value analysis. The chief design engineer also Assurance
ridiculed the idea of going for plastic in place of metals and saw in it a
conspiracy to cheapen their merchandise.
Thomas thus faces a conflict of view points. The president has given
an ultimatum to reduce cost by at least 5 per cent, and his company's
design experts are uneasy about outside interference. Would-be-
suppliers are anxious in re-designing Drill-A-Thon to promote their
own shops.
Now, answer the following queries:
i) How can Thomas start a sound value analysis programme?
ii) How should he handle the reactions of his present supplier?
iii) In what way can he use the offered help of the would-be-suppliers who
can be genuinely helpful?
Quality Assurance
10) Why are averages of samples used in control charts rather than
individual readings?
12) In the example in the text, the sampling plan A with n = 35 and c=1 has
α = 0.16 and β = 0.14, both too large to be acceptable.
(b) If the specification limits are 10.002 ± 0.004 cms, what percentage of
the product is defective, assuming that the process output deviations are
normally distributed?
Dodge, H.F. and H.G. Romig,. Sampling Inspection Tables: Single and
Double Sampling, John Wiley: 'London.
Feigenbaum, A.V.,. Total Quality Control,. McGraw Hill: Delhi. Ingle, S and
N. Ingle,. Quality Circles in Service Industries, Prentice Hall: Englewood-
Cliffs.
Juran, J'.M. and F.M. Gryna,. Quality Planning and Analysis, McGraw Hill
(Indian Reprint-TMH): Delhi,
346
Demarle, D.J. and L.M. Shillito, 1982. Value Engineering, Chapter 7-3 in G. Value
Engineering
Salvendy (ed)., Handbook of Industrial Engineering', John Wiley: New York. and Quality
Assurance
Dobler, D. W, Lee, Lamar Jr. and D.N. Burt, 1984. Purchasing and Materials
Management: Text and cases, McGraw-Hill Book Co.: New York.
347
Capacity Planning,
Work and Job
Design & Value
Engineering
348