Jennifer Crisp Thesis
Jennifer Crisp Thesis
Jennifer Crisp Thesis
Jennifer J Crisp
BE Hons (UQ) M Eng (QUT) MIEAust MIEEE
February 2004
Key Words
asset management, infrastructure management, electricity transmission
systems, network performance, financial performance, fuzzy logic, rule-based
expert system, system dynamics modelling
Abstract
This thesis draws on techniques from Management Science and Artificial
Intelligence to explore organisational aspects of asset management in
electricity transmission enterprises. In this research, factors that influence
policies and practices of asset management within electricity transmission
enterprises have been identified, in order to examine their interaction and
how they impact the policies, practices and performance of transmission
businesses. It has been found that, while there is extensive literature on the
economics of transmission regulation and pricing, there is little published
research linking the engineering and financial aspects of transmission asset
management at a management policy level. To remedy this situation, this
investigation has drawn on a wide range of literature, together with expert
interviews and personal knowledge of the electricity industry, to construct a
conceptual model of asset management with broad applicability across
transmission enterprises in different parts of the world. A concise
representation of the model has been formulated using a Causal Loop
Diagram (CLD).
2
The research demonstrates the key impact of routine maintenance
effectiveness on the condition and performance of transmission system
assets. However, performance of the transmission network, is not only
related to equipment performance, but is a function of system design and
operational aspects, such as loading and load factor. Type and
supportiveness of regulation, together with the objectives and corporate
culture of the transmission organisation also play roles in promoting various
strategies for asset management. The cumulative effect of all these drivers
is to produce differences in asset management policies and practices,
discernable between individual companies and at a regional level, where
similar conditions have applied historically and today.
3
Table of Contents
1 Introduction.................................................................................... 22
1.1 Questions prompting this research topic........................................ 22
1.2 Background to the research........................................................... 23
1.2.1 Transmission networks ................................................................23
1.2.2 Characteristics of transmission system plant ...............................24
1.2.3 Transmission enterprises .............................................................25
1.3 Defining asset management .......................................................... 25
1.4 Purpose of the research ................................................................ 28
1.5 Scope ............................................................................................ 28
1.6 Methodology .................................................................................. 28
1.7 Key Assumptions, Key sources .................................................... 30
1.8 Limitations ..................................................................................... 31
1.9 Structure of this thesis ................................................................... 31
2 Literature review ............................................................................ 34
2.1 The CIGRE Study .......................................................................... 35
2.1.1 Regional differences in maintenance practices............................36
2.1.2 Regional differences in maintenance spending............................38
2.1.3 Regional differences in replacement criteria ................................39
2.1.4 Regional differences in outage management...............................42
2.2 Strategic Level Asset Management ............................................... 43
2.2.1 Assessment of Regulatory impacts on transmission ....................44
2.2.1.1 Changes to structure of the electricity industry .......................... 44
2.2.1.2 Regulation within transmission................................................... 45
2.2.1.3 Research on regulation, structural reforms and governance...... 49
2.2.2 Assessment and management of market impacts .......................55
2.2.3 Interconnection of networks .........................................................57
2.2.4 Embedded generation..................................................................57
2.2.5 Risk management in transmission organisations .........................58
2.2.6 Level of performance ...................................................................61
2.2.7 Performance measurement..........................................................62
2.3 Process Level Asset Management ................................................ 62
4
2.3.1 RCM and its influence on asset management in transmission.....63
2.3.2 Condition based maintenance (CBM) ..........................................65
2.3.3 Justification and selection of condition monitoring .......................65
2.3.4 Maintenance period optimisation .................................................66
2.3.5 Strategies to increase circuit availability.......................................68
2.3.6 Criticality in transmission asset management ..............................69
2.3.7 Reliability modelling .....................................................................70
2.3.8 Life cycle costing..........................................................................71
2.3.9 Criteria for replacement of equipment ..........................................72
2.4 Equipment Level Asset Management ............................................ 74
2.5 Identifying the need for research ................................................... 74
3 Asset Management Relationships ................................................. 77
3.1 Factors of influence for asset management in transmission .......... 77
3.1.1 External / Business-related factors ..............................................77
3.1.2 Internal factors .............................................................................78
3.1.3 System-related factors .................................................................81
3.1.4 Environment-related factors .........................................................87
3.2 Important asset management relationships for transmission
enterprises ................................................................................................... 87
3.2.1 Factors affecting failure rate.........................................................88
3.2.1.1 The impact of climate and loading on failure rate....................... 88
3.2.1.2 The impact of equipment ageing on failure rate ......................... 92
3.2.1.3 The link between maintenance history and failure rates ............ 94
3.2.1.4 The effect of predictive maintenance on failure rates................. 95
3.2.1.5 Geographical factors affecting failure rate.................................. 95
3.2.1.6 The effect of voltage on failure rate............................................ 95
3.2.1.7 Other factors affecting failure rate .............................................. 96
3.2.1.8 Summary of factors affecting failure rate.................................... 97
3.2.2 Failure rate and corrective maintenance ......................................98
3.2.3 Use of time-base maintenance ....................................................98
3.2.4 Use of predictive maintenance.....................................................99
3.2.5 Use of online condition-based maintenance ................................99
3.2.6 Use of offline condition-based maintenance ..............................100
3.2.7 Factors affecting maintenance spending....................................100
5
3.2.8 Investment in new equipment ....................................................102
3.2.9 Drivers for equipment replacement ............................................102
3.2.10 Refurbishment of equipment ......................................................103
3.2.11 Drivers for system augmentation ...............................................104
3.2.12 Investment spending ..................................................................105
3.2.13 Ease of raising capital ................................................................107
3.2.14 Reliability of supply ....................................................................107
3.2.15 Availability ..................................................................................109
3.3 Summary of AM relationships...................................................... 111
3.3.1 Key elements in the model.........................................................111
3.3.2 Feedback loops in the model .....................................................112
3.3.3 Discussion on Chapter 3 and the CLD model ............................115
4 Modelling ..................................................................................... 117
4.1 Methodology ................................................................................ 117
4.2 Characteristics of the model ........................................................ 118
4.3 Desired outputs ........................................................................... 119
4.4 Potential modelling methods........................................................ 120
4.4.1 Fuzzy modelling .........................................................................120
4.4.2 System dynamics modelling.......................................................121
4.4.3 Markov analysis .........................................................................123
4.4.4 Time-based modelling of the decision-making process..............124
4.5 Selection of model methodology.................................................. 124
5 The multi-level fuzzy model ......................................................... 126
5.1 Development of the multi-level fuzzy model ................................ 126
5.1.1 Implementation of fuzzy modelling .............................................126
5.1.2 Model structure ..........................................................................130
5.1.3 Verification of the fuzzy model ...................................................134
5.1.4 Validation of the fuzzy model .....................................................136
5.1.5 Summary of data used in regional studies for the fuzzy model ..137
5.1.6 Refinement of the fuzzy model...................................................140
5.1.7 Summary of modelling methodology and implementation of the
fuzzy model..................................................................................................141
5.2 Results – Regional Comparisons using Fuzzy Modelling ............ 141
5.2.1 Failure rate.................................................................................142
6
5.2.2 Reliability of supply ....................................................................143
5.2.3 Availability of circuits ..................................................................147
5.2.4 Use of predictive maintenance...................................................148
5.2.5 Maintenance spending ...............................................................152
5.2.6 Refurbishment of equipment ......................................................154
5.2.7 Replacement of equipment ........................................................155
5.2.8 Discussion of results ..................................................................158
5.2.8.1 Efficacy of the methodology ..................................................... 158
5.2.8.2 Insights to be gained from these studies.................................. 160
5.2.8.3 Discussion of results of fuzzy modelling – regional cases........ 171
5.3 Case Studies for individual companies/countries ........................ 173
5.3.1 Australian case study – Powerlink Queensland .........................173
5.3.1.1 Description of the Powerlink Queensland case study .............. 173
5.3.1.2 Results of the Powerlink Queensland case study .................... 177
5.3.2 Malaysian case study.................................................................178
5.3.2.1 Description of the Tenaga Nasional Berhad case .................... 179
5.3.2.2 Results of the Tenaga Nasional Berhad Case Study ............... 185
5.3.3 Japanese case study .................................................................185
5.3.3.1 Description of the Japanese case study................................... 186
5.3.3.2 Results of the Japanese case study......................................... 189
5.3.4 US utility case study...................................................................191
5.3.4.1 Description of the Duke Energy case study ............................. 191
5.3.4.2 Results of the Duke Energy case study ................................... 194
5.3.5 UK utility case study..................................................................195
5.3.5.1 Description of the National Grid Company, UK case study ...... 195
5.3.5.2 Results from the NGC, UK case study ..................................... 200
5.4 Use of the model for strategic decision-making ........................... 201
5.5 Summary of results from fuzzy modelling .................................... 207
6 Investigations using system dynamics modelling ........................ 209
6.1 Simulation in system dynamics modelling ................................... 210
6.2 Model verification and validation in system dynamics modelling . 211
6.3 Repairable and non-repairable systems theory – application to this
model 216
6.4 Modelling population ageing and asset value .............................. 219
7
6.5 Condition deterioration, maintenance effectiveness and predictive
maintenance .............................................................................................. 221
6.6 Linking the age and condition models ......................................... 225
6.6.1 Impact of maintenance effectiveness on asset population and
value for a condition-based replacement/ refurbishment scenario ...............229
6.6.2 Impact of use of predictive maintenance on asset population and
value for a condition-based replacement/refurbishment scenario ................232
6.7 Age-based replacement and the impact on asset value and failure
rate 239
6.7.1 Impact of varying maintenance effectiveness fraction................240
6.7.2 Effect of (condition-based) refurbishment for age-based model242
6.7.3 Comparison of age-base and condition based replacement
models with refurbishment for different values of maintenance effectiveness244
6.8 Remedial maintenance of poor condition assets ......................... 246
6.9 Replacement on failure only ........................................................ 248
6.10 The impact of maintenance and replacement policy on debt and
profit 251
6.11 Comparison of profit outcomes for various replacement policies. 258
6.12 Sensitivity of profit to failure rate assumptions............................. 259
6.13 Comments on Maintenance efficiency and the impact of
replacement and maintenance strategies on maintenance spending ........ 261
6.14 Impact of failure rate on system performance.............................. 262
6.14.1 Effective redundancy..................................................................262
6.15 Impact of system augmentation rate on network composition and
performance............................................................................................... 265
6.16 Summary of findings from system dynamics modelling ............... 271
7 Discussion of regulation of transmission utilities supported by
modelling results ........................................................................................ 274
7.1 Desirable traits in electricity transmission enterprises ................. 274
7.2 Implications for regulation of transmission utilities ....................... 276
7.2.1 Overall revenue..........................................................................276
7.2.2 Revenue based on return on investment ...................................278
7.2.3 Drivers of Operations and Maintenance.....................................280
8
7.2.4 Performance-based incentives in regulation of transmission
enterprises 281
7.3 The effect of changing regulation ................................................ 282
8 Conclusions ................................................................................. 284
Appendix A Sources of Data.................................................................... 291
A.1 General Data Sources and treatment of data ...................................... 291
A.1 Development of Regional Case Data Sets .......................................... 294
Bibliography ............................................................................................... 313
9
List of Figures
Figure 1 Maintenance strategies employed by region.................................. 38
Figure 2 Comparison of direct maintenance spending by region. ................ 39
Figure 3 Estimation of operational life for replacement purposes ................ 40
Figure 4 Estimated rate of replacement of assets - compared by region ..... 41
Figure 5 Replacement of assets by category and region ............................. 42
Figure 6 Comparison of planned outages per circuit per annum ................. 42
Figure 7 Unplanned outages per circuit and per 100 km of circuit by region 43
Figure 8 Profit as intention compared by region. Data are from (CIGRE SC
23 and 39, 2000).................................................................................... 79
Figure 9 Maintenance relative to manufacturers' recommended levels
compared by region (CIGRE SC 23 and 39, 2000). Series from left to
right are: a) more than recommended; b) less than recommended; c)
neither specified. This information is relevant mainly for substation
equipment such as transformers, circuit breakers and protection
equipment. ............................................................................................. 81
Figure 10 Bus configuration schemes in use in various parts of the world... 83
Figure 11 Flexibility compared by region, calculated from data in (CIGRE SC
23 and 39, 2000). Results show significant variability in substation
design practices across regions............................................................. 84
Figure 12 Connectivity compared by region, calculated using data from the
CIGRE study .......................................................................................... 85
Figure 13 Geographic factor is compared by region. Values are calculated
from data in the CIGRE study. ............................................................... 86
Figure 14 Circuit breaker failure rates as a function of age.......................... 93
Figure 15 Influence diagram of transmission asset management relationships
............................................................................................................. 112
Figure 16 Membership functions for climatic factor.................................... 126
Figure 17 The membership functions for parameter load growth– an example
of membership functions estimated from real numeric data, in this case
percentage recent load growth............................................................. 127
Figure 18 The decision tree for the task Investment in new equipment ..... 128
Figure 19 Effect of translating model as a snapshot .................................. 132
10
Figure 20 Actual structure of maintenance spending, from fuzzy model.
(Note equipment replacement and loading subtasks have not been
elaborated, for reasons of diagram clarity)........................................... 133
Figure 21 Comparison of unplanned outages per 100km of circuit and
unplanned outages per circuit from CIGRE study with failure rate from
model. .................................................................................................. 142
Figure 22 Supply point reliability predicted by the model. The arrows indicate
the range of observed values from Table 15........................................ 147
Figure 23 Sensitivity diagram of offline CBM with attitude to new technology
and labour skill for the North American region. X marks the coordinates
used for the North American base case. .............................................. 151
Figure 24 Maintenance spending predicted by model output compared with
CIGRE study data ................................................................................ 152
Figure 25 Comparison of refurbishment as a percentage of direct
maintenance costs (from CIGRE study) with model predictions for
refurbishment levels............................................................................. 154
Figure 26 Replacement of equipment - predicted rate from model compared
with CIGRE Study data ........................................................................ 155
Figure 27 Availability as a function of flexibility for three cases from fuzzy
model ................................................................................................... 161
Figure 28 Availability as a function of maintenance actions increasing
availability for three regions. Availability for WE is sensitive to this
parameter about the current operating point (28)................................. 165
Figure 29 Sensitivity of reliability to connectivity for three regions ............. 166
Figure 30 Combined effect of connectivity and flexibility on reliability for WE
case. X denotes the existing situation................................................. 167
Figure 31 Failure rate as a function of maintenance history and proportion
aged equipment for South America. X marks the estimated levels of
maintenance history and proportion of aged equipment. ..................... 168
Figure 32 Sensitivity of routine maintenance and total maintenance spending
to maintenance relative to manufacturers' recommended levels ......... 201
Figure 33 Impact of use of predictive maintenance on reliability for TNB case
............................................................................................................. 202
11
Figure 34 Sensitivity of reliability to failure rate contribution of load and
climate for TNB case............................................................................ 203
Figure 35 Sensitivity of reliability to flexibility and connectivity for TNB case
............................................................................................................. 204
Figure 36 Availability as a function of live working and combining
maintenance activity by circuit. Current operating point is shown as X.
............................................................................................................. 205
Figure 37 Sensitivity of availability to use of online CBM for Powerlink
Queensland case study. The calculated value of use of online CBM for
current parameters is moderate (43).................................................... 206
Figure 38 Availability as a function of flexibility for the Powerlink case ...... 207
Figure 39 Simple main chain showing ageing process .............................. 220
Figure 40 Simple model of deteriorating condition, failure, refurbishment and
replacement ......................................................................................... 222
Figure 41 Condition deterioration model with deterioration rate a function of
maintenance effectiveness, and refurbishment and replacement of poor
condition equipment a function of predictive maintenance................... 223
Figure 42 Graphical representation of relationship between PCA detected
and use of predictive maintenance ...................................................... 224
Figure 43 Graphical representation of the relationship between maintenance
effectiveness and fraction deteriorating ............................................... 225
Figure 44 This diagram shows the links between failure of poor condition
assets and age-related failures. ........................................................... 226
Figure 45 This simplified diagram illustrates the links between replacement of
poor condition assets and the replacement of assets from different age
groups, for condition-based replacement. ............................................ 228
Figure 46 Variation in condition of assets with (preventive) maintenance
effectiveness fraction, and PCA failing fraction. ................................... 229
Figure 47 Impact of maintenance effectiveness on failure rate.................. 230
Figure 48 Number of assets in different age groupings as a function of
maintenance effectiveness fraction, for MTBF PCA of 2 years. ........... 231
Figure 49 Total depreciated asset value as a function of maintenance
effectiveness ........................................................................................ 231
12
Figure 50 Variation of the condition of equipment within the asset population
with use of predictive maintenance ...................................................... 233
Figure 51 Impact of predictive maintenance on failure rate, if condition-based
replacement/refurbishment criteria are used; MTBF PCA 2 years. ...... 234
Figure 52 Impact of varying use of predictive maintenance on asset age
distribution............................................................................................ 234
Figure 53 Depreciated value of assets decreases as use of predictive
maintenance increases ........................................................................ 235
Figure 54 Refurbishment increases with increasing use of predictive
maintenance ........................................................................................ 235
Figure 55 Depreciated asset value for the case of refurbishment of 50% of
detected PCA and no refurbishment of PCA. The replacement of
detected PCA is held constant at 50%................................................. 236
Figure 56 Comparison of failure rate for 50% replacement of detected PCA
and 100% replacement of detected PCA. Refurbishment of PCA is not
undertaken in either case. MTBF PCA is 2 years for both studies. ...... 238
Figure 57 Total depreciated value compared for cases with 50% and 100%
replacement of detected PCA. Refurbishment of PCA is not undertaken
in either case. MTBF PCA is 2 years for both cases........................... 238
Figure 58 Simplified age-based replacement model: fully depreciated assets
are replaced. Replaced items are assumed to come from PCA and any
remaining assets are replacements of GCA. Refurbishment of PCA is
allowed................................................................................................. 240
Figure 59 Failure rate as a function of maintenance effectiveness fraction for
an age-based replacement model........................................................ 241
Figure 60 Distribution of asset age as a function of maintenance
effectiveness fraction for an age-based replacement model (shown for
MTBF PCA of 2 years)......................................................................... 242
Figure 61 Total depreciated asset value as a function of maintenance
effectiveness for an age-based replacement scenario (illustrated for a
cased with MTBF PCA of 2 years). ...................................................... 242
Figure 62 Failure rate as a function of maintenance effectiveness for age-
based replacement case with no refurbishment and refurbishment at 20%
13
of detected PCA, with predictive maintenance level 50%. MTBF of PCA
is 2 years in both studies. .................................................................... 243
Figure 63 Total depreciated value as a function of maintenance effectiveness
for age-based replacement with no refurbishment and 20% of detected
PCA refurbished. MTBF of PCA is 2 years for both studies. ............... 243
Figure 64 Comparison of failure rate for condition-based replacement 50% of
detected PCA, and 50% predictive maintenance and age-based
replacement of assets (assets > 40 yrs). ............................................. 244
Figure 65 Comparison for total depreciated value of condition-based
replacement (20% of detected PCA, 50% predictive maintenance) and
age-based replacement (>40yrs) ......................................................... 245
Figure 66 Total depreciated asset value with increasing use of remedial
maintenance of PCA ............................................................................ 247
Figure 67 Failure rate as a function of fraction failed PCA repaired........... 247
Figure 68 Effect of replacement on failure only policy, without remedial
maintenance and with 50% of failed PCA repaired to condition before
failure (MTBF PCA 2 years). ................................................................ 250
Figure 69 Comparison of failure rate for three replacement strategies. Other
parameters: MTBF PCA 5 years, use of predictive maintenance 50%,
refurbishment of detected PCA 20%.................................................... 250
Figure 70 Total depreciated value as a function of maintenance effectiveness
for a replacement-on-failure-only strategy, without remedial maintenance.
............................................................................................................. 251
Figure 71 Illustration of model dependencies when retained revenue and
debt calculations are added to the model. ........................................... 254
Figure 72 Impact on profit, debt and depreciated value of variation of
maintenance effectiveness................................................................... 256
Figure 73 Comparison, for the condition-based replacement policy case, of
retained earnings with and without refurbishment of PCA ................... 257
Figure 74 Effect on retained earnings of optimising asset value compared
with the case with no optimisation........................................................ 258
Figure 75 Comparison of retained earnings for three different replacement
scenarios. An optimisation factor of 0.9 is used, and there is no
refurbishment in each case. ................................................................. 259
14
Figure 76 Retained earnings is presented as a function of maintenance
effectiveness for three replacement strategies and MTBF PCA of 5 years.
(Other parameters: use of predictive maintenance 50%, replacement of
detected PCA 50% in condition-based replacement case; refurbishment
of detected PCA 20% in all cases; optimisation factor 1.0).................. 260
Figure 77 Retained earnings as a function of maintenance effectiveness.
(Parameters: MBTF PCA of 10 years, all other parameters same as
previous case.)..................................................................................... 260
Figure 78 For the North American base case this graph shows how
increasing redundancy reduces the impact of aging equipment on the
reliability of supply................................................................................ 265
Figure 79 A 3% rate of augmentation of assets per annum – clearly
impractical............................................................................................ 266
Figure 80 Simplified model incorporating system augmentation ................ 267
Figure 81 Modelled relationship between load growth and network maturity
............................................................................................................. 269
Figure 82 Modelled relationship between network maturity and value per
asset .................................................................................................... 269
Figure 83 The asset growth rate and total replacement value of assets as a
function of time, and with increasing network maturity......................... 270
Figure 84 Network maturity and load growth as a function of time............. 270
Figure 85 Age distribution of assets as a function of time.......................... 271
15
List of Tables
Table 1 Breakdown of maintenance spending by region ............................. 37
Table 2 Major failure frequency for SF6 circuit breakers 63kV and above,
placed in service after Jan 1978 ............................................................ 96
Table 3 Major failure frequency for GIS in service ....................................... 96
Table 4 Rules generated for the task investment in new equipment.......... 128
Table 5 Summary of model tasks and their inputs ..................................... 134
Table 6 Input Parameters used in regional studies for fuzzy model........... 138
Table 7 Reliability measures from various parts of the world..................... 143
Table 8 Effect of network configuration on supply reliability....................... 146
Table 9 Circuit availability .......................................................................... 147
Table 10 Availability – Model predictions compared with actual data ........ 148
Table 11 Comparison of model predictions with reported maintenance
strategies ............................................................................................. 150
Table 12 Substation equipment 20 and more years of age........................ 157
Table 13 Parameters used to assess availability and their values for AU, NA
and WE cases...................................................................................... 160
Table 14 Outputs from Fuzzy Model – Regional Studies ........................... 162
Table 15 Components of the task maintenance activities increasing
availability for AU, NA and WE............................................................. 165
Table 16 Parameters used to determine reliability and their values for AU, NA
and WE ................................................................................................ 166
Table 17 Parameters used to determine failure rate and their values for the
Asian and South American cases ........................................................ 168
Table 18 Parameters contributing to the task proportion poor condition
equipment with values for Asia and South America ............................. 168
Table 19 Factors contributing to maintenance spending, with values shown
for AU, NA and WE .............................................................................. 169
Table 20 Factors contributing to routine maintenance costs (for AU, NA and
WE)...................................................................................................... 169
Table 21 Inputs to the task refurbishment for three regions....................... 171
Table 22 Input parameters for the Australian Case study .......................... 177
Table 23 Outputs for the Australian case study ......................................... 177
16
Table 24 Inputs to fuzzy model for Malaysian case study.......................... 184
Table 25 Outputs from fuzzy model for the TNB case Study ..................... 185
Table 26 Input data for the Japanese Case Study ..................................... 188
Table 27 Results for the Japanese Case Study ......................................... 189
Table 28 Input data for the US Utility Case Study...................................... 193
Table 29 Results from the US Utility Case Study....................................... 194
Table 30 Input parameters for the UK utility case study............................. 199
Table 31 Results of the UK utility case study ............................................. 200
Table 32 Factors contributing to availability and their values for the Powerlink
Case .................................................................................................... 205
Table 33 Maintenance activities increasing availability for the Powerlink Qld
Case .................................................................................................... 205
Table 34 Data used in fuzzy model and their sources ............................... 293
Table 35 Enterprises in Asia – Business parameters at 1998.................... 296
Table 36 Production of electricity in billion kWh from (World Bank, 2001b) 298
Table 37 Labour cost in $US (World Bank, 2000b).................................... 299
Table 38 Debt and interest coverage for government owned enterprises in
Australia 1997-1998 and 1998-99 (Productivity Commission, 2002) ... 301
Table 39 Credit ratings from some former Soviet Block companies........... 303
Table 40 Credit rating of South American electricity companies from
(Standard & Poor's, 1999).................................................................... 309
Table 41 Enterprises in Western Europe – Business parameters at 1998
(Standard & Poor's, 1999).................................................................... 311
Supplementary Material
Software models on compact disc
17
List of Abbreviations
ACCC Australian Competition and Consumer Commission
AM asset management
CBM condition-based maintenance
CLD causal loop diagram
CT current transformer
DEA data envelopment analysis
DORC depreciated optimised replacement cost
DSS decision support system
FACTS flexible AC transmission system
FERC Federal Energy Regulatory Commission (USA)
FMEA failure modes effects analysis
FMECA failure modes effects and criticality analysis
IPP independent power producers
LCC life cycle costs
MTBF mean time between failures
MV membership value (fuzzy sets)
NERC National Electricity Reliability Council (USA)
ODV optimised deprival value
O&M operations and maintenance
ROCOF rate of occurrence of failure (repairable systems)
RCM reliability-centred maintenance
RBSE rule-based schedule evaluation
SFD stock flow diagram (in system dynamics modelling)
SVC static VAR compensator
TFP total factor productivity
TNSP transmission network service provider
VIMS visual interactive modelling system
VT voltage transformer
WACC weighted average cost of capital
18
Abbreviations used in System Dynamics models
AA aged asset
GCA good condition asset
MLA mid life asset
PCA poor condition asset
YA young asset
VAA very aged asset
Region identifiers
A Asia
AU Australasia and South Africa
EE Eastern Europe (former Soviet Block countries)
NA North America
SA South America
WE Western Europe
19
Statement of Original Authorship
I declare that the work presented in this thesis is, to the best of my
knowledge and belief, original, except as acknowledged in the text, and that
the material therein has not been submitted, either in whole or in part, for a
degree at this or any other university.
20
Acknowledgements
I wish to acknowledge the members of CIGRE Joint Working Group 23/39
Reliability and Maintenance for their efforts in undertaking “An international
survey of maintenance policy and trends” and thank them for permission to
use the survey data in my research.
Thanks also to Powerlink and Ergon Energy for technical and financial
support of this project. The financial support from these two companies
contributed to the cost of travel, enabling me to undertake interviews with
representatives of transmission companies in Europe and the USA.
21
1 Introduction
This present research was prompted by the question: Why do the policies
and practices of transmission enterprises vary appreciably across different
regions of the world when all transmission networks serve essentially the
same purpose? A question that follows from this is: Do these variations
reflect differing circumstances or disparities in performance? It was
anticipated that exploration of these questions would reveal avenues for
improving the performance of transmission businesses and the networks they
manage.
22
1.2 Background to the research
1
including those connected through bulk supply points
23
1.2.2 Characteristics of transmission system plant
Transmission equipment can generally be described as capital intensive,
robust, long-lived and not easily relocatable. Equipment lives of forty and fifty
years are not uncommon, and some networks have operating equipment up
to eighty years old.
Overhead transmission lines are distributed assets, the main parts of which
are conductors, insulators and towers. Conductors may or may not include
earth wires, depending on the design policy of the network, and the lightning
incidence rate. A recent trend has been to use overhead earth wire with an
embedded optical fibre for wide band-width communications. Series reactive
devices may be used on transmission circuits for the purpose of enhancing
system stability.
24
Underground cables can be single or three-phase, and at transmission
voltage levels, are usually constructed with a protective metal sheath around
the cable. The main elements of cables are the conductors and associated
terminations.
25
them so as to effectively and efficiently meet the desired
objective.
26
• Managing asset’s financial base i.e. its valuation; regulatory pricing
reviews; and
• Managing the brand, for new “brownfields” and potential “greenfields”
business.
The purpose of asset management is to turn assets into a revenue stream.
27
asset management the emphasis is on developing policies and practices that
support the short and long-term goals of the organisation taking into account
a broad range of drivers.
1.5 Scope
It is at the strategic level of asset management that this thesis seeks to make
a contribution to knowledge. Therefore the analyses and models presented
take a broad, high-level view of the subject. Although the study focuses on
the management of physical assets of the organisation, some references are
made to financial management when this impacts on management of
physical assets.
1.6 Methodology
The research may be described broadly as a data acquisition phase and a
model implementation and exploration phase. Within the implementation
28
stage two methodologies are presented, which enable different facets of the
research topic to be explored.
The structure of the multi-level rule-based model is derived from the CLD,
and the rules are based on the relationships between factors of influence.
The model is validated against data sets representing composite regional
and individual utility cases. Reasons for variations between regional cases
and potential means of improving performance in individual cases are
explored.
29
The second implementation involves the use of system dynamics models to
explore core parts of the asset management model in more detail. The
models are implemented and tested incrementally. A model linking ageing
and condition degradation of assets is developed. From the age distribution
of the asset population, the value of the asset base and its impact on
revenue can be determined. From the condition distribution, the performance
of assets under various maintenance and replacement strategies can be
examined. By combining the age and condition models it is possible to
explore the effects of various combinations of strategies on the performance
of equipment and profitability of the company. The methodology employed
for this research offers significant potential for application to a range of asset
management problems.
30
• That conclusions can be drawn from system dynamics models using
assumed data, provided that the data are with reasonable ranges in
their context of use.
1.8 Limitations
Data limitations have been a major concern in this research:
• Regions tested have been limited to those represented in the CIGRE
study.
• Data quality and accessibility have been a major source of uncertainty.
Certain important parameters have had to be estimated. Other data
have been of questionable quality. Ambiguities also exist in the
CIGRE study data, and answers in many questions are incomplete.
• Mismatches arise between data from difference sources.
These limitations have led to the need to use methodologies that are robust
in the face of uncertainty and imprecision of data. A lack of data from certain
parts of the world has meant that the fuzzy model has not been tested for
some of the more extreme cases possible. Likewise, for the system
dynamics model, the investigation has been limited to well-documented
cases, for which sensible parameters can be obtained.
31
performance of transmission enterprises. A conceptual model in the form of
an influence diagram (or causal loop diagram) is developed. This model
forms the basis for implementations described in Chapters 5 and 6.
Chapter four examines the nature of the model presented in Chapter 3, and
investigates ways of implementing this model with a view to
• Verifying and validating the model, and
• Gaining insights into the research topic.
The process of identifying suitable methodologies is explained and two
approaches are selected. One is to interpret the causal loop diagram of
Chapter 3 to a more detailed stock-flow diagram form, and use a system
dynamics icon-based program to examine the dynamics of the model. The
other approach employs the fuzzy-logic capabilities of a rule-based expert
system shell to examine the relationships in the model, and compare
predicted results with published performance information.
32
Chapter 7 contains a discussion of regulation, in the light of findings from this
research. Finally, in Chapter 8 the main findings from the research are
summarised, and the significant contributions to knowledge highlighted.
33
2 Literature review
Historically the focus of asset management was on existing equipment,
particularly maintenance of that equipment. After World War II, as
manufacturing became more mechanised, there was an increase in interest
in processes, particularly in the areas of maintenance and replacement.
Successful processes such as Total Productive Maintenance (TPM)
(Nakajima, 1986) and Reliability Centred Maintenance (RCM) (Moubray,
1992) were developed. Maintenance planning and scheduling was examined
to improve the efficiency of maintenance work.
The period since the 1960s has spawned a large number of research papers
on maintenance optimisation and replacement strategies (see Section 2.3.4).
The penetration of this research into industry generally has been slow
(Dekker, 1996), and the electricity transmission sector has not been faster to
take up these methods. However, Decision Support Systems, based on
operations research methods are starting to become commercially available
(Dekker, 1996). Use of these systems is likely to become more widespread in
the next ten years.
Over the past twenty years the narrow focus of asset management has been
expanded to include the whole life-cycle of plant – planning, procurement,
commissioning, operations, maintenance, replacement and / or refurbishment
decommissioning and disposal. Life cycle costing (Standards Australia,
1999b) has become an established process for evaluating different
purchasing options, operational and maintenance strategies.
34
a broader range of considerations than those taken into account at the
process or equipment levels of asset management. These decisions rely
heavily on information generated at the lower levels of asset management.
Strategic level asset management can be seen as driving much of the
research at the process and equipment levels.
The remainder of this chapter is in two parts: the first part introduces an
international survey that supplied the impetus for this research and much of
the data used in preparation of case studies. In the second part of the
chapter, other literature pertaining to strategic asset management of
transmission enterprises will be reviewed; trends in process and equipment
level asset management will also be described, but in less detail.
35
Some attempt was made in the survey to obtain information on performance
outcomes (such as reliability and availability), but these results are very
incomplete. The survey also suffers from ambiguities in some questions
and/or responses which must be taken to account when comparing results.
Furthermore there is some information important to the present investigation
that is not recorded in the study. It is particularly sparse in the areas of
business/financial and environmental drivers. Nevertheless the CIGRE study
provides a window of insight into the drivers of asset management in different
utilities and regions that is not available from any other source.
The authors of the CIGRE study have kindly permitted use of the raw data in
this thesis. The company details have been stripped from this data for
reasons of confidentiality, but other details such as region and ownership-
type are available for comparison.
Despite the fact that transmission networks serve the same purpose world-
wide and all have similar types of equipment, the CIGRE study reveals
significant differences in the ways in which these networks are managed.
Some of these differences also manifest when comparison is made by
region, suggesting that common practices within a region may exist. In the
following sections some of the major differences highlighted by the survey
will be presented. Factors of influence identified from the survey will be
introduced in Chapter 3. Performance outcomes from the survey, in addition
to those mentioned here will be presented in Chapter 5, supplemented by
information from other sources.
36
Table 1 Breakdown of maintenance spending by region
Preventive Corrective Refurbish/Repair Other
A 54% 11% 29% 6%
AU 53% 19% 17% 11%
EE 46% 16% 30% 8%
NA 46% 35% 8% 12%
SA 57% 10% 30% 3%
WE 59% 15% 18% 8%
37
6.0
38
Normalised maintenance cost / 9
asset value component 8
7
6
5
4
3
2
1
0
A AU EE NA SA WE
Region
39
category responses were also given. The analysis in Figure 3 shows a wide
variation between regions. In North and South America the practice of
estimating plant life appears to be significantly less common.
6
assessment (max 7)
average equipment
categories for life
5
4
3
2
1
0
A AU EE NA SA WE
40
Median replacement - all categories or
9.0
The results show that Eastern Europe was undertaking a large amount of
replacement of equipment at the time of the survey. Inspection of individual
category data (Figure 5) suggests that this was mainly in protection
equipment category, but also included moderate levels of replacement of
switchgear and control equipment. The assessments in Figure 5 have been
prepared assuming that null values are equivalent to zeros if the respondent
has given numeric values in any other equipment category for this question.
The data shown in Figure 5 for South America represent only two responses.
41
Median replacement % (over 4 years)
16
14
SWGR
12
TRANSF
10 LINES
8 TOWER
6 CABLES
PROTN
4
CONTRL
2
0
A AU EE NA SA WE
5
4
3
2
1
0
A AU EE NA SA WE
average median
There are also variations in planned outages in different regions (Figure 6),
although the difference between average and median values suggests
variations within regions as well. Note that these data are rather sparse –
42
there are only two responses from South America and three from North
America.
5
4 Unplanned
outages
3 per100km
2
Unplanned
1 outages/cct
0
A AU EE NA SA WE
Regions
Figure 7 Unplanned outages per circuit and per 100 km of circuit by region
43
• Performance measurement, performance indicators and
benchmarking;
• The impact of interconnection of systems;
• The impact of embedded generation;
• The potential benefits and opportunities associated with new
technology; and
• Likely developments in environmental management and regulation.
These will be examined in the following sections.
Motivations for these reforms have varied and the forms of the resultant
electricity industry structures have also varied from one jurisdiction to
44
another. Historically the electricity industry was viewed as an asset of
strategic importance to the country, and best managed as a single entity
(Cope, 2000). In the early 1980s this view was challenged by new economic
theory insisting that free and competitive markets were better at delivering
basic services than government agencies (Cope, 2000). For the electricity
industry it was perceived that competition, particularly among generators and
retailers, would lead to an improvement in efficiency of the electricity industry,
with resultant lower prices to consumers. In some countries (eg Argentina
(Lalor and Garcia, 1996 ), Victoria Australia (Theunissen et al., 1998)),
electricity restructuring and privatisation was seen as a way of providing
additional capital and/or a mechanism for retiring public debt by selling
assets to private investors.
45
• Productive efficiency (achieved when individual firms produce goods
or services at least cost);
• Allocative efficiency (achieved when resources used to produce goods
or services are allocated according to their highest value uses); and
• Dynamic efficiency (achieved when firms make ongoing changes to
technology and products in response to changes in consumer tastes
and productive opportunities).
46
The types of regulation existing today for transmission businesses may be
classified into the following categories, (listed most favourable to least
favourable for credit quality by Standard & Poor’s assessment) (Greer, 2001):
• Rate based regulation (Cost-plus regulation);
• Self regulation (Light-handed regulation);
• Revenue cap regulation;
• Price cap regulation (Rate cap regulation);
• Non-transparent regulation;
Under self-regulation, utilities set their own price levels and pricing
mechanisms, generally with the requirement to justify these levels to
customers (eg Sweden (Greer, 2001), New Zealand (Read, 1997)).
For revenue cap regulation the total revenue which may be collected by the
transmission business is capped. Revenue is generally calculated based on
return of and on investment plus operations and maintenance costs. In CPI-
X schemes (such as used in Australia (ACCC, 1999a)) the operations and
maintenance component of revenue is adjusted for inflation and by a factor
47
“X“ to encourage efficiency improvements. Adjustments are made for over or
under-collection of revenue. Financial risk arises from a number of sources
including:
• The valuation of assets;
• The calculation of rate of return on assets; and
• Determination of the value of the “X” factor.
48
2.2.1.3 Research on regulation, structural reforms and governance
Research has been undertaken largely from a public policy/economics
perspective. Topics have included the structure, ownership and method of
regulation of the electricity industry, and whether reforms have achieved the
desired results, transmission pricing mechanisms, regulatory governance and
regulatory risk and the associated topics of congestion management and
stimulating investment.
There has been little research relating the extensive changes in regulation to
the asset management within utilities, even though there have been
significant changes to external drivers for asset management. However an
examination of the literature suggests several ways in which regulation
impacts or should impact on transmission asset management.
49
constraints that impact on the market (ACCC, 2002b). It is not yet clear how
this will be implemented.
There is a school of thought that says that transmission prices should provide
a locational signal to customers (generators and consumers) to encourage
them to use the network in a way that is efficient in terms of system losses
and use of transmission assets (Hogan, 1998, Camfield and Schuster, 2000).
Efficient use of transmission could potentially defer the building of more
transmission infrastructure. Elements of locational pricing are incorporated
into Australia’s zonal pricing scheme and the Pennsylvania- New Jersey –
Maryland nodal pricing scheme (Sioshansi and Morgan, 1999). However,
because transmission constitutes only a small fraction of total electricity
pricing it is unlikely that these signals are strong enough to have much
impact on the siting of major generators or loads. Nevertheless transmission
pricing signals may illuminate the need for transmission enhancements
(Kirby, 1999).
50
Poor regulatory governance can expose transmission network owners to
considerable risk (Stern and Holder, 1998). In particular:
• Transmission businesses are highly capital intensive, and the assets once
installed are sunk assets. Hence investors are exposed to risk of adverse
policies set by governments eg by failing to allow maintenance of income,
or reneging on explicit or implicit contracts.
• Electricity services are vitally important to the welfare of all households,
and also to industrial output; this means that prices to customers are
highly political. Price changes (eg caused by abolition of cross-subsidies
or even recovery of full costs) can make a large impact on household and
industrial costs. Hence there is a temptation for governments to interfere
with the regulation of electric utilities.
Consideration of these factors can be avoided if the state owns the utility. In
such cases the functions of policy making, ownership and management and
regulation can become blurred, and end-user pricing tends to become highly
politicised. Under these circumstances there is often little incentive for
utilities to operate efficiently. Examples from Stern include Indian State
Electricity Boards, which are chronically loss-making, and Indonesian and
Malaysian energy companies, that are earn a low real rate of return on
assets and have pervasive cross-subsidies.
51
continue supplying electricity to strategically or politically important
customers. In 1996 the government also instructed the National Electricity
Regulatory Commission to leave retail prices unchanged until further notice.
Accordingly the regulatory commission instructed the National Dispatch
Centre to apply downward corrections to the daily average marginal price,
contrary to market rules. A proliferation of barter and other non-cash
payments further undermined the application of market rules, as the National
Dispatch Centre could only collect and allocate cash payments.
52
There is much less research published about the impact of regulation from
the perspective of the transmission company. Evidence of the impact of
deregulation and restructuring on AM issues can sometimes be found in
descriptions of strategies employed by different companies. Certain common
threads can be observed in these documents:
• In the past ten years there has been strong downward pressure on
operation and maintenance costs (Davies et al., 1998, Jefferies,
1997). This has occurred not only in enterprises that have been
subjected to extensive restructuring and re-regulation, but also where
the regulation and structure of the industry is largely the same as it
was in 1990 (See for example (Percebois and Wright, 2001),
discussing Electricité de France (EdF)). In the USA in the period 1990-
96 maintenance spending in transmission declined by 22% (Kirby,
1999), even though restructuring was only in its infancy in the US
during this period.
• For transmission entities, particularly those formerly part of vertically
integrated utilities, there has been an increase in uncertainty in
planning, and lead times for installation of new plant have been
reduced (Powerlink Queensland, 2000) (Urwin, 1999).
• The pressure to improve efficiency in operations and maintenance,
together with increased uncertainties in planning network
augmentation have focussed attention on risk management (Jay and
Williams, 2001, Australasian CIGRE Asset Management WG, 2001)
within transmission organisations to a greater extent than ever before.
Jones et al (Jones et al., 2000) suggest that for Australia and New Zealand
the regulatory drivers towards higher availability and reliability but lower
operations and maintenance cost, encourage network owners to consider
new technologies. It is also argued that the high capital component (80%) of
revenue could be considered to encourage a strategy of capital investment,
especially if this also reduces operations and maintenance costs. This
results (Jones et al., 2000) in inclusion of the following criteria for the
selection of new technologies:
• Minimal inherent safety risk;
53
• High self-monitoring and remote interrogation capability;
• Low maintenance requirements; and
• Integration with other substation systems.
Some useful research has come about as a result of these drivers, especially
from industry-based organisations. For example in (CIGRE WG B2.13,
2002) the authors draw on decision science methods to examine options to
replace or upgrade a transmission line, in the light of uncertain generation
developments. The paper advises the analysis of threats and opportunities
from external sources, in addition to assessment of the company’s own
strengths and weaknesses in order to assess different options. It is an
excellent example of the application of strategic thinking to asset
management.
54
• Parasitic – Activities that waste organisation resources (eg tower
painting).
Three overriding issues are identified for the analysis of outsourcing
opportunities: risk, cost and quality/effectiveness.
55
• Planning uncertainties: the lack of central planning of generation
development means that lead times for transmission planning are
reduced.
• Operation of the network in ways not intended by original designs:
Changing transfer patterns, for example, can cause large swings in
reactive support requirements and consequently higher numbers of
switching operations on reactive plant, with the result of greater wear
on circuit breakers.
• Increased opportunity for embedded generators: This could reduce
use of parts of the transmission network, increasing the potential for
stranded costs.
• Competition with other asset owners for development of contestable
assets could impact on profitability and
• Competition between regulated and unregulated asset developments
could change utilisation of plant. For example, in Australia
unregulated interconnectors may be built and can operate in direct
competition with regulated interconnectors owned by transmission
network service providers.
In the UK, changes to generation patterns, and short lead times for projects
have led to installation of significant reactive plant and the development of
relocatable static VAR compensators (Urwin, 1999). The use of relocatable
equipment reduces the risk that plant will become redundant in the future.
56
2.2.3 Interconnection of networks
Another major trend in electricity industries world-wide has been the
interconnection of electricity networks (Hammons et al., 1998, CIER et al.,
2001). There are significant benefits for interconnection of networks:
• Interconnection promotes more efficient use of generation capacity by
using structural differences in load profiles (for instance time of peak
load differences in different time zones).
• Reserve capacity required to cope with loss of generation (or
transmission outages) is shared between interconnected systems,
thus reducing the level of reserve required on individual systems.
• In an electricity market the interconnection of networks potentially
increases competition between generators, and can lead to reductions
in average price of electricity and price volatility.
For transmission network service providers interconnections pose a number
of challenges:
• The differences between actual and design network power flows can
be exacerbated when previously separate well-developed networks
are interconnected.
• When networks are interconnected operating and reliability standards
have to be harmonised (CIER et al., 2001). This may require
upgrading of equipment.
• Interconnection of networks can result in new stability limits (dynamic
or transient stability) which may impact on the operation of the
network, or may mean a requirement to install new control equipment
such as FACTS devices or Static VAR Compensators (SVCs).
• Despite potential benefits it may be difficult to build interconnections,
for reasons including the need to deal with multiple jurisdictions,
difficulty justifying the costs in terms of benefit (this has been the
Australian experience) and public opposition to the building of
transmission lines.
57
generation projects. This has arisen from acceptance of “Global Warming”
as a phenomenon of human origin, recognition of the need to reduce the
emission of “Greenhouse Gases”, and also an effort to decrease the use of
non-renewable resources for energy generation.
In other parts of the world there has been concern expressed that embedded
generation may reduce transmission system utilisation with possible
repercussions for revenue. In (CIGRE WG B2.13, 2002) the Working Group
identifies “spreading distributed generation” and “use of renewable energy
resources” as two of the threats/opportunities that need to be considered
when planning transmission augmentations.
58
adverse effects (Standards Australia, 1999a). Considerations of risk
management are pervasive in many of the Strategic Asset Management
topics discussed so far. Risk management entails analysing and controlling
risks to which an organisation is exposed. Within operations and
maintenance areas the focus on risk management has translated into
changes in maintenance strategies
• Greater use of Reliability-Centred Maintenance (RCM)(Sherard, 2001,
Basille et al., 1995, Balzer et al., 2000, Allison and Jay, 2001, Lee,
1997) (See also section 2.3.1);
• Importance (criticality) of equipment on the network being taken into
account for operations and maintenance strategies (Davies et al.,
1998, Stewart, 2001);
• A trend towards the use of predictive maintenance strategies, and
away from more expensive, but low risk, time-based replace-overhaul
strategies (Davies et al., 1998).
The efficiency and risk management focuses have been drivers for some
useful projects and developments including some drawing on operations
research techniques. Interesting developments in this area will be discussed
in more detail within the context of Process Level Asset Management
(Section 2.3).
59
rating determination (eg (Standard & Poor's, 1999)), which in turn
impacts on the cost of capital.
• System risk relates to actions taken within the power system that
increase the probability of not being able to fulfil a specific
transmission service (Damstra et al., 2000). This includes risks
associated with transmission constraints or outages.
The CIGRE Joint Working Group 23/39-07 (Damstra et al., 2000) categorises
system risk as three types:
• Type 1 System risk associated with outages for maintenance
activities;
• Type 2 System risk through delaying maintenance resulting in
unknown component deterioration; and
• Type 3 System risks arising from not taking an outage and operating
the system with known defective or depleted plant or equipment.
The paper suggests that Type 1 risks are influenced by system topology, age
and state of equipment, generation priorities, difficulties in short-term outage
planning, need to reduce outage times and use of weekend working.
Type 2 risks are influenced by the effect on equipment lifetime of use of
online condition monitoring and new technology to reduce equipment
maintenance and the number of opportunity outages (through plant failure).
The paper recommends the use of RCM techniques to identify and quantify
risk. The use of commercially-available Decision Support Tools for
maintenance optimisation is also suggested. Bundling maintenance (doing
as much maintenance as possible in the same circuit outage) is identified as
an option that reduces Type 1 risk without increasing Type 2 risk.
Type 3 risks and certain Type 1 risks (including risk of tripping circuits) are
typically managed by operational procedures.
60
2.2.6 Level of performance
Level of performance issues are starting to assume a high level of
importance to transmission businesses. There are a number of aspects to
this:
In general there is an impression among transmission companies of
increasing customer expectations for quality of supply. For de-integrated
entities formerly part of a vertically integrated industry structure, increased
expectations may be accompanied by a greater exposure to litigation for
supply loss than previously, especially from generators. For instance Jones
(Jones et al., 2000) says “the major impact on service levels has been the
increased expectations of some market participant and the increased liability
associated with operating in a market environment”.
There is a growing trend for regulators to set targets for reliability and quality
of supply levels, and for incentives/penalties to apply. It is therefore
necessary to balance potential incentives/penalties against the costs
associated with achieving the regulatory targets.
61
2.2.7 Performance measurement
Performance measurement is of great interest to regulators, particularly
comparison of performance between different utilities. A survey of
benchmarking techniques and studies was made by Jasamb and Pollit
(Jasamb and Pollitt, 2001). The authors report few benchmarking exercises
in transmission. Four countries report use of international benchmarking of
electricity transmission companies: Columbia uses Data Envelopment
Analysis (DEA) to compare construction costs; the Norwegian regulator
compares its regional transmission networks with those of Sweden using
DEA to set firm-specific efficiency requirements and revenue caps; the
Netherlands plans to use DEA for setting transmission tariffs using yardstick
regulation; for the National Grid Company comparison has reportedly been
made with 40 utilities using DEA and Total Factor Productivity (TFP).
62
• Maintenance cost drivers and risk management are fostering research
towards maintenance optimisation.
• Cost and reliability drivers are driving increased use of RCM and a
trend toward the use of condition-based maintenance.
• Risk management, risks associated with the regulatory system and
low return on capital are encouraging investigations into replacement
policies, and encourage strategies that take into account the criticality
and condition of equipment when considering maintenance or
replacement.
• Life cycle costing is being used to justify the expenditure of extra
capital in order to reduce operation and maintenance costs. The focus
on reducing maintenance is in line with regulatory drivers.
• Reliability drivers have fostered research into probabilistic reliability
modelling, and investigations into the effects of different configurations
of equipment on reliability.
• Market drivers and in some cases regulatory drivers, (through
performance standards for example) are placing pressure on utilities
to develop strategies to increase availability, leading to changes in
maintenance strategies.
63
• Identify appropriate actions to prevent each failure mode (Tasks must
be both technically feasible and worth doing – a function of
consequence and cost);
• Decide what to do if a preventive task cannot be found to address a
failure mode. (This may involve rebuilding or discarding the item
periodically, redesigning the item or doing nothing, depending on the
consequences of failure).
The first four steps are also known as Failure Modes Effects Analysis
(FMEA), and the first five steps, including consequence, are referred to as
FMECA.
The concepts involved in FMEA and RCM have become pervasive in asset
management, even though wide-scale adoption of the RCM method has not
occurred in distribution and transmission sectors of the electricity industry
(ECAR Electric Equipment Panel, 1999, Endrenyi et al., 2001). The main
reason for this appears to be the resources required (financial and personnel)
for full implementation of RCM. As a result there are now variants and
computer tools to streamline the RCM process available on the market.
One variant of RCM has recently been employed by the National Grid
Company of the UK. The strategy known as Rule Based Schedule
Evaluation (RBSE) (Allison and Jay, 2001) involves matching current
maintenance schedules with known failure models and deterioration rates in
order to eliminate unnecessary, ineffective or excessive maintenance. RBSE
can also flag maintenance work that can be undertaken without an outage. It
is expected that this process will reduce data collection and condition data
analysis, and the amount of work done during outages. It is also anticipated
to reduce protection system maintenance by up to 95%. A similar technique
was recently described in detail in (Anderson, 2002). These approaches are
likely to be effective only if current maintenance practices address all
important failure modes and if excess maintenance is being undertaken.
64
2.3.2 Condition based maintenance (CBM)
While time-based maintenance (or more precisely scheduled
repair/replace/overhaul task-based maintenance (Hastings, 2000)) remains
the most common form of maintenance process in the transmission sector
(CIGRE SC 23 and 39, 2000), condition based maintenance (CBM) or as
Moubray (Moubray, 1992) describes it, the “Scheduled On-condition Task” is
becoming increasingly important in the industry. Condition-based
maintenance comprises condition monitoring, assessment and maintenance
actions (including refurbishment and replacement), based on condition.
Condition assessment can potentially provide the following benefits (Urwin,
1999) when integrated in an overall asset management strategy:
• Improved risk management of assets;
• Improved management of environmental risks;
• Ratings and performance improvements leading to avoidance of
constraints (and associated costs); and
• Better targeting of assets for refurbishment and replacement.
65
sooner when CBM is applied to older equipment than when applied to new
equipment (CIGRE WG 13-09, 2000). In (IEEE, 2000, Bergman, 2001,
Bergman, 1999) Bergman and the IEEE Guide (IEEE, 2000) advocate use of
RCM to identify economic condition monitoring opportunities. Likewise, the
CIGRE guide (CIGRE WG 13-09, 2000) identifies failure modes, effects,
condition monitoring techniques to address these failure modes, and
suggests methods for assessing the potential benefits of CBM applied to
switchgear.
66
• In some cases the potential benefits do not justify the expense of
modelling.
67
Annually these simple results are analysed for each type of equipment, also
taking into account the manufacturer and age of the equipment. For
equipment that scored mainly ‘A’s the maintenance interval is increased. For
equipment that scored mainly ‘B’s no change is made. For each ‘C’ score an
immediate investigation is made to determine if other equipment of the same
type has the same problem. A decision is made on whether to decrease the
maintenance interval, avoid buying equipment of the same type or let the
manufacturer prove the problem will not recur.
68
maintenance is undertaken on another circuit supporting the same part of the
transmission network, or alternatively to reduce constraints on network
operation that occur during maintenance of circuits. In these cases
maintenance may be scheduled for periods of lower load, such as weekends
or over-night or during periods of milder weather (CIGRE SC 23 and 39,
2000).
At Scottish Power the concept of criticality has been applied to all aspects of
asset management (Stewart, 2001). In this strategy the commitment of
resources depends on the criticality rating assigned to the equipment. In the
area of inspection for example, equipment rated low criticality would receive
inspections to meet statutory requirements, equipment rated medium
criticality would have targeted information collected and only highly critical
equipment would be considered for on-line condition monitoring.
69
100 and a condition rating, also in the range 1 to 100, which may be
constructed from a number of different parameters. Importance and
condition pairs of coordinates are plotted on a graph. A high value of
importance means that the equipment has a major influence on the network.
When an axis 45 degrees to the importance and condition axes is drawn, the
priority for maintenance or replacement is determined from the distance of
the (Importance, Condition) coordinates to this new axis. The greater the
distance, the higher is the priority given to this equipment.
From this definition it can be seen that for transmission systems, the design
of the network plays a major role in providing for both security and adequacy.
In transmission systems reliability is built into the network by the use of
redundancy. Traditionally an N-1 planning criterion was used, and this is still
the most common method of ensuring reliability today (CIGRE SC 23 and 39,
2000). An N-1 criterion means that the system must be able to operate
without loss of supply when any single contingency occurs. Examples of
single contingencies can include a line fault or an abnormal weather
condition.
70
Alternatively it is possible to model the reliability of the network using
probabilistic methods. The main methodologies employed for the
assessment of network reliability are
• Monte Carlo simulations, and
• Markov models.
Modelling has been applied to serve a number of different purposes:
• A number of applications have been developed to examine network
planning options to improve reliability (Bak-Jensen, 1999, Dialynas et
al., 1996). EPRI has developed a Probabilistic Reliability/Risk
Assessment tool for transmission systems (Lee and Hoffman, 2001).
This tool calculates risk indices for overloading, under-voltage,
transient and dynamic stability conditions. It may have application for
planning or as a real-time tool for system operation security
assessment. Other applications have focussed on the distribution
system (Brown et al., 1996, Goel, 2000).
• Applications have been developed to explore reliability within various
subsystems of the transmission network, such as protection, and
substation configuration (Atanackovic et al., 1999, Karlsson et al.,
1997, Meeuwsen and Kling, 1997b, Meeuwsen and Kling, 1997a,
Vermeulen et al., 1998).
• Reliability assessment including condition deterioration in equipment
has been the subject of a number of research endeavours (Hoskins et
al., 1997, Hoskins et al., 1999, Endrenyi and Wellssow, 2001,
Endrenyi et al., 2001).
71
• Support management considerations affecting decisions during any
life-cycle phase.
• Identify attributes of the product which significantly influence the LCC
of the product so that they can be properly managed.
Considerations include the value of cost elements, timing of cash flows and
time value of money. The process should be an on-going one over the life of
the product – actual costs should be fed back into the evaluation process to
improve cost estimates and identify improvements.
72
have developed a long term plan for equipment replacement (for example,
some 92% of responses from the CIGRE study). This study identified that
the most important criteria influencing the system-wide replacement plans of
transmission businesses were:
• Deterioration of transmission system performance
• Load growth
• Availability of capital (particularly among respondents from North
America, Eastern Europe and Australasia).
Other criteria cited include changing transmission design criteria, changing
customer expectations and regulatory decisions. This list is curious in that
there is no mention of economic end of life, condition, criticality or age as
factors contributing to the transmission replacement plan. Deterioration of
system performance (as defined in this survey question) includes reliability,
power quality, safety and customer interruptions. These parameters are
lagging measures of risk, and it is strange that they would be used as criteria
influencing the long-term replacement plan. Perhaps the survey question
design is at fault for not offering other choices of criteria.
73
technical obsolescence is important, risk is the dominant reason for
replacement.
This explains why the myriad of capital replacement and economic life
models found in operational research have not been extensively adopted
by transmission enterprises.
A few applications including elements of risk and having an electricity
industry and focus have recently been published. In (Hastings et al., 1999)
risk cost is included in a techno-economic analysis, using equivalent annual
cost and repair limit theory.
74
differences in asset management practices world-wide. Perhaps this is a
function of the level to which different drivers operate on different
organisations. For example in a discussion paper (Australasian CIGRE
Asset Management WG, 2001) on asset management in Australia and New
Zealand the following statement:
Business processes established within each electricity utility
to deal with asset management are based on a number of
factors specific to that utility. These factors, and their impact,
vary from utility to utility and consequently result in diverse
approaches to asset refurbishment and replacement
decisions.
Since the transmission utilities, in Australia at least, are operating under the
same market and regulatory conditions, this statement could imply that other
drivers, such as internal, business-related or system related drivers may also
play a significant role in defining asset management policies. Furthermore it
is proposed here that the interaction of all drivers may impact on AM policies.
Its is also hypothesised that existing conditions (eg debt level, system
configuration, load growth to name a few) and the effect of interacting drivers
may define or limit the effectiveness of asset management policies for
particular utilities.
Little, if any, research has been done to explore asset management policies
in an holistic manner, even though the literature suggests that managers are
actively considering strategy level AM issues, taking into account a range of
factors. While external drivers such as regulation and market impacts have
been, to some extent, described in literature, internal drivers such as
corporate culture issues and historical practices, and the influence of system-
related and environmental factors have been largely ignored. Yet these
factors may not be insignificant: substation configuration for example can
have a significant influence on reliability and availability of circuits, all other
conditions being the same: transmission businesses with high levels of
flexibility built into substation configurations will find it easier to achieve high
circuit availability.
75
performance, including financial performance. Benchmarking studies may
reveal areas that could be improved, but not whether the strategies employed
by other utilities will be effective when applied under different conditions.
Since the capital value of transmission assets is high, and revenue is directly
related to asset management, decisions on asset management policy can
have a major impact on the financial well-being of transmission enterprises.
However there appear to be few tools available to assist the transmission
asset manager to make such assessments. The proposed research is aimed
at providing the necessary links between input factors, policies and practices
and performances needed to explore strategic level decisions. The
processes and models developed here should, therefore, potentially be
adaptable for individual companies for use in strategic decision support.
76
3 Asset Management Relationships
This chapter is structured in three parts. In the first part the factors impacting
on asset management will be examined; the second part explores the
relationships between these factors; and the third part draws together these
relationships to construct a model of transmission asset management in the
form of an influence diagram.
77
seen as affecting adequacy of maintenance, historical revenue sufficiency
will have affected historical maintenance effectiveness. Historical
maintenance effectiveness, in turn, is a factor contributing to current levels of
reliability.
Issues relating to the cost of capital can limit the level of system
augmentation and equipment replacement undertaken on the network. This
is discussed in greater detail in Section 3.2.8.
Labour costs can also play a part in asset management decisions. High
labour costs may make decisions to use online condition-based maintenance
more economically desirable. In areas with low labour costs enterprises may
undertake higher levels of labour-intensive maintenance activities.
There are also country specific external drivers. Regulations, for example,
may mandate replacement of assets at a certain age (for example in the
former USSR, standards mandated replacement of circuit breakers at 25
years of age (Batyayev et al., 1994)), or regulations may discourage
replacement. In the New Zealand regulatory framework, revenue is based on
the Optimized Replacement Value of assets (Energy Policy Group, 1995),
and there is less incentive to replace assets than under Australian
regulations where the Optimized Depreciated Replacement Value is used
(Crisp, 2001). Another example of external factors is the taxing of Sulphur
hexafluoride (SF6) or the proposed banning of (new) equipment using SF6
for insulation in some Western European countries, because of its
contribution to global warming as a “greenhouse gas” (Anonymous, 2002)
78
A major driver of asset management is the goal of the organisation – whether
this is profit or meeting of some other defined targets. There is a strong
regional variation in profit as intention (Figure 8), with North America the only
region with more than 50% of respondents to the CIGRE study claiming this
goal, and no positive responses to this question from Eastern European
survey participants. Management priorities can also be deduced from the
choice of performance indicators. For instance, having profit as a goal and
maintenance cost as a performance indicator suggests a downward pressure
on maintenance costs.
Enterprises with profit
60
50
motive (%)
40
30
20
10
0
A AU EE NA SA WE
Regions
Figure 8 Profit as intention compared by region. Data are from (CIGRE SC 23 and 39,
2000).
Practices related to the replacement of assets affect financial- and system
performance. For example, selection of age or frequency of failure as the
dominant criterion for replacement of assets could result in quite different
network age profiles over time, with implications for debt, depreciation and
possibly, revenue. (Chapter 6 contains a more detailed examination of these
relationships.) Furthermore, results from the CIGRE study show variation in
accounting practices for replacement of equipment: some transmission
entities treat replacement of equipment as an investment under some or all
conditions. This may affect revenue or depreciation, depending on
79
regulations pertaining to the organisation, and in turn may make transmission
entities more or less willing to replace equipment.
80
Percent of respondents
120
100
80
60
40
20
0
A AU EE NA SA WE
Regions
Load factor is the ratio of average electrical load on the transmission network
to peak load. If a network has a low load factor the equipment maximum
capacity will have to be high in order to meet maximum demand, but for
much of the time it will be loaded at much lower levels. This results in an
81
inefficient use of capacity, and a network with high replacement cost for its
energy throughput. A high load factor implies a more efficient use of
equipment, but if loading levels are also high it also makes taking equipment
out of service for maintenance more difficult to do without reducing system
security. On systems with high load factors, more maintenance might need
to be done at weekends or during the night when loading is lower.
Alternatively, use might be made of live working techniques and/or online
condition-based maintenance. The impact of load factor on maintenance is
also influenced by system configuration issues.
Two other system configuration issues that affect system performance are
the flexibility of the system and the connectivity of the system. Transmission
circuits are generally connected together in substations. Circuits are
connected to busses via circuit breakers. Different arrangements of busses
and circuit breakers are used, giving different levels of flexibility for the
reconfiguration of circuits (Giles, 1970). Some of the common arrangements
are double bus, the breaker-and-a-half scheme, single breaker and ring-bus
systems. These are illustrated in Figure 10. Some configurations (eg
breaker-and-a-half and double bus) provide the flexibility to maintain a circuit
82
breaker without disconnecting the associated circuit from the network. This
can reduce outage time and fault restoration time.
83
100
Percent flexibility
80
60
40
20
0
A AU EE. NA SA WE
Regions
84
total number of bays
connectivity factor =
demand in GW (1)
The regional distribution of connectivity factor is shown in Figure 12. Data
are from the CIGRE study.
Connectivity factor (GW )
-1
200
160
120
80
40
0
A AU EE NA SA WE
Regions
Figure 12 Connectivity compared by region, calculated using data from the CIGRE
study
2
Average circuit length might also be used, but these data were not available from the
CIGRE study
85
50
30
20
10
0
A AU EE NA SA WE
Regions
Figure 13 Geographic factor is compared by region. Values are calculated from data
in the CIGRE study.
Equipment age and technology can also impact on the cost of maintenance
and on system performance. Some transmission equipment, such as the
circuit breaker, has seen great technological change over time. This has
(generally) resulted in improved reliability and lower maintenance costs for
newer equipment compared with older equipment. One manufacturer, for
instance, claims an increase in mean time between major failures (MTBF) of
their high voltage circuit breakers from approximately 20 years in 1972, to
more than 700 years in 1996, owing to technology and design changes
(Knobloch et al., 2000). Even for equipment such as transformers, where
there has not been any major change in technology for several decades,
there can still be age-related reliability considerations. Such equipment can
exhibit age-related degradation, which will reduce its reliability gradually over
a period of time (Tanaka et al., 1993, Allan, 1991). Transmission systems
having high proportions of newer or older equipment therefore should exhibit
respectively higher or lower system reliability, all else being equal.
Alternatively, if preventive maintenance is undertaken and effective, they
might exhibit similar reliability but different levels of maintenance cost.
86
3.1.4 Environment-related factors
Environmental conditions to which transmission networks are subjected vary
significantly from one region to another and even within regions.
Environmental conditions can have a significant effect especially on failure
rates of equipment and the costs associated with maintaining the system.
They can also impact on the cost of infrastructure. Environmental factors
include the following:
• Climate type and severity can affect failure rates and associated costs.
(This will be discussed in more detail in Section 3.2.1.1.)
• The presence of corrosive atmospheres (salt and/or sulphur) affects
maintenance costs and can be a significant consideration in
replacement decisions (Jones et al., 2000);
• Unstable geologic conditions affect cost of new assets (IEA, 1999);
• Rugged terrain makes installation and maintenance more costly;
• In rocky terrain with high resistivity it is more costly and difficult to
protect overhead transmission against lightning damage;
• Highly urban conditions make building new assets more difficult and
expensive (discussed further in section 3.2.12). According to an IEA
study, one of the factors contributing to the high price of electricity in
Japan is the high cost of land (IEA, 1999);
• Large distances between load and generation make networks more
costly to build and maintain, and increases likelihood of system
security problems such as poor dynamic stability.
• Remoteness of transmission from population centres can impact on
the cost of maintenance and response time to equipment problems
(Jones et al., 2000)
87
3.2.1 Factors affecting failure rate
In the context of this study, failure rate means the level of unplanned
equipment outages occurring on the transmission system per unit time, rather
than a specific hazard rate for a particular type of equipment. In general
failure rates can be represented as three possible phases: a wear-in or infant
mortality phase, a random failure phase and a wear-out phase, in the well
known bath-tub curve (See Section 6.3 for more detail). In this section
attention is largely given to the wear-out phase and the impact of
environment and loading and maintenance management techniques on
overall failure rates.
88
increasing its effective age, and under high ambient temperatures the effects
will be more severe. For instance the IEEE guide for loading mineral-oil
immersed transformers recognises aging of conductor insulation and
cumulative permanent degradation of mechanical properties of structural
insulation materials as functions of the time-temperature history of the
equipment (IEEE Transformers Committee, 1991). As mechanical strength
of the insulation degrades it becomes more vulnerable to mechanical
stresses, and will finally reach the point where even a small mechanical force
will cause dielectric failure (CIGRE WG 12.09, 1993). If predictive
maintenance is used and takes account of these effects, overall failure rates
are not likely to be increased significantly. However, equipment may need to
be replaced at an earlier calendar age than if overloading had not occurred,
and this could lead to an increase in the rate of replacement of equipment.
89
Nevertheless, long-term ageing may make the transformer
more prone to failure through such events.
90
overhead earth wires also reduces the voltage stresses experienced by
substation equipment, which may reduce failure rates.
Apart from lightning, another possible source of fault is from trees falling
across lines. Vegetation is more likely to be a problem in places with high
rainfall, and forested landscape, and especially in warm to hot wet climates
where vegetation growth is rapid. This source of fault is not outside the
control of the transmission company, and need not result in higher failure
rates provided an effective vegetation management program is in place.
91
• A program of washing insulators may be set up – this increases
maintenance costs.
• In times of dry weather a monitoring program can be set up to
ascertain the risk of flashover, and initiate washing as required – a
(potentially smaller) increase in maintenance costs.
92
It is common practice, once a major failure is identified, to check other
devices of the same type and eliminate the possibility of failure by this
mechanism by either maintenance or design changes. A documented
example illustrating this practice is the NV Sep description in (Davies et al.,
1998). This results in a lower failure rate than otherwise would have been
recorded, a phenomenon known as data censoring.
50
(per 100 CB years)
40
Failure rate
Oil
30
20 SF6
10
0
1950s 1960s 1970s 1980s 1990s
Decade of installation
93
3.2.1.3 The link between maintenance history and failure rates
It is logical to assume that there is a link between maintenance and failures in
equipment, and thus reliability. Why else are predictive and routine
maintenance done, other than to decrease the potential for failures, and
improve or maintain reliability? The empirical link has rarely been shown.
One important reason for this is that it is often maintenance history, rather
than current maintenance or spending that determines failure rate.
94
3.2.1.4 The effect of predictive maintenance on failure rates
Predictive maintenance can reduce the number of failures by
1. Predicting that a failure will occur, based on condition assessment,
possibly coupled with history of equipment duty, and
2. Taking actions to restore the equipment to good condition (or
replacing the equipment) to avoid the predicted failure.
95
life of electrical insulation systems is directly influenced by the intensity of
stress or stresses -voltage, temperature, mechanical and environmental -
imposed on the insulation during the operation of the equipment. For
instance Aggarwal (Aggarwal et al., 2000) reports that the failure rate of
insulators on 400kV lines is far greater than that for 275kV lines. Most
defective units are at the high voltage end of the string, adding weight to the
argument that the failure rate is voltage-related.
Some dependence between voltage and failure rate has also been reported
for circuit breakers and transformers. Results from the Second International
Survey of Reliability for Circuit Breakers above 63kV (Janssen et al., 1995)
clearly illustrates a voltage dependency for failure rate, as shown in Table 2.
Results from the Second International Survey of GIS in Service (Chan et al.,
1998) (Table 3) are less clear.
Table 2 Major failure frequency for SF6 circuit breakers 63kV and above, placed in
service after Jan 1978
Failure rate (failures per 100
Voltage range (kV) Sample Size (CB years)
breaker yrs)
63-<100 0.275 24335
100-<200 0.680 23520
200-<300 0.814 10933
300-<500 1.210 9917
500+ 1.967 1983
96
Noor, 2002). This may be caused by design failures or quality control
problems during manufacturing. Purchasing of poor quality equipment can
result from failure to undertake life cycle cost analysis, or, particularly in
some developing nations, companies may be compelled (by governments) to
purchase from particular suppliers.
In some cases quality problems may arise from the failure of usually reliable
suppliers to master a new technology. For instance higher failure rates of
GIS in the USA compared with other countries has been attributed (among
other causes) to supply of prototype designs to customers, design and
production problems in early stages of manufacture and lack of appreciation
of the need for site assembly under clean conditions, especially at high
voltages (Eriksson et al., 1994).
Skill and purchasing issues are often difficult to detect without first-hand
knowledge of the transmission organisation concerned, because they are not
likely to be admitted in writing by the company. However they may be quite
significant in some cases.
97
Cumulative degradation effects can be thought of as contributing to the
proportion of poor condition equipment on the network.
Voltage as a factor contributing to failure rate has not been modelled in this
study, because most utilities have a range of transmission voltages, and EHV
equipment which has the highest failure rates is comparatively rare.
Therefore it is considered that overall transmission voltages will not play a
major role in system-wide failure rates.
98
bays from two to three years, and for some maintenance activities the
interval was increased from two to six years (Davies et al., 1998).
Companies which are willing to reduce maintenance below recommended
levels, and which operate their equipment under conditions that make this
possible without increasing failure rates, may be able to reduce maintenance
costs in this way.
99
Another, perhaps less significant, driver is geographic factor. A high
geographic factor, implying long distances between population centres, may
be an incentive to use more online CBM, especially when high travel times
combine with high labour costs (Jones et al., 2000).
100
In investor-owned utilities where maintenance is seen as a negative by
investors and investment as a positive, there is also an incentive to account
as much as possible to investment and as little as possible to operations and
maintenance. For example FERC (the US federal regulator) allows the
capitalisation of the use of a product called Cable Cure by Utlix, used to
restore the dielectric strength of underground cables (Teixiera, 2001). This
practice may contribute to the very low values of direct maintenance cost
reported for North America in the CIGRE study. A wide range of accounting
practices with regard to maintenance and capital has been observed in
Australian utilities (Beardow, 2003). Under the Australian regulatory
framework there may be an advantage in treating expenditure as
maintenance, up to the amount permitted in the regulatory determination.
The rationale for this is that expenses are recovered immediately, but
capitalised items run the risk of having their value reduced in subsequent
regulatory resets.
101
reduction in maintenance costs, because it is easier to undertake
maintenance during normal working hours. The effect of connectivity on
maintenance cost is tempered by the loading level (and load factor). At times
of very high loading, equipment may not be accessible for maintenance, even
on systems with high connectivity, because of the reduction in system
security that occurs when equipment is taken out of service. Hence high
connectivity will only reduce maintenance cost significantly on lightly to
moderately loaded systems.
102
The rate of replacement owing to failure is determined by the failure rate.
The conditions that cause equipment to be in such poor condition that it
needs to be replaced are the same as those that cause failure in the wear-
out phase. However, because of the use of predictive maintenance, failure is
averted and the equipment is replaced instead. Fitness for duty may be
related to load growth, but this could be considered as system augmentation,
rather than purely replacement. Equipment replacement for reasons of
obsolescence is probably a very small percentage of cases, and is unlikely to
impact much on overall replacement rate of equipment (except, perhaps for
secondary systems such as communications equipment and protection
relays). End of life considerations will be influenced by the criteria used for
replacement. If age is a replacement criterion, then the proportion of aged
equipment on the system will also influence the overall rate of equipment
replacement. Economic end of life could also be influenced by the treatment
of replacement as either investment or maintenance. In investor-owned
companies, investment is usually seen as positive by the share market,
whereas increased maintenance cost can be seen as negative (Sherard,
2001). If revenue is not adequate, the level of replacement for reasons other
than failure is likely to be very low.
Criteria for refurbishment may be condition, age or possibly failure rate. The
ability of a company to ascertain the need for refurbishment or replacement
of a piece of equipment, on the basis of condition, will depend on its level of
usage of condition-based maintenance. However, if preventive maintenance
is effective some detection of poor condition equipment will be possible even
if the use of predictive maintenance is not at a high level.
103
revised to reflect the expected remaining life of the refurbished asset. This
allows capital to be recovered and a return on investment to be achieved.
104
• Increasing system fault levels; or
• Changing patterns of network loading, as a result of energy trading, new
generation or new interconnections (including network constraint
management).
Augmentation may also be a solution to security of supply issues, such as
dynamic and transient stability.
105
obtain or is too expensive, this will limit the potential for system augmentation
and equipment replacement.
Cost per item can be reduced by purchasing efficiencies that result from
quantity of purchases. In some cases transmission entities can develop
special relationships with vendors, for instance by being pioneers for
106
introduction of a new technology into the market. They may therefore be
able to negotiate significantly lower prices for equipment purchases.
The combined risk associated with lending to a company, and hence the cost
of capital, is reflected in the company’s credit rating, if it has one.
107
of transmission capacity) and augmentation of the network. A reduction in
redundancy might arise from very high load growth and inadequate capital to
finance augmentation. Occasionally demand can fall: many countries of
Eastern Europe experienced reduced demand for several years after the
collapse of the Soviet Union (Lovei, 1998, Dobozi and Pohl, 1995). In this
case redundancy and reliability for the system might actually increase, in the
short term, beyond design levels3.
For series systems where all probabilities of failure are small (Equation 4)
(Hastings, 2000)
Fsys ≈ F1 + F2 + F3 … (4)
3
In fact problems of sustained overvoltage occurred (Batyayev et al., 1994) as a result of the
lightly loaded lines, which may have increased failure rates, offsetting the effects of
increased redundancy.
108
the longer the conductor, the more series elements contained in the circuit
and the higher its potential unreliability. Thus for systems having high value
of average line length the proportion of unreliability owing to lines will be
higher compared with the proportion owing to substations.
3.2.15 Availability
Availability is a measure of the proportion of time that a component or system
is available to do its job. Circuit availability has historically been considered a
useful measure of performance in some countries, notably Australia (ACCC,
2002b). It includes planned and unplanned outages of circuits and does not
take into account impact on the customer. Unplanned outages relate to
failure rate and associated remedial maintenance actions. Maintenance
practices that reduce the number and duration of scheduled and
unscheduled outages will also impact on availability. These include:
109
• Use of predictive maintenance, and particularly online condition-based
maintenance – this reduces routine maintenance outages and
• Combining maintenance activities by circuit – this reduces the number
of circuit outages; and
• Use of live maintenance techniques for lines and/or substations.
Flexibility within substation configuration also reduces restoration time and
the number of scheduled circuit outages by enabling substation equipment to
be maintained without removing circuits from service.
110
consequences for network reliability and/or maintenance costs. This and
other issues relating to the regulation of transmission enterprises are
discussed in detail in Chapter 7.
111
+
+ routine + maintenance rel
skill labour maint cost to
geographic
cost recommended
spread - +
attitude to + +
refurb.
technology
- + cost
+
+ use of offline +
+ CBM - maintenance
proportion of spending +
equipment + financial
installed since use of
+ drivers
1990 predictive - + -
maintenance -+
+ refurbishment -
replacemt
+ ++ of equip. + + maint.cost
+ + +
maint.
+ + - corrective
effectiveness
taxes &
- + maint. cost dividends
use of -
online CBM -
+ + -
proportion
+ live - revenue
+ or failure rate + poor condit.
+ equip. + available
+ a/hours + financial
work + resource
construction
- - perform.
outages - + + + incentives
- +
- + + + replacement
- availability as
++ + investment
+ proportion of +
aged
load freq. of failure
combined equipment
climate & factor replacement
maintenance + severity criterion
activities - -
+ +
- loading + +
+ replacement of
flexibility reliability equipment
+
+
+ + age as + +
replacement
+ + criterion
+ + interest &
connectivity + + repayment
redundancy
+ system ease of
cost of augmentation + raising + +
land capital debt
investment + cost
+ +
spending - rate of
load
++ - debt
external growth level
factors size of
increasing cost + company
barriers +
per asset - gov. debt -
+ + + support -
special rel. regulatory
rugged + purchasing
+ with vendors support
earthquake terrain efficiencies
zone
+
negative time
positive influence
+ correlation - correlation lag
KEY:
112
of the CLD form does not contain all the detail necessary for a full
understanding of the model’s behaviour, but it is possible to identify
reinforcing and balancing loops. Reinforcing loops are equivalently known as
positive feedback loops. In a reinforcing loop the action of the loop is to
influence the parameter in the same direction as it is already moving (a
destabilising influence). On the other hand, balancing or negative feedback
loops tend to return the parameter to its initial value (a stabilising influence).
Some feed back loops involving available financial resource are:
available financial resource + replacement of equipment +investment
spending - available financial resource
113
Similarly a loop involving augmentation of the network instead of replacement
of equipment also reinforces this loop. There is another loop that directly
connects use of online CBM with reducing maintenance spending. This
connection was added because use of online CBM has a stronger negative
affect on maintenance spending than offline CBM, because of the labour and
resources involved in undertaking off-line CBM. The loop thus formed is also
reinforcing:
Other loops allow for the possibility of refurbishing poor condition equipment,
rather than allowing it to fail, or refurbishing it after failure (for example):
maintenance spending +maintenance effectiveness delay -proportion
of poor condition equipment +refurbishment of equipment+ maintenance
spending
These, too, are balancing loops. The delay in these loops means a short
term improvement in balance sheets can be obtained by reducing
114
maintenance spending below adequate levels, and there is some evidence
occurring in practice.
115
• Construction of a generic model of transmission asset management
with broad application to transmission utilities around the world;
• Filling a gap in knowledge in this field by combining in the analysis
aspects of network design, corporate issues and external influences
on transmission asset management; and
• Representing the system structure concisely in the form of a Causal
Loop Diagram which reveals the loop-structures and possible
behaviours of the system.
116
4 Modelling
In Chapter 3 a model of asset management in transmission enterprises was
developed. However the model needs to be taken further, in order to
address the research topic. The first requirement is to validate the model.
The second consideration is how to extract information from it that
• Can demonstrate why regional variations in asset management exist;
and
• Can be of use to managers of transmission organisations wishing to
identify levers for performance enhancement.
To achieve these purposes it is necessary to implement the model in a form
in which data representing particular cases can be used to predict outcomes
that can then be tested against known results. The model also needs to be
constructed in a way that permits sensitivity of outputs to factors of influence
to be examined. To investigate regional variations regional data should be
used, and for performance enhancement individual case studies could be
employed. The set of relationships expressed in the model apply equally to
individual cases and regional studies.
4.1 Methodology
The methodology developed for this research can be summarised in the
following steps:
1. Define the scope and level of the problem
• Define purpose (Section 1.4)
• Set boundaries (Section1.5)
• Set level of abstraction/detail (Section 1.4, 1.5, Chapter 3)
2. Develop the structure and relationships of the model – conceptual model
(Relationships – Chapter 3, Structure – Section 3.3).
117
3. Identify the characteristics of the problem, data and desired outputs
(Sections 4.2, 4.3);
4. Match problem characteristics and purpose of investigation with suitable
methodologies (Section 4.4);
5. Implement model (fuzzy model Sections 5.1.1, 5.1.2 ; system dynamics
model Sections 6.4 to 6.15)
6. Verify model implementation against conceptual model (fuzzy model
Section 5.1.3; system dynamics model Section 6.2)
7. Validate the model (fuzzy model Sections 5.1.4, 0, 5.2.1 to 5.2.7, and
5.3.1 to 5.3.5; system dynamics model Sections, 6.2, 6.6.2, 6.12, 6.13, 6.15);
8. Refine the model according to results; Repeat steps 6 to 8 as necessary
Section 5.1.6).
9. Use model to investigate the problem. Assess outcomes against
reasonable expectations and limitations of the model. If necessary, repeat
steps 4 to 9 (fuzzy model Sections 5.2.8.2, 5.4; system dynamics model
Sections 6.6 to 6.15).
At this stage the first two steps have been completed. Chapter 5 describes
the implementation, verification, validation and use of a multi-level fuzzy
rule-based model to support the aims of the research project. In Chapter 6
the process from implementation to assessment is repeated for a system
dynamics model, encompassing core parts of the conceptual model
developed in Chapter 3.
Potential input data for use in a study are of variable quality, even from the
CIGRE study. CIGRE study data are highly incomplete in some critical
118
parameters. It is also necessary to supplement data in this study with from
other data sources, making the construction of consistent data profiles a
challenge. The input data are most easily represented as a mixture of
quantitative and non-quantitative values.
The quality and quantity of data for comparison of model outputs with values
from real systems is limited. The CIGRE study is a useful source, and has
the advantage that input data profiles and outputs derived from the one
source should be reasonably consistent with each other. However, for some
survey questions the data are highly incomplete, especially when
performance measures or spending figures were requested. Hence
supplementary material is also needed for comparison of outputs.
119
4.4 Potential modelling methods
Most input data for this application can be easily represented as fuzzy
parameters with logical outputs eg attitude to new technology (conservative,
120
moderate, aggressive). Output values are also expressed as linguistic
values eg reliability (high, moderate, low), which can be “defuzzified” to a
numeric on a scale established by the modeller (eg 1- 100). Expert system
shells, some with convenient graphical user interfaces are available for
purchase, and suitable for implementing this type of model.
4
The particular software chosen for implementation was also not conducive to the use of
feedback loops in the model.
121
first proposed for application to strategic management problems in the 1960s
(Forrester, 1961), and has since then found application in many fields (see
Chapter 6 for more information). In system dynamics modelling the behaviour
of the model over time can be explored. Several systems dynamics software
packages exist that enable the model to be expressed graphically, as
combinations of symbols. In Stock-Flow Diagrams (SFD) (Lane, 2000) stock
or reservoir symbols, generally shown as rectangles, represent state
variables and some sort of valve symbol is used to represent rate variables.
Ordinary variables may be indicated by a circle. Underlying the graphical
presentation of the model is a set of differential equations. Solving these
using numerical methods such as Euler and Runge-Kutta techniques permits
the time-development of the model to be explored.
For the purpose of this research the use of system dynamics modelling can
provide the depth of analysis not achievable with the CLD model. The
impreciseness of the input data and of most relationships in the model means
that simulation parameters would have to be synthesised, and outputs
assessed for reasonableness against expected ranges of values.
The methodology facilitates the use of sensitivity studies which may provide
insights into the relationships represented in the model. It can also be used
to understand model’s limits.
122
• Verification is greatly simplified by graphical representation of loops;
• It can provide numeric outcomes. However, implementation of the
system dynamics model requires a high degree of parameter
estimation, and results can be only indicative.
• It is easy to test the sensitivity of model outcomes to changes in levels
of inputs.
Disadvantages of this methodology:
• Changes in decision criteria (eg for replacement of equipment)
require the structure of the model to be changed, a time consuming
process.
• Complexity of full mathematical implementation makes models,
potentially, more difficult to implement and validate.
• Data parameters are buried in the model (although with some
additional work this limitation can be overcome).
• Rules that can be easily expressed in terms of linguistic variables can
be represented as approximate mathematical relationships, but in this
form their validity is more difficult to assess.
123
The model presented in Figure 15 would not be easily adapted to this form of
representation. It would, however, be possible to represent the core parts of
the model (assets degrading, failing, being replaced, being refurbished) using
this method.
124
A multi-level rule-based model employing fuzzy modelling concepts has been
created based on the relationships expressed in Chapter 3. A set of regional
data profiles has been developed and applied to the rule set, permitting
predicted outcomes to be assessed against available performance data.
125
5 The multi-level fuzzy model
This chapter contains five sections. The first section describes the
implementation, testing and verification of the multi-level fuzzy model. The
second and third sections present studies by regional case sets, and case
studies on individual companies. In Section 5.4 the use of the fuzzy model
as a strategic management tool is examined, based on the individual case
studies. Findings are summarised in Section 5.5.
1.0
Membership function
Mild Extreme
Moderate
0.5
0
0 20 40 60 80 100
Climatic factor level
Figure 16 Membership functions for climatic factor
126
Membership functions for the output values are represented either as
‘normalized’ functions on a 0-100 scale, as shown in Figure 16, or as
membership functions reflecting the actual form of the data (Figure 17).
1.0
Membership function
High
0.5
Low Moderate
0
0 5 10 15 20
Load growth recent in %
Figure 17 The membership functions for parameter load growth– an example of
membership functions estimated from real numeric data, in this case percentage
recent load growth.
127
outcome of the rule. When several rules with the same outcome are fired,
the outcome is assigned the maximum MV calculated from all the rules.
system augmentation
high high
high high
medium medium
low medium
high high
medium medium
low low
Figure 18 The decision tree for the task Investment in new equipment
This task has three possible outcomes (high, medium, low) only two
components - equipment replacement and system augmentation, both of
which are fuzzy tasks. Investment in new equipment generates only seven
fuzzy rules. These are shown in Table 4.
128
Rule Conditions Outcome
equipment replacement is medium AND
3 medium
system augmentation is medium
equipment replacement is low AND
4 medium
system augmentation is medium
equipment replacement is high AND
5 high
system augmentation is low
equipment replacement is medium AND
6 medium
system augmentation is low
equipment replacement is low AND
7 low
system augmentation is low
As an illustration of how the fuzzy logic works consider the case where
system augmentation = 30, and
equipment replacement = 20.
If the membership graph of system augmentation is similar to Figure 16:
MV (30, low) = 0.66
MV (30, medium) = 0.33
MV (30, high) = 0.
Similarly from the membership graph of equipment replacement:
MV (20, low) = 1
MV (20, medium) = 0
MV(20, high) = 0
129
For each outcome, the MV is taken as the maximum MV from the group of
rules having that outcome.
MV (high) = 0
MV (medium) = 0.33
MV (low) = 0.66
In this example the highest values for outcomes low, medium and high in
investment in new equipment, are 0 to 20 (an average of 10), 50 and 80 to
100 (average 90) respectively. The outcome investment in new equipment
level associated with this task is:
0.66 x10 + 0.33x50 + 0 x90
level = = 23
0.66 + 0.33 + 0.0
The outcome description is determined from the outcome with the highest
MV, in this case “low”. Both a numeric and a descriptive outcome for results
have been recorded in this model, because the combination provides more
information than either descriptive or numeric result alone.
130
To incorporate the delays, for example between maintenance spending and
proportion of poor condition equipment, historical values of the parameters
have been used: for maintenance effectiveness in past years, historical
maintenance adequacy has been used. Similarly, the historical level of
available financial resource is named historical revenue sufficiency.
131
maintenance rel to
geographic + manufacturer
spread skill
attitude to + recommended
technology labour
- cost + +
+ use of offline
maintenance
CBM
proportion of + spending +
+ financial
young
drivers
-
equipment + - +
use of predictive
maintenance
refurbishment
+ -
of equip. --
- load
+ + factor
+ -
+ +
+ historical
+ - + maintenance
-
use of online adequacy
+
CBM
+ proportion poor
-
available
failure rate + condit. equip. financial
+ resource
construction -
+
outages
++ +
- availability replacement
as
historical proportion of investment
revenue +
+ aged
sufficiency equipment freq. of failure
+ replacement
combined climate & criterion
maintenance + severity loading
+
activities
- +
live +
working
+ replacement of
equipment
flexibility
reliability
+
+ +
age as
+ + + replacement
criterion +
redundancy
connectivity +
+ ease of
+ system
+ + raising
cost of augmentation capital
land
investment
+ + rate of load
+ spending growth -
-
factors size of external
increasing cost + + company barriers + debt level
per asset -
+ + special rel. regulatory
+ with vendors support
+ purchasing
earthquake rugged terrain efficiencies
zone
+
negative time
positive influence
+ correlation
- correlation lag
KEY:
132
six inputs, depending on the interaction of input parameters. The decision
tree also becomes difficult to debug. The solution to this is to decompose the
problem into logical sub-tasks. In the case of maintenance spending this
task has been decomposed into five subtasks, as illustrated in Figure 20.
maintenance
spending
+ +
+ + +
climatic
proportion
factor
loading aged
equipment
connectivity
+
flexibility attitude to
skill Key: positive negative
technology
attribute correlation correlation
+ -
proportion historical
maintenance rel geographic task/
young revenue
to recommended factor subtask
equipment sufficiency
133
Table 5 Summary of model tasks and their inputs
Task / Subtask Name Parameters & subtasks (subtasks bolded)
construction outages; failure rate; flexibility; maintenance
availability
actions increasing availability
construction outages refurbishment, equipment replacement; system augmentation
corrective maintenance costs labour costs; failure rate
cost of finance credit rating
debt repayments cost of finance; revenue sufficiency; debt level
regulatory support; debt level; revenue sufficiency; credit rating
ease of raising capital
known; credit rating
replacement on condition; replacement on failures;
equipment replacement
replacement on age; financial incentive- replacement
use of online CBM; ruggedness of terrain; cost of land;
factors increasing asset costs
earthquake zone; geographic factor
spending limit; use of predictive maintenance; failure
failure rate contribution of load & climate; proportion poor condition
equipment
failure contribution of load & climate climate (type), climatic factor, loading
financial driver - maintenance maintenance spend as KPI; profit as intention; revenue sufficiency
financial incentive - replacement ease of raising capital; revenue sufficiency, debt repayments
factors increasing asset costs; purchasing efficiencies;
investment cost
investment in new equipment
investment in new equipment equipment replacement; system augmentation
loading pilfering, losses
use of predictive maintenance; use of online; live work;
maintenance actions increasing availability
combined maintenance activities
corrective maintenance costs; refurbishment costs;
maintenance spending replacement costs as maintenance; routine maintenance
costs; spending limit
proportion poor condition equipment historical maintenance adequacy; proportion aged equipment
special relationship with vendor; investment in new equipment;
purchasing efficiencies
size of company
financial driver maintenance; use of predictive maintenance;
refurbishment
proportion poor condition equipment
refurbishment costs labour cost, refurbishment
reliability redundancy; connectivity factor; failure rate; flexibility
replacement on age age as replacement criterion; proportion aged equipment
use of predictive maintenance; proportion poor condition
replacement on condition
equipment; refurbishment
number of failures as replacement criterion; frequency of failures
replacement on failures
as replacement criterion; failure rate; refurbishment
equipment replacement; replacement as investment; financial
replacement cost as maintenance
driver - maintenance
use of online CBM; geographic factor; maintenance relative to
routine maintenance cost recommended; labour cost; system factors reducing
maintenance cost
spending limits financial driver maintenance; revenue sufficiency
ease of raising capital; external barriers; load factor; loading ;
system augmentation
load growth recent; investment cost as KPI; revenue sufficiency
system factors reducing maintenance costs connectivity factor; flexibility; load factor; redundancy
labour skill; profit as intention; maintenance spending as KPI;
use of offline CBM
revenue sufficiency; attitude to new technology; labour cost
proportion young equipment; attitude to new technology;
use of online CBM
geographic factor; historical revenue sufficiency
use of predictive maintenance use of online CBM; use of offline CBM
134
be displayed in the attributes view for the task. Alternatively all instances in
which a task or attribute is used, can be listed in a usage report. The linkage
of tasks may be examined on the map view.
The second step is to verify the rules associated with each task. This is a far
more time-consuming process. It entails ensuring that the rules in the model
are in accordance with the relationships presented in Chapter 3.
For simple tasks (such as that illustrated in Figure 18) it is possible to check
the decision tree visually. For tasks that have many inputs or for which the
relationships between variables are complex, visual scanning of decision
trees is not practical. Two approaches have been taken to overcome this
problem. One solution has been to structure the problem as a multi-level
task, by decomposing it into more manageable sub-tasks. An example of
this was given in Figure 20, with regard to maintenance spending.
135
loop), run the program through one iteration of the loop then run the whole
range of values to obtain the matrix of outputs, as required.
The development cycle works most efficiently if the model is constructed and
verified iteratively as follows:
• A task is created first using attributes as inputs.
• The task is tested by varying its attributes over their appropriate
ranges.
• Then the attributes are converted to tasks, and additional decision
trees are added at the deeper level, and so on.
However, in practice it is not always possible to construct the model in
this way, because of the highly interconnected nature of the system being
modelled, and also because one’s understanding of the system changes
gradually over time as more experience is gained with the model.
The process of validation generally falls into one of two categories (Pidd,
1996): black box or transparent box testing. In transparent box techniques
the internal working of the model are examined. In black box testing the
outputs of the model are assessed against a range of inputs, ignoring the
internal structure of the model.
For this application the black box testing has been performed by creating a
set of data profiles for different regions of the world, and comparing the
results against the best available data on performance and policies. The
rationale for this is that all datasets are tested against the same set of rules,
136
and if the model is valid then all datasets should give outputs consistent with
available data. There are drawbacks with this approach:
• Both the input data and the outputs for comparison are less than
perfect - incomplete, inconsistent, not always corresponding to the
same set of companies or countries or the same time period. This
makes it unlikely that a perfect match between inputs and results will
be achieved, even if the model is perfectly correct.
• The regional data tends to be very “average”, because they are
created from averaged or typical data. They therefore tend not to test
the rules at the extreme values of data ranges.
Additional testing with individual case studies engages a larger proportion of
model rules, although some data have also had to be estimated for these
cases. However, sufficient data to create sets for individual case studies
have not come to hand for some of the more extreme cases that could
potentially be applied to this model.
5.1.5 Summary of data used in regional studies for the fuzzy model
Appendix A details the sourcing and treatment of data for regional case
studies. These data inputs are summarised in Table 6 .
137
Table 6 Input Parameters used in regional studies for fuzzy model
Parameter A AU EE NA SA WE
Age as replacement criterion very significant (100) insignificant (25) very significant (82) significant (42) significant (48) significant (42)
Attitude to technology moderate (40) aggressive (65) moderate (60) moderate (35) moderate (45) moderate (60)
Business acumen moderate (50) moderate (50) low (25) moderate (60) moderate (50) moderate (60)
Climate tropical & wet sub-tropical temperate temperate tropical & wet temperate
Climatic factor moderate (40) moderate (50) extreme (65) mild (30) moderate (60) moderate (60)
Combining of maintenance
medium (44) medium (63) low (33) high (71) low (0) medium (57)
activities (by circuit)
Connectivity factor low (14) moderate (20) moderate (21) moderate (20) low (14) high (32)
Cost of land low (30) low (30) moderate (40) moderate (50) low (20) moderate (50)
Credit rating A (40) A (50) BB (30) A (40) BB (30) AA (70)
Debt level moderate (60) moderate (50) moderate (40) moderate (45) high (75) moderate (55)
Earth quake zone No (30) No (10) No (10) No (20) No (20) No (20)
External barriers low (20) moderate (40) moderate (50) moderate (60) low (30) high (80)
Flexibility high (84) moderate (43 high (67) high (69) high (90) low (31)
Frequency of failure as
significant (57) very significant (77) significant (50) significant (58) significant (60) significant (60)
replacement criterion
Geographic factor moderate (16) moderate (21) low (11) moderate (17) high (39) low (6)
Historical revenue sufficiency adequate (65) not a concern (80) inadequate (40) not a concern (75) inadequate (40) not a concern (80)
Investment cost as KPI significant (55) very significant (75) insignificant (33) insignificant (26) insignificant (0) insignificant (30)
medium $US 19000
Labour cost low $US 9000 pa low $US 2000 pa high $US 29000 pa low $US 5000 pa high $US 26000 pa
pa
Labour skill moderate (50) high (70) high (70) high (70) moderate (50) high 70
Live work low 24% low 20% low 11% low 11% moderate 57% low 3%
Load factor moderate (57%) moderate 62% moderate 63% moderate 61% high 72% high 65%
Load growth (recent) high (9.1%) moderate 3.5% low 1.0% low 2.7% moderate 7.4% low 2.9%
Losses (T&D) moderate (11%) moderate 9% very high 18% low 7% high 15% low 7%
Historical maintenance
maintained (65) maintained (65) under-maintained (30) maintained (65) under-maintained (25) maintained (65)
adequacy
Maintenance relative to
more than at recommended more than less than more than at recommended
manufacturers’ recommended
recommended (85) levels (56) recommended (100) recommended (15) recommended (80) levels (45)
levels
Maintenance spending as KPI significant (55) very significant (75) insignificant (18) very significant (72) insignificant (20) significant (53)
Number of failures as
very significant (67) significant (62) significant (50) significant (58) significant (40) significant (58)
replacement criterion
Pilfering low (20) low (10) high (70) low (10) low (30) low (10)
Profit as intention No (36) No (38) No (0) Yes (58) No (20) No (28)
Proportion of aged equipment low 6% low 10% low 3% moderate 14% low 6% low 10%
Proportion of young
high 65% moderate 37% moderate 56% low 30% moderate 62% moderate 39%
equipment
138
Parameter A AU EE NA SA WE
Redundancy moderate (n-1) (50) moderate (n-1) (50) moderate (n-1) (50) moderate (n-1) (50) moderate (n-1) (50) moderate (n-1) (50)
reasonably supportive reasonably supportive reasonably supportive
Regulatory support highly supportive (70) highly supportive (50) highly supportive (70)
(35) (78) (40)
Replacement considered an
very significant (100) very significant (100) very significant (83) very significant (86) very significant (80) very significant (100)
investment
Revenue sufficiency
adequate (60) not a concern (70) adequate (50) not a concern (70) adequate (55) not a concern (80)
(available financial resource)
Ruggedness of terrain not rugged (30) not rugged (30) not rugged (30) not rugged (30) not rugged (30) not rugged (30)
Size of company medium (40) medium (25) small (30) medium (50) medium (20) medium (50)
Special relationship with
no use (30) no use (35) no use (10) no use (30) no use (20) no use (35)
vendors
139
5.1.6 Refinement of the fuzzy model
The refinement and validation processes are closely linked, as explained in
Section 4.1. During validation, one or more cases might produce an outcome
that is considered too high or too low compared with outputs from other
cases. There are a number of options for correcting such problems:
140
• Finally, the inability of the fuzzy model to represent fully the feedback
mechanisms and time delays of the model is recognised as a limitation
of the technique.
The results from the validation and refinement processes are presented in
Sections 5.2 and 5.3 for regional studies and individual case studies
respectively.
The methods used for verification, validation and refinement of the multi-level
fuzzy rule-based model, have been described in detail in this section,
including the development of regional case studies for use as input data.
141
5.2.1 Failure rate
Failure rate is a key factor in the transmission asset management model. It
impacts on many other model outputs – including reliability, availability,
maintenance costs and replacement costs. It is therefore important that the
values obtained in the calculation of failure rate accurately reflect observed
values.
Figure 21 shows a comparison of unplanned outages per circuit and per 100
circuit-kilometres from the CIGRE study and the failure rate output parameter
from the model. The differences between the per-circuit and per-100km-of-
circuit values reflect the fact that some failures are related to the length of
circuit (lightning flashovers for example) while some are not related to circuit
length (substation equipment failures for instance). For transmission
systems with, on average, low circuit lengths (WE and EE), the unplanned
outages per circuit will give better measure of forced outage rate. On the
other hand, for systems with greater average line length (SA, notably), the
unplanned outages per 100km circuit length should be a more accurate
reflection of outage rates.
4
low moderate high.
Unplanned
3 outages
per100km
2
Unplanned
1 outages/cct
0 model
A AU EE NA SA WE
Regions
142
model predicts results similar to actual values, although it underestimates
slightly the failure rate for South America. The reason for this is not entirely
clear – although comparison with the maintenance cost graph suggests that
either the system is under-maintained, which over time would result in higher
failure rates, or that the climatic severity factor in the model is too low, in
which case the model overestimates the additional corrective maintenance
costs associated with a high failure rate.5 Alternatively it may be a matter of
poor data quality (in maintenance costs and/or failure rates).
5
Note that there were only three responses in the CIGRE study from South America
providing the required information. These responses may not be typical of the region as a
whole.
143
Region Location Value Description Source Assessment
Queensland 3.8 (Brown, 2001a) High
South
2.4 (SAIIR, 2001) High
Australia
(Office of the
Western Tasmanian
5 High
Australia Regulator,
2001)
(Office of the
Tasmanian Moderate-
Tasmania 17
Regulator, high
2001)
Years 1997/98 and 1998/99. Number
24 moderate-
AU Queensland of unplanned outages causing loss of (ACCC, 2002b)
20 high
supply per year. (T)
5.3 (Plantagie,
AU South Africa System minutes lost in 1998,1999 (T) High
3.8 2000)
Average system reliability from four (CIGRE SC 23
AU unspecified 99.5% High
responses in CIGRE study (T) and 39, 2000)
system reliability 1 respondent from (CIGRE SC 23
EE unspecified 99.7% High
CIGRE study (T) and 39, 2000)
value assumed to be unreliability
(CIGRE SC 23
EE unspecified 10% (target was 5%) – 1 respondent from Low
and 39, 2000)
CIGRE study (T)
min/customer/yr average interruption
Consolidated (Kurihara,
NA <10 duration index (transmission + High
Edison NY 1999)
distribution) in period 1990-1996
1988 – 1994
1995 -1996
Florida Light & 40-60 (Kurihara, high-
NA min/customer/yr average interruption
Power 120 1999) moderate
duration index (transmission +
distribution)
1989-1996
Southern
approx min/customer/yr average interruption (Kurihara, high-
NA California
38-78 duration index (transmission + 1999) moderate
Edison
distribution)
(Hours) customer average interruption (BC Hydro,
NA BC Hydro 2.57 Moderate
duration index (T,D) in 2001 2002)
(Hours) service average interruption (Hydro Quebec
HQ high-
NA 0.51 duration index in 2001 (T). Excludes Transenergie,
Transenergie moderate
exceptional events. 2002)
Data for 97/998 and 98/99.
Southern Percentage of 500kV lines without
57.9%
NA California forced outages. (Note this is equipment (ACCC, 2002b)
52.6%
Edison reliability rather than reliability of
supply)
Data for 97/98 and 98/99. Percentage
Southern
74.6 of 220kV lines without forced outages.
NA California (ACCC, 2002b)
81.70 (Note this is equipment reliability rather
Edison
than reliability of supply)
144
Region Location Value Description Source Assessment
97/98 and 98/99 500kV Annual forced
Southern
0.63 outage frequency (number per line per
NA California (ACCC, 2002b)
1.0 year) (Note this is equipment reliability
Edison
rather than reliability of supply)
97/98 and 98/99 220kV Annual forced
Southern outage frequency (number per circuit
0.7
NA California per year) (Note this is equipment (ACCC, 2002b)
0.48
Edison reliability rather than reliability of
supply)
Transener, High-
SA 0.5-1.5
Argentina Forced outages per 100 circuit-km per moderate
Regional year (Note this is an indicator of
(ENRE, 2001)
transmission Typically equipment reliability rather than supply Moderate-
SA
boards, 4 reliability) low
Argentina
Average value from six responses for (CIGRE SC 23
WE Unspecified 99.4% High
system reliability from CIGRE study and 39, 2000)
14 Figures for 1997/98 and 1998/99.
WE NGC, UK
5 Number of incidents on the
Scottish 6 transmission system resulting in loss of
Power, UK 9
supply to one or more customers from
(OFGEM,
faults on the transmission system. High
2001)
These include faults on connection
Hydro-electric, 8
UK 19 assets where the loss of supply
resulted from customer choice of
connection arrangement.
Unplanned unavailability of circuits
98/99 and 99/00. Forced outages due
to plant breakdown or forced
0.16%
WE NGC maintenance taken with less than one (NGC, 2000) High
0.26%
week notice. (Note this is a measure
of equipment reliability not supply
reliability)
The CIGRE study data also are highly incomplete and, in a number of cases,
figures were reported without explanation of the method of calculation
employed. Six of 28 respondents from Western Europe gave percentage
values for system reliability (not supply reliability), using Equation (5).
Reliability = 1 –
1/(no. ccts) * ∑ (hours of unplanned availability) (5)
(8760 – hours of planned unavailability)
145
Sys minutes lost =
unsupplied energy *60/peak demand (6)
Unsupplied energy is in MWh and peak demand in MW. Note that supply
point reliability and system reliability defined in Equation (5) are not
equivalent (one does not include impact on customer, the other does), but
are related.
In the model an attempt has been made to predict supply point reliability
based on system characteristics and asset management policies and
practices (including historical ones). The results by region (Figure 22), when
compared with Table 7, are reasonable but more data for comparison,
especially from South America, Eastern Europe and Asia would be beneficial.
Reliability, as seen by customers, is strongly influenced by network
configuration, especially redundancy on the network. Typically transmission
systems are designed to withstand common outages without loss of supply to
the customer (N-1 planning criterion), so loss of supply incidents are
infrequent, even on systems with moderately high equipment outage rates.
Highly interconnected systems will have higher reliability, all else being
equal, because of a higher number of alternative paths for supply. The
cumulative effect of connectivity and redundancy is illustrated in two sets of
figures (Table 8) reported in (ACCC, 2002b).
The reliability of supply for this utility is eight to ten times greater than it would
be if each load was supplied radially through a single line.
146
Reliability of Supply-Model
A AU EE NA SA WE
Figure 22 Supply point reliability predicted by the model. The arrows indicate the
range of observed values from Table 15.
147
Region Location Value Description Source Assessment
95.5% 1x low
three responses (of possible (CIGRE SC 23
EE Unspecified 60.0% 1x moderate
six) for circuit availability and 39, 2000)
99.0% 1x high
Southern
NA California 99.99% Circuit availability (ACCC, 2002b) high
Edison
97.78%
three responses (of possible (CIGRE SC 23 1 x moderate 2
NA Unspecified 99.9%
seven) for circuit availability and 39, 2000) x high
100%
99%
three responses (of possible (CIGRE SC 23 1 x moderate
SA Unspecified 95%
five) for circuit availability and 39, 2000) 2x high
99.5%
Unavailability of circuits
1997/8. Includes large
NGC 3.7% (OFGEM, 2001) moderate
components from construction
outages
Scottish Power 3.3% moderate
Unavailability/Availability of the
Hydro-Electric 2.5% (Perez-Arriaga et moderate
transmission network
Finland 99.999% al., 2002) high
99.8%
95.84%
99%
WE 98.5%
98%
99.2%
1 x low
90% Fourteen responses (of (CIGRE SC 23
Unspecified 5 x moderate
98.2% possible twenty eight) and 39, 2000)
8 x high
97.48%
97%
98.79%
99.02%
98%
98.99%
The CIGRE study reports circuit availability average of 98% excluding one
respondent for whom there were special reasons for low availability. Table
10 compares the model outputs with average values from CIGRE data and
the range of values from all sources. Predicted results agree well with
reported data for circuit availability across all regions.
148
As mentioned in Section 2.1.1, the figure suggests that Australasia/South
Africa, and South America have the highest use of online condition-based
maintenance. Australasia/South Africa, Eastern Europe and Western Europe
have relatively higher use of offline CBM; North American respondents report
relatively low usage. High predictive maintenance usage (combining online
and offline CBM) should also be associated with low corrective maintenance
and vice-versa, if the equipment is in similar condition. This relationship
seems to hold true for Asia and North America which have relatively high
corrective and lower predictive maintenance, and for Australasia/ South
Africa with low usage of corrective and higher predictive maintenance. The
South American data are more ambiguous, but perhaps the relatively high
level of corrective maintenance is an indication of historically poor
maintenance quality rather than low level of predictive maintenance in 1998.
The relatively high level of corrective maintenance employed as a strategy
might be a reflection of spending limitations and poor maintenance history.
Table 11 compares the predictions of the model with data from the CIGRE
study.
The predicted level of online CBM in South America is lower than that
suggested by the CIGRE study. The use of a particular strategy can be
considered to be a function of need, inclination and opportunity. The use of
online CBM may be motivated by a need to maintain a high level of circuit
availability. (See Section 6.14.1 for a discussion on the effect of redundancy
on system risk, and the need to maintain high availability.) Note that two
South American respondents to the CIGRE study also report high levels of
live-working; live working is also aimed at increasing circuit availability. The
rapid growth in electricity consumption in South America provides the
opportunity to introduce online CBM, as online condition-monitoring is
cheaper to purchase with new equipment than to retrofit to aged equipment.
However, opportunity may be limited by available financial resource. For this
reason the model does not predict high use of online CBM in South America.
However, it may be that the model overestimates the capital cost of “typical”
online CBM or that the types of online CBM practiced in South America are
less capital intensive than the self-monitoring devices favoured in some other
149
countries (eg Australia). If so, then there may be greater opportunity for use
of online predictive maintenance in South America than suggested by this
model.
The North American entry for Offline CBM is surprisingly low. Inspection of
the CIGRE data reveals that one respondent indicated a time-based
maintenance strategy only for the protection equipment category (a
regulatory requirement), and no entries in any other category. Another two
nominated time-based and time-based plus corrective maintenance as
general strategies. If these results are typical of North American companies,
the level of skill applied to maintenance may be lower than estimated and/or
the attitude to technology more conservative than estimated in input data for
this model.
150
100
50-60 90
80
40-50
x 70
30-40 60 Labour
20-30 50 skill level
40
10-20
30
0-10 20
10 10
30
50
70
90
Attitude to new
technology
Figure 23 Sensitivity diagram of offline CBM with attitude to new technology and
labour skill for the North American region. X marks the coordinates used for the
North American base case.
151
discussions by the author with some utility representatives in the US appear
to support this argument.
Maintenance spending -
8 median
high
cost / asset value
model
component
moderate
model
4
2
0 low
A AU EE NA SA WE
Region
152
1/7*[(RatioB * Bays(50-199kV) + (RatioT*Tower(50-199kV)) + RatioL*OHL(50-199kV)+
RatioC * Cable(50-199kV))] (7)
where
RatioB = 1; Ratio T = 0.27; Ratio L = 0.053; RatioC = 2.22
Bay(n-m kV) is the number of bays in the nominated voltage range n to m kV
Tower (n-m kV) is the number of towers in the nominated voltage range n to m kV
OHL( n-m kV) is the length of overhead line in the nominated voltage range n to m kV and
Cable(n-m kV) is the total length of underground cable in the nominated voltage range n to m
kV.
The ratios were calculated using estimated initial costs of the equipment and
associated maintenance costs discounted over 40 years to give a net present
value(CIGRE SC 23 and 39, 2000 p A2-2). The values calculated using this
base are normalised to a scale of 1 to 100 for comparison purposes.
153
5.2.6 Refurbishment of equipment
Refurbishment costs
maintenance cost x
normalised maint
- model
4
0
A AU EE NA SA WE
Regions
Both CIGRE survey and model results suggest that Eastern Europe has
relatively high levels of refurbishment costs and North America relatively low.
The CIGRE data suggest that Australasia/South Africa and Western Europe
spend more on refurbishment that North America; this is also consistent with
model outputs
154
5.2.7 Replacement of equipment
Figure 26 illustrates model predictions and CIGRE data for replacement rate.
The CIGRE survey asked for a general answer for percentage of equipment
replaced in the past four years, and /or the same information for seven
categories of equipment. To obtain results for comparison it was necessary
to make some assumptions about the data. The rules used are as follows: If
a general answer were given this was used, otherwise an average value over
the seven categories was taken. Some respondents gave no answer at all.
It was assumed when averaging the seven categories that if some categories
had non-zero numbers and others had none that the empty categories were
intended to be zeros. In some cases this may make the averages lower than
true figures. The use of average values across all categories will all produce
some distortion of results, unless all categories contain equal number of
items.
10.0
Median all categories or
Replacement -model
low moderate high
8.0
general (%)
6.0
4.0
2.0
0.0
A AU EE NA SA WE
Median Model
155
The model appears to overestimate the level of replacement in South
America, underestimate replacement in Eastern Europe/former Soviet Block
countries and Western Europe.
The South American case is interesting: despite relatively high failure rates
(shown by model predictions and confirmed by CIGRE study results) and
model predictions of relatively high levels of poor condition equipment, the
reported level of replacement is lower than predicted. Inspection of Figure 25
suggests that refurbishment could be at a slightly higher level than predicted
by the model. Refurbishment can displace replacement (both cannot be
applied to the same equipment at the same time), so this may be part of the
reason for overestimation of replacement by this model. However, inspection
156
of Table 20 below suggests another possibility. This table shows that South
America has a relatively low level of equipment approaching its nominal life.
It may be that utilities in South America are choosing to repair and refurbish
rather than replace equipment that is in poor condition (even though relatively
young). If poor-condition equipment is repaired but not restored to good
condition overall, the effect is to increase failure rates (see Section 6.8).
157
5.2.8 Discussion of results
158
sifting of survey responses, and assumptions about particular answers.
Performance data from this survey were particularly sparse. The CIGRE
study data have had to be supplemented by use of many other sources.
While every effort has been made to ensure that the supplementary material
is compatible with the CIGRE survey results, the data do not relate to the
same set of companies. Even within the CIGRE survey results this
compatibility problem can arise where respondents to one question are not
the same set of respondents to another question (since many respondents
did not answer all questions).
Another data problem arises because many of the circumstances that make
performance, policies and practices different from one enterprise to the next
are taken for granted by those involved. Thus these things are rarely
documented but they can have a significant impact on outcomes. To
understand the differences it is necessary to “read between the lines”. The
interviews conducted with industry representatives have also proven useful
for this purpose. An example is the understanding of reliability, which
appears to vary widely. Corporate culture is another area that can
significantly impact on performance.
The use of regional data to test the model has advantages and
disadvantages. The main advantage was being able to use the CIGRE study
results to access a range of data that is not readily available from other
sources. It was not possible to do this on a country by country basis because
the data were stripped of company and country details (for confidentiality
reasons). The main disadvantage was that in large regions such as Asia and
South America, where there are wide variations in asset management
practices, maturity of networks and financial circumstances, it was difficult to
combine data into a reasonable “typical” regional case. In Asia, for instance,
there are some countries with mature slow growing electricity networks and
many others with rapidly expanding networks and high load growth.
Revenue adequacy and indebtedness also vary significantly over the region.
159
Developing a “typical” profile in such cases tends to produce an “average”
result that masks the more extreme conditions. From a modelling point of
view this means that only middle-of-the-range rule conditions are tested,
rather than the full possible range. For this reason it was decided to
undertake some case studies of individual companies in order to refine the
model.
The main limitation with the fuzzy model is its inability to represent feedback
loops and delays fully. For this reason the system dynamics model has been
developed, and will be used to investigate some of the more important
relationships and feedback mechanisms. On the other hand, a benefit of this
formulation is that it encompasses a much broader range of inputs than is
generally possible with more traditional engineering modelling techniques.
Table 13 Parameters used to assess availability and their values for AU, NA and WE
cases
Parameter AU NA WE
maintenance actions
moderate (50) moderate (52) low (28)
increasing availability
construction outages low (24) low (10) low (15)
failure rate low (10) low (24) low (16)
flexibility moderate (43) high (69) low (31)
160
Examination of this table suggests that the parameters maintenance actions
increasing availability and flexibility may have a role in this result. The
sensitivity of availability to flexibility is plotted in Figure 27.
100
high
80
availability.
60
moderate
AU
40
NA
20 WE
low
0
0 20 40 60 80 100
flexibility %
Figure 27 Availability as a function of flexibility for three cases from fuzzy model
161
Table 14 Outputs from Fuzzy Model – Regional Studies
Output Parameter A AU EE NA SA WE
Availability high (98-100%) (70) high (98-100%) (85) moderate (95-98%) (32) high (98-100%) (85) moderate(95-98%) (50) moderate (95-98%) (62)
Construction outages moderate (45) low (24) moderate (50) low (10) moderate (60) low (15)
Corrective maintenance
low (27) low (10) low (10) low (23) low (30) low (10)
costs
Cost of finance moderate (30) low (10) moderate (50) moderate (30) moderate (50) low (10)
Debt repayments low (40) low (10) moderate (37) low (23) high (83) low (17)
Equipment replacement low (28) low (24) medium (50) low (16) medium (47) low (24)
Ease of raising capital easy (70) easy (90) moderate (50) easy (70) moderate (50) easy (90)
Factors increasing asset
low (41) low (33) low (24) low (34) moderate (44) low (31)
costs
Failure rate medium (34) low (10) medium (37) low (24) medium (65) low (16)
Failure rate contribution
moderate (50) low (10) moderate (30) low (10) moderate (63) low (23)
of load & climate
Financial drivers for
low (34) moderate (56) high (50) high (58) low (30) low (23)
maintenance spending
Financial incentive
high (77) high (90) moderate (50) high (74) low (10) high (90)
replacement
Investment cost high (63) very low (18) moderate (53) very low (20) very high (86) very low (17)
Investment in new
high (86) low (23) medium (50) low (10) high (76) low (15)
equipment
Loading heavily loaded (50) heavily loaded (40) heavily loaded (51) moderately loaded (30) v. heavily loaded (63) moderately loaded (30)
Maintenance actions
low (35) moderate (50) low (10) moderate (52) moderate (59) low(28)
increasing availability
Maintenance spending low (31) high (47) moderate (55) moderate (35) low (30) high (73)
Proportion poor condition
low (23) low (30) moderate (50) moderate (30) moderate (53) moderate (30)
equipment
Purchasing efficiencies high (60) low (10) low (23) low (10) low (10) low (10)
Refurbishment low (14) low (23) moderate (50) low (12) moderate (34) low (29)
Refurbishment costs low (12) moderately low (21) moderately low (30) low (7) low (10) moderately low (27)
Reliability of supply high:99-100% (72) high: 99-100% (90) moderate: 95-98% (68) high: 99-100% (83) moderate: 95-98% (50) high: 99-100% (90)
Replacement costs
low (10) low (10) low (10) low (10) low (10) low (10)
(maintenance only)
Replacement on age low (22) low (20) low (20) low (20) low (20) low (20)
Replacement on
low (23) low (30) moderate (50) low (24) moderate (40) low (30)
condition
Replacement on failures low (34) low (20) moderate (20) low (24) moderate (57) low (20)
Routine maintenance
moderate (50) moderate (42) moderate (54) moderate (41) moderate (50) moderate (48)
costs
162
Output Parameter A AU EE NA SA WE
Spending limits -
moderate (50) unlimited (70) moderate (30) unlimited (70) moderate (40) unlimited (90)
maintenance
System Augmentation high (77) medium (30) low (10) low (10) medium (69) low (10)
System factors reducing
high (90) medium (42) high (73) high (75) high (90) medium (46)
maintenance costs
Use of offline condition-
moderate (37) moderate (66) moderate (50) moderate (30) moderate (43) moderate (57)
based maintenance:
Use of online condition-
moderate (32) moderate (33) low (10) low (26) low (10) low (24)
based maintenance
Use of predictive
moderate (32) moderate (68) moderate (50) low (23) moderate (40) moderate (56)
maintenance
163
Figure 27 reveals that in this case, although the availability predicted for the
Western European case is sensitive to flexibility, it is not sensitive around the
present level (31%): a large change in flexibility from 31% to 80% would be
required to achieve a significant improvement in availability. The model also
suggests that availability is not as sensitive to flexibility in the other two
cases. In the North American case it can also be observed from Figure 27
that the maximum availability is constrained by a parameter other than
flexibility.
The task maintenance activities increasing availability has four inputs: live
working, combining maintenance activities (by circuit), use of online CBM and
use of predictive CBM.
Table 15 does not reveal large differences in values for any of the
parameters contributing to the task maintenance activities increasing
availability but, compared with the Australasian case, the values for the
Western European case for live working, combined maintenance activities
and use of offline CBM are all slightly lower. The North American case
exhibits a higher level of combined maintenance activities and slightly higher
164
use of live working than the Western Europe case, but lower use of online
CBM and predictive maintenance in general.
100
80
availability
AU
60
NA
40
WE
20
0
0 20 40 60 80 100
maintenance actions increasing
availability
165
For reliability the model uses four parameters – redundancy, connectivity,
flexibility and failure rate, three of which are related to system design.
Increases in any of redundancy, connectivity or flexibility will tend to increase
reliability, while failure rate acts in the opposite direction.
Table 16 Parameters used to determine reliability and their values for AU, NA and WE
Parameter AU NA WE
connectivity moderate (20) moderate (20) high (32)
failure rate low (10) low (24) low (16)
flexibility moderate (43) high (69) low (31)
redundancy moderate (50) moderate (50) moderate (50)
100
high
80
reliability
moderate
60
AU
40
NA
20 WE
low
0
0 10 20 30 40
connectivity (normalised 1-100)
166
90
flexibility
70
85-95
50
75-85
x 30 65-75
55-65
0
0
12
18
24
30
361
low moderate high
connectivity
167
Table 17 Parameters used to determine failure rate and their values for the Asian and
South American cases
Parameter Asia South America
Failures load & climate moderate (50) moderate (63)
Proportion poor condition equipment low (23) moderate (53)
Spending limit moderate (50) moderate (50)
Use of predictive maintenance moderate (32) moderate (41)
Note that all the inputs to the task failure rate are themselves tasks. The
factors that contribute to proportion of poor condition equipment are
maintenance history and proportion of aged equipment.
As Table 18 reveals, the difference between the two regions derives from
maintenance history.
40
36
proportion aged equipment
32
high
60-70
28
50-60
low moderate
24
40-50
(%)
20
30-40
16
20-30
12
8
X
4
10
30
50
70
90
168
very sensitive to the estimated value of maintenance history. Any
maintenance history level less than about 50 would give the same result.
Table 19 Factors contributing to maintenance spending, with values shown for AU, NA
and WE
AU NA WE
corrective maintenance
low (10) low (23) low (10)
costs
refurbishment costs moderately low (21) low (7) moderately low (27)
replacement costs (treated
low (10) low (10) low (10)
as maintenance)
routine maintenance costs moderate (42) moderate (41) moderate (48)
spending limits unlimited (70) unlimited (70) unlimited (90)
The lower routine maintenance costs from North America are partially offset
by a slightly higher value for corrective maintenance costs, consistent with
higher corrective maintenance costs as a proportion of total maintenance
costs observed in the CIGRE study (reported in Table 1).
Table 20 Factors contributing to routine maintenance costs (for AU, NA and WE)
Parameters AU NA WE
System factors reducing
medium (42) high (75) medium (46)
maintenance costs
Use of online CBM moderate (33) low (26) low (24)
Geographic factor moderate (21) moderate (17) low (6)
Maintenance relative to
at recommended levels less than recommended at recommended levels
manufacturers’
(56) (15) (45)
recommended level
labour costs medium ($19k p.a.) high ($29k p.a.) high ($26k p.a.)
169
Examination of Table 20 reveals two main contributors to the difference in
routine maintenance costs between these cases: The NA case has a higher
value for system factors reducing maintenance costs, and a lower value for
maintenance relative to manufacturers’ recommended levels, both of which
will act to reduce routine maintenance costs. The four factors taken into
account for system factors reducing maintenance costs are redundancy,
flexibility, connectivity and load factor. It is the high flexibility level for North
America that results in the high value for the system factors task: redundancy
and flexibility have greater impact than connectivity on maintenance costs.
170
Table 21 Inputs to the task refurbishment for three regions
Parameter AU NA WE
proportion poor condition
moderate (30) moderate (30) moderate (30)
equipment
use of predictive
moderate (68) low (23) moderate (56)
maintenance
financial driver
moderate (56) high(58) low (23)
maintenance spending
This table suggests that for North American companies, which use less
predictive maintenance, there is less opportunity to utilise refurbishment of
poor condition assets as a strategy, since the level of detection of poor
condition assets will be lower. The financial driver to keep maintenance
costs down may also discourage the use of refurbishment as a maintenance
strategy, (although it may be considered capital investment). In a
comparison between Australasia and Western Europe, the difference is that
in the latter there is less pressure on maintenance costs than in the former.
However, the real strength of the model is the ability it gives the user to
investigate the causes of differences in results between cases. A question
was posed in Section 5.2.8.1: can the model be simplified by identifying
dominant factors? The answer is that while there are clearly core elements
within the model that play an important role in many outputs, different factors
dominate in the different cases studied.
171
The model shows that performance is limited by factors that vary from one
case to the next. Some of these factors are within the control of the
enterprise; others are outside its control. Hence even with the best intentions
it may be not possible for one enterprise to achieve the same level of
performance as another. A corollary to this is that the revenue needs of
transmission enterprises will vary, between utilities and over time according
to current and historical circumstances; this translates to differences in
transmission prices.
• Within the factors that are controllable, some are able to be modified
within a short time-frame; to effect change in other parameters, such
as flexibility, requires a longer time-frame and considerable capital
expenditure.
• Different aspects of performance, eg reliability and maintenance
spending, share some of the same factors of influence. Therefore
changes in policy will affect multiple aspects of a company’s
performance.
• The sensitivity of outputs to inputs around the present levels of those
inputs is different for different cases. The significance of this is that a
solution that is highly effective for one company may be of little use in
the circumstances of another company.
172
5.3 Case Studies for individual companies/countries
In this section, five case studies will be examined. Two of these are from
Asia: a Japanese case representing companies operating in a mature
network and a Malaysian case where the network is in a phase of rapid
development. The other cases are from Australia, Western Europe and
North America. Although the current status of utilities is described, where
possible, the cases have been constructed using data from 1998, in line with
CIGRE study data.
173
330kV, 6084 circuit km of 275kV, 3984 km of 132kV and 528km of 110kV.
There was no increase in length of cables employed.
174
subject to high rainfall and humidity in summer. The south-eastern part of
the state has a high lightning incidence during summer months.
Load growth is moderate, but load factor and plant utilisation are relatively
high compared with other mature networks. Transfer capacity on the grid
varies with different system operating conditions, including which generators
are operating and their level of output. These factors, coupled with
competitive forces and the entry of new generating capacity, have resulted in
considerable uncertainty in planning of network augmentations (Green et al.,
2002). Many sections of the network operate at of near capacity for extended
periods, especially in summer when the grid is more heavily loaded relative
to its capacity (Green et al., 2002). System demand grew by 2.5% from
1997/8 to 1998/9(Powerlink Queensland, 1999), and 4.1% in 2000/1
(Powerlink Queensland, 2001), moderate by world standards. Transformer
utilisation was 32 - 33% for the period, and losses were 4.3 to 4.1 %.
(Transmission losses are higher for Queensland than other Australian utilities
because of Queensland’s long transmission lines.) Load factor for 1998/9
was approximately 69% (ratio energy imported on the grid to maximum ½ hr
generated) (Powerlink Queensland, 1999). Performance of the network in
terms of reliability and availability is high (see Table 7 and Table 9 for
reliability and availability respectively).
175
• Decommissioning some substations (Simpson, 2001).
176
Table 22 lists the input parameters for the case data-set, based on this
analysis and a response to the CIGRE survey.
177
Output parameter Value
Investment in new equipment medium (43)
Loading heavily loaded (40)
Maintenance actions increasing availability moderate (57)
Maintenance spending low (31)
Proportion poor condition equipment moderate (30)
Purchasing efficiencies low (23)
Refurbishment low (18)
Refurbishment costs low (15)
Reliability high: 99-100% (90)
Replacement costs as maintenance low (10)
Replacement on age low (20)
Replacement on condition low (30)
Replacement on failures low (20)
Routine maintenance costs moderate (40)
Spending limits (maintenance) moderate (57)
System Augmentation medium (45)
Factors reducing maintenance costs medium (46)
Use of offline condition-based maintenance moderate (66)
Use of online condition-based maintenance moderate (43)
Use of predictive maintenance high (71)
Results from the model generally appear to be in line with observed activities
and performance. The availability is high, and this is consistent with reported
data (see Table 9). The result reported in the table above may be slightly
reduced by the effect of construction outages. In practice Powerlink has
been able to minimise construction outages in some cases by building new
plant adjacent to older plant, avoiding the need to take circuits out of service
during the construction phase. Transmission companies in more urban areas
may not share the luxury of available space to do this. However, the model
does not take into account the available space when calculating construction
outages.
The model for ease of raising capital is fairly simplistic, and does not take into
account the size of the local capital market. Hence it seems likely that the
model overstates the ease of raising capital in this case. This may slightly
affect the level of equipment replacement.
178
In Sabah the supplier is Sabah Electricity Board (SEB) and in Sarawak the
supplier is Sarawak Electricity Supply Corporation (SESCo) (for generation,
transmission and distribution). The case study will focus on TNB, which has
a high public profile.
TNB is part privately owned, part government owned. In 1997 the Malaysian
government was still the majority stakeholder (Hills, 1997). It has a
sovereign credit rating from Standard & Poor’s of BBB (Standard & Poor's,
2002). It is government-controlled, and its core activities are driven by the
Malaysian government’s industrialisation program (Hills, 1997). The
Malaysian government has a goal of making Malaysia a developed nation by
2020. In January 2001 Asia Week reported that Tenaga was planning to trim
its state ownership from 70% to 51% (Shameen, 2001). The company has
179
been divesting itself of generating plant, and will use the proceeds to retire
most of its debt (Shameen, 2001).
Tenaga has purchased the Sabah Electricity Board, now SESB. Currently a
significant amount of capital is being expended for system rehabilitation work
in Sabah, including upgrading the 66kV network to 132kV and 275kV. This
part of the network had been experiencing significant reliability problems.
Between 1991 and 1995 the transmission and distribution networks were
expanded both to improve coverage and to enhance reliability and stability.
By the end of the Sixth Plan period, 92% of rural households in Malaysia
were served with electricity, compared with 80% in 1990 (Hills, 1997). The
focus of the Seventh Plan (1996-2000) was on expansion and upgrading of
the transmission and distribution infrastructure (Hills, 1997). Of total
expenditure on rural electrification projects by the Federal government, 87%
was for grid extension projects (Hills, 1997). TNB additionally invested RM
100 million in rural electrification projects in the peninsula. The
“unprecedented growth in demand especially in Peninsula Malaysia strained
the TNB system, resulting in supply interruptions” (Hills, 1997).
180
The Malaysian Ministry of Energy, Communications and Multimedia (MECM)
believes that the Malaysian Electricity Market will require investment of the
order of $US 18.5 billion (RM70Billion) over the next ten years: 60-70% in
generation, and the rest in transmission, distribution and retail (Trade
Partners UK, 2002).
In January 1997 Asia Week reported that Tenaga planned to spend some
$US 2 billion a year until 2000 on infrastructure, including $US2.8 billion for
146 substations (Singh and Poh, 1997). Asia Week speculated on whether
TNB would be able to achieve this, given its worsening debt position. Today
construction is continuing but significant parts of the plan have still been
delayed, because the current load growth is slower than predicted at the time
the plan was developed (Mohd Noor, 2002).
181
problem is more severe in Sabah, than on the peninsula, but even so
amounts to a significant loss of revenue.
In 1997 Tenaga announced that it had reduced the outage index by nearly
70% over a 19 month period; the index is in minutes lost per customer per
year. At the time of the announcement it was about 300, down from 1000 in
mid-1995. (In Singapore customer-minutes-lost in 1996 was 40-50, but
Singapore’s system is entirely underground. (Singh and Poh, 1997)) The
current (2002) index for transmission system minutes lost stands at 17
minutes. This index includes all incidents occurring on the transmission
system that cause loss of load (Mohd Noor, 2002).
TNB has a huge variety of equipment: policy has been to buy the cheapest
available that meets technical specification. Some equipment from particular
suppliers has caused reliability problems. Currently there is no emphasis on
life cycle costs for transmission.
Circuit breakers are mainly SF6 – both AIS and GIS (outdoor as well as
indoor). Management has been willing to try new technologies. All oil circuit
breakers have been replaced at around 30 years of age because of number
of failures occurring (Mohd Noor, 2002). These CBs were originally from the
UK.
The climate, which is hot and very wet, with a high lightning incidence (200
lightning days per year) (Mohd Noor, 2002), plays a significant role in
equipment failures. The main causes of failure (Mohd Noor, 2002) are
• Lightning (especially on towers with steel crossarms – used mainly in
hilly areas where extra strength is required);
• Encroachment (people, trees);
182
• Failure of timber cross-arms on towers;
• Degradation of insulators;
• Corrosion on conductors;
• Internal faults on substation equipment;
• Transformer explosive failures;
• Lightning arrestor failures;
• Animals (especially monkeys) shorting out substation equipment.
The regulator is part of the government; the regulatory process is not very
transparent. To ensure that there is adequate supply of electricity to meet
183
future needs the government is keen to encourage IPPs and develop a
competitive generation market. It also recognises the need for sufficient
transmission development. The government is sensitive to reliability and
quality of supply issues but is also sensitive to the price of electricity paid by
consumers. Therefore, although the regulator is generally fairly sympathetic
to the needs of TNB, they do not always get the price adjustments that they
seek.
There are now some customers of TNB needing very high power quality eg
integrated circuit chip manufacturers. These large and influential companies
can apply pressure on TNB on supply quality and reliability.
The full data set for the Malaysian case study is listed in Table 24 below.
184
5.3.2.2 Results of the Tenaga Nasional Berhad Case Study
Table 25 Outputs from fuzzy model for the TNB case Study
Output parameter Value
Availability low (>95%) (38)
Construction outages moderate (37)
Corrective maintenance costs low (10)
Cost of finance moderate (50)
Debt repayments high (70)
Equipment replacement medium (40)
Ease of raising capital moderate (50)
Factors increasing asset costs moderate (47)
Failure rate medium (43)
Failure rate contribution of load & climate moderate (46)
Financial drivers for maintenance spending high (50)
Financial incentive replacement high (50)
Investment cost high (64)
Investment in new equipment medium (50)
Loading heavily loaded (31)
Maintenance factors increasing availability moderate (58)
Maintenance spending high (69)
Proportion poor condition equipment moderate (37)
Purchasing efficiencies moderate (30)
Refurbishment low (5)
Refurbishment costs low (5)
Reliability moderate: 95-98% (62)
Replacement costs as maintenance moderate (37)
Replacement on age low (22)
Replacement on condition low (20)
Replacement on failures moderate (43)
Routine maintenance costs high (80)
Spending limits (maintenance) unlimited (70)
System Augmentation medium (50)
System factors reducing maintenance costs low (26)
Use of offline condition-based maintenance low (26)
Use of online condition-based maintenance low (26)
Use of predictive maintenance low (18)
185
5.3.3 Japanese case study
A “typical” Japanese case study has been developed, based on combined
data for a number of Japanese utilities.
Load growth has been very low in recent years reflecting low growth in the
Japanese economy. Load factor is also fairly low. This has been identified
as a problem that results in low efficiency in the utilisation of plant
(generation and transmission) (IEA, 1999).
186
interest coverage owing to access to low interest rates and high income.
Surprisingly only one of the three Japanese respondents from the CIGRE
survey reported profit as the utility’s motive, the other two nominating
meeting fixed financial targets as their intention.
Operations and maintenance costs are high, and utilities have been
attempting to reduce these in the face of introduction of competition between
utilities. This is evident also from the CIGRE survey data, in which all three
respondents have high maintenance costs, and two of the three are among
the highest in the survey. Only one of the three respondents reported on
refurbishment costs as a proportion of maintenance, but for this one the
proportion was quite high for switchgear, transformers, overhead lines and
cables.
Reliability of supply appears to be quite high (see Table 7). CIGRE study
reliability and availability data for the particular data sets of interest are
scanty. However, the calculated values for unplanned outages per circuit
and per 100km of line are very low, for the two data sets for which required
information was provided. This suggests that the condition of equipment is
very good, and implies high standards of maintenance. The CIGRE study
results suggest that this is predominantly time-based, and that more
maintenance than recommended by manufacturers is undertaken. All three
responses reported doing more maintenance than recommended. In none of
the three responses was condition-based maintenance reported to be a
major strategy employed. One respondent indicated that corrective
maintenance was also used as a strategy.
187
All three responses indicate that age and condition are used as criteria for
replacing equipment. One respondent also nominated number of failures as
a replacement criterion. Two of the three respondents report moderate levels
of aged equipment (bays > 40 years of age) – 19.8% and 22.6%; the third
utility reports 1.1% of aged equipment. Perhaps the utility with the very low
percentage of equipment over forty years of age uses a lower trigger for
replacement than the other two. The three also report moderate levels of
equipment less than 20 years of age, ranging from 41% to 53%, with the
highest of these being from the utility with the lowest proportion of equipment
over forty years of age.
Table 26 summarises the input data used for this case study. The values
from the CIGRE study have been averaged. For True/False answers one
true answer was translated to a level of 33 (out of 100), two trues to 67 and
so on. For the parameter redundancy, a level slightly above the N-1 level
was used.
188
Input Parameter Value
Proportion of young equipment moderate 48%
Redundancy moderate (n-1) (60)
Regulatory support highly supportive (80)
Replacement considered an investment very significant (100)
Revenue sufficiency not a concern (90)
Rugged terrain moderate (60)
Size of company large (65)
Special relationship with vendors no use (30)
Examination of Table 27 suggests the model results are consistent with the
observations noted in the description of this case, with the exception that the
model predicts only moderate levels of maintenance spending. The
elements contributing to the model of maintenance spending are routine
maintenance, refurbishment and corrective maintenance costs, replacement
costs if treated as maintenance, and the spending limits. Maintenance
spending is not constrained by financial considerations in this case. The
189
replacement costs element is low because replacement is always considered
an investment in this case. In this case corrective maintenance cost will be
very low because of the low level of poor condition equipment.
The model also predicts low refurbishment levels, based on the very low level
predicted for poor condition equipment. (The model does not consider the
possibility of refurbishment based on age alone, which is possibly an area for
improvement. However no data are currently available for criteria used for
decisions on refurbishment.) There is some suggestion that the actual level
of refurbishment may be relatively high (see comments in the previous
section). If the predicted level of refurbishment level were higher this would
have pushed the predicted maintenance spending to a higher level also.
This may indicate an unnecessarily high level of spending on maintenance
and refurbishment in particular, which could possibly be reduced significantly
if more condition-based maintenance were used.
190
5.3.4 US utility case study
This case study is based on a utility not represented in the CIGRE survey. In
building the data set for this case a greater number of assumptions have had
to be made than for some of the other cases. The North American base case
has been used as a starting point for developing this case with adjustments
made based on available information about the practices of this company
compared with typical North American companies.
191
Share-price is sensitive to budget over-runs, so spending is monitored
closely throughout the year. If funds run short some projects need to be cut.
Risk is taken into account in decisions associated with curtailing a project,
including the risk of double contingencies. Money can not be tied-over to the
following year, so it is critical that all operations and maintenance money is
spent.
192
• Assign to each tie station a criticality value (high or low for transmission,
and high, medium, low for distribution stations) based on an evaluation of
• legal;
• social/political; and
• environmental criteria,
in combination with the equipment failure criticality assessment.
• Develop maintenance tasks, based on collected maintenance information
and the FM/FC library. The equipment’s criticality rating is used to
determine the frequency of the preventive maintenance.
This utility is considered one of the best performing of all US utilities6. Its
system performance and attention to customer requirements have meant that
it has not been subjected to as much regulatory pressure or reform as many
other utilities.
6
Duke Energy has been named in Fortune Magazine as Most Admired Company in the
Energy Sector (2002-3) and Most Admired Company – Gas & Electric Utilities (1999-2001)
based on criteria including (among others) Management and Product Quality, Long-term
Investment Value and Use of Corporate Assets.
193
Input Parameter Value
Redundancy moderate (n-1) (50)
Regulatory support highly supportive (75)
Replacement considered an investment very significant (86)
Revenue sufficiency not a concern (70)
Rugged terrain not rugged (20)
Size of company medium (60)
Special relationship with vendors some use (40)
Comparison the two sets of results suggests that, in the Duke Power case,
corrective maintenance costs are slightly lower and the financial drivers on
maintenance spending greater than the average for North America.
Corrective maintenance costs are slightly lower because of a lower failure
rate (10 compared with 24 for the NA case). This results from higher use of
194
predictive maintenance (50 compared with 23) and lower proportion of poor
condition equipment (18 compared with 30). The difference calculated level
of financial drivers for maintenance (90 compared with 58 for NA) is
influenced most strongly by the parameter profit-as-intention, for which the
Duke case has been assigned a value 90, based on an interview with staff,
and the NA case has a value 58, based on 4 of 7 North American
respondents to the CIGRE study indicating that profit was the main goal of
the company.
Ownership of the National Grid Company was initially by the twelve Regional
Electricity Companies (RECS), but in 1995 the UK government required the
RECS to divest themselves of their shares. NGC became a publicly traded
company in December 1995. As a business NGC has been very successful:
it is part owner of transmission networks in Argentina and Zambia and owner
of a transmission and distribution company in the New England, USA (NGC,
USA). It also has interests in interconnectors in Australia, the USA and the
UK. In 2002 NGC merged with Lattice, a holding company for the England
and Wales gas transmission company Transco, to become NGC Transco.
195
NGC, UK, is the part of this business that owns and operates the electricity
transmission network of England and Wales. It is a regulated monopoly
operating under a price capped incentive-based (RPI – X) regulation. The
regulation scheme has generally been seen to be successful in reducing
operations and maintenance costs (EIA, 1997).
The first ten years after electricity deregulation saw the end of centrally
planned generation and the proliferation of privately-owned generators. NGC
is required to connect these generators into the transmission grid within
ninety days(Urwin, 1999). The new generation plant, largely combined-cycle
gas-fired, has been installed with relatively low lead times, sometimes
replacing other more expensive generation. The notice for closures of
generation is even shorter – a minimum of six months. These changes in
generation patterns have resulted in changes to loading and reactive support
requirements on the network. This has led NGC to install significant amounts
of reactive compensation equipment to manage changing voltage support
requirements (Urwin, 1999). To manage the rapidity of changes in voltage
support requirements they have developed transportable Static VAR
Compensators (SVCs). Between 1990 and 1998 some 6000 MVAR of
196
capacitors and 3300 MVAR of SVCs were installed on the network (Urwin,
1999).
Load is much higher in winter than summer owing to heating loads. Most
outages are planned over the summer period. Very little live-line working,
and no live substation work is done, partly because of health and safety
considerations, and partly because of the extra time required for doing the
job under live conditions. However, it is gradually becoming more difficult to
take circuits out of service for maintenance, because of increased loading on
circuits generally.
While the climate is not usually severe, there are occasionally severe storms,
and high levels of faults are often associated with these. Salt pollution is
probably the worst climatic/geographic issue. Sometimes silicone coatings
are put on insulators to reduce flashover and sometimes substations are built
in-doors to protect from pollution.
197
(Urwin, 1999). Refurbishment is done in order to enable plant to reach
planned life, and mainly only on pressurised head air blast circuit breakers,
which need a mid-life refurbishment to achieve planned life (Allison and Jay,
2001).
198
the year. The information is used as a reference source to support the
capital replacement plan, including replacement priority and for the
improvement of asset management policy. Work has been undertaken to
improve the efficiency of the asset health review process, and to translate the
knowledge gained into more accessible formats. One initiative to improve
the quality of data is the use of hand-held computers for logging of
inspections; data transfer directly to the maintenance database.
Table 30 summarises the input parameters derived for this case study.
199
Input Parameter Value
Number of failures as replacement criterion significant (58)
Pilfering low (10)
Profit as Intention Yes (80)
Proportion of aged equipment low 2%
Proportion of young equipment moderate 44%
Redundancy moderate (n-1) (50)
Regulatory support reasonably supportive (65)
Replacement considered an investment very significant (100)
Revenue sufficiency not a concern (80)
Rugged terrain not rugged (20)
Size of company large (70)
Special relationship with vendors no use (30)
from the CIGRE study7, confirms that the maintenance spending (at the time
of the survey) was high compared with the average for Western Europe.
7
filtering on the basis of {region = WE; size = large, ownership = private; functions = transmission only}
200
Note that the case description above suggests that NGC are taking steps to
reduce routine maintenance costs (eg through use of the RBSE tool and
maintenance optimisation studies).
Figure 32 shows that maintenance costs for the NGC are very sensitive to
the efficiency with which routine preventive maintenance is performed. Thus
the measures being implemented to improve maintenance efficiency should
be very effective in reducing costs in this case.
100
80 maintenance
spending
60
40 routine
maintenance
20 cost
0
0 20 40 60 80 100
maintenance relative to manufacturers'
recommended levels
To illustrate this premise reliability will be examined for the TNB case: for this
case study the model suggests that there may be some scope for improving
reliability of supply. Reliability of supply is a function of system design and
201
equipment reliability. In the model there are four attributes for the task
reliability: flexibility, connectivity, redundancy and failure rate. Failure rate is
also a task; it has four subtasks as inputs – failures load and climate (the
contribution of load and climate to failure rate), use of predictive
maintenance, proportion of poor condition equipment and spending limits
(maintenance). This last factor only comes into play if maintenance spending
is severely limited, which not the true in this case. The model calculates that
use of predictive maintenance is low for TNB. If use of predictive
maintenance is increased then this may reduce failure rates and hence
improve reliability of supply. Figure 33 suggests that only a modest increase
in reliability is achievable by increasing use of predictive maintenance in this
case. However, it may be worthwhile to pursue this, if the cost of
implementing predictive maintenance is not great. It is clear that, in this
case, other factors limit the effectiveness of this strategy. Likewise, reducing
proportion of poor condition equipment has little appreciable effect on
reliability.
100
reliability - model
90
80
70
60
50
0 20 40 60 80 100
use of predictive maintenance
202
80
reliability - model
60
40
20
0
0 20 40 60 80 100
failure contribution of load & climate
Figure 34 Sensitivity of reliability to failure rate contribution of load and climate for
TNB case
Figure 34 suggests that the failure rate contribution of load and climate has
more effect on reliability for this case. The current point of operation (failure
load and climate = 46, reliability = 64) has been included as a point on the
graph. For values above the current value the model predicts a rapid drop in
reliability, but reducing this value to 40 or below, increases reliability only
slightly to 66, or the moderate-high level. This analysis suggests that there
are few opportunities to make major improvements in reliability from
strategies that affect equipment performance in this case.
203
40
36
high
32
28 connectivity
(normalised
moderate
24
value 1 to
20
100)
16
x
12 85-95
low
8 75-85
4 65-75
10
30
50
70
90
55-65
low moderate high
45-55
flexibility (% )
204
The task availability contains four attributes, which are listed in Table 32 with
associated values for the Powerlink case.
Table 32 Factors contributing to availability and their values for the Powerlink Case
Attribute Value
construction outages low (27)
failure rate low (10)
flexibility low (34)
maintenance actions increasing availability moderate (57)
Inspection of this table suggests that there may be some scope for gains by
increasing flexibility and/or by increasing the level of the task maintenance
actions increasing availability. The factors that contribute to the maintenance
actions task and their values are shown below in Table 33.
Table 33 Maintenance activities increasing availability for the Powerlink Qld Case
Attribute Value
combining maintenance activities( by circuit) medium (63)
live working low 20%
use of online CBM moderate (43)
use of predictive maintenance high (71)
90 maintenance activities
low moderate high.
70
by circuit %
combining
x
50
30 87-92
10 82-87
10
30
50
70
90
77-82
low moderate high
72-77
live working %
67-72
205
undoubtedly increases risk to workers. As the discussion for this case
explained, Powerlink is now implementing both these strategies.
100
low moderate high.
80
availability
60
40
20
0
0 20 40 60 80 100
low moderate high
use of online CBM
Figure 37 illustrates the predicted effect of increasing the use of online CBM
on availability for the Powerlink case8. Online CBM also contributes to
predictive maintenance in general. Increases in online CBM and predictive
maintenance both have potential to increase circuit availability. In this case,
analysis suggests that sensitivity to this parameter is not high around the
current level (calculated from the model as moderate (43)). Hence,
Powerlink would have to increase its use of online CBM significantly to
achieve a modest improvement in availability. Since the predicted value of
online CBM is fairly high by world standards, increasing online CBM
significantly might prove to be an expensive exercise, if it involves retrofitting
condition monitoring to older equipment.
8
Note that the wavy effect of this graph is a function of the use of fuzzy rules. In reality the
graph is likely to be smooth.
206
100
The examples in Section 5.4 illustrate several important features of the fuzzy
AM model:
• The fuzzy model can be used to identify options for performance
improvement.
• It can give an estimate of the likely effectiveness of different options,
given existing conditions. The time-frames for these options will also
range from short- to long-term.
• It can identify barriers to improvements in performance.
207
The model demonstrates that performance among transmission utilities, and
their ability to improve it, may be limited by existing factors such as design of
existing network, and the rate at which the network can be modified.
External factors like climate type and severity may also impact on potential
best performance. The conclusion that can be drawn from these studies is
that solutions cannot necessarily be translated from one utility to another:
options must be analysed in the context of existing conditions for each
enterprise.
208
6 Investigations using system dynamics modelling
In Chapter 4 system dynamics modelling was identified as a potentially useful
tool for investigating, in detail, certain core elements of the conceptual AM
model constructed in Chapter 3. Analysis of the causal loop diagram (Figure
15) showed that there were complex feedback loops involving maintenance,
failure rate, replacement and refurbishment. The relationship between
maintenance and failure rate was found to have a time lag, dependent on
rate of the deterioration of equipment condition. Because of the feedback
loops and time-dependencies, these types of relationships are difficult to
model with a fuzzy rule-based model, but are more easily represented using
a system dynamics model.
209
expressed in terms of how rates affect levels and levels affect rates. In
systems dynamics, models tend to be built at an aggregate level with rates
regarded as continuous through time (Pidd, 1998 p230). For example, in this
study we deal with asset populations, their distributions and failure rates
rather than individual assets.
In this chapter, models are developed, using the system dynamics software
package Stella Research (High Performance Systems Inc, 2002), to examine
the relationships between asset population age- and condition-distributions,
and maintenance, refurbishment and replacement policies. The effect of
maintenance and replacement strategies on asset value, revenue and profit
will be examined, assuming straight line depreciation, and revenue cap
regulation in the form applied to Australian transmission utilities (ACCC,
1999a). The impact of asset management policies on network performance
will also be studied in terms of failure rate of equipment.
210
half the current value of dt; if there is a difference then dt is too large. The
Stella program documentation (High Performance Systems Inc, 2002)
suggests this method, and also that dt should not be larger than 0.5 the
shortest delay in the model.
For the current application the 4th order Runge-Kutta numerical integration
method has been employed. A dt of 0.25 (years) was found to produce
satisfactory results.
One problem that has become apparent, during the verification process, is
that of prioritisation of multiple flows from a stock that is not permitted to
become negative. If the model calls for greater outflows from a stock than the
current level plus inflows, then the Stella program assigns outflows according
to its internally generated priority levels. The internally generated priorities
do not necessarily match the priorities required for the model. To overcome
this problem it was found necessary to override the program, by explicitly
apportioning outflows, in cases of limited supply. An example, in which this
measure was necessary, is for retained earnings (Section 6.10). In the
model there are outflows from retained profit of interest repayments,
dividends, capital funding of assets and a flow to adjust the debt level so that
211
the intended gearing ratio is maintained. It was found necessary to force the
program to assign the combined revenue plus retained earnings to cover
interest payments first, capital payments second, adjustments to the debt
level third and dividends last. Without these modifications capital funding, for
example, was given higher priority by the program than interest repayments.
The validity of a model is judged on its suitability for its intended purpose
(Forrester, 1961): a model that is useful for one purpose could be misleading
if used in a manner for which it was not intended. Coyle (Coyle, 1977 p181)
states that establishing model validity is “unquestionably one of the most
difficult areas in management science.” He defines validation (Coyle, 1977 p
181) as the process by which we establish sufficient confidence in a model to
be prepared to use it for some particular purpose.
Ideally in order to validate a model one would compare it directly with the
system that it simulates. However, Coyle contends that, in practice, it is
seldom possible to make a change to a real system and observe its effect: in
management systems it is very difficult to isolate the effect of policy changes
from other things that have happened to the system. Therefore true
validation of systems dynamics applications in management science is not
possible (Coyle, 1977 p182), and the best that can be achieved is a
confidence-building exercise. Coyle proposes that the system dynamics
modeller address the following series of questions (Coyle, 1977 p182):
• Are the system boundaries correct? The model should include those
elements that can alter behaviour, but keep in mind the purpose of the
model.
• Are there any gross errors (for example, negative values of items that
should only be positive or values that are beyond reasonable
bounds)?
• Is there a correspondence between the model structure and the
system? The decisions functions in the model should reasonably
reflect those actually used.
• Are the parameter values correct? Coyne suggests that this may not
be a very important consideration, as the dynamics of a system are
212
usually not affected much by most of the parameters, provided they
are within a fairly broad range. However there may be a few
parameters that are critical to the dynamics of the system.
• Does the model reproduce system behaviour sufficiently well? Coyle
states that in practice it is seldom possible to test this: data on policies
are scarce and rarely are the policies consistently applied. The
available data will also never cover all model outputs so many
variables must remain untested. Coyle advises that it is seldom
justified to attempt to apply statistical verification of system dynamics
models.
In this particular application, the purpose of the model is to examine the
impact on system and financial performance of different policies for
maintenance and replacement in transmission systems.
213
Any gross misrepresentations, (such as those arising from the prioritisation of
outflows, as described above) have been corrected during the development
of the model. Testing and verification, as recommended by Pidd (Pidd, 1998
p158), have been undertaken throughout the development of the model.
Likewise, validation of sections of the model has been undertaken as an
integral part of the development process. For example, in Section 6.15,
addition of augmentation at a constant rate of 3% per annum (a value not
untypical of mature networks today) was found to increase the number of
assets on the system, in the longer term, to an impracticable level. This
prompted consideration of the relationships between load growth, system
maturity, size and number of assets. It also led to insights about the effects,
of system augmentation level and system maturity, on asset management
policies employed by transmission enterprises in developing countries
compared with those in developed countries.
214
• Dividends are modelled, but levels have been set to zero.
Comparison is made on the basis of retained earnings as this avoids
having to choose a level for dividends.
• The relationships between network maturity and load growth has been
estimated, based on published load growth figures and estimated
maturity (modelled graphically) (Section 6.15);
• Relationship between asset average value and network maturity
(modelled graphically) (Section 6.15);
In this model the age-related failure rates are generated based on the
condition-related failures, and rules described in Section 6.6. Failure rates,
as a function of age for different types of transmission equipment, could
potentially be obtained (with some effort) from maintenance databases of
transmission enterprises. However, failure rates as a function of condition are
likely to be more difficult to acquire, unless the utility has developed condition
indices for its equipment (for instance, of the type suggested in (Balzer et al.,
1998)). Actual values will vary with the type of equipment being examined.
Since a generic asset has been used for this study it was not considered
necessary to attempt to find particular values. If this model were applied to a
particular asset class, in an extension to this research, then it would be
appropriate to model the parameters more precisely. Instead, the overall
failure rate predicted by the model is compared with some published
information on transmission equipment (see Section 6.6.1).
215
The relationships between maintenance effectiveness and degradation, and
predictive maintenance and detection of poor condition assets are more
difficult to validate, as no data currently exists for these types of relationship.
Justification of the shape of the relationship curves has been attempted by
explaining the reasoning behind choice of shape (see Section 6.5).
Likewise the relationships between network maturity and load growth and
network maturity and average asset value are estimates of parameters for
which no data currently exist.
216
For repairable systems a constant failure rate (rate of occurrence of failure
ROCOF) is often assumed. This assumption is valid if all elements in the
system exhibit a constant failure rate, which is generally not the case for
mechanical equipment, or if there is no dominant failure mode, in which case
the mixing effect of replacements and failures leads to an approximately
constant failure rate (Davidson, 1988 p38-9). The assumption of constant
failure rate also requires that all repairs of equipment restore it to “as good as
new condition” (Davidson, 1988 p39). The constant-failure-rate assumption
may be invalid in cases where equipment is replaced by new technology that
is more reliable than the original equipment; this can result in reliability
growth over time. If equipment is not repaired to “as good as new” condition
there will be an increasing failure rate with time.
For transmission equipment the assumption of constant failure rate may not
be valid. For example in the study of circuit breaker failures (Hastings and
Crisp, 2001) the failure rate illustrated in Figure 14 shows an increasing trend
with age. Since circuit breakers have been the subject of significant
technological development of the past forty years (Knobloch et al., 2000) this
may be a combination of increasing age-related failure rate and reliability
growth resulting from technological improvements. The assumption of
perfect repair is also doubtful because of the likelihood of imperfect
maintenance (see also the discussion on this topic in Section 6.8) and the
existence of some failure modes for which repair is not feasible. In analysis
of electrical power system problems an assumption of constant failure rate is
often used for reliability analysis (for example, (Brown, 2001b)), as this
greatly simplifies the analysis. However, in replacement decisions for major
equipment (Hastings et al., 1999) the increasing risk of failure with age may
be taken into account.
217
remaining life for transformers (Allan, 1991). Underground cables also exhibit
failures associated with ageing of insulation. Ageing in insulation is a
common cause of degradation in the condition of transmission system
equipment. All power system equipment relies on insulation for continued
operation. The rate of ageing is dependent on the nature of the combined
external stress and the corresponding inherent resistance of the insulating
materials to these stresses (Bernstein and Brancato, 1993). The external
stresses to which insulation is exposed include mechanical forces, electrical
stresses (kV/cm) and temperature. These external stresses are present to
various degrees throughout the life of electrical equipment, so that the
equipment should be expected to show an increasing hazard rate from
insulation related causes with age. To the extent that the insulation is
integral to the equipment (eg in transformers, reactors, capacitors) the
degradation caused by insulation ageing could be considered non-repairable.
By contrast, in overhead lines, insulators can be replaced individually. This
failure mechanism is therefore avoidable by maintenance, and the effect of
replacing failed insulators, in the course of preventive maintenance, may be
to flatten the overall age-related ROCOF (Davidson, 1988 p38-39) from this
cause, for this class of equipment, to a pseudo-constant value. Corrosion is
another major source of failure in overhead lines (both in the conductor and
insulator strings) (Aggarwal et al., 2000). Degradation of mechanical
properties of transmission lines may also be exhibited, in association with
corrosion or heat related effects. While corrosion is repairable to some
extent, it is difficult to repair to as good as new condition, in which case an
increasing ROCOF could be anticipated (as discussed above).
For the present study an allowance is made for the possibility of increasing
failure rate (ROCOF) with age. The model assumes that
• There is a relationship between the age and condition of equipment;
218
• Preventive maintenance can affect the rate of degradation of overall
condition of assets (but cannot eliminate degradation entirely);
• Refurbishment can restore equipment to “as good as new” condition;
• Repair related to a particular failure condition will not alter the overall
condition of the asset.
The population of assets is modelled using a structure called the main chain,
which is commonly used for any sort of ageing process (Richmond, 2001
p101). In this simple model (Figure 39) there are four states, corresponding
to young (YA), mid-life (MLA), aged (AA) and very aged assets (VAA). It is a
feature of the main chain structure that, in steady state, the asset population
will distribute itself in proportion to the average residence time associated
with each state (stock)(Richmond, 2001 p101)9.
In Figure 39 large rectangles represent stocks of items, and the solid arrows
indicate the direction of flows. The circles represent ordinary variables (also
called converters), the values of which may be constant or calculated.
Circles with plus signs denote summers. The summer is a short-hand way of
indicating a summation of a number of inputs. Dotted lines show
relationships. For instance, the flow rate between young assets and midlife
assets, is defined as (young assets 0 to 9 years)/(young yr range), where
young yr range is the number of years represented by the range, in this case
9
It is noted that there are strong parallels between the main chain structure in system
dynamics modelling and Markov modelling. The Markov transition probabilities are similar to
the failure rates and rates of transition from one state to another in the system dynamics
formulation.
219
a constant, 10. Similar relationships are defined for the other flows between
states.
+ Sum of
all replaced MLA AA VAA
replaced replaced replaced
YA yr range MLA yr range AA yr range
young assets mid life assets aged assets very aged assets
(0 -9 yrs) (10-29 yrs) (30-39yrs) (40+ yrs)
MTBF
early MTBF MTBF MTBF MTBF
early random random random random
randomly VAA
failing randomly randomly MLA MLA failing failing
randomly
failing failing failing failing
failing
+
Sum all MTBF
MTBF MTBF
failing VAA
MLA AA
Failures of assets can occur in any stage of an asset’s life. Random failures
can occur at any time. Infant mortality failures (early failing in the diagram)
can occur in the early stages after commissioning. Age-related failures
(wear-out) can occur in later stages. Failure rates are calculated by the
number of assets in a stock (state) divided by the mean time between failures
(MTBF) for each failure type. This version of the model assumes all assets
that fail are replaced (indicated on the diagram as a summer labelled sum of
all replaced). Since the number of assets in each age group becomes
constant in steady state, the overall failure rate is constant when the system
reaches steady state.
220
avenue for further research. For this study an expected life, for depreciation
purposes, of forty years is assumed.
Total depreciated value = value per asset/life expectancy of assets *
(young_assets__0_to_9_years*(life expectancy of assets- age of young assets) +
mid_life_assets_10_to_29_years*(life expectancy of assets- age of ml assets) +
aged_assets_30_to_39_yrs*(life expectancy of assets – age of aged assets)) (8)
Note that all replacement values are in present-day values. It is assumed for
the purpose of modelling that there is no variation in the real cost of
replacements with time, for replacements which have the same technical
capacity as those assets being replaced.
For this application will be assumed that assets are in either good condition
(GCA) or poor condition (PCA). These states are connected using a main
chain structure (Figure 40). Equipment can fail randomly and assets in poor
condition can fail from condition-related causes. For example, a transformer
with poor condition paper insulation has a higher probability of failing if a
lightning fault occurs on a connected circuit, than if the same fault occurs
near a transformer in good condition (also depending on the fault current). In
this diagram the flow associated with early failing is shown as a function of
GCA. It is, however more correctly modelled as a function of the age of the
asset. In the following sections the linkage to the age and condition models
is described, and this will be corrected.
221
fraction
PCA refurbished
sum all
failing
GCA randomly MTBF randomly PCA
early failing random failing failing MTBF
failing
PCA
MTBF GCA
early failure
10
It is also a function of other factors such as loading and duty as discussed in Chapter 3.
222
fraction detected
PCA refurbished
sum all
failing
GCA randomly MTBF randomly PCA
early failing random failing failing MTBF use of
failing
PCA predictive
MTBF GCA maintenance
early failure
223
1
0.6
0.4
0.2
0
0 20 40 60 80 100
Use of predictive maintenance %
224
fraction deteriorating
0.12
0.1
0.08
0.06
0.04
0.02
0
0 0.2 0.4 0.6 0.8 1
1- maintenance effectiveness
225
• The number of PCA failing is conserved in the age-based
representation. It is assumed that poor condition assets are in the
highest age groups (i.e. failed assets are first taken from very-aged
assets group, then remainder from younger groups in order of
decreasing age.) Figure 44, below illustrated these relationships in a
diagram simplified to maintain clarity.
replacement of very aged assets
very aged
young assets mid life assets aged assets
assets
(0 -9 yrs) (10-29 yrs) (30-39yrs)
(40+ yrs)
good
poor condition
condition deterioration
assets (PCA)
assets (GCA)
early randomly
randomly PCA
failing failing
failing failing
Figure 44 This diagram shows the links between failure of poor condition assets and
age-related failures.
226
• For aged assets there are also two limiting conditions:
1. The MTBF of aged assets is not less that the MTBF PCA.
2. Number of assets failing per year cannot be greater than the
number of assets in poor condition failing per year less the very-aged
assets failing from the same cause.
• The same applies for mid-life assets except that the number of assets
failing per year is limited by number of assets in poor condition failing
per year less the combined very-aged and aged assets failing per
year.
Since the model is combined from two main-chain structures and the total
asset population is conserved, it also reaches a steady state condition.
227
replacement of very aged assets
young assets mid life assets aged assets very aged assets
(0 -9 yrs) (10-29 yrs) (30-39yrs) (40+ yrs)
early randomly
failing failing randomly PCA
failing failing
Figure 45 This simplified diagram illustrates the links between replacement of poor
condition assets and the replacement of assets from different age groups, for
condition-based replacement.
There are some limiting assumptions in this model.
• The effect of remedial maintenance has not been addressed in this
version of the model – it has been assumed that all equipment that
fails will be replaced. The effect of repairing failed poor condition
assets will be considered in Section 6.8.
• It is also assumed that the transmission enterprise is able to claim
revenue for failed assets that have been replaced. This is a
reasonable assumption, except that if revenue is set in advance (say
for five years) the company may or may not be able to recoup the
revenue for a replacement asset until the next revenue reset.
228
A range of tests was performed to check the validity of the model, in addition
to the rules described previously:
• Total failures per annum must be the same in age and condition-
based representations.
• Total failures per annum from each type of failure (infant mortality,
random and wear-out) must be the same for the age-based
representation and the condition-based representation.
• Total number of assets must be conserved (and equal) for age and
condition-based representations.
The model can be used to investigate the sensitivity of failure rate and asset
age-distribution to various parameters and strategies. A number of possible
scenarios are examined in the following sections.
200
Poor Condition
150
Assets
100
50
0
0 0.2 0.4 0.6 0.8 1
Maintenance Effectiveness fraction
229
As maintenance effectiveness is increased the proportion of assets in good
condition increases (Figure 46). This means that fewer poor-condition assets
fail (Figure 47) and fewer are refurbished or replaced (on the basis of
condition). As a result the number of aged and very aged assets increases
(Figure 48), and the depreciated value of the asset population is reduced
(Figure 49).
7
6
average failure rate
5
4
% pa
3
2
1
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
maintenance effectiveness fraction
230
800
600 ya
assets mla
400
aa
200 vaa
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
maintenance effectiveness fraction
1000
depreciated asset
800
600
value
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
231
The average failure rate for the whole asset population is in the range 6 to
1.8% over the maintenance effectiveness fraction range of 0.1 to 0.9 for
MTBF PCA of 2 years. For MTBF PCA of 10 years, maintenance
effectiveness has less effect: the range of values is 3 to 1% for the range of
maintenance effectiveness from 0.1 to 0.9.
Note that failure rate, indicated in this study, is of the right order for
transmission equipment. A CIGRE study into failure in transformers(CIGRE
WG 12.05, 1983), which considered only transformers not more than 20
years old found an overall failure rate of 2% per annum. If older equipment
had been included in the survey this figure could be slightly higher. Taking
only equipment in the range 0 to 30 years (young, mid-life and aged
equipment) the range of failure rates over the same maintenance
effectiveness range is 6 to 0.6% and 3 to 0.49% for the cases with MTBF
PCA of 2 and 10 years respectively.
11
Major failure – complete failure of a circuit breaker causing loss of one or more
fundamental function. Requires removal of the breaker from service within 30 minutes.
Minor failure – failure (inability to perform a required function), other than a major failure.
232
examined. To achieve this, the use of predictive maintenance is varied from
10 to 90%, which in turn, affects the proportion of PCA detected.
For this study a maintenance effectiveness fraction of 0.7 was used. 50% of
detected poor-condition equipment is replaced and 50% of poor condition
equipment is refurbished. For this example the MTBF PCA is assumed to be
2 years.
1000
800
assets
600 GCA
400 PCA
200
0
0 50 100
use of predictive maintenance %
Figure 50 Variation of the condition of equipment within the asset population with use
of predictive maintenance
233
failure rate % assets
3
2.5
2
p.a. 1.5
1
0.5
0
0 20 40 60 80 100
use of predictive maintenance %
600
500
young assets
400
assets
mid-life assets
300
aged assets
200
very aged assets
100
0
0 50 100
use of predictive maintenance
%
234
remains unchanged while the condition is restored: assets refurbished to
good condition may remain in service for some time beyond when their
depreciated value declines to zero.
depreciated value of
600
500
400
assets
300
200
100
0
0 20 40 60 80 100
use of predictive maintenance %
14
12
10
8
6
4
2
0
0 20 40 60 80 100
use of predictive maintenance %
235
PCA replaced, but one with 50% of detected PCA refurbished and the other
with 0% refurbished.
600
400
200
0
0 20 40 60 80 100
use of predictive maintenance %
50% 0%
Figure 55 Depreciated asset value for the case of refurbishment of 50% of detected
PCA and no refurbishment of PCA. The replacement of detected PCA is held constant
at 50%
Refurbishment can be either treated as a maintenance expense or
capitalised. If it is expensed costs can be recovered (provided they are
allowed by the regulator). On the other hand, if the refurbishment is
capitalised, a profit may be earned on the investment. If the book value is
modified then some return of investment could also be achieved. In practice
there may be some uncertainty over the additional life that refurbishment of
an asset can achieve. Thus there may be a risk that return on and of
investment may not be achieved if refurbishment is capitalised.
12
In the case of Electranet the ACCC quarantined the refurbishments from optimisation for
10 years and allowed depreciation of the refurbishment costs over the same period,
effectively addressing the risk posed by optimisation.
236
company may not be able to obtain full return on investment or return of
investment. For some types of equipment refurbishment is perhaps the most
appropriate type of maintenance – transmission lines, for example. For the
case where refurbishment is necessary, this study highlights the importance
of revaluing refurbished equipment to appropriate levels.
Note that if one compares the failure rate of the 100% replacement of
detected PCA case and the 50% refurbishment, 50% replacement case,
(Figure 51) the model predicts slightly lower failure rates for the latter. This is
because the infant mortality failure rate of refurbished equipment has not
been modelled.
A scenario where less than all detected PCA are replaced or refurbished
might arise where the utility has limited financial resources. This situation is
quite common. It is likely to occur when the level of augmentation of the
system is high, and debt levels are also high, as has been evident in a
number of developing countries. It may also occur when circumstances lead
to a loss of revenue (such as during the period of transition from communist
to capitalist economy in countries of the former Soviet Block). Even in
developed countries utilities will not always have the capital to undertake all
237
projects simultaneously. The need to smooth capital spending over time is a
factor often taken into account in replacement plans (CIGRE WG 37.27,
2000).
3.5
failure rate % p.a.
3
2.5
2
1.5
1
0.5
0
0 20 40 60 80 100
use of predictive maintenance %
50% 100%
Figure 56 Comparison of failure rate for 50% replacement of detected PCA and 100%
replacement of detected PCA. Refurbishment of PCA is not undertaken in either case.
MTBF PCA is 2 years for both studies.
asset value (units)
total depreciated
600
580
560
540
520
500
0 20 40 60 80 100
use of predictive maintenance %
50% 100%
Figure 57 Total depreciated value compared for cases with 50% and 100%
replacement of detected PCA. Refurbishment of PCA is not undertaken in either case.
MTBF PCA is 2 years for both cases.
238
6.7 Age-based replacement and the impact on asset value and failure
rate
In this model it is assumed that fully depreciated assets are replaced. This
translates to replacing equipment in the very-aged assets group. When age-
based replacement is undertaken, instead of condition-based replacement,
some equipment in poor condition may not be replaced and some equipment
in good condition may be replaced. If a strong relationship between age and
condition exists, a reasonable approach is to assume that the very-aged
assets to be replaced are in poor condition. If more very-aged assets are to
be replaced than the number of items in poor condition then the remainder
are replaced from those in good condition. In practice there is likely to be
more variability in the condition of aged equipment than this simple model
suggests, because of the effect of such things as loading, ambient
temperature and duty.13
The construction of this model is very similar to the previous version, except
that now there is a link from very aged assets being replaced to PCA being
replaced and GCA being replaced (as illustrated in Figure 58). The link from
use of predictive maintenance to PCA being replaced and the links from PCA
being replaced to very aged assets being replaced, aged assets being
replaced and mid-life assets being replaced are all removed. There is no
replacement of assets aged less than forty years because only fully
depreciated assets are replaced. As in previous studies, refurbishment is
undertaken on the basis of condition.
13
For instance the duty for circuit breakers switching reactive loads is more onerous than for
those switching unity power factor loads. Breakers switching reactive devices are also likely
to operate more frequently since they are often switched on a daily cycle based on line
loading. The breakers with reactive loads are therefore likely to suffer wear-out earlier than
those with unity power factor loads.
239
replacement of very aged assets
young assets mid life assets aged assets very aged assets
(0 -9 yrs) (10-29 yrs) (30-39yrs) (40+ yrs)
replacement of GCA
early randomly
failing failing randomly PCA
failing failing
240
effectiveness, the number of assets in poor condition is high, and thus there
will be a high failure rate of poor condition assets. For high failure rate, and,
therefore, high level of replacement of failed assets, the number of assets in
the very-aged assets group is low. However, as maintenance effectiveness
increases the number of very-aged assets increases, while the number of
poor condition assets is reduced; therefore the proportion of poor condition
assets replaced annually is very high. Hence the number of failures of poor
condition assets becomes quite low. For maintenance effectiveness 0.8 and
above, the model predicts that all PCA, and a small number of good condition
assets, are replaced annually. This accounts for the levelling of the failure
rate graph at maintenance effectiveness fraction of 0.8.
10
failure rate (% p.a.)
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness
MTBF of PCA:
5 yrs 10 yrs 2 yrs
This age distribution results in a total depreciated value that decreases with
increasing maintenance effectiveness (Figure 61), but levels off at
maintenance effectiveness of 0.8.
241
1000
800
assets 600
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness
1000
(asset value units)
800
600
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness
242
PCA are being replaced.
10
failure rate % p.a 8
6
4
2
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
1000
800
(units)
600
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
Compared with the case with refurbishment, the total depreciated value of
assets, for the case with refurbishment, is slightly higher (Figure 63)
243
because, as in previous models, no revaluation of refurbished assets has
been undertaken.
10
failure rate % p.a.
8
6
4
2
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
244
assets, which is higher for higher maintenance effectiveness fraction. In
practice, because there are likely to be poor-condition assets with age less
than the replacement cut-off, as previously explained, the age-based
replacement strategy is not likely to be quite as successful at high
maintenance effectiveness fractions as this simple model predicts.
Nevertheless it would appear from the results that either age- or condition-
based replacement strategies can produce satisfactory results (in terms of
system performance) provided adequate effective maintenance is
undertaken.
total depreciated value
1000
800
(units)
600
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
condition-based age-based
245
6.8 Remedial maintenance of poor condition assets
Although, for the purpose of reliability analysis it is often assumed that repair
is to “as good as new” condition, in practice this often not the case
(Davidson, 1988 p12). Davidson explains that this can occur when repair of
one element in a device leaves other parts still in a “wear out” condition. This
means, in reliability terms, that the condition after repair may be “as bad as
old”.
246
Figure 66 and Figure 67 show the impact of these changes on the model
outcomes: the condition-based model with maintenance effectiveness of 0.7,
use of predictive maintenance 50%, refurbishment of detected PCA 0.2, and
fraction of detected PCA replaced 0.5 is used as a based case (for which
fraction failing PCA repaired is 0.0). The value of fraction failing PCA
repaired is then varied in the range 0.1 to 0.9.
total depreciated asset
540
520
value (units)
500
480
460
440
0 0.2 0.4 0.6 0.8 1
fraction failed PCA repaired
Figure 66 Total depreciated asset value with increasing use of remedial maintenance
of PCA
4
failure rate % p.a.
2
1
0
0 0.2 0.4 0.6 0.8 1
fraction failed PCA repaired
247
(condition-based) refurbishment, where assets are restored to good
condition, and the effect of increasing refurbishment is to reduce failure rate.
The conclusion that can be drawn from this is that a policy of repairing poor
condition assets is detrimental to system performance. Repairing good
condition assets would not have the same performance penalty, because
these are returned to good condition. The enterprise could then have the
benefit of retaining the return on and of asset value for the remaining life of
the asset. This is particularly true for assets failing from infant mortality – if
these can be repaired most of their useful life is still ahead of them.
248
The effect of employing a replacement on failure-only policy is now
investigated, using the same parameters as were used for the previous study
(except that the case is studied both with remedial maintenance and without
remedial maintenance.)
Figure 68 illustrates that this policy results in high failure rates for low
maintenance effectiveness. It also reinforces the conclusion, in the previous
section, that repairing failed PCA has a detrimental effect on failure rates
(The 50% remedial maintenance case generates higher failure rates than the
0% case over the full range of maintenance effectiveness).
249
therefore explain the very low direct maintenance costs reported for the North
American respondents of the CIGRE study.
6
5
failure rate % p.a.
4
3
2
1
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
condition-based age-based replace on failure only
250
the condition-based replacement strategy first introduced in Section 6.6. It
can be concluded that, compared with the condition-based replacement
strategy, the replace-on-failure-only strategy is lower cost, similar in effect on
depreciated asset value (at least in cases using straight line depreciation)
but comes equipment failure rate penalty.
1000
Total depreciated value
800
600
(units)
400
200
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness fraction
14
It is noted that the ACCC used a benchmark value of 60% for gearing ratio calculation in
the Electranet case, although the actual gearing ratio for this company was 80% at the time.
251
The model has been developed based on the Australian method of revenue
calculation. The revenue calculation for Australian Transmission Network
Service Providers (TNSPs) has three components (Equation 9):
Revenue = WACC * DORC + Depreciation + O&M (9)
where:
WACC = weighted average cost of capital;
DORC = depreciated optimised replacement costs; and
O&M = operations and maintenance.
Straight line depreciation is used in this calculation. The term optimised
indicates that the return on capital is based on prudent expenditure: the
regulator has the power to disallow return on capital for sub-optimum capital
projects, which is intended to provide a disincentive for over-expenditure.
The O&M component is based on anticipated costs, adjusted for inflation and
an efficiency gain, the value of which is set by the regulator. This is
described as a CPI-X scheme (see also sections 2.2.1.2, and 0 for more
information).
252
revenue, and the CPI – X scheme is considered by some15 to provide a
disincentive to reducing O&M. The assumption that there is no impact on
maintenance effectiveness is more difficult to defend, in the longer term, if
the regulator continues to apply a minus X adjustment.
15
This view was expressed in a CIGRE Asset Management seminar (Murray, 2000). The
disincentive to cost reductio is partly offset by a scheme which allows profits from reductions
in O&M costs to be retained in part over the next regulatory review period.
253
internal funding ratio target
gearing
ratio
accumulating debt
WACC debt reducing debt
return
on capital
annual
avg age AA depreciation
DORC interest
rate
expected life
young assets mid life assets aged assets very aged assets
(0 -9 yrs) (10-29 yrs) (30-39yrs) (40+ yrs)
purchasing
assets
The outflows from retained earnings are dividends (set to zero), capital
funding of assets, interest and repaying debt. In practice a portion of capital
spending is funded from earnings and the remainder from debt. To model
this relationship an internal funding ratio and a target gearing ratio have been
defined. The amount drawn from retained earnings for capital funding of
asset is initially the value of assets replaced multiplied y the internal funding
ratio. The amount funded from debt is the total value of assets replaced less
the amount funded from capital. If funds are available, after interest
payments have been made, they are transferred from retained earnings to
254
maintain gearing at the target level. This is the flow repaying debt. Gearing
ratio has the usual meaning here: ratio debt to (debt plus equity), where debt
plus equity equals retained earnings plus DORC. A target gearing ratio of
60% has been used, based on the benchmark level used by the Australian
regulator for a recent revenue decision (ACCC, 2002a). For consistency the
values of WACC (7.17%) and interest rate (6.39%) have been drawn from
the same source.
An optimisation factor of 1 has been assumed for the initial study (i.e. no
optimisation). The effect of introducing optimisation is considered later in this
section.
255
maintenance effectiveness values greater than the break-even point), give
results that are independent of initial conditions.
1000
800
(1 = asset value)
TDV
monetary units
600
retained
earnings
400
debt
200
0
0.5 0.6 0.7 0.8 0.9
maintenance effectiveness
256
(asset value units)
300
retained earnings
250
200
150
100
50
0
0.5 0.6 0.7 0.8 0.9 1
maintenance effectiveness
The model does not take into account possible reductions in replacement
cost from assets that are optimised down in value or completely optimised
out. Figure 74 suggest that a moderate amount of optimisation will have a
significant effect on the profitability of the company. The break-even point for
profitability is increased significantly when optimisation factor of 0.9 is applied
to return on capital and return of capital. Note however, that the point of
maximum retained earning is the same for both cases, although the level of
maximum retained earnings is much lower for the case with optimisation.
257
300
Figure 74 Effect on retained earnings of optimising asset value compared with the
case with no optimisation
258
180
259
300
250
(asset value units)
retained earnings
200
150
100
50
0
0 0.2 0.4 0.6 0.8 1
maintenance effectiveness
300
250
(asset value units)
Retained earnings
200
150
100
50
0
0 0.2 0.4 0.6 0.8 1
Maintenance effectiveness fraction
260
6.13 Comments on Maintenance efficiency and the impact of
replacement and maintenance strategies on maintenance
spending
It is evident from the previous studies that replacement and maintenance
strategies have a bearing on maintenance spending. Other factors also
contribute to this, notably maintenance efficiency and labour cost.
261
discrepancy between the maintenance spending predicted by the fuzzy
model and actual maintenance spending reported for the Japanese cases
suggests that maintenance efficiency could be improved in that country,
despite high maintenance effectiveness. The lack of financial drivers to
reduce maintenance costs in Japan, at least until recently, is likely to be a
major cause of persistent inefficiency.
262
For this network there are only two points of interconnection with another
transmission network, plus connections to sub-transmission / distribution
networks: for highly intermeshed and interconnected, moderately loaded
networks in Western Europe and North America the effective redundancy
factor is likely to be much higher. This means that significantly higher
equipment failure rates can be sustained for the same supply reliability, or
alternatively that with effective maintenance practices very low levels of
unreliability should be readily achievable. It also supports the commonly held
view that, for networks of low connectivity (eg South America),
interconnection to adjacent networks can be of significant benefit, in terms of
improving reliability of supply to customers.
263
the level of replacement of equipment is low (see Figure 4) and use of
both offline and online CBM is low compared with other regions (See
Figure 1). The Fuzzy Model also adds some weight to these
arguments – use of a replace-only-on-failure criterion will have the
effect of increasing two inputs proportion of aged equipment and
redundancy. The effect on reliability of supply of different proportions
of aged equipment for three levels of redundancy ranging moderate
(50) to high (70) is illustrated in Figure 78, using the North American
base case. The graph confirms that as redundancy increases, the
impact of aging equipment on reliability of supply is reduced.
• Enterprises that have lower levels of financial drivers on maintenance
spending, and which operate in networks of high effective redundancy
(eg Western Europe, Japan), could achieve very high levels of supply
reliability (and circuit reliability) by employing a moderate amount of
predictive maintenance and condition-based replacement. Availability
of circuits may not be as high, compared with other enterprises,
because higher effective redundancy implies lower risk associated
with taking lines out of service.
• In networks with more moderate levels of effective redundancy (eg
Australasia, South America and parts of Asia, failure rates of
equipment will have a higher impact on reliability of supply. Therefore
in order to achieve high reliability, high maintenance effectiveness is
required. A relatively high level of use of predictive maintenance (eg
in Australia, refer to Table 11) will be effective in maintaining failure
rates at low levels (See Figure 21).
• Networks with very low levels of effective redundancy (eg India), are
likely suffer from low reliability of supply. In such networks the system
risk associated with maintenance is high and hence utilities will be
under pressure to achieve a high level of availability of circuits, as is
reported for India (Kumar et al., 2002).
264
Reliability of supply
high
moderate
low
0 10 20 30 40
proportion of aged equipment %
Redundancy:
moderate 50 mod-high 60 high 70
Figure 78 For the North American base case this graph shows how increasing
redundancy reduces the impact of aging equipment on the reliability of supply.
The particular data that have been used here for calculating effective
redundancy are seldom published, but should be readily obtainable from the
databases of transmission enterprises. It would be very informative to
compare these parameters to obtain a basis for comparing the likely impact
of different operation and maintenance schemes on performance of the
system. This is an area recommended for further research.
265
400000
350000
300000
250000
assets
200000
150000
100000
50000
0
0 20 40 60 80 100 120 140 160 180
years
GCA PCA
Clearly this is not a practical situation. The first point is that it is simply not
practical to expect the number of assets to grow indefinitely, for reasons of
space required for instance. In practice as networks grow the capacity per
asset (and therefore value per asset) grows. The rate of increase of assets
probably decreases gradually with maturity of a network. In the long term it is
unrealistic to expect that the Earth can support ever increasing energy
demand, in which case the rate of increase of assets will probably decline to
zero. If multiple smaller assets are replaced with fewer larger capacity
assets as they need to be replaced then the total number of assets on the
network could decline over time, even if the replacement value of assets
increases.
There are signs that this is already occurring in some places: For example,
in Western Europe there is a strong trend today toward the replacement of
assets with higher capacity and/or more compact designs because of
extreme difficulties in obtaining land for augmentation (Aesbasch et al., 2000,
Lamsoul et al., 2000, Mittard et al., 2002). As networks mature and the
266
population density increases in other parts of the world, such pressures are
also likely to extend to other regions.
replacement of very aged assets
young assets mid life assets aged assets very aged assets
(0 -9 yrs) (10-29 yrs) (30-39yrs) (40+ yrs)
network
replacement of poor condition assets
maturity
maturity
aug. fraction maintenance
effectiveness
early randomly
failing failing randomly PCA
failing failing
load growth
rate %
augmentation
rate all failed assets replaced (no delay)
267
straight line. This means that for 100% network maturity the rate of increase
of assets from augmentation drops to zero. Network maturity is assumed to
increase at a rate of 2% per annum to a maximum of 100%; this relationship
is implemented through the connector between network maturity and the flow
increasing maturity. This is also modelled as a graphical function, which is
simply constant from 0 to near to 100% maturity and then drops to zero.
Load growth is also assumed to be a function of network maturity.
The load growth has potential to grow most quickly for networks of low
maturity as more consumers are added to the network and the growth of
supply of electricity fosters industrial growth. As the network becomes
mature, the growth rate is reduced to the rate at which the consumption of
users is increased (Khatib, 1998). Khatib reports that the global growth rate
of electricity consumption was about 4% per annum in the past forty years
but is expected to drop to 2.9% per annum in the period 1997 to 2020.
However, during this period the average growth rate in developing countries
is expected to be between 4-6% per annum. The global rate of electricity
demand growth is expected to drop to about 1.7% per annum in the period
2020 to 2030, as the networks in currently developing countries become
more mature. These figures support the argument that load growth is
reduced with increasing network maturity. Some currently developing
countries have experienced significantly higher growth rates than 6% in
recent years: in the period 1980-1997 the average annual growth in
production of electricity (figures from (World Bank, 2000a)) was 13.5% in
Indonesia, 12.1% in the Republic of Korea, 12.5% in Thailand and an
unusually high 33.1% in Paraguay. By contrast, in European Union countries
the growth in production was 2.4% per annum, over the same period.
268
25
20
load growth %
15
10
0
0 20 40 60 80 100
network maturity %
3.5
3
value per asset
2.5
2
1.5
1
0.5
0
0 20 40 60 80 100
network maturity
Figure 82 Modelled relationship between network maturity and value per asset
When this model is run a more reasonable asset growth plot is obtained as
shown in Figure 83. The corresponding time-development of network
maturity and load growth are shown in Figure 84.
269
10,000 8,000
(units)
6,000
4,000
4,000
2,000 2,000
0 0
0 50 100 150 200
years
Figure 83 The asset growth rate and total replacement value of assets as a function of
time, and with increasing network maturity.
100 20
network maturity (%)
0 0
0 50 100 150 200
years
270
profitability could potentially benefit from modelling their policies using these
or similar techniques.
4000
3500 MLA
3000
2500
assets
2000 YA
1500
1000 AA
500 VAA
0
0 50 100 150 200
time (years)
271
• A policy of refurbishment of poor condition assets is effective in
reducing failure rate but will result in reduced depreciated value of
assets unless refurbishment is capitalised.
• At lower maintenance effectiveness levels an age-based replacement
policy produces a higher failure rate and lower replacement levels
than a condition-based scenario.
• A replacement on failure only policy, with low levels of condition-based
refurbishment can result in very low maintenance costs at small failure
rate penalty if coupled with high preventive maintenance effectiveness
and efficiency.
• For the simplified model of the Australian revenue calculation,
condition-based replacement produces the highest retained earnings,
but age-based replacement produces a high level of retained earnings
over a wider range of maintenance effectiveness levels. This effect is
accentuated for higher levels of MTBF of Poor Condition Assets.
• A replacement-on-failure-only can produce better retained earnings
outcome at lower levels of maintenance effectiveness than either
condition- or age-based replacement strategies, particularly when the
MTBF of Poor Condition Asset is high.
• Repair of poor condition assets increases overall failure rates, all else
being the same, but repair of assets generally in good condition is
worth considering.
• The impact of failure rate on the reliability of supply is dependent on
the effective redundancy of the network. The effective redundancy
depends not only on the configuration and loading of transmission
network but also on interconnected networks including other
transmission networks to which there are interconnections, together
with sub-transmission and distribution networks that provide parallel
paths for power flow. Networks with high effective redundancy will be
more tolerant to failure rates than networks with lower effective
redundancy.
• A measure for determining effective redundancy has been proposed:
272
the number of forced outages of equipment (in a year)/ number of
forced outages resulting in loss of supply (in a year).
This figure could be averaged over five years to account for the
variation arising from non-uniformity in the connectivity and loading of
networks.
• System augmentation tends to mask the underlying impacts of
maintenance and replacement policies on network performance and
profitability. For networks with high growth rates less attention may be
given to optimising maintenance and replacement policies than that
given in low growth rate networks.
273
7 Discussion of regulation of transmission utilities
supported by modelling results
The results from the studies performed for this research highlight the
important influence of regulation on the performance of the transmission
enterprise. One of the main ways that a transmission enterprise can be
influenced to improve its performance is through the mechanism of
regulation. Since transmission enterprises are generally treated as regulated
monopolies regulation is of fundamental importance to the ongoing viability of
the transmission enterprise and the transmission network it supports. It is
therefore valuable to consider the desirable traits of the transmission
enterprise, and the implications for regulation.
274
Cost to users can be narrowly defined as the price of electricity – which
reflects the operation and maintenance costs, level of augmentation and
equipment replacement, debt servicing, financial management and profit-
making by the transmission enterprise. However, in a broader sense, cost
also includes the impact of network constraints on the generation costs or
market price for generated electricity (depending on whether an electricity
market exists), and any environmental costs associated with the transmission
of electricity. In a merit-order despatch system, transmission constraints can
force out-of-merit-order generation despatch. In a competitive market
transmission constraints can cause very high spot prices for electricity which
may be a reflection of costs or opportunistic bidding by generators. Two
factors that impact on cost therefore are effective redundancy of the network
(defined in chapter 7) and circuit availability. In practice, the impact of circuit
availability will be different for different circuits, and depends on effective
redundancy: If effective redundancy for part of a network is high then the
effect of circuit availability on network constraints for circuits in that part of the
network will be low, and vice versa.
275
should make appropriate use of advances in technology consistent with
efficient operation and maximum benefit to society.
This is consistent with sustainable and low cost operation, because failure to
observe appropriate safety standards exposes an enterprise to significant
risk.
276
The results in this thesis suggest that the adequacy of revenue is a function
of a range of factors, not simply the network’s size or capacity. Maintenance
and operating costs will depend on the age and condition of the network, the
cost of labour, length of travel times, failure rate (including the impact of
climate and loading), the need to undertake work outside normal hours or to
undertake live work. Deterioration of the transmission network’s condition is
a function of climate (particularly ambient temperature), loading and
effectiveness of past preventive maintenance as well as time. These factors
are either outside the control of the transmission enterprise or a function of
past decisions that have consequences for the present network.
Investment needs depend on current loading levels and load factor as well as
anticipated load growth. Any need to upgrade network performance or to
reduce network constraints by increasing capacity, redundancy or replacing
poor condition equipment will also require capital spending. Rapid rates of
system augmentation need to be funded by commensurate increases in
revenue most probably increased debt.
The cost per asset (of same size and function) may also vary significantly,
depending on factors such as ruggedness of terrain, level of seismic activity,
lightning incidence, the likelihood of high winds or ice storms, the length of
lines and the need to employ expensive technology options like GIS and
underground cables (particularly in highly urban areas). Consumers with
high supply quality needs may need to be provided with a transmission
supply with higher specifications for performance – eg higher redundancy
level and/or over-designed equipment; this is likely to result in a more
expensive network. These special requirements are likely to be reflected in
higher revenue requirements and thus higher transmission prices.
277
7.2.2 Revenue based on return on investment
Revenue based on return on investment is generally a large component of
the revenue for transmission enterprises. For Australia and New Zealand a
figure of 80% for the capital components of revenue was suggested by Jones
(Jones et al., 2000). This component has a large impact on revenue
sufficiency and it is important that it provides appropriate drivers for the
disposition of income.
The return on investment component of revenue has two main parts – the
rate of return that is deemed to be appropriate and the valuation of assets to
which it applies. Asset value appears to be a source of major difference from
one regulator to the next ((Perez-Arriaga et al., 2002)). In the USA return on
investment is largely based on historical asset values. By contrast, in the
Australia it is based on deprival value, interpreted as Depreciated Optimised
Replacement Costs and in New Zealand the Optimised Replacement Value
is used. The use of optimisation can potentially have a significant effect on
profitability as illustrated in Section 6.11. Likewise the use of depreciated
asset value has a negative effect on revenue that is accentuated as the life of
assets is extended beyond their book-life (by means of effective
maintenance, for example). Although interest repayments are decreased
with increasing asset life, profitability can actually decrease with improved
maintenance effectiveness, when coupled with a condition-based
replacement strategy, if depreciated asset value is used as the basis for
calculation of return on investment. In fact Figure 75 suggests that under the
Australian regulatory framework there is an incentive to replace assets on the
basis of age: not only is there no reduction in the return-on-investment
component of profit with increasing maintenance effectiveness, there is also
an opportunity to reduce maintenance costs and increase reliability of supply
by replacing old maintenance-intensive equipment with new less-
maintenance-intensive plant. However, replacement solely on age is not
consistent with allocative efficiency because equipment of the same age can
have quite different performance because of design, duty and environmental-
factors. This problem highlights the necessity to match book-life of assets
with the physical process of asset deterioration.
278
It is noted that a recent discussion paper by the Australian regulator (ACCC,
2003) proposes to apply the regulatory test to all types of capital expenditure
including replacement and refurbishment. At time of regulatory reset the
regulator will assess whether the regulatory test process has been
appropriately applied, in order to decide if a project should be included in the
asset base for purposes of revenue calculation. It is not yet clear what effect
this will have on the asset management practices of Australian TNSPs. The
regulatory test is itself also under review.
Because the usefulness of assets remains constant over most of their life,
and only decreases in the wear-out phase of condition, it is arguable that
deprival value of transmission assets is more closely related to the
replacement value than to the depreciated replacement value of assets.
Deprival value is most closely related to the condition of the assets.
279
7.2.3 Drivers of Operations and Maintenance
A common theme in recent literature on asset management is the pressure to
reduce operations and maintenance costs. This trend has been experienced
in both locations where electricity reform has been introduced and those in
which it has not been introduced. Ideally the aim is to maximise the efficiency
of O& M without compromising its effectiveness. In Chapter 6 the strong links
between maintenance effectiveness and both equipment failure rate and
financial performance were demonstrated. It is therefore important that
transmission enterprises not be driven to reducing maintenance spending
below levels capable of sustaining effective maintenance. The results of
reducing maintenance below adequate levels would not be immediately
evident in system performance but will be seen several years later.
In its recent discussion paper (ACCC, 2003) the Australian regulator has
indicated a preference for benchmarking of O&M costs. This practice has
also been adopted in the UK in respect to RECs (see Section 2.2.1.2). As
noted by the ACCC document, nearly all the regulatory difficulty relating to
280
the use of exogenous cost measures arises from the problem of
distinguishing legitimate cost differences from variations due to controllable
efficiency differences alone. The fuzzy modelling in this research strongly
highlights the diverse causes of differences in costs and performance
between different transmission utilities; as a result there is a risk of
inequitable assessments.
281
standards for Australian transmission network service providers (ACCC,
2002b). Availability of circuits in general is not a parameter that should be
maximised: 100% availability indicates that either no maintenance has been
undertaken or that it has been done with the equipment in service. There is a
cost penalty associated with live working in addition to personnel safety
concerns, so it should not be undertaken unless necessary. Likewise a low
availability may be function of construction or refurbishment of lines or
substation equipment rather than poor performance. On the other hand it is
appropriate that transmission enterprises be given incentives to minimise
overall costs to consumers including the effect of transmission constraints,
either by maximising availability on critical circuits or by increasing effective
redundancy of the network for those parts of the network participating in
constraints.
282
Tools such as those presented in this thesis can assist managers to
understand the impact of both external and internal drivers on the
performance of their networks and their businesses. As such they may assist
to hasten the process of aligning asset management strategy to the new
circumstances that confront them.
283
8 Conclusions
This thesis has broken new ground in the application of organisational
modelling concepts to transmission asset management. It draws on
techniques from Management Science and Artificial Intelligence to explore
problems intractable by traditional engineering methodologies. In doing so it
opens up opportunities for the development of new decision support tools for
transmission enterprises. Indications from discussions with electricity
industry managers are that there are currently no commercially available
tools directed at the strategic level of asset management in electricity
transmission. Furthermore, evidence from available literature suggests that
systematic research integrating the engineering, regulatory and financial
aspects of transmission asset management is very rare. On the other hand,
the pace of change in the electricity industry throughout many parts of the
world has never been so great. There is an urgent need to reassess
traditional policies and practices of asset management, and realign them with
current external drivers. At stake are the financial viability of the transmission
company and the ongoing performance of the transmission network. The
research contained in this thesis is therefore both timely and valuable.
The purpose of this thesis has been to examine the factors that influence
policies and practices of electricity transmission organisations, and to
investigate their impact on the performance of those enterprises
Since research covering the full scope of the problem is scarce, it has
therefore been necessary, in the knowledge acquisition phase of this
research, to draw on a very broad range of literature, together with expert
interviews from industry representatives from various parts of the world, and
extensive personal knowledge of the electricity industry, in order to construct
a model of asset management in the electricity transmission sector. This
conceptual model of the system, developed in Chapter 3, has been
represented concisely in a causal loop diagram. The development of this
generic model is a significant contribution to a new area of research. It
284
clearly illustrates structure of system, indicates the complex feedback
mechanisms and suggests potential interactions of variables.
285
with this type of model, has been successfully achieved by developing data
sets representing typical regional values and individual companies and
testing values predicted by the model against published information
(aggregated regional values and information reported for individual
enterprise). This procedure develops confidence in the model’s predictive
power.
There are some unusual and useful features of the fuzzy rule-based model:
• Unlike most benchmarking techniques this tool can be used to
compare a range of enterprises with markedly different operating
circumstances.
• Because of the hierarchical structure of the model, the underlying
causes of difference in performance can be investigated. This can
provide information not usually accessible from benchmarking studies.
• It has been demonstrated (Chapter 5) that the model can be used to
identify opportunities for and barriers to performance enhancement.
Sensitivity of performance outcomes to changes in inputs have been
shown to vary from one enterprise to the next, suggesting that
solutions effective for one utility may not be appropriate for use by
another transmission enterprise. Application of the model to such
problems may therefore avoid costly mistakes.
286
previous model, was an exercise in building confidence that the outcomes
generated by the model were explainable and consistent with observed data.
The model, which links the age and condition distributions of an asset
population, has provided valuable insights into the nature of transmission
asset management. This structure enables the financial aspects of asset
management to be linked with maintenance, refurbishment and replacement
strategies, including those based on asset condition. Whereas the fuzzy
model allows for a breadth of analysis, the system dynamics model allows
deeper analysis of the effect of asset management strategies on profitability.
The impact of maintenance effectiveness, and condition-based maintenance
on asset valuation and revenue for age and condition-based replacement
and refurbishment scenarios have been examined for the Australian system
of revenue determination for transmission enterprises. The model can
readily be adapted to other types of regulation.
287
Another non-trivial but potentially fruitful avenue for research is to model
maintenance spending using the system dynamics model. As the CLD and
fuzzy models have demonstrated, a complex combination of factors
contributes to maintenance spending: Maintenance effectiveness relates to
routine time- or condition-based maintenance activities, including minor
corrective actions. It impacts on equipment condition, and through this,
failure rate. Failure rate of poor-condition assets may be reduced by
effective use of condition-based refurbishment and/or replacement of
equipment. Routine, corrective, remedial and condition-based maintenance
all contribute to the cost of maintenance. Refurbishment and replacement
costs may also be included in maintenance spending, depending on
accounting practices of the utility. The efficiency with which maintenance is
undertaken (including skill and targeting of maintenance activities to need)
has a bearing on cost, together with the cost of parts and labour. There may
be an optimum level of maintenance spending per asset (of a particular type)
that depends on the method by which revenue is determined and the
effective redundancy of the network. It would be extremely useful for utilities
to be able to explore relationships between profitability, maintenance cost
and maintenance effectiveness for different asset management strategies.
The results of this research suggest that system dynamics modelling is an
appropriate technique for this type of investigation.
288
businesses operating today in a climate of rapid change, against a backdrop
of existing network, traditional practices and limited tools for analysis.
289
Summary of Contributions
The main contributions of this thesis are:
• A review of relationships between drivers of asset management in
electricity transmission, network development, system and enterprise
performance;
• Development of a generic model of policy-level asset management in
electricity transmission organisations, applicable across a wide range
of transmission enterprises;
• Application of multi-level fuzzy rule-based modelling techniques to
transmission asset management;
• Demonstration of how this model can be used to identify causes of
difference in performance between utilities and to identify strategies
for and obstacles to performance enhancement within a transmission
enterprise;
• Application of system dynamics modelling to transmission asset
management;
• Development of a model effectively linking the ageing and condition-
degradation process, and through this connecting maintenance and
replacement strategies with equipment performance and financial
performance of a transmission business;
• An assessment and comments on the relationship between equipment
and network performance, relating this to maintenance and
replacement strategies in different parts of the world; and
• A review of the impact of regulation on transmission asset
management and performance.
290
Appendix A Sources of Data
Factors of lesser importance, for which no data were available, have been
omitted from the model. This will have a secondary level effect on availability
and the maintenance spending.
291
by Western European data, and data from some regions, especially South
America, are quite incomplete. One obvious error in maintenance spending
for an Australian company has been corrected (from figures published in its
Annual Report of that year).
In general, although a few other dubious figures have been detected it has
not been possible to correct these because while the raw data from the
survey is accessible, the company (and country) details have been omitted.
For cases of data that are clearly invalid, these data have been omitted from
averages used in this study. The lack of country information has made it
difficult to match data from the CIGRE study with data from other sources (eg
labour costs, load growth). For example it appears likely that three of the
nine respondents from Asia are from Japan. For Japan the labour rate is
much higher than the average labour cost in Asia, and the load growth rate is
much lower than many countries in Asia. Hence if the make-up of the
sample group from Asia from the CIGRE study were known, the average
labour cost for this group could be significantly higher than the average for
Asia as a whole. This has implications for maintenance spending predicted
for this case.
292
general responses, some only equipment-specific responses, some both and
some none. This complicates the analysis and assumptions on the meaning
of null or general responses need to be made. Examples of these types of
analysis were given in Section 2.1 and its subsections.
293
Attribute Source
USA: (Hirst, 2000, Kirby, 1999)
External barriers Western Europe: UK (Jay and Williams, 2001, Allison
and Jay, 2001), Switzerland: (Buckner, 2002)
Flexibility (CIGRE SC 23 and 39, 2000)
Frequency of failure as replacement criterion (CIGRE SC 23 and 39, 2000)
Geographic factor (CIGRE SC 23 and 39, 2000)
Ukraine: (Lovei, 1998)
Russia: (Wilson, 1998)
Lithuania: (Standard & Poor's, 1999)
Historical revenue sufficiency
Argentina &Latin America: (EIA, 1997)
Japan: (IEA, 1999)
Australia (ACCC, 2002a, ACCC, 2000)
World Bank data labour cost taken as same as
Labour cost
manufacturing sector (World Bank, 1999b)
Unless known an moderate value has been assumed
Labour skill Malaysia :(Mohd Noor, 2002)
Western Europe:(Davies et al., 1998)
Load factor (CIGRE SC 23 and 39, 2000)
Load growth (recent) (World Bank, 2000a)
Losses (T&D) (World Bank, 2001c)
Various sources including interviews (Allison and Jay,
2001, Bower, 2001, Lee, 2001, Mohd Noor, 2002,
Sherard, 2001, Stewart, 2001, Teixiera, 2001),
technical and economics papers:
Maintenance history (historical maintenance Ukraine: (Lovei, 1998)
effectiveness) Kazakhstan: (World Bank, 1999a, Ametov et al., 1999,
Standard & Poor's, 1999)
Argentina &Latin America: (EIA, 1997)
Australia & New Zealand: (McMahon, 1995);(Allan et al.,
1992, Allan, 1993) (ACCC, 2002a)
Maintenance relative to manufacturers’ recommended
(CIGRE SC 23 and 39, 2000)
levels
Maintenance spending as KPI (CIGRE SC 23 and 39, 2000)
Number of failures as replacement criterion (CIGRE SC 23 and 39, 2000)
India: (Audinet, 2002)
Latin America: (Rudnick and Zolezzi, 2001)
Pilfering
Malaysia: (Mohd Noor, 2002)
Value assumed to be low unless specifically known
Profit as intention (CIGRE SC 23 and 39, 2000)
Proportion of aged equipment (CIGRE SC 23 and 39, 2000)
Proportion of young equipment (CIGRE SC 23 and 39, 2000)
(CIGRE SC 23 and 39, 2000)
Redundancy
India: (Audinet, 2002)
(Standard & Poor's, 1999) (Standard & Poor's, 2001,
Standard & Poor's, 2002)
Regulatory support
South Africa: (Plantagie, 2000)
Japan: (IEA, 1999)
Replacement considered an investment (CIGRE SC 23 and 39, 2000)
USA: (Teixiera, 2001, Sherard, 2001)
Revenue sufficiency (available financial resource)
Russia, Croatia, Lithuania : (Standard & Poor's, 1999)
Ruggedness of terrain Encarta (Microsoft, 2001)
Size of company (CIGRE SC 23 and 39, 2000)
Generally no special relationship except for case studies
Special relationship with vendors of individual companies where a special relationship is
known to exist
294
known outcomes for individual case studies. It is therefore important that the
regional data sets developed in the following subsections reflect, as closely
as possible, typical regional data profiles. Some items within the regional
case sets are also used for the individual cases, where case-specific data
have not been available.
Asia
The electricity industry in Asia is still largely comprised of vertically integrated
utilities, mainly state owned, except in Japan where there are ten privately
owned utilities. Regulation is largely rate-based and fairly supportive,
reflecting the strategic importance of the industry to the economic
development of the region. However there is a driver, especially in cases
where the government is the regulator, to hold prices as low as possible
particularly for domestic consumers, and this can impact on revenue
sufficiency. In the worst cases, tariffs for electricity do not enable companies
to cover costs (Audinet, 2002). Table 35 summarises financial appraisals
from (Standard & Poor's, 1999) for the Asian region. Note that many
countries in the region were at the time experiencing an economic downturn
as a result of the Asian financial crisis. This exposure to currency
fluctuations is reflected in the effect on debt coverage and consequently in
credit ratings (foreign currency ratings). However, it can be observed from
the table that the debt level in Asian electricity enterprises is typically fairly
high, and interest coverage from revenue fairly low, except in Japan, where
utilities have historically enjoyed generous regulatory frameworks, and
access to low interest capital (Standard & Poor's, 1999). In the case of a
government-owned enterprise the debt incurred by the electric company is
typically guaranteed by the government, and therefore attracts a higher credit
rating than would a stand-alone company
295
Table 35 Enterprises in Asia – Business parameters at 1998
sufficiency
Regulatory
Ownership
Debt level
Business
Function
currency
Revenue
Country
acumen
support
foreign
Credit
rating
Name
local/
##
#
*
Japan Chubu P GTD AA 82.9% high well managed v. supportive 3.5x int. cov.
Japan Chugoku P GTD AA- 84.4% v. supportive 3.5 x int. cov.
Japan Hokkaido P GTD AA 77% well managed v. supportive 4.1x
Japan Kansai P GTD AA 81% v. supportive 3.5 x int. cov.
Japan Kyushu P GTD AA 82% v. supportive 3.6 x int. cov.
Japan Shikoku P GTD AA-- 72.8% v. supportive 3.1x int. cov.
Japan Tohoku P GTD AA- 82% v. supportive 3.3 x int. cov.
Japan Tokyo P GTD AA 87.8% v. supportive 3.3 x int. cov.
A
Thailand Egat G GTD 65% well managed supportive 2.8x int. cov.
BBB-
A+
Hong Kong Hong Kong Electric Co. P GTD <40% well managed; very profitable v. supportive 7.1x int. cov.
A
BBB-
Korea KEPCO G GTD 56% supportive
(for. cur)
2.1 x int. cov.
uncertain
Philippines National Power Corp. G GTD BB+ 80% (1997)
support
1.7x (1998)
moderate
Taiwan Taiwan Power Co. G GTD AA 37.9% conservative 2.5x int. cov.
support
1.5 x int. cov.
Tenaga Nasional BBB low prices, adequate
Malaysia 78% G GTD (1998)
Berhad BBB- operational performance
5.5 x in (1995)
# Ownership: G – government; P private
## Functions G – generation, T– transmission, D – distribution
* int. cov.: interest coverage from earnings (presented as a number of times)
296
The companies listed in Table 35 are some of the better performing
companies in the region. There are others with far worse financial situations,
and poorer electricity supply. In India for instance many of the state-based
transmission and distribution companies suffer from under-funding, partly
from tariffs that are too low, partly from chronic levels of pilfering (Audinet,
2002). Consequently the networks in these areas suffer from inadequate
capital and maintenance expenditure, resulting in poor operational
performance. In Cambodia an Asian Development Bank news release from
2000 (Asia Development Bank, 2000) states that “the country lacks adequate
power everywhere except Kompong Cham, Phnom Penh, Siem Reap, and
Sihanoukville. In the needy provinces, private sector operators have neither
the capital nor the creditworthiness to fund rehabilitation or expansion of their
systems.
The high growth in electricity sales in the region on average has contributed
to the debt exposure of companies by necessitating the augmentation of
electricity networks. In some cases this has led to a purchasing regime
based on minimum capital cost rather than minimal life cycle costs for
equipment (Mohd Noor, 2002). In Japan, however, high level (conservative)
specification of equipment has apparently resulted in lower failure rates (in
GIS equipment at least (Chan et al., 1998)), compared with other countries
as well as higher capital expenditure. Because of the high growth rate the
average age of equipment is typically fairly low in Asia.
297
growth has been coupled with the increase in the number of Independent
Power Producers in the region (EIA, 2002d). These typically operate in
parallel with the existing state-owned electric company, and transmission
function is carried out by the state-owned enterprises. In some countries
electricity growth has been supplemented by a significant rural electrification
program: Bangladesh, India, Pakistan, Sri Lanka, Thailand, Viet Nam and the
Lao PDR (UNESCO, 1999). By 1998 almost all villages in Thailand had
access to electricity.
298
Table 37 Labour cost in $US (World Bank, 2000b)
Country Labour cost (manufacturing) in $US 1995-1999
Bangladesh 671
China 729
Hong Kong 13539
India 1192
Indonesia 1008
Japan 31687
Korea, Republic of 10743
Malaysia 3429
Pakistan 6214
Philippines 2450
Sri Lanka 604
Singapore 21317
Thailand 2705
Vietnam 711
Climate is also diverse across this large region, ranging from tropical and wet
in equatorial regions through to subtropical and temperate further north.
Some areas such as Malaysia have a high lightning incidence and the
southern parts of Asia experience tropical storms that contribute to failure
rates of equipment. Some countries in the region are prone to earthquakes
and volcanoes, notably Japan, Indonesia and the Philippines.
299
The revenue cap of Australian transmission companies is calculated based
on the Depreciated Optimised Replacement Costs (DORC) of assets
multiplied by the weighted average cost of capital (WACC) plus an allowance
for depreciation and operation and maintenance (O&M) costs. The operation
and maintenance allowance is adjusted for inflation less a factor X, an
incentive for reducing O& M costs. A new incentive-based scheme has been
recently introduced for service level performance targets, particularly
availability and reliability.
In South Africa Eskom is the state-owned vertically integrated utility, the fifth-
largest utility in the world (Plantagie, 2000). It operates in a supportive rates-
based regulatory environment. Eskom has been involved in a major rural
electrification program providing electricity to an additional 1.75 million
homes in the period from 1994 to 2000 (Plantagie, 2000). This has required
additional transmission infrastructure to maintain a high level of supply
reliability (system minutes lost 3.1 in 1999, 5.3 in 1998 (Plantagie, 2000)).
Eskom’s operation is considered sound, its local currency credit rating is A-
and its foreign currency rating was BBB- in September 2000. In 1998 its debt
level (total debt/total capital) was 58% (fairly high) and its funds from
operations interest coverage was 2.4 x (all financial figures from Standard
and Poor’s (Plantagie, 2000)).
Table 38 shows the debt and funds from operations coverage of interest for
four publicly-owned electricity companies in Australia. Western Power is
vertically integrated, but the others are transmission only. The Tasmanian
utility is very lightly leveraged compared with the others, which are
moderately leveraged.
300
Table 38 Debt and interest coverage for government owned enterprises in Australia
1997-1998 and 1998-99 (Productivity Commission, 2002)
Powerlink Transgrid (New Transend Western Power
(Queensland) South Wales) (Tasmania) (Western Australia)
Year 97-98 98-99 97-98 98-99 97-98 98-99 97-98 98-99
Debt to total assets
38.4 41.1 37.4 35.2 n.a. 3.5 65.6 64.7
(%)
Interest coverage
2.7 2.5 2.0 2.0 n.a. 91.7 x 2.4 2.3
(x)
The South Australian government sold (200 year lease) its transmission
network to Electranet Pty Ltd in 2000. Standard and assigned a credit rating
of BBB+ to Electranet (Standard & Poor's, 2001 p150) The ACCC considers
Electranet’s business profile to be in the range above average to excellent
(ACCC, 2002a p102). However, it does have an aggressive financial policy
(gearing ratio of 80%)(ACCC, 2002a p115).
Typically the electricity systems in Australia are mature, with nearly all the
population having access to electricity supply through an electricity network
or, in remote locations, a local supply. The augmentation of the network
therefore is in line with loading and load-growth, which varies from one state
to another, but is generally moderate.
301
decline occurred in 1990 to 1993 followed by a period of gradual
recovery. In the Commonwealth of Independent states (CIS) the
decline continued until about 1998 (World Bank, 2001a).
• The industrial sector shrank, and the service industry grew. The
output from industry and agriculture in 2001 was 45% of 1990 levels
(World Bank, 2001a). This had an inevitable flow-on to electricity
usage, and demand from industrial loads dropped significantly in the
period (Dobozi and Pohl, 1995).
• Private sector output grew substantially during the 1990s, especially in
some of the CSB countries (notably the Czech Republic, Hungary,
Estonia and Romania).
• Poverty increased sharply during the period, because of falling output
and an increase in income inequality.
In the electricity industry in this region the following effects have been
observed:
• There has been a reduction in electric energy consumption and peak
load during the period. Power intensive industries were among the
hardest hit by industrial restructuring (Dobozi and Pohl, 1995).
• Electricity prices rose substantially during the period, but there was
widespread non-payment problems (Dobozi and Pohl, 1995).
• There was some technological regress due to reduced investment and
lack of funding for basic maintenance and repair work (Dobozi and
Pohl, 1995). The European Commission has estimated that some
tens of billions of USD in investment funds are needed to upgrade
Eastern European power systems to international standards (von
Hirschhausen and Opitz, 2001)
• The lack of a well-functioning judicial system and poor regulatory
governance, substantial institutional instability and regulatory risk
make investment in power system infrastructure in transition countries
risky (von Hirschhausen and Opitz, 2001).
• The development of competitive electricity markets is hampered by
inadequate metering and communications systems in some countries
(von Hirschhausen and Opitz, 2001, World Bank, 1999a).
302
Prior to the 1990s the electricity industries in Soviet Block countries were
typically state-owned vertically integrated monopolies, subject to some
form of rate-based regulation (von Hirschhausen and Opitz, 2001).
Power consumption in the Soviet Union was among the highest in the
world. Capacity utilisation was below international standards. The
connectivity of the network was relatively high (von Hirschhausen and
Opitz, 2001).
Data from the CIGRE study suggests that only a small percentage of
equipment is over forty years old, the typical life expectancy for equipment in
303
Western Europe. This is at odds with documents suggesting that a large
proportion of equipment is past its design life and in need of replacement.
However, it would appear that the design life of (the predominantly air-blast
technology) transmission switchgear in the USSR was 25 years (Batyayev et
al., 1994).
304
The transmission grids of the United States have evolved into three large
networks.
• The Eastern Interconnected System covers the eastern two-thirds of
the U.S and strongly interconnected with the Canadian system.
• The Western Interconnected System includes states in the South
West, and areas west of the Rocky Mountains, and is also strongly
integrated with the Canadian system.
• The Texas Interconnect has interconnections with Mexico.
The transmission networks are largely owned and operated by some of the
larger utilities (EIA, 2000). Wholesale trade in electricity (reselling) has been
increasing gradually, and is being encouraged by the federal government.
Specifically, in 1996 the Federal Energy Regulatory Commission (FERC)
issued Order 888 which opened (non-discriminatory) transmission access to
non-utilities, and Order 889 which required utilities to develop electronic
systems to share information about available transmission capacity.
The changes taking place in the North American electricity industry have had
a number of effects on transmission asset management:
• In the uncertain regulatory environment utilities have been reluctant to
commit to development of transmission augmentations, when
adequate remuneration has not been assured (Hirst, 2000).
• Increases in wholesale electricity transactions have changed power
flow patterns, highlighting transmission constraints.
305
• Transmission constraints have been further highlighted by the market
failure in California in 2000.
• As a result there have been calls for regulators to encourage the
building of transmission (since it represents only a small part of total
cost, but has an important role market operation.)
• Utilities have been reducing operations and maintenance costs in a
bid to be more competitive.
• Regulators have been more conscientious about keeping operations
and maintenance costs down, and therefore have applied pressure on
utilities to reduce costs.
Apart from uncertainty arising from the ongoing restructuring of the electricity
industry some other factors have also been identified as contributing to a low
level of network augmentation (especially interconnections) (Hirst, 2000). In
the US there is strong public opposition in some parts of the country to the
building of electricity infrastructure, including issues of visual pollution,
degradation of land prices, benefits accruing to other places rather than
where the line is to be situated. This is further complicated by the need to
deal with multiple sets of regulations and public authorities when proposed
transmission lines cross state boundaries or federally-owned land.
306
developed certain characteristics. Networks are mature and highly
interconnected. Network expansion is viewed favourably by investors and
regulators, but there is pressure to maintain low operation and maintenance
costs. This is also confirmed by the CIGRE maintenance survey in which all
respondents from North America reported doing less maintenance than
recommended by manufacturers. The CIGRE study also suggests only low
overall usage of condition-based maintenance in this region. Offline
condition-based maintenance appears to be common for expensive
equipment like substation transformers (Lee, 2001, Sherard, 2001).
Equipment is generally kept in service until it has failed (Lee, 2001, Teixiera,
2001). Replacement of failed equipment is favoured over refurbishment.
Age does not seem to be considered a criterion for replacement of equipment
(Sherard, 2001, Teixiera, 2001).
Credit ratings of US utilities are typically around the BBB to low A levels, with
the median level BBB+ in 2001 (after the Californian electricity market crisis)
(Standard & Poor's, 2001). The overall trend between 1999 and 2001 was
negative.
South America
Industry restructuring has been a feature of the electricity industry in South
America. Chile in 1982 was one of the first countries in the world to set up an
electricity market. Argentina in 1992 adopted extensive market-based reform
of its industry. This was followed by reform in Peru in 1993, Bolivia and
307
Colombia in 1994 and Central American countries Panama, El Salvador,
Guatemala, Nicaragua, Costa Rica and Honduras in 1997. Brazil, Venezuela
and Ecuador have also started an electricity reform process. Extensive
privatisation within the electricity industry has also occurred in Chile,
Argentina, Bolivia and Peru (CIER et al., 2001).
While electricity consumption per capita is still relatively low there has been a
rapid growth in demand for electricity.
Prior to the reform process the electricity industry was categorised by state-
owned vertically integrated utilities, suffering from inadequate investment in
generation, transmission and distribution capacity (Rudnick and Zolezzi,
2001). By the 1980s electricity infrastructure was “antiquated” (EIA, 1997
p64) and suffering from poor maintenance practices (EIA, 1997 p64).
Electricity utilities were described as inefficiently operated (EIA, 1997)
(Rudnick and Zolezzi, 2001). Pilfering was a major concern (EIA, 1997,
Rudnick and Zolezzi, 2001) and electricity prices high.
Credit levels across the region vary significantly with ownership, local
economy performance, risk (especially those companies involved in
generation) and debt level. Table 40 summarises data from (Standard &
Poor's, 1999) relating to the credit worthiness of companies in 1998.
308
Table 40 Credit rating of South American electricity companies from (Standard &
Poor's, 1999)
Credit rating
Ownership Functions (local/
Country Company Financial status
# ## foreign
currency)
Compania de
int. cov 3.1 x *
Transporte de Energia
Argentina P (25% G) T BBB- FFO to debt 15.2%
Electrica en Alta
**
Tension (Transener)
Eletrobras-Centrais
BB- moderate debt, govt
Brazil Electricas Brasileras G GT
B+ guaranteed
SA
Empresa Electrica del rel. high debt; high
Chile P GT BB-
Norte Grande SA risk generation
strong management
Empresa Nacional de & operations
Chile P GT A-
Electricidat (Endesa) Int. cov. 2.5 x *
FFO to debt 13%
Empresa de Energia BBB T&D parts of
Columbia P GTD
del Pacificon SA, ESP BBB- company low risk
Interconexion 76% G A- 9% return on assets;
Columbia T
Electrica SA ESP (in 1998) BBB- int. cov. 4 x
Electricidad de
Venezuela P ? B+
Caracas
# Ownership: G – government; P private
## Functions G – generation, T– transmission, D – distribution
FFO – funds from operations
Int. cov. – interest coverage from earnings, expressed as a multiplier
For those countries with private investment system augmentation has been
proceeding rapidly. The length of medium and high-voltage lines in
Argentina, for instance, increased by 42% in 1991-1997(Abdala and
Chambottleyron, 1999).
309
America grant concessions to private investors for the construction of new
lines, even when the main grid is publicly owned (Fischer and Serra, 2000).
Western Europe
Western Europe is characterised by highly meshed networks with varying
degrees of interconnection and transfer capability across state boundaries.
Performance standards are generally high. Electricity prices vary
significantly from one state to the next, and transmission prices also vary
significantly from country to country.
The EU Directive 96/92/EC which was passed in 1997 and which became
effective 19 February 199916 has been a catalyst for change in the electricity
markets of Western Europe. The EU Directive was designed to facilitate
market liberalisation by requiring non-discriminatory network access to all
users and increased transparency and separate accounting for generation,
transmission and distribution (Richer, 2000a). Under the Directive’s
schedule, 33% of demand, equating to customers with energy usage of 9
GWh or more, would be open to competition (choice of supplier) by 2003.
16
Member countries were given two years to implement the directive.
310
Where regulatory reform has occurred, in the UK, the Nordic region and
Germany the vertically integrated electricity industry has been split into
separate parts. Other countries have so far retained their vertically
integrated utilities.
311
In some parts of Europe environmental factors are becoming significant
drivers of asset management:
• There is a growing use of distributed generation, particularly wind-
powered and combined heat and power. This can change the use of
and loading patterns on the transmission network.
• In some countries there is a move to reduce the use of SF6 as an
electrical insulator, because of its greenhouse effects. A much greater
effort is being put into elimination of SF6 gas leaks and reclaiming SF6
to avoid environmental damage.
312
Bibliography
Allan, D., Boyd, K. and Lang, P. (1992) 'Condition monitoring techniques for
high voltage insulation effectiveness and economics' in Electric
Energy Conference 1992. EECON '92. 'Driving Systems Harder'.
Preprints of Papers. 19-21 Oct. 1992 Brisbane, Qld., Australia 293-8
313
Allan, D. M. (1993) 'Practical life-assessment technique for aged transformer
insulation' IEE Proceedings A (Science, Measurement and
Technology), 140 5 404-8.
Amato, F., Peelo, D. and Winkler, M. (1999) 'Life cycle cost management - A
modern instrument for investment decisions' in Electricity '99
Conference and Exposition "Technology for a changing industry".
March 29 to March 31 1999.Transactions. 29-31 March 1999
Vancouver, BC 1-5
Ametov, I., Kasymova, V., Borisovsky, V., Zyryanov, A., Petrov, G. and
Preigel, A. (1999) Status of the electricity pool in Central Asia and the
problems of efficient joint use of water and energy resources in the Syr
Darya Basin Task Order No. 813 Contract PCE-I-00-96-00002-00,
Central Asia Mission, U.S. Agency for International Development,
June 1999
Anders, G., Endrenyi, J. and Yung, C. (2001) 'Risk-based planner for asset
management [of electric utilities]' IEEE Computer Applications in
Power, 14 4 20-26.
314
Atanackovic, D., McGillis, D. T. and Galiana, F. D. (1999) 'Reliability
comparison of substation designs' Power Delivery, IEEE Transactions
on, 14 0885-8977 903-910.
Audinet, P., Verneyre, F. (2002) Electricity in India. Providing power for the
millions., International Energy Agency, Paris.
Bak-Jensen, B. B., J.; Bjerregaard, C.G.; Jensen, P.R. (1999) 'Models for
probabilistic power transmission system reliability calculation' Power
Systems, IEEE Transactions on, 14 0885-8950 1166-1171.
Balzer, G., Brandl, M., Strnad, A., Rohsler, H. and Schnettler, A. (1998) 'A
computer aided, reliability-centered maintenance strategy for power
networks' Plant Engineer, 42 1 8-11.
Balzer, G., Scmitt, O., Halfmann, M., Neumann, C. and Strnad, A. (2000)
'Reliability centred maintenance of substation and overhead lines: a
tool for optimised management' in CEPSI 2000
315
Bell, S. (2003) 'Asset Monitoring' in ESAA Study School on Asset
Management February 2003 University of Queensland, Brisbane,
Australia
Brown, R. E. H., A.P.; Willis, H.L.; Luedtke, F.A.; Born, M.F. (2001b)
'Assessing the reliability of distribution systems' IEEE Computer
Applications in Power, 14 0895-0156 44-49.
Chan, T. M., Heil, F., Kopejtkova, D., O'Connell, P. O., Taillebois, J.-P. and
Welch, I. (1998) 'Report on the second international survey on high
voltage gas insulated substations (GIS) service experience' in
International conference on large high voltage electric systems 30 Aug
- 2 Sep 1998 Paris, France Paper 23-102
CIER, ESMAP and World Bank (2001) Regional electricity markets in South
America. Phase 1. Identification of issues for the development of
regional power markets 01601, CIER, ESMAP World Bank, December
2001
316
CIGRE AP13 (2001) Circuit Breaker Replacement: Transmission company
practices Australia and New Zealand Unpublished discussion paper,
August 2001
CIGRE WG 13-09 (2000) User Guide for the Application of monitoring and
diagnostic techniques for switching equipment for rated voltages of
72.5kV and above. Brochure No. 167, CIGRE, August 2000
Cope, D. (Ed.) (2000) Energy sector deregulation in the Apec region, Asia
Pacific Energy Research Centre, Tokyo, Japan.
Damstra, R. D., Baylis, J. A., Hoekstra, H. E., Aupied, J. A., Greeneklee, P.,
Tremblay, P., Simoens, L. and Allison, M. R. (2000) 'A review of
methods for the management of transmission outage risk.' in CIGRE
2000. Session papers. August 2000 Paris Paper 23/39-07
317
Davies, T. C., Wester, P., Renaud, P., Slofstra, J. W., Prieto, J., Sundklakk,
H., Baylis, J. A. and Allison, M. R. (1998) 'Drivers for change in
transmission maintenance policy and the role of computer based
information and decision support systems' in Proceedings -
International conference on large high voltage systems August 1998
Paris, France Paper 23/37/39-02
Duke Energy (2002) Westcoast Energy and Union Gas corporate credit
ratings lowered by Standard and Poor's Duke Energy Accessed on 20
Sep. 2002 www.duke-
energy.com/decorp/content/newscenter/newsreleases/2002
ECAR Electric Equipment Panel (1999) How the aging of major equipment
impacts reliability 99-EEP-61, ECAR, May 1999
EIA (1996) The changing structure of the Electric Power Industry: An update
DOE/EIA- 0562(96), Energy Information Administration, U.S.
Department of Energy, December 1996
318
EIA (1997) Electricity Reform Abroad and U.S. Investment Energy
Information Administration, U.S. Department of Energy, September
1997
EIA (2002d) International Energy Outlook 2002 EIA, Dept of Energy, USA
Accessed on 7 April 2003 www.iea.doe.gov/oiaf/eio/pdf/electricity.pfd
Endrenyi, J., Aboresheid, S., Allan, R. N., Anders, G., Asgarpoor, S., Billin ,
Chowdhury, N., Dialynas, E. N., Fipper, M., Fletcher, R. H., Grigg, C.,
Mc Calley, J., Meliopoulos, s., Mielnik, T. C., Nitu, P., Rau, N.,
Reppen, N. D., Salvaderi, L., Schneider, A. and Singh, C. (2001) 'The
present status of maintenance strategies and the impact of
maintenance on reliability' IEEE transactions on power systems, 16 4
638-646.
319
Energy Policy Group, M. o. C. (1995) Light-Handed Regulation of New
Zealand's Electricity and Gas Industries Energy Policy Group Ministry
of Commerce, Accessed on 19/09/2000 www.med.govt.nz/ers/electric
Eriksson, A., Pettersson, K. G., Krenicky, A., Baker, R., Ochoa, J. R. and
Leibold, A. (1994) 'Experience with gas insulated substations in the
USA' in 1994 IEEE Power Engineering Society Transmission and
Distribution Conference (Conf No. 94CH3428-0) 369-75
Flintoff, A. (2001) International utility ratings and ratios Standard and Poor's
Accessed on 20/9/02
www.standardandpoors.com/Forum/Ratings/Commentaries/Corporate
Finance
Green, M., Waddell, R., McCarthy, P., Kumble, C., Southwell, P. and
Manglick, A. (2002) 'Trends and approaches to planning standards,
service standards and new investment in a deregulated market -
Australian and New Zealand experience.' in CIGRE Session 39. Set of
papers presented to the CIGRE 2002 session 25-30 August 2002
Paris Paper 37-302
Greer, I. (2001) Rating methodology for global power utilities Standard &
Poors Accessed on 20/9/02
320
www.standardandpoors.com/australiaNZ/resourcecentre/methodology
/corporateinfrastructure
Hammons, T., Taher, F., Voropai, N. I., Belyaev, L. S., Podkovalnikov, S. V.,
Shutov, G. V., Povh, D., Woodford, A., Vallee, G. J., Doucet, G. J.,
Meisen, P. and Weimers, L. (1998) 'International high-voltage grids
and environmental implications' IEEE Power Engineering Review,
August 1998 1-42.
Hauret, C. (2001) Despite strength, credit quality for U.S. Electric Utilities is
trending negatively Standard & Poor's Accessed on 20/9/2002
www.standardandpoors.com/Forum/RatingsCommentaries/Corporate
Finance
Hogan, W. (1998) 'Getting the prices right in PJM: What the data teaches us'
The Electricity Journal, 11 7 (August / September) 61.
321
Hoskins, R. P., Brint, A. T. and Strbac, G. (1998) 'A structured approach to
Asset Management within the electricity industry' Utilities Policy, 7 4
221-232.
ICEM A/P (1997) Country Report - Malaysia. Energy industry and trade
union strategy in Asia ICEM A/P Accessed on 30 September 2002
IEEE (2000) IEEE Guide for Selection of Monitoring for Circuit Breakers IEEE
Std C37.10.10-2000, IEEE, March 2000
Janssen, A. L. J., Degen, W., Heising, C. R., Bruvik, H., Colombo, E., Lanz,
W., Fletcher, P. and Sanchis, G. (1995) 'A summary of the final results
and conclusions of the second international enquiry on the reliability of
high voltage circuit breakers' in Proceedings of the 35th Session.
International Conference on Large High Voltage Electric Systems.
Aug.-3 Sept. 1994 Paris France Paper 13-202
322
Jasamb, T. and Pollitt, M. (2001) 'Benchmarking and regulation: international
electricity experience' Utilities Policy, 9 107-130.
Karlsson, D., Wallin, L., Olovsson, H.-E. and Solver, C.-E. (1997) 'Reliability
and life cycle cost estimates of 400 kV substation layouts' Power
Delivery, IEEE Transactions on, 12 4 1486-1492.
Klir, G. J. and Yuan, B. (Eds.) (1996) Fuzzy sets, fuzzy logic and fuzzy
systems. Selected papers by Lofti A. Zadeh, World Scientific,
Singapore.
KLSE (2002) Tenaga Nasional Berhard (TNB) Kuala Lumpa Stock Exchange
Accessed on 30/9/2002 www.klse.com.my/website/listing/lc/tnb.htm
Knobloch, H., Marin , H., Schramm, H. H., Kerchesch, P., Schiemann, A., de
Hesselle, M., Moller, K., von Starck, R. and Aachen, R. W. T. H.
(2000) 'Technological trends in high-voltage circuit -breakers' in
CIGRE Session 2000. International Conference on Large High Voltage
Systems August 2000 Paris Paper 13-106
323
Kogan, V. I., Fleeman, J. A., Provanzana, J. H. and Shih, C. H. (1988)
'Failure analysis of EHV transformers' IEEE Trans. on Power Delivery,
3 2 672-83.
Lee, P. (2001) Asset management at San Diego Gas and Electric, Semi-
structured interview: (Expert Interview), Recipient Crisp, J., 30 October
2001
324
Lovei, L. (1998) Electricity Reform in Ukraine: The impact of weak
governance and budget crises Public Policy for the Private sector Note
No. 168, World Bank Group Accessed on 19/9/00
www.worldbank.org/html/fpd/notes/
325
MIT Systems Dynamics Group (1990) Systems Dynamics Education Project
MIT, Sloan Business School Accessed on 4 August 2003
sysdyn.clexchange.org
Mock, K. and Bodek, D. (2001) Challenges mount for public power in the
U.S. Standard & Poor's Accessed on 20/9/2002
www.standardandpoors.com/Forum/RatingsCommentaries/Corporate
Finance
NGC (2000) Report to the Director General of Gas & Electricity Markets.
Transmission system performance. Financial Year 99-2000. National
Grid Company,
326
North American Reliability Council (1994) Regional Reliability Criteria.
Summary of regional criteria and guides for planning reliable bulk
electric systems North American Reliability Council, November 1994
327
Power Grid Corporation (2001) Annual Report 2000 - 2001 Power Grid
Corporation of India,
Pryor, B. M., Gibson, D., Blakeley, R. and Finn, J. (1998) 'Life cycle
management philosophies for transmission substations' in CIGRE
Session 1998. August 1998 Paris Paper 23-109
328
Saeed, K. (1998) 'Sustainable trade relations in a global economy' System
Dynamics Review, 14 2-3 107-128.
Senge, P. M., Kleiner, A., Roberts, C., Ross, R. B. and Smith, B. J. (1994)
The fifth discipline fieldbook. Strategies and tools for building a
learning organisation, Nicholas Brealey Publishing, London.
Shameen, A. (2001) 'Asia's big power play' Asia Week 27 2 19 January 2001
Singh, A. and Poh, S. K. C. (1996) 'A tussle over power profits' Asia Week 7
December 1996
Singh, A. and Poh, S. K. C. (1997) 'Hot wires and cold cash. Money
problems hobble Tenaga's expansion' Asia Week 17 January 1997
Standard & Poor's (1999) Electric Utilities Standard & Poor's, September
1999
Standard & Poor's (2001) Project and Infrastructure Finance Review 2001.
Criteria and commentary Standard & Poor's, October 2001
Standard & Poor's (2002) Asia Ratings List Standard & Poor's Accessed on
30/9/2002
329
www.standardandpoors.com/ratingsActions/RatingsLists/asianratings/
printmalaysia.htm
Tanaka, T., Okamoto, T., Nakanishi, K. and Miyamoto, T. (1993) 'Aging and
related phenomena in modern electric power systems' IEEE Trans. on
Electrical Insulation, 28 5 826-44.
Theunissen, J., Klebanowski, A., Ooi, K., Bennett, K. and Rednell, D. (1998)
'Management of protection & local control practices within a privatised
electricity supply industry - Transmission utility perspective' in
International conference on Large High voltage Electric Systems 30
August - 5 September 1998 Paris, France Paper 34-201
330
Vermeulen, S. T. J. A., Rijanto, H. and van der Duyn Schouten, F. A. (1998)
'Modelling the influence of preventive maintenance on protection
system reliability performance' Power Delivery, IEEE Transactions on,
13 0885-8977 1027-1032.
Wilson, M. (1998) Reforming the Russian electricity sector Public Policy for
the Private Sector. Note No.139. World Bank Group Accessed on 20
September 2000 www.worldbank.org/viewpoint/index.asp
World Bank (2000b) World Development Indicators. Table 2.6 Wages and
Productivity World Bank Accessed on 20/9/2000
www.worldbank.org/data/databytopic
World Bank (2001a) Transition. The first ten years. Analysis and lessons for
Eastern Europe and the former Soviet Union, The World Bank,
Washington DC.
World Bank (2001c) World Development Indicators. Table 5.9 Power and
Communications World Bank Accessed on 20 March 2002
www.worldbank.org/data/databytopic
331
Zadeh, L. A. (1988) 'Fuzzy Logic' Computer, 83-93.
Zsiga, A. (2002) Nordic power sector: return to credit stability? Standard &
Poor's Accessed on 20/09/02
www.standardandpoors.com/Forum/RatingsCommentaries/Corporate
Finance
332